CITY OF SAN MARINO

PUBLIC WORKS DEPARTMENT

REQUEST FOR QUALIFICATIONS / REQUEST FOR

PROPOSALS FOR PROJECT MANAGEMENT /

CONSTRUCTION INSPECTION SERVICES FOR THE

STREET REHABILITATION PROGRAM
MAY 16, 2024
Senior Project Manager/Construction Manager: Zack Faqih, PE, ICC Certified, MSCE, CBO, QSD/P Management Contact: Crystal Fraire, PE, QSD/P, President (Principal in Charge) 17130 Van Buren Boulevard, Suite 122, Riverside, CA 92504 Phone. 951.310.7470 | Fax. 949.630.3242 | [email protected]

Page 1 ends

Table of Contents
Section 1. Proposal Summary ................................................................................................... 3 Title Page ......................................................................................................................... 1 Transmittal Letter............................................................................................................ 4 Executive Summary........................................................................................................ 5 Project Manager Qualifications and Experience.......................................................... 6 Client References.......................................................................................................... 13 Proposed Approach & Performance Criteria.............................................................. 14 Section 2. Financial Information.............................................................................................. 22 Financial Statements .................................................................................................... 23 Claims and Litigation History ...................................................................................... 24 Certificate of Insurance ................................................................................................ 25 Section 3. Response Forms..................................................................................................... 26 Acceptance of Form of Professional Service Agreement ........................................ 27 Section 4. Discretionary Supplemental Materials.................................................................. 28 Sample Documents....................................................................................................... 29 Appendix A.................................................................................................................... Resumes Pricing Proposal ...................................................................................... Submitted Separately

Page 2 ends

SECTION 1:

PROPOSAL SUMMARY

Page 3 ends

TRANSMITTAL LETTER
May 16, 2024
Amber Shah, PE, Public Works Director
City of San Marino, Parks and Public Works Department
2200 Huntington Drive, San Marino CA 91108
Subject: Request for Qualifications/Request for Proposals for Project Management / Construction Inspection Services for the Street Rehabilitation Program
Dear Ms. Shah,
Z&K Consultants Inc. (Z&K) proudly presents our proposal to the City of San Marino’s Request for Qualifications/Request for Proposals for Project Management/Construction Inspection Services for the Street Rehabilitation Program. Z&K is a certified Disadvantaged Business Enterprise (DBE), Women’s Business Enterprise (WBE), and Small Business Enterprise (SBE) in Southern California. Z&K specializes in the provision of Construction Inspection, Project Management, Construction Management, Construction Administration, Pre-Construction Inspection, Staff Augmentation, and other Professional Engineering Consulting Services. The Z&K Team has held numerous similar contracts for local agencies, including the City of San Marino.

Potential Performance | The Z&K Team has been working diligently to understand every aspect of the project, including performing a constructability review for the City. This involvement provides us with a deeper understanding of the challenges and the key elements that the project may be facing and familiarity with the site and stakeholders. This knowledge and preliminary legwork will help us to hit the ground running and help the contractor understand the project better, preventing possible issues. Our Team has the ability, capacity, and skill to perform the contract and effectuate the work. We understand the project construction scope of work includes, but is not limited to the following: mobilization; traffic control and construction signage; removal and replacement of concrete curb and gutter, concrete cross gutter and concrete driveway approaches; installation of ADA compliant curb ramps; clearing and grubbing; removal and preparation of native subgrade materials; removal and disposal of Macadam base materials; localized pavement repairs; construction of coldmilling asphalt concrete pavement and overlay with hot mix asphalt (HMA); surface reconstruction; full reconstruction; removal and restoration of traffic markings and striping; painting curb house numbering and curb face painting.

Years of Work Experience | Our proposed Senior Project Manager/Construction Manager, Zack Faqih, PE, ICC Certified, MSCE, CBO, QSD/P, has over 32 years of experience and is thoroughly familiar with the City’s upcoming project. He will personally lead the Z&K Team and has a strong team of high-quality individuals to perform the tasks in this RFP. Tom Dawson, ICC Cert, CBO, has worked on numerous projects within the City of San Marino and will oversee this project as the Regional Supervising Inspector. Eddie Davalos is the proposed Senior Construction Inspector and Jimmy Martin is the Alternate Senior Construction Inspector to cover any night work, weekend, work, overtime, or as needed.

Brittany Duhn, PE, QSD/P is the proposed Project Manager and has also has extensive experience in the City of San Marino. This Team works efficiently and with great comradery with City staff to achieve the community's goals. Z&K has over 15 years of experience.

Experience with Similar Projects | Z&K has successfully delivered over 60 street improvement projects in the past 5 years with similar work. We have a track record of performing excellent services on similar contracts through saving significant time and cost from identification of the critical elements controlling the project schedule to providing alternate solutions. We have successfully completed multiple projects in the City of San Marino.

Satisfactory Performance | We have created unique staffing plan to meet the City’s needs and expectations for this Project. We are proud to Team up with Converse Consultants for Material Testing Services. Z&K has carefully selected this “A-Team” and has committed our most qualified staff for the duration of the contract to deliver successful the City’s Projects. Our Team has successfully held contracts in the City of San Marino, including the Street Rehabilitation Program, Project No. 20-9271; Street Rehabilitation Program, Project No. 21-9271; and Lift Station Improvement Program, Project No. 21-8022.

I will serve as the management contact for the full duration of the contract, and I am authorized to bind the firm to the terms of the proposal, execute legal documents on behalf of the firm, and negotiate and contractually obligate the Project Manager pursuant to all terms and conditions started in the Proposal. This Proposal shall be valid for a period not less than 90 days.

Z&K Consultants, Inc. does not have any exceptions and commits to accept the terms and conditions to the language in the RFP documents. Z&K Consultants, Inc. is a California C Corporation. Z&K intends to enter into a Professional Services Agreement with the City for the services as defined in the RFQ/RFP and acknowledges that there were no addendums. We are excited about this opportunity to serve the City of San Marino and are committed to the successful and early completion of the City’s Project.

Sincerely,
Crystal Fraire, PE, QSD/P, President (Principal in Charge) 17130 Van Buren Boulevard, Suite 122, Riverside, CA 92504 Phone. 951.310.7470 | Fax. 949.630.3242 | [email protected] The Z&K Team has
successfully
completed over 60
Street Improvement
Projects in the past 5
years.

Page 4 ends

EXECUTIVE SUMMARY
Z&K Consultants Inc. (Z&K) is a leading provider of Construction Management and Construction Inspection services. We are a full-service civil engineering firm specializing in professional engineering services ranging from construction management, inspection, project management, labor compliance, structural engineering, and staff augmentation. Z&K is in a strong financial position and does not have any conditions that may impede our firm’s ability to provide the services requested in this proposal. Our Team recently completed the City of San Marino’s Street Rehabilitation Program, Project No. 20-9271 and San Marino’s Street Rehabilitation Program, Project No. 21-9271.

Our Team has provided a constructability review to the City for this Project and understand all aspects of the project. We have worked with the City of San Marino and the Designer, NCE, on the previous Street Rehabilitation Programs and know the community well. We are excited for the opportunity to continue working with the City.

The Z&K Team has successfully completed over 60 Street Improvement Projects providing Construction Management and Inspection services. We believe that this is the best team to complete the project, having Converse Consultants working together to meet and exceed the needs of this project. Our team members are multidisciplinary and have numerous licenses and certifications. Our proposed team is exceptionally strong and will ensure the successful delivery of the Project. Z&K has carefully selected this "A-Team" and has committed our most qualified staff for the duration of this contract. We understand the importance of meeting budgets and schedules; we have a strategic plan in place to deliver this project with such benchmarks in mind.

Our proposed key personnel are familiar with the City’s expectations and know the community well. The Z&K Team has carefully examined the project’s requirements to identify key personnel best suited to deliver excellent services for this project. Z&K takes a proactive approach to Quality Assurance and Quality Control. We believe that no project is too small for quality and that everyone is responsible for quality. It is our goal to deliver a well-constructed project that will meet the City’s expectations of quality and functionality. We have successfully utilized CM Agency delivery on a host of projects.

Through this experience we have developed management procedures that promote collaboration and teamwork, improve quality and maximize the value of the City’s project.

