East Bay Greenway Multimodal Project 1

ALAMEDA COUNTY TRANSPORTATION COMMISSION
East Bay Greenway Multimodal Project: San Leandro Construction Package

ALAMEDA COUNTY TRANSPORTATION COMMISSION
San Leandro Facilities and Transportation Committee Project Update PresentationOctober 8, 2026 East Bay Greenway Multimodal Project 2
East Bay Greenway Multimodal North SegmentLake Merritt to Bayfair – Construction Packages E 10th St
E 12th St
Oakland: Lake Merritt to Fruitvale Oakland: Fruitvale to San Leandro San Leandro Caltrans
East Bay Greenway Multimodal Project 3
San Leandro Project Limits
E14th Street
San Leandro Blvd
San Leandro / Caltrans Construction Package limits
San Leandro Construction Package Caltrans Construction Package East Bay Greenway Multimodal Project 4
Schedule by Construction Package
Complete
Construction (est.)*
Construction
Contract Award
Environmental Design Complete
Clearance
Construction PackageOakland North 9/18/25 4/10/26 9/24/26 (est.) 10/22/29 Oakland South 9/18/25 2/22/27 (est.) 9/6/27 (est.) 9/5/30 San Leandro 9/18/25 4/3/26 7/23/26 (A) 6/30/28
East 14th 9/18/25 2/18/27 (est.) 8/19/27 (est.) 8/18/30*Weather dependent East Bay Greenway Multimodal Project 5
Project Features
Image sources: NACTO, Alta, Google Images, FHWA
Shared use paths
Protected intersections
Protected bike lanes
Pedestrian signals
Flashing beacons
Bus stop improvements Raised medians
Accessible curb ramps
East Bay Greenway Multimodal Project 6
Recent Project Milestones San Leandro Construction Package• April 2026 – Design Completion and Right-of-Way Certification
• June 2026 – Allocation of Active Transportation Program Grant Funds
• July 2026 – Award of Construction Contract• September 2026 – Issuance of Notice to Proceed to contractor
• October 14, 2026 – Groundbreaking Celebration
East Bay Greenway Multimodal Project 7
Project construction team• Contractor – Bay Cities Paving and Grading, Inc.  City of San Leandro and Alameda County experience
• Construction Manager – Consor Engineering• Project Sponsor – Alameda CTC• Project Agency Partners – City, BART, AC Transit East Bay Greenway Multimodal Project 8
Construction sequencing/phasing
• Approximately 275 working days of fieldwork, weather
dependent
• Work limited to two blocks or 1500 feet work zones at one time
• Typical duration of work along a work zone ~3 to 4 weeks East Bay Greenway Multimodal Project 9
Construction Communications
• Close coordination between Alameda CTC PIO, City PIO, and CM team PIO• Direct outreach to major businesses, housing complexes fronting project • Multilingual Mailing • Multilingual Door Hangers• Multilingual Project Hotline• Project Webpage/Email Address • On-on-One/Small Group Stakeholder Meetings • Languages: English, Spanish, Simplified Chinese East Bay Greenway Multimodal Project 10
Construction – Community/Stakeholder Resources • Multilingual Project Hotline: 1-888-642-4555 • Project Webpage:
www.alamedactc.org/eastbaygreenway
• Email Address: [email protected]• Alameda CTC PIO: Amy Linehan East Bay Greenway Multimodal Project 11
Construction – what to expect
• Working hours – likely 7 AM to 4 PM• Holiday work/weekend work/night work – should be limited with advance notice provided; no night work planned. • Lane closures (limited to multiple blocks at a time)
 One lane per direction One direction at a time Likely in place 24/7 • Temporary closures of some side streets possible
East Bay Greenway Multimodal Project 12
Construction – what to expect• Cyclist detours/diversions – work adjacent to the existing bike lane will require bike traffic to share the open lane with vehicles; Share the Road signs will be used. • Pedestrian detours/diversions – will include sidewalks and curb ramp improvements; advance signage and audible information will be in place alerting to the detour • Temporary bus stop relocation (AC Transit, Links shuttle)• BART station access – minimal impacts to driveway access; advance coordination with BART will occur prior to any work / impacts East Bay Greenway Multimodal Project 13
Construction – what to expect• Access to properties – impacts limited to sidewalk improvements that may require modified access routes; coordination and advance notice will occur • Trash, USPS, and other delivery services to be
maintained throughout
• Noise, dust, etc. – efforts will be made to limit impacts with dust control requirements in place related to air quality East Bay Greenway Multimodal Project 14
Groundbreaking Celebration:

When: October 14, 2026 (1:00PM) Where: Boys and Girls Club of San Leandro (2200 San Leandro Blvd) [email protected]
East Bay Greenway Multimodal Project 15 Alameda County Transportation Commission • 1111 Broadway, Suite 800 Oakland, CA 94607 • 510.208.7400 Forging a Path
for the
East Bay Greenway!
Photo TBDPhoto TBDPhoto TBD
For more information, visit
www.AlamedaCTC.org/eastbaygreenway