Cities Index.
D - Amended Scope and Compensation Schedule

San Leandro City Council
June 15, 2026

Document
D - Amended Scope and Compensation Schedule
Meeting
June 15, 2026
Body
San Leandro City Council
Original file
235 KB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.

Amendment No. 2 to
Consulting Services Agreement between City of San Leandro and Larry Walker Associates for Municipal Regional Stormwater Permit (MRP3) Compliance Planning Support Exhibit A – Page 1 of 1

EXHIBIT A

SCOPE OF SERVICES
Consultant will provide services in the development and implementation of workplans to assist the City by providing enhanced support to meet critical near-term compliance needs and ongoing support. The enhanced support includes work efforts not currently in LWA’s support contract with the City as well as continuation of compliance planning and annual report support through the end of the contract period (June 2027) and include:
• Task 1.0 – Compliance Planning & As Needed Support
• Task 2.0 – MRP Annual Report (2025-2027 Annual Report) • Task 3.0 – Trash Implementation
• Task 3.1 – PLDA Program Development & Set Up
• Task 3.2 – Ongoing OVTA Program Support
• Task 3.3 – C.10 Compliance Reporting & Tracking
• Task 4.0 – Asset Management Implementation Support
• Task 5.0 – Cost Reporting Support
Amendment No. 2 to
Consulting Services Agreement between City of San Leandro and Larry Walker Associates for Municipal Regional Stormwater Permit (MRP3) Compliance Planning Support Exhibit B – Page 1 of 2

EXHIBIT B

COMPENSATION SCHEDULE
LWA will complete work on a time and materials basis and consistent with the budget provided in Table 1 and the LWA rate schedule. Individual task budgets may be reallocated between tasks with City approval.

Table 1. Estimate Budget (July 2025-June 2026)
Task Description Effort (hours) Costs
1 Compliance Planning & As Needed Support 67 $15,700
2 MRP Annual Report
2025-2027 Annual Report 110 $20,600
3 Trash Implementation

3.1 PLDA Program Development and Set Up 94 $17,900

3.2 Ongoing OVTA Program Support 199 $36,800

3.3 C.10 Compliance Reporting & Tracking 191 $38,100
4 Asset Management Implementation Support 110 $26,000
5 Cost Reporting Support 29 $ 5,700
Total 800 $160,800