Z&K has extensive experience providing Construction Management and Inspection Services on similar projects to the City of Indio’s Project. The Z&K team has provided services for the following similar Contracts and projects:

Street Rehabilitation Program, Project No. 20-9271 (City of San Marino) Street Rehabilitation Program, Project No. 21-9271 (City of San Marino) El Segundo Boulevard Improvement Project (City of El Segundo) Street Rehabilitation Program, 30+ Major City Streets (City of San Bernardino) Residential & Arterial Pavement Improvement, I-159/I-139 (City of Torrance) Ramona Ave. & Walnut Ave. Traffic Signal Modifications and Street Improvement Project (City of Chino) Kimball/El Prado/Central Traffic Signal Improvement Project (City of Chino) 11th Street Traffic Signal Modifications, Pavement Rehab, & Intersection ADA Project (city of Chino) Euclid Ave – State Route 83 Intersection Improvements and Traffic Signal Modifications (City of Chino) Second Street Bridge Widening over Warm Creek & Roadway Widening (City of San Bernardino) Bedford Wash Bridge and Street Improvements (City of Corona) Hamner Avenue Bridge Roadway Widening (RCTD)
River Road Bridge Replacement and Roadway Widening (County of Riverside) Street Rehabilitation Program - Three Separate Projects throughout the City (City of Lake Forest) Citywide Parkway Maintenance, Street Rehabilitation, & Slurry Seal Project (City of Costa Mesa) Slurry Seal Program for Various Locations Citywide (City of Chino) Alley/Sanitation Rehabilitation Project (City of Chino) FY 19-20 & FY 20-21 Street Rehabilitation Projects – Two Separate Phases (City of Alhambra) 2021-2022 Resurfacing Project: Residential Resurfacing Phase I (City of Irwindale Annual Residential Rehabilitation Project - Phase 1 & 2A (City of Compton) Anza/Vista Montana/Pacific Coast Highway Intersection Improvement Project (City of Torrance) 801-0081 Citywide Pavement Rehabilitation Project FY 18/19 & FY 19/20 (City of Moreno Valley) Pavement and Sidewalk Rehabilitation of 10 City Streets (City of San Bernardino) Infill Housing Sidewalk and Street Improvements Of 5 Major Streets (City of San Bernardino) Sidewalk and Street Improvements of 11 Major Streets (City of San Bernardino) Sidewalk Gap Closure Safe Routes to School, Project No. 13288 (City of San Bernardino) CDBG Local Streets Rehabilitation Project (City of Norwalk) Walnut Grove Street Resurfacing Project (City of Rosemead) Alley Rehabilitation Project Phase I, II, and III from Chino Ave to B Street (City of Chino) Farmer Boys Street and Traffic Signal Improvement Project (City of Chino) I-215/Van Buren Interchange Parking Lot (County of Riverside)

Page 5 ends

PROJECT MANAGER QUALIFICATIONS AND EXPERIENCE
Our Senior Project Manager/Senior Construction Manager has a team comprised of experienced and highly regarded professionals who have demonstrated a capacity to perform services similar to the Services on a cost-effective basis. Our Team will perform day-to-day Project Services. Z&K is a California C Corporation. Our Team has worked together on numerous similar projects. We understand that substitution of personnel named in the proposal during the Proposal process or during performance of the Services shall require City’s written approval.

ZACK FAQIH, PE, MSCE, QSD/P, CBO, ICC CERT. | SENIOR PROJECT MANAGER/CONSTRUCTION MANAGER Zack Faqih, PE, MSCE, QSD/P, CBO, ICC Cert. has over 32 years of construction management experience and will be the dedicated Project Manager for this contract. In this role, he will be responsible for the overall management of the contract. Mr. Faqih has full working knowledge of construction practices for street improvement projects.

He has worked in every position included in this contract. Mr. Faqih has experience in the Construction Management, Construction Inspection, Project Management, and Contract Administration of capital improvement and public works projects, and has successfully delivered over 40 similar street improvement projects including street improvements, slurry seal, pavement rehabilitation, traffic signal modifications, fiber communication, CCTV cameras, street lighting, intersection improvements, sewer and storm drain improvements, traffic signal improvements, curbs, gutters, sidewalks, bridge projects, and access ramps. He has extensive experience managing multiple projects in Los Angeles County and Orange County since 1999. Mr. Faqih’s experience extends to interfacing and coordinating with the Caltrans-Local Assistance Program, Counties, Cities, Funding Agencies. He has excellent skills in understanding construction contracts, review and control project cost and schedule, coordinate and assist in negotiating change orders, maintain project as-builts, managing multiple subconsultants and supervise inspection staff. Mr. Faqih excels in providing detailed constructability review of project plans and specifications, which minimizes the potential project delays and change orders and assists the client from pre-award to project close-out to ensure full funding reimbursement.

Mr. Faqih’s experience extends to interfacing and coordinating with the CaltransLocal Assistance Program, Counties, Cities, Funding Agencies on the local, state, and federal level. He has excellent skills in understanding construction contracts, reviewing and controlling project cost and schedule, negotiating change orders, providing project updates to the client, ensuring timely review of critical path method (CPM) schedule to track any changes in critical path and delays, maintaining project as-builts, and managing multiple subconsultants.

Mr. Faqih’s expertise includes knowledge of Cities & Counties regarding Federal Funding, and in providing guidance and resolution in maintaining claim avoidance. His accumulated knowledge of FHWA/Caltrans/Greenbook Standards & Manuals, Procedures, and chain of command is a valuable tool in gaining agency cooperation and approvals. He has won several binding arbitrations on behalf of his clients for issues ranging from concurrent time delay claims, loss of production claims, differing site condition claims, rock claims, and defective concrete. He has served as an Expert Witness for underground claims and scheduling issues. Mr. Faqih’s experience and background makes him the City’s ideal candidate:

P Skilled in effective and creative conflict resolution and risk management
P Extensive background (32+ years) in construction
management of street rehabilitation projects including
civil, structural, mechanical, electrical, and
instrumentation components.

P Skilled in effective and creative conflict resolution and risk management and claims experience
P Provides concierge-level services to impacted residents as it relates to their access into and out of their property, noise, dust, and general disruption to their neighborhood P Continual communication of work progress and any and
all issues arising during construction
P Provides a weekly newsletter that can be shared with
City leaders
P Timely resolution of resident-related issue

PROFESSIONAL REGISTRATION
» Professional Engineer, P.E.

State of California, C57958
» SWPPP (QSD) & (QSP)
Certificate # 22055

EDUCATION
» MSCE - Structures
Cal State Fullerton 2005
» BSCE - Civil /Transportation
Cal State LA 1985

CERTIFICATIONS
» Certified Accessibility
Inspector/Plans Examiner
» Certified Building Official
» Certified Plans Examiner
» Certified Mechanical Inspector
» Certified Plumbing Inspector
» Certified Electrical Inspector
» OSHA 30 Hour
» State Certified HERS Rater
» Certified Emergency Inspector
» C.G.B.P Certified Green
Building Inspector
» Certified Special Inspector for Fire
Proofing
» Certified Special Inspector for
Structural Welding
» Certified Special Inspector for
Structural Steel
» Certified Special Inspector for
Reinforced Concrete
» Certified Special Inspector for
Structural Welding
» Certified Special Inspector for
Structural Steel
» Certified Special Inspector for
Reinforced Concrete

Page 6 ends

TOM DAWSON, CBO, ICC CERTIFIED | SENIOR SUPERVISING INSPECTOR Mr. Dawson has over 28 years of experience providing quality control and quality assurance with extensive experience on of numerous major capital improvement projects including street improvements, traffic signal improvements, roadway widenings, bridges, transmission mains, new wells, tanks, reservoirs, water and wastewater treatment plants, pipelines, lift stations, booster pump stations, retaining walls, dewatering, parks and facilities, landscaping and irrigation improvements, utility installation, roadway widenings, grade separations, masonry walls, storm drain projects, roadway projects, street rehabilitations, and large-scale water and wastewater projects. He has provided construction inspection services for numerous local agencies. He has extensive Public Works Inspection experience and understands the expectations of the City since he has worked in the public and private sectors.

Mr. Dawson has completed numerous projects in the City of San Marino and knows the City and community well. He will oversee this project and provide his expertise and support to the Team as needed.

Mr. Dawson has provided project management during planning stages and with construction management and continuous inspection and onsite project supervision of all trades. He overseed onsite supervision to ensure compliance with all local, state, and federal requirements from concept to completion. He oversees quality control and code compliance inspection services with observation reports for owners, engineers, and local jurisdictions. He provides all required government permits and coordinating required inspections.

EDDIE DAVALOS | SENIOR CONSTRUCTION INSPECTOR
Mr. Davalos has over 25 years of experience in public works inspection, construction management, contracting, quality control, construction inspection, and management of large-scale capital improvement projects, and has successfully delivered over 35 street improvement projects, involving street improvements, intersection improvements, median improvements, ADA ramp improvements, bike lanes and bike trails, conduit installation, traffic signal improvements, asphalt overlay, construction staging, traffic control, clearing and grubbing, SWPPP preparation, manholes and utility covers, loop detectors, PCC sidewalk, speed humps, and pedestrian crossings. Mr. Davalos’s expertise extends to his familiarity with Caltrans, Federal Department of Labor and State of California Division of Labor Standards Enforcement, and equal employment opportunity compliance monitoring.

JIMMY MARTIN, ACI, ICC CERT. | ALTERNATE SENIOR CONSTRUCTION INSPECTOR Mr. Martin has more than 27 years of construction management and inspection experience on capital improvement projects and is a certified ICC and ACI. Jimmy has been performed senior construction inspection services for various projects including pavement rehabilitations, traffic signal improvements, slurry seal projects, roadway widenings, intersection improvements, new intersections, bridges, interchanges, street improvements, traffic signal modifications, retaining walls, sound walls, MSE walls, sewer pipeline projects, water pipeline projects, water treatment facilities, wastewater treatment facilities, pipeline projects, and lift stations and has successfully delivered over 25 street improvement projects.

BRITTANY DUHN, PE, QSD/P | PROJECT MANAGER
Ms. Duhn has extensive experience in project management, office engineering, contract administration, document control, labor compliance oversight, and construction management, and has successfully delivered over 20 street improvement projects, involving street improvements, intersection improvements, ADA ramp improvements, bike lanes and bike trails, conduit installation, traffic signal improvements, asphalt overlay, construction staging, traffic control, clearing and grubbing, SWPPP preparation, coldmill and overlay, manholes and utilty covers, loop detectors, PCC sidewalk, speed humps, and pedestrian crossings. These are great testaments of Ms. Duhn’ managerial and oversight project experience. She gained tremendous experience in the design, operations, and maintenance by working closely with various stakeholders. Ms. Duhn has thorough knowledge of submittals, RFIs, and CCO review, project filing, daily reporting, quantity tracking, and project coordination.

This “A-Team” has worked together in this same capacity on multiple street improvement projects. This same Team worked on the previous City of San Marino’s Street Rehabilitation Program (Two Projects). In addition to their extensive project specific experience, this team has great synergy and works very well together as well as with City Staff. All above key members are local to the area and are excited about the opportunity to improve their community. Our strategic and efficient staffing approach also results in significant cost savings to the City. These key members have performed a site visit and performed a preliminary constructability review of the project. We are confident that our proposed “A-Team” will provide outstanding customer service and cost savings for the City.

LICENSES & REGISTRATION
» ICC Certified
» Fire Inspector 1
» Building Plan Examiner
» CA Combination Inspector
» CA Commercial Plumbing
Inspector
» CA Commercial Mechanical
Inspector
» CA Residential Mechanical
Inspector
» CA Residential Electrical
Inspector
» CA Residential Plumbing
Inspector
» Certified Building Official
» CLB License No. 674861
» OSHA 30 Hour Training

Page 7 ends

ORGANIZATION CHART
Z&K Consultants Inc. (Z&K) is a leading provider of construction management and inspection services. We are a full-service civil engineering firm specializing in Project Management, Plan Review, Program Management, Construction Management, Construction Administration, Construction Inspection, Pre-Construction Inspection, Staff Augmentation, and other Professional Engineering Consulting Services.

CONVERSE CONSULTANTS (MATERIAL TESTING) | Converse is an employee-owned corporation, with 9 offices and more than 150 employees throughout the United States. Their professional and technical staff includes in-house geotechnical engineers, engineering geologists, environmental scientists, deputy inspectors, laboratory and field technicians, drafting/CAD specialists, and other specialized support personnel. Their laboratories are certified by the Division of the State Architect (DSA), California Department of Transportation (Caltrans), US Army Corps of Engineers, American Association of State Highway and Transportation Officials (AASHTO), and the Cement and Concrete Reference Laboratory (CCRL).

TEAM QUALIFICATIONS/EXPERIENCE
Resumes of key personnel are included in Appendix A.

STAFFING CHART
Construction ManagementConstruction InspectionStreet Improvement ProjectsConcrete Curb & GutterCross Gutter & DrivewaysADA Compliant RampsMacadam Base MaterialLocalized Pavement RepairsCold-milling Asphalt Concrete Pavement Hot Mix Asphalt (HMA)Surface ReconstructionFull ReconstructionTraffic Markings & StripingCurb House NumbersCurb Face PaintingProject Close Out Zack Faqih, PE, MSCE, QSD/P, CBO, ICC Cert.

Senior Project Manager/Construction Manager ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü Thomas Dawson, CBO, ICC Cert.

Senior Supervising Inspector ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü Eddie Davalos
Senior Construction Inspector
ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü
Jimmy Martin, ACI, ICC Cert.

Senior Construction Inspector ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü Brittany Duhn, PE, QSD/P
Project Manager
ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü ü

Page 8 ends

FIRM EXPERIENCE
The Z&K Team has successfully performed Construction Management and Inspection services for projects for numerous public agencies. The following projects have been completed on time and within budget.

CITY OF SAN MARINO | STREET REHABILITATION PROGRAM, PROJECT NO. 20-9271 Z&K Consultants, Inc. provided Construction Management and Inspection Services for the City of San Marino’s Annual Street Rehabilitation Program, Project No. 20-9271. Work included a citywide roadway pavement rehabilitation project including construction of cold-milling asphalt concrete pavement and re-paving with hot mix asphalt (HMA) and asphalt rubber hot mix (ARHM), clearing and grubbing, removal and disposal of Macadam base materials where encountered, localized pavement repairs, replacing impacted traffic striping, markings, and loop detectors, curb painting, replacing damaged curb and gutter, adjusting utility frames and grates, utility coordination, and providing temporary traffic control in conformance with Contract Documents and applicable permits and regulations. Z&K provided our services for the Construction Phase, Close-Out Phase and provided additional services as needed. Z&K provided concierge-level service to impacted residents as it relates to their access into and out of their property, noise, dust and general disruption to their neighborhood; provided continual communication of work progress and any and all issues arising during construction; Provided a weekly newsletter from the construction inspector that can be shared with city leaders and residents is highly recommended; and Provided timely resolution of resident-related issues CITY OF SAN MARINO | STREET REHABILITATION PROGRAM, PROJECT NO. 21-9271 Z&K Consultants, Inc. provided Construction Management and Inspection Services for the City of San Marino’s Annual Street Rehabilitation Program, Project No. 21-9271. Work included a citywide roadway pavement rehabilitation project, with over 30 street segments, including construction of cold-milling asphalt concrete pavement and re-paving with hot mix asphalt (HMA) and asphalt rubber hot mix (ARHM), clearing and grubbing, removal and disposal of Macadam base materials where encountered, localized pavement repairs, replacing impacted traffic striping, markings, and loop detectors, curb painting, replacing damaged curb and gutter, adjusting utility frames and grates, utility coordination, and providing temporary traffic control in conformance with Contract Documents and applicable permits and regulations. Z&K provided our services for the Construction Phase, Close-Out Phase and provided additional services as needed. Z&K provided concierge-level service to impacted residents as it relates to their access into and out of their property, noise, dust and general disruption to their neighborhood; provided continual communication of work progress and any and all issues arising during construction; Provided a weekly newsletter from the construction inspector that can be shared with city leaders and residents is highly recommended; and Provided timely resolution of resident-related issues.

CITY OF EL SEGUNDO | EL SEGUNDO BOULEVARD IMPROVEMENT PROJECT, PW 23-02 The Z&K Team is providing Project Management, Construction Management, Construction Inspection, Pre-Construction Inspection, and Contract Administration Services for this project, which involves the following: rehabilitate existing pavement along El Segundo Boulevard between Illinois Street and Isis Avenue; and rehabilitation along Nash Street, between El Segundo Boulevard and Imperial Highway. Several options of pavement rehabilitation were considered, and the recommended option would include cement stabilized base with an asphalt overlay. Install curb ramps on El Segundo Boulevard at Illinois Street, Continental Boulevard, Nash Street, Douglas Street, and Aviation Boulevard intersections. Install curb ramps on Nash Street at Grand Avenue, Mariposa Avenue, Maple Avenue, Atwood Way, a midblock crosswalk, and Imperial Highway intersections.

CITY OF SAN BERNARDINO | STREET IMPROVEMENT PROGRAM (30+ MAJOR CITY STREETS) Z&K Consultants, Inc. is providing Project Management, Construction Management and Inspection Services for this longterm, on-call contract with the City of San Bernardino, which includes street resurfacing and pavement rehabilitation for over 30 major streets and multiple major street intersections in the City. The projects include roadway and pavement rehabilitation, concrete improvements, cross gutters, curb and gutters, curb ramps, ADA improvements, storm drain and pipeline relocation, traffic signal improvements, traffic control, full depth removal and replacement of asphalt concrete, cold milling and AC overlay of existing asphalt concrete, slurry seal application PCC sidewalk, replacement of existing PCC driveways, driveway approaches, curb ramps, retaining curbs, parkway culverts, cross gutters, asphalt-concrete pavement, removal and replacement of trees, clearing and grubbing, installation and configuration of multiple traffic loop detectors and bicycle traffic loop detectors, installation of city project signs, preservation of existing city survey monuments, adjusting manhole and utility covers to grade, reconfiguration and installation of street lighting, and installation.

Our Projects include the following similarities to the City of San Marino’s Street Rehabilitation Program:
ü Street Improvement ü Mobilization
ü Traffic Control and Construction
Signage ü Removal and Replacement of
Concrete Curb and Gutter
ü Concrete Cross Gutter and
Concrete Driveway Approaches
ü Installation of ADA Compliant
Curb Ramps
ü Clearing and Grubbing
ü Removal and Preparation of Native
Subgrade Materials
ü Removal and Disposal of Macadam
Base Materials
ü Localized Pavement Repairs
ü Construction of Cold-Milling Asphalt
Concrete Pavement
ü Overlay with Hot Mix Asphalt (HMA)
ü Surface Reconstruction
ü Full Reconstruction
ü Removal and Restoration of
Traffic Markings and Striping ü Painting Curb House Numbering and Curb Face Painting
ü Construction Management
ü Labor Compliance Monitoring ü Inspection Services
ü Material Testing Services

Page 9 ends

CITY OF CARSON | CITYWIDE PAVEMENT REHABILITATION AND SLURRY SEAL PROGRAM The Z&K Team is providing Construction Management, Project Management, and Inspection oversight services for this Project which includes all four districts of the City of Carson. Z&K is providing Construction Management and Inspection to identify all streets, sidewalks, curb ramps, etc that are in disrepair and need to be added to the project scope. Z&K team is working concurrently with the contractor onboard to provide project scope of work and maps as the contractor completes each district. Scope of work includes traffic control, striping, pavement markings, cold milling, leveling course, asphalt rubber hot mix, traffic loop detectors, concrete improvements, and slurry. In addition to providing the design and scope of the project, Z&K team is performed construction inspection and management services, review of traffic control plans, SWPPP review and implementation, coordination of geotechnical and material testing, labor compliance, attending and coordination construction progress meetings, submittal and request for information review, verification of project pay item quantities, invoice review, preparing daily inspection reports, change order review, developing punch lists for the contractor, ensuring quality control and quality assurance, and assisting in public relations management.

CITY OF TORRANCE | NZA/VISTA MONTANA/PACIFIC COAST HIGHWAY INTERSECTION IMPROVEMENT

PROJECT & RESIDENTIAL & ARTERIAL PAVEMENT IMPROVEMENT
Z&K Consultants, Inc. has provided Construction Management and Construction Inspection services for a series of projects for the City of Torrance, including the 2020 Residential & Arterial Pavement Improvement Project and the Anza/Vista Montana/Pacific Coast Highway Intersection Improvements project. These projects consist of street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other. Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection.

CITY OF TORRANCE | RESIDENTIAL & ARTERIAL PAVEMENT IMPROVEMENT PROJECT, I-159/I-139 Z&K Consultants, Inc. is providing Project Management, Construction Management and Construction Inspection services for this project, which consists of pavement improvements to a residential neighborhood and four arterial streets.

Improvements include roadway and pavement rehabilitation, concrete improvements, cross gutters, curb and gutters, curb ramps, ADA improvements, clearing and grubbing, application of slurry seal, cold mill and AC overlay, removal and disposal of existing pavement, localized pavement repairs, as well as tree removals and replacements, asphalt berm replacement, AC base course, PCC sidewalk, PCC driveways and driveway approaches, access and ramps, replacing pavement markings and striping on concrete and asphalt, and installation of raised pavement markers and City project signs.

CITY OF CHINO | RAMONA AVE. AND WALNUT AVE. TRAFFIC SIGNAL MODIFICATIONS AND

STREET IMPROVEMENTS PROJECT
Z&K Consultants, Inc. has provided Construction Management and Construction Inspection services for a series of projects for the City of Chino Ramona Ave and Walnut Ave Traffic Signal Modifications Project. The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other. Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection. The scope also involved landscaping improvements, AC base course, ARHM pavement, concrete repairs to curb, gutter, sidewalk, driveways and driveway approaches, and replacing markings and striping on concrete and asphalt.

CITY OF CHINO | KIMBALL/EL PRADO/CENTRAL TRAFFIC SIGNAL IMPROVEMENT PROJECT Z&K Consultants, Inc. has provided Construction Management and Construction Inspection services for a series of projects for the City of Chino Kimball/El Prado/Central Traffic Signal Improvement Project. The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other. Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection. The scope also involved landscaping improvements, AC base course, ARHM pavement, concrete repairs to curb, gutter, sidewalk, driveways and driveway approaches, and replacing markings and striping on concrete and asphalt.

CITY OF CHINO | 11TH ST. TRAFFIC SIGNAL MODIFICAITONS, PAVEMENT RECONSTRUCTION ALLEY, AND

INTERSECTION ACCESSIBILITY PROJECT
Z&K Consultants, Inc. has provided Construction Management and Construction Inspection services for a series of projects for the City of Chino 11th Street Pavement Reconstruction Alley and Intersection Accessibility Project. The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other.

Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection. The scope also involved drainage improvements, landscaping improvements, AC base course, ARHM pavement, concrete repairs to curb, gutter, sidewalk, driveways and driveway approaches, and replacing markings and striping on concrete and asphalt.

Page 10 ends

CITY OF CHINO | EUCLID AVENUE – STATE ROUTE 83 INTERSECTION IMPROVEMENTS AND TRAFFIC SIGNAL

MODIFICATION PROJECT
Z&K Consultants, Inc. has provided Construction Management and Construction Inspection services for a series of projects for the City of Chino Euclid Ave State Route 83 Intersection Improvements and Traffic Signal Modification Project. The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other. Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection. The scope also involved drainage improvements, landscaping improvements, AC base course, ARHM pavement, concrete repairs to curb, gutter, sidewalk, driveways and driveway approaches, and replacing markings and striping on concrete and asphalt.

CITY OF SAN BERNARDINO | SECOND STREET BRIDGE OVER WARM CREEK & ROADWAY WIDENING Z&K Consultants provided Construction Management Services as a prime consultant for the Second Street Bridge Over Warm Creek. This project is located in downtown San Bernardino; this project involves construction on the 2nd Street bridge between Arrowhead and Mountain View Avenues. Overall, the project involves demolishing the existing bridge, widening sidewalk by one foot on each side, installing bridge barrier railings in conformance with AASHTO standards, street improvements, retaining walls, steel piles, pavement grinding, new asphalt concrete pavement, reinforced concrete pipe, utility relocations, and winterization of the creek. This project must comply with the Santa Ana Regional Water Quality Control Board (401 Permit), U.S. Army Corps of Engineers (404 Permit), and Department of Fish and Wildlife (1602 permit).

CITY OF CORONA | BEDFORD WASH BRIDGE AND STREET IMPROVEMENTS Z&K Consultants provided Construction Management Services as a prime consultant for the Bedford Wash Bridge. The overall site consists of approximately 508 acres located south of Eagle Glen Parkway and Cajalco Road, west of the I-15 Freeway in the City of Corona, Riverside County, California. The single span bridge structure is located roughly in the northeasterly portion of the site. The bridge spans over a newly constructed flood control channel. The project includes abutments, street improvements, a roundabout, CIDH piles, retaining walls, utility relocations, concrete barrier type 842, AC paving, cast-in-place post-tensioned girder, structure approach, drainage, signage, and landscaping. This project included permitting from the Department of Fish and Wildlife, US Army Corps of Engineers, RWQCB 401, and ADL Agreement notification.

RCTD | HAMNER AVENUE BRIDGE ROADWAY WIDENING
Z&K Consultants (Z&K) provided Construction Management services as a lead subconsultant. The project replaces the existing two-lane Hamner Avenue Bridge with a six-lane bridge, designed to the latest version of the seismic code and scour design criteria. The Z&K Team was heavily involved in both the design and construction of the River Road Bridge Replacement. The profile of the new bridge and approach roadways places the bridge structure entirely above the 100- year water surface elevation (WSE). The new bridge would include three 12-foot lanes and a 4-foot shoulder in each direction (northbound and southbound) separated by a 4-foot curbed median, and a 12-foot wide, barrier-separated multipurpose trail on the east side of the bridge. To the north of the bridge, Hamner Avenue will include three 12-foot lanes and a 4-foot shoulder in each direction along with a 5-foot sidewalk on the east side of the roadway.

COUNTY OF RIVERSIDE | RIVER ROAD BRIDGE REPLACEMENT AND ROADWAY WIDENING Z&K provided Construction Management services as a lead subconsultant which involved the construction of a new bridge, demolition of existing bridge and new approach roadways in, over, and around the Santa Ana River. The new bridge is ~20 feet higher than the existing bridge and provides an all-season crossing. The new bridge is 1200 feet long by 78 feet wide cast-in-place prestressed concrete (CIP-PS) Box Girder superstructure supported by pier walls on driven steel piles.

Abutments are supported by 5 feet diameter x90 feet deep cast-in-drilled holes (CIDH) piles. The project also included the relocation of Edison Overhead Transmission & Distribution Powerlines and fiber optic lines for the entire length of the project, construction of 30-inch sewer force main and 3×20-inch water lines, other Time Warner & AT&T Lines.

CITY OF LAKE FOREST | STREET REHABILITATION PROGRAM (THREE SEPARATE PROJECTS) The Z&K Team is providing Project Management, Construction Management, Construction Inspection, Pre-Construction Inspection, and Contract Administration Services for these projects, which involves the street resurfacing and the slurry seal. Relevant project features include street resurfacing and rehabilitation, application of slurry seal, grinding and overlay, cold milling, concrete improvements, ARHM pavement, AC base course, aggregate base, signing, striping, markings and pavement legends, removal and replacement of PCC curb ramps, removal and replacement of PCC sidewalk, bike lane traffic loops, Type E traffic loops, dig-outs, sewer and storm drain manhole adjustments, and water valves adjustments.

CITY OF COSTA MESA | CITYWIDE PARKWAY MAINTENANCE & STREET REHABILITATION PROJECT Z&K Consultants, Inc. is providing Construction Management, Construction Inspection, and Project Management Services for this citywide street improvement program in the City of Costa Mesa. This project includes street improvements, intersection improvements, ADA ramp improvements, conduit installation, traffic signal improvements, mobilization, curb and gutters, sidewalks, driveway approaches, spandrels, cross gutters, adjustment of manholes and utility covers to grade, procurement and application of slurry seal Type II, crack sealing, traffic signing, striping and markings, installation of traffic markers and speed humps, and implementation of traffic control.

Page 11 ends

CITY OF CHINO | SLURRY SEAL PROGRAM (VARIOUS LOCATIONS CITYWIDE) Z&K Consultants Inc. is providing Project Management, Construction Management, and Inspection oversight services for this Project which includes street rehabilitation and slurry seal of various streets, including, Pipeline Ave from City Limits to City Limits, Chino Ave from City Limits to City Limits and Schaefer Ave from City Limits to City Limits. Scope of work includes pavement improvements, street resurfacing, crack sealing, slurry seal, localized dig-outs, striping removal/install, and traffic loop detectors.

CITY OF ALHAMBRA | FY 19-20 & 20-21 STREET REHABILITATION PROJECTS The Z&K Team is performing Project Management, Construction Management, Construction Inspection, and Labor Compliance Services for this project, which consists of the pavement and street rehabilitation of 23 local street segments located south of Mission Road, west of Garfield Avenue, east of Atlantic Boulevard, and north of Valley Boulevard.

Improvements include street resurfacing, slurry seal treatment, varying depths of cold mill and overlay, construction staging, full depth removal and reconstruction, concrete improvements such as removal and replacement of broke and off-grade sidewalk, ADA ramps that need updating, broke and off-grade curb and gutter, PCC sidewalk, installation of loop detectors, adjustment of manhole covers and utility covers to grade, driveway aprons in need of repairs, and concrete cross gutter reconstruction. (Two Separate Projects)
CITY OF IRWINDALE | 2021-2022 RESURFACING PROJECT: RESIDENTIAL RESURFACING PHASE I Z&K provided Construction/Project Management and Inspection for this project. The project included street resurfacing, traffic control, raised crosswalks, speed humps, cold milling and AC overlay of existing asphalt concrete, construction of new curb and gutter, PCC sidewalk, installation and configuration of multiple traffic loop detectors, installation of city project signs, preservation of existing city survey monuments, adjusting manhole and utility covers to grade, installation of pavement markings and striping. Related work includes mobilization, traffic control, assisting in preparation of NPDES, local utility coordination, construction management.

CITY OF COMPTON | ANNUAL RESIDENTIAL REHABILITATION PROJECT, PHASE 1 & 2 Z&K Consultants, Inc. provided Construction/Project Management and Inspection Services for this Project. This is a street rehabilitation project of seven major City streets. Myrrh Street is CDBG funded and managed separately. The scope of work consists of asphalt overlay, clearing and grubbing, construction of cold mill and AC overlay, slurry seal application, HMA pavement, ARHM overlay, AC base course, aggregate base, full depth AC slot pavement, PCC sidewalk and pavement, PCC curb and gutters, PCC cross gutter, alley intersection, sidewalk, driveway approach, curb ramps including detectable warning surfaces, signing, striping, markings, pavement legends, speed hump, landscaping, irrigation, adjusting manhole and utility covers to grade, water valve, water meter, street lighting, installation of loop detectors and bicycle loop detectors, traffic signal modification, adjustment of streetlight and traffic signal pull boxes to grade. Z&K inspectors performed mobilization, construction staging coordination in heavily traveled intersections, traffic control, SWPPP and erosion control plan preparation. Services also included full-service construction management, pre-construction, establishing a management information system, reviewing traffic control plans, meetings, issues management, scheduling, cost control, labor compliance, reviewing RFIs and Submittals, change orders, dispute resolution, quality control/inspection, public relations, permits/environmental compliance, progress payments, monthly staff reports, site safety, as-builts drawings, final walkthrough, and project completion reports. Project was within schedule and budget.

CITY OF MORENO VALLEY | 801-0081 AND 801-0084 CITYWIDE PAVEMENT REHABILITATION PROJECTS Z&K Consultants is providing Construction Inspection Services as part of the Construction Management and Construction Inspection team for the City of Moreno Valley Citywide Pavement Rehabilitation project. The project is to rehab some of Moreno Valley City Streets as per plan, it includes cold milling to 1.5” and place 1.5” ARHM asphalt, removing and reconstructing an ADA Access ramps, inspection the grinding depth and limits, checking asphalt material mix design, assuring the ambient temperature, as well as the asphalt temperatures, are within specification.

CITY OF NORWALK | CDBG LOCAL STREETS REHABILITATION PROJECT Z&K Consultants, Inc. is providing Construction Management and Inspection services for the Local Streets Rehabilitation Project, funded by the Community Development Block Grant (CDBG) fund. The scope of work includes improvements to concrete appurtenances, including cross gutters, curb and gutters, upgrades of curb ramps to ADA standards, and intersection improvements, traffic signal improvements, bike lanes, underground utility coordination, conduit installation, and rehabilitation of roadway pavement conditions.

CITY OF ROSEMEAD | WALNUT GROVE AVE. RESURFACING PROJECT, PHASE I Z&K Consultants, Inc. is providing Project Management, Construction Management and Inspection Services for this project, which involves street resurfacing of Walnut Grove Ave., from Marshall St. to Grand Ave. in the City of Rosemead. In addition to street improvements, the project included intersection improvements, removal and replacement of existing AC pavement, cold mill and overlay, asphalt pothole repairs, replacement of PCC sidewalk, removal and replacement of ADA ramps, curb and gutter, bike lane and bike trail, traffic signal modifications, installation of medians, adjustment of manholes and utility covers to grade, installation of specialty and bicycle loop detectors, pedestrian crossings, and roadway markers.

CITY OF SAN MARINO | LIFT STATION IMPROVEMENT PROJECT, PROJECT NO. 21-8022 Z&K Consultants, Inc. is providing Project Management, Construction Management and Inspection Services for this project.

The project will perform operational and functional upgrades to the City’s sewage lift station located on Avondale Road, with potential upgrades to the City’s other two sewage lift stations (located on Orlando Rd and Monterey Rd) as additive alternates.

Page 12 ends

CLIENT REFERENCES

CITY OF CHINO
Contact Name: Michele Hindersinn, Principal Engineer
Address: 13220 Central Ave, Chino, CA 91710
Phone Number: (909) 334-3213
Email Address: [email protected]
Projects:

Ramona Ave. and Walnut Ave. Traffic Signal Modifications and Street Improvements Project; Kimball/El Prado/Central Traffic Signal Improvement Project; 11th Street Traffic Signal Modifications, Pavement Reconstruction Alley, and Intersection Accessibility Project; Euclid Avenue – State Route 83 Intersection Improvements and Traffic Signal Modification Project; Slurry Seal Program (Various Locations Citywide)
Key Staff: Zack Faqih, Tom Dawson, Brittany Duhn, & Eddie Davalos

CITY OF CARSON
Contact Name: Arlington Rodgers, Public Works Director
Address: 18620 S Broadway, Carson, CA 90248
Phone Number: (310) 847-3500
Email Address: [email protected]
Project: Citywide Pavement Rehabilitation and Slurry Seal Program Key Staff Assigned: Zack Faqih, Tom Dawson, Brittany Duhn, Eddie Davalos, & Jimmy Martin

CITY OF SAN BERNARDINO
Contact Name: Alex Qishta, PE, Former Director of Public Works Address: 290 N D St, San Bernardino, CA 92401
Phone Number: (760) 369-0801 x307
Email Address: [email protected]
Projects:

Street Improvement Program (30+ Major City Streets); Second Street Bridge Over Warm Creek & Roadway Widening
Key Staff: Zack Faqih, Tom Dawson, Brittany Duhn, Eddie Davalos, & Jimmy Martin

Page 13 ends

PROPOSED APPROACH & PERFORMANCE CRITERIA
The Z&K Team has been working diligently to understand every aspect of the project, including performing a constructability review for the City. This involvement provides us with a deeper understanding of the challenges and the key elements that the project may be facing and familiarity with the site and stakeholders. This knowledge and preliminary legwork will help us to hit the ground running and help the contractor understand the project better, preventing possible issues. Our Team has the ability, capacity, and skill to perform the contract and effectuate the work. We understand the project construction scope of work includes, but is not limited to the following: mobilization; traffic control and construction signage; removal and replacement of concrete curb and gutter, concrete cross gutter and concrete driveway approaches; installation of ADA compliant curb ramps; clearing and grubbing; removal and preparation of native subgrade materials; removal and disposal of Macadam base materials; localized pavement repairs; construction of cold-milling asphalt concrete pavement and overlay with hot mix asphalt (HMA); surface reconstruction; full reconstruction; removal and restoration of traffic markings and striping; painting curb house numbering and curb face painting.

The City's Parks and Public Works Department is responsible for the maintenance and repair of 59.8 centerline miles of public streets, including 21.4 miles of arterial streets, 5.6 miles of collector streets and 32.9 miles of local streets. The Department is also responsible for the maintenance and repair of 12 parking lots and 22 alleyways. The Project is a citywide roadway pavement rehabilitation project consisting of 26 segments of on various residential, collector, and arterial streets throughout the City of San Marino with a PCI of 53 or below.

We understand that the Project will be advertised for construction bid in May 2024 with construction anticipated to begin in Summer 2024 and be completed within 90 working days.

CAPITAL IMPROVEMENT PROGRAM | Since 2018 the City has completed an annual street rehabilitation project as part of its overall Street Rehabilitation Program. The goal of the Council-adopted Pavement Management Plan is to move the City to a maintenance-only footing by 2032. The annual project helps improve resident and pedestrian safety by improving the condition of the streets.

CONSTRUCTABILITY REVIEW & LESSONS LEARNED | The Z&K Team has been working diligently to understand every aspect of the project. We provided a constructability review to the City to integrate improvements to the plans prior to bidding. We reviewed the plans, specifications, and cost estimate provided by the City. We were pleased to see that many of the comments and lessons learned that we had on previous projects were addressed and implemented by NCE. Our comments are a follows:

Z&K thoroughly reviewed the plans and specifications and recommend adding language for the following items:
• Clarify all trucking routes with City approval prior to starting any asphalt removals / dig outs and prior to any slurry sealing or asphalt placement.
• Contractor will use a flagman / overwatch for all trucks operating in the vicinity of any trees. The flagman will monitor all trucks to ensure that raising or lowering truck beds do not come in contact with existing trees and do not damage trees.
• Contractor shall not perform truck operations where existing trees are in the vicinity of trucks without the supervision of the Inspector to ensure no trees are damaged during construction activities.

Z&K is recommending the following language revisions:

Inspector will video all adjacent intersections and approved trucking routes prior to asphalt operations to memorialize all adjacent streets and all striping for asphalt tracking and damage to striping.

This is included in the Plans (Sheet 2 of 7), General Notes Item 12 includes “The Contractor shall restore any and all pavement and other facilities outside limits of work affected by the construction operations at no additional cost.

It is the Contractor’s responsibility to videotape or document existing conditions prior to start of work to substantiate any previous damage; copies of which shall be provided to the Engineer.

We recommend revising this to the following and also adding it to the specifications. “The Contractor shall restore any and all pavement and other facilities outside limits of work affected by the construction operations at no additional cost. It is the Contractor’s responsibility to videotape or document existing conditions prior to start of work to substantiate any previous damage; copies of which shall be provided to the Engineer for approval.

We recommend updating the following section:
3-5.1.7 Curb Ramps | 3. Prior to the start of construction, the Contractor shall provide all required construction surveying and layout work for installation of an ADA-compliant curb ramp including ADA-compliant slopes. The construction surveying and layout work shall be reviewed by the Engineer and Construction Manager. The Plans note an assumed Caltrans Standard Plan installation “Case” for each location, but it shall be the Contractor’s responsibility to coordinate with the Engineer and Construction Manager to field fit the curb ramp installation and the Engineer shall make a final determination as to a suitable ramp “Case”. (TP-18)

7. In the case the Contractor believes it is not technically feasible to develop an ADA-compliant curb ramp, the Contractor shall note the site design exceptions and furnish to the Engineer the best fit layout for approval in writing prior to demolition of the existing improvements and layout of the new curb ramp. (TP-19) [REPLACE WITH]

Page 14 ends

7. In the case the Contractor believes it is not technically feasible to develop an ADA-compliant curb ramp per the standard Caltrans cases, the ramps shall be laid out and modified to fit field conditions with the Engineer and Construction Manager to achieve ADA compliant slopes.

In Addition to adhering to the American Public Works Association “Tree Protection & Preservation.” (TP-23) and Section 400-1.2.9 Excavation (TP-25), Contractor shall be responsible for conducting a tree inspection and survey with the City Arborist and inspector prior to any construction activity to ascertain if any trees need to be trimmed for truck access below 14 feet and to ensure any tree or tree root removal has been reviewed and approved. Any tree root removal will be under the direct supervision of the City Arborist.

Any trees damaged by the contractor or any subcontractors will be evaluated for restoration as well as monetary fines to the contractor. Any tree repairs and/or damage shall be reviewed and approved by the City Arborist. Add that language to the following section:
400-1.2.13 Repair and Replacement

1. General: Repair or replace trees, shrubs and other vegetation damaged by construction operations within 1 working day.

2. Trees: Remove and replace trees indicated to remain that are more than 25-percent dead or in unhealthy condition damaged by construction operations.
a. Provide new trees of the same size and species.

3. Soil Aeration: Aerate surface soil compacted during construction 10-ft. beyond dripline and no closer than 3-ft. from tree trunk.

Below are important items to note that were already added to the specifications from lessons learned from previous projects.

Contractor will be required to use non-tracking tack and use a water truck during all asphalt and slurry operations to prevent asphalt tracking to adjacent streets.

16. Tack Coat. The Contractor shall place trackless tack coat on all cold-milled surfaces to be paved, between HMA or ARHM lifts, and against all AC or PCC vertical surfaces against which new HMA or ARHM is to be placed. Tack coat shall be applied at a uniform rate of 0.05 to 0.10 gallons per square yard. (TP-15)

13. Watering of area to prevent tracking of material will be allowed if no water enters the storm drain system and the Contractor adheres to all local and state water quality regulations, and these Contract Documents. (TP-14) Concrete replacement will adhere to the City concrete color guides for all curbs, gutters and sidewalks. c. Color shall match existing and shall be “Half Fawn”, using an integral concrete colorant. Contractor shall submit a color sample to the City for approval prior to ordering materials. (TP-6) Any concrete curbs / gutters removed and replaced will require the replacement completed without standing water and water drainage with a running water test approved by the inspector.

4. Prior to demolition of any PCC driveway approach associated with a curb and gutter repair, the Contractor shall perform a field survey taking adequate measurements of the existing driveway approach including but not limited to measurement of the existing longitudinal and cross (transverse) slope and flowline slope, or sufficient spot elevations to determine these slopes. (TP-17)
3-12.3 Noise Control

1. A noise level limit of 65 dbA at a distance of 50 feet shall apply to all construction equipment on jobsite regardless of ownership. Use of excessively loud warning signals shall be avoided except in cases required for personnel protection.
300-2 Unclassified Excavation
a. Macadam Base: Macadam base pavement exists in localized areas within the project site. The project plans indicate where macadam base was encountered during preliminary pavement coring and the approximate thickness of macadam base. However, the location and thickness of existing macadam base may not be consistent throughout the project site. The work for removal and disposal of macadam base shall be included in the Contractor’s bid price for unclassified excavation and remove surfacing and base.

SCHEDULE & CLAIMS
Our Team has won several binding arbitrations on behalf of our clients for issues ranging from concurrent time delay claims, loss of production claims, differing site condition claims, rock claims, and defective concrete. We have served as an Expert Witness for underground claims and scheduling issues. Our construction support services team gives considerable attention to monitoring project schedules. We will coordinate, review and make recommendations for changes to the Critical Path Method (CPM) schedule generated by the contractor. As changes or discrepancies occur between the CPM schedule and as-built conditions, the project schedule and cost estimates will be updated. We will review the contractor's schedule on a weekly basis. We will track critical milestones, and if the contractor has missed or is tracking to miss a particular milestone, we will work closely with the contractor to formulate a recovery plan so as to minimize any potential impacts. Finally, we will maintain our own as-built schedule, typically on P3 or MS Project platform, reflecting actual durations and completion dates.

We have found this to be a very powerful tool in any potential schedule claims made by the contractor. Indeed, it saves our team from having to reconstruct actual timelines forensically (from inspection reports or inspector diaries).

Page 15 ends

PRELIMINARY SCHEDULE
We have prepared a draft construction schedule below.

Activity ID Activity Name Original Duration Start Finish SMPR CI SMPR CITY OF SAN MARINO - STREET REHABILITATION PROGRAM 90 17-Jun-24 22-Oct-24 SMPR.3 SMPR.3 ADMINSTRATION A 90 17-Jun-24 22-Oct-24
SMPR.3.1 NTP CONTRACT MILESTONES 90 17-Jun-24 22-Oct-24 C1005 CONSTRUCTION NTP - PROPOSED CONTRACT DURATION 90 WORKING DAYS 90 17-Jun-24* 22-Oct-24 C1015 CONSTRUCTION START DATE NTP JUNE 17, 2024 0 17-Jun-24* SMPR.3.2 PREPARE/SUBMIT/REVIEW SUBMITTALS 0 17-Jun-24 17-Jun-24 A1035 CONSTRUCTION SCHEDULE 0 17-Jun-24*
A1036 NOTIFICATION TO RESIDENTS 0 17-Jun-24*
A1120 CONCRETE MIX DESIGNS 0 17-Jun-24*
A1130 AC MIX DESIGNS 0 17-Jun-24*
A1140 SIGNING, STRIPING AND CURB PAINTING 0 17-Jun-24*
SMPR.11 SMPR.11 CONSTRUCTION 82 17-Jun-24 10-Oct-24
A1410 MOBILIZATION 5 17-Jun-24* 21-Jun-24
SMPR.11.2 CONCRETE IMPROVEMENTS 1 28 24-Jun-24 01-Aug-24 A1420 REMOVE AND REPLACE CURB AND GUTTER 26 24-Jun-24* 30-Jul-24 A1430 REMOVE AND REPLACE CONCRETE DRIVEWAYS 9 24-Jun-24 05-Jul-24 A1450 REMOVE AND REPLACE CURB RAMPS AND CROSS GUTTER 28 24-Jun-24 01-Aug-24 SMPR.11.3 AC IMPROVEMENTS 1 24 02-Aug-24 05-Sep-24
SMPR.11.3.1 STREET SEGMENTS 2,3,9, 10 R 3 02-Aug-24 06-Aug-24 A1540 ORLANDO SEG 10 REMOVE AND INSTALL 2" ARHM 1 02-Aug-24 02-Aug-24 A1600 ORLANDO SEG 9 REMOVE AND INSTALL 2" ARHM 1 05-Aug-24 05-Aug-24 A1610 LOMBARDY SEG 2&3 REMOVE AND INSTALL 2.5" ARHM 1 06-Aug-24 06-Aug-24 SMPR.11.3.3 STREET SEGMENTS 7,8,22 R 9 07-Aug-24 19-Aug-24 A1620 ORLANDO RD SEG 7 & 8 REMOVE 4" INSTALL 4" 5 07-Aug-24 13-Aug-24 A1630 OXFORD SEG 22 RD REMOVE 3.5" INSTALL 3.5" 4 14-Aug-24 19-Aug-24 SMPR.11.3.2 STREET SEGMENTS 15,13,6 R 3 20-Aug-24 22-Aug-24 A1550 ASHBOURNE SEG 15 REMOVE 2 INSTALL 2" ARHM 1 20-Aug-24 20-Aug-24 A1560 OLD MILL RD SEG 6 REMOVE 4 " INSTALL 2" HMA 1 21-Aug-24 21-Aug-24 A1570 URMSTROM PL SEG 13 REMOVE 4" INSTALL 2" HMA 1 21-Aug-24 21-Aug-24 A1580 OLD MILL RD SEG 6 INSTALL 2" ARHM 1 22-Aug-24 22-Aug-24 A1590 URMSTROM PL SEG 13 INSTALL 2" ARHM 1 22-Aug-24 22-Aug-24 SMPR.11.3.4 STREET SEGMENTS 4 & 14 R 2 23-Aug-24 26-Aug-24 A1645 MESA RD SEG 4 REMOVE 2.5" INSTALL 2.5" ARHM 1 23-Aug-24 23-Aug-24 A1650 ST ALBANS SEG 14 REMOVE 4" INSTALL 2" HMA 2 23-Aug-24 26-Aug-24 SMPR.11.3.5 STREET SEGMENTS 16,17,23 R 2 27-Aug-24 28-Aug-24 A1660 CANTEBURY RD SEG 16 REMOVE 2" INSTALL 3" 2 27-Aug-24 28-Aug-24 A1670 CHAUCER RD SEG 17 REMOVE 3.5" INSTALL 3.5" 2 27-Aug-24 28-Aug-24 A1680 RALEIGH DR SEG 23 REMOVE 5" INSTALL 5" 2 27-Aug-24 28-Aug-24 SMPR.11.3.6 STREET SEGMENTS 1 R 2 29-Aug-24 30-Aug-24
A1690 DEL MAR AVE SEG 1 REMOVE 4.5" INSTALL 4.5" 2 29-Aug-24 30-Aug-24 SMPR.11.3.7 STREET SEGMENTS 11,12,24,25,26 R 3 03-Sep-24 05-Sep-24 A1700 ROANOKE RD SEG 11 REMOVE 5.5" INSTALL 5.5" 2 03-Sep-24 04-Sep-24 A1710 ROANOKE RD SEG 12 REMOVE 4" INSTALL 4" 2 03-Sep-24 04-Sep-24 A1720 SHERWOOD RD SEG 24,25,26 REMOVE 2.5" INSTALL 2.5" 1 05-Sep-24 05-Sep-24 SMPR.11.8 STRIPING AND PUNCHLIST 1 25 06-Sep-24 10-Oct-24 A1490 LAYOUT AND STRIPING, CURB MARKINGS 15 06-Sep-24 26-Sep-24 A1530 PUNCHLIST 10 27-Sep-24 10-Oct-24
Jul Aug Sep Oct Nov Dec
2024
22-Oct-24, SMPR CITY OF SAN MARINO - STREET REHABILITATION PROGRAM 22-Oct-24, SMPR.3 ADMINSTRATION
22-Oct-24, SMPR.3.1 NTP CONTRACT MILESTONES
CONSTRUCTION NTP - PROPOSED CONTRACT DURATION 90 WORKING DAYS CONSTRUCTION START DATE NTP JUNE 17, 2024, 17-Jun-24*
17-Jun-24, SMPR.3.2 PREPARE/SUBMIT/REVIEW SUBMITTALS
CONSTRUCTION SCHEDULE, 17-Jun-24*
NOTIFICATION TO RESIDENTS, 17-Jun-24*
CONCRETE MIX DESIGNS, 17-Jun-24*
AC MIX DESIGNS, 17-Jun-24*
SIGNING, STRIPING AND CURB PAINTING, 17-Jun-24*
10-Oct-24, SMPR.11 CONSTRUCTION

MOBILIZATION
01-Aug-24, SMPR.11.2 CONCRETE IMPROVEMENTS

REMOVE AND REPLACE CURB AND GUTTER

REMOVE AND REPLACE CONCRETE DRIVEWAYS

REMOVE AND REPLACE CURB RAMPS AND CROSS GUTTER
05-Sep-24, SMPR.11.3 AC IMPROVEMENTS
06-Aug-24, SMPR.11.3.1 STREET SEGMENTS 2,3,9, 10
ORLANDO SEG 10 REMOVE AND INSTALL 2" ARHM
ORLANDO SEG 9 REMOVE AND INSTALL 2" ARHM
LOMBARDY SEG 2&3 REMOVE AND INSTALL 2.5" ARHM
19-Aug-24, SMPR.11.3.3 STREET SEGMENTS 7,8,22
ORLANDO RD SEG 7 & 8 REMOVE 4" INSTALL 4"
OXFORD SEG 22 RD REMOVE 3.5" INSTALL 3.5"
22-Aug-24, SMPR.11.3.2 STREET SEGMENTS 15,13,6
ASHBOURNE SEG 15 REMOVE 2 INSTALL 2" ARHM
OLD MILL RD SEG 6 REMOVE 4 " INSTALL 2" HMA
URMSTROM PL SEG 13 REMOVE 4" INSTALL 2" HMA
OLD MILL RD SEG 6 INSTALL 2" ARHM
URMSTROM PL SEG 13 INSTALL 2" ARHM
26-Aug-24, SMPR.11.3.4 STREET SEGMENTS 4 & 14
MESA RD SEG 4 REMOVE 2.5" INSTALL 2.5" ARHM
ST ALBANS SEG 14 REMOVE 4" INSTALL 2" HMA
28-Aug-24, SMPR.11.3.5 STREET SEGMENTS 16,17,23
CANTEBURY RD SEG 16 REMOVE 2" INSTALL 3"
CHAUCER RD SEG 17 REMOVE 3.5" INSTALL 3.5"
RALEIGH DR SEG 23 REMOVE 5" INSTALL 5"
30-Aug-24, SMPR.11.3.6 STREET SEGMENTS 1
DEL MAR AVE SEG 1 REMOVE 4.5" INSTALL 4.5"
05-Sep-24, SMPR.11.3.7 STREET SEGMENTS 11,12,24,25,26
ROANOKE RD SEG 11 REMOVE 5.5" INSTALL 5.5"
ROANOKE RD SEG 12 REMOVE 4" INSTALL 4"
SHERWOOD RD SEG 24,25,26 REMOVE 2.5" INSTALL 2.5"
10-Oct-24, SMPR.11.8 STRIPING AND PUNCHLIST

LAYOUT AND STRIPING, CURB MARKINGS

PUNCHLIST

CITY OF SAN MARINO STREET REHABILITATION PROGRAM
PROJECT NO 22/23-9271
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work
Milestone
summary

Page 16 ends

MANAGEMENT APPROACH
The team proposed on this project have over 25 years of experience in construction management and construction inspection. We have successfully utilized CM Agency delivery on a host of projects. Through this experience we have developed project management procedures that promote collaboration and teamwork, improve quality and maximize the value of the above project. Z&K’s past performance with Cities, Counties, and other agencies show our remarkable ability to control costs, guarantee great quality of work, and meet all project deadlines.

We understand the importance of Schedule Control and are known in the industry for assisting the contractor to cut the project schedule and to yield significant savings for our clients through reduction of overhead construction management and construction costs. The most significant saving is less inconvenience to the traveling public and less City exposure due to shortened construction duration. This will help extend excess project funds into other important projects.

Z&K Consultants, Inc. provides proven professional construction management techniques to ensure the safe construction of a quality project completed on time and within budget. Z&K accomplished this by establishing the systems, policies, and procedures necessary to ensure adequate project controls are in place. The Construction Manager must ensure all parties understand the basic responsibilities and interrelationships of all team member such as the Owner (both project management and operations), the Design Engineer, the Contractor, and the construction management team. Additionally, a good Construction Manager must have the knowledge and experience to effectively understand the interrelationships between the key management components of time, information, cost, and quality. Decision making, including obtaining sufficient information to make reasoned decisions, is the key element leading to a successful project. the project. The Z&K approach is founded on a thorough understanding of each of the management components critical to the project.

TIME MANAGEMENT | Time management uses scheduling to accurately manage and track the restrictive elements of time and resources throughout the project. The key to a successfully implemented and managed schedule is the development of an accurate, detailed, and realistic baseline schedule. Z&K will review the Contractor’s baseline schedule to ensure it is accurate and reasonable. Activity durations and logic ties will be examined for accuracy and constructability.

The schedule logic and activity durations will also be analyzed to ensure the Contractor does not use float suppression techniques. Schedule float is a valuable resource for the Owner and the Contractor.

Schedule implementation and administration is the next step in proper time management. The Contractor’s actual progress will be documented daily. The Z&K Team will review the progress with the Contractor at the weekly meetings. The Contractor’s three-week-look-ahead schedule will be compared with the work plan on the record schedule to ensure the Contractor continues to use the record schedule as a management tool. We will check the record schedule for activities with start dates that did not begin during the review period. This proactive approach flags potential delay issues for further discussion.

COST MANAGEMENT | Z&K will take the lead to ensure a cost management system is properly implemented and maintained. Z&K’s cost management role will be in two parts. The first is to track the value of the completed work to ensure accurate and detailed monthly progress billing by the contractor. Secondly, Z&K will proactively manage the change order process. The monthly progress billing may be tied to the construction schedule. A cost loaded critical path method (CPM) schedule is a valuable management tool. Each month, the Construction Inspector will review and approve the updated cost loaded CPM. Work activities and material deliveries will be assigned the correct completion percentage by the Contractor.

This will be reviewed by the Construction Inspector and discrepancies will be addressed.

If necessary, the Contractor will revise and resubmit the schedule of values. This process ensures the Owner is accurately billed for the completed work monthly. Changes in work and unforeseen conditions will be closely monitored. Any costs for changes will be managed by the Z&K construction management team. An ongoing log of potential change issues will be maintained. These issues will be discussed and updated at each weekly meeting.

FUNDING MANAGEMENT | Z&K will ensure that the City has all necessary information to comply with the funding requirements. Our team is experienced in complying with funding reporting and filing requirements. We pay close attention to these requirements and deadlines so that project funding remains unaffected and so that file audits are conducted quickly and efficiently. Our team is also experienced in ensuring that project documents show compliance with DBE reporting requirements, DBE goals, and/or good faith effort documented. Proper Project documentation is key in any audits.

QUALITY MANAGEMENT | Quality management is an inherent CM responsibility. Z&K is knowledgeable and capable in all aspects of quality management. Quality assurance is the application of systematic methods to verify the effective implementation of quality control procedures. Z&K will manage the quality of the project by taking the quality assurance lead role and implementing the Z&K quality assurance program, which allocates quality control responsibilities to the various project participants to ensure the constructed product conforms to the contract plans and specifications. This includes a detailed inspection plan, inspection procedures, and documentation procedures for all inspection and test reports. Z&K will review the Contractor’s quality control procedures to ensure adequacy. Quality control issues will be discussed at each weekly meeting. An ongoing deficiencies/corrective items list will be maintained, reviewed, and updated weekly.

Quality assurance includes quality of the constructed work as well as the quality of the Contractor’s document processes (such as the Contractor’s submittals and RFIs). In Z&K’s experience, lack of quality in the paperwork with items such as poor submittals and unanswered RFIs may lead to lack of quality in the constructed product. Deficiencies in submittal quality control by the Contractor often leads to incorrect or inferior equipment and materials being installed. Z&K will be proactive with the Contractor to ensure the quality of their submittals. Likewise, lax procedures for the processing of RFIs may lead to misunderstandings and delays.

Page 17 ends

Z&K will take a proactive approach with the Contractor and the Design Engineer to ensure the quality of the RFI process is maintained. Finally, Z&K regularly performs internal audits of its field operations to ensure the proper implementation of procedures for Z&K’s quality assurance program.

INFORMATION MANAGEMENT | Proper information flow is crucial to the success of a project. A construction project generates a large amount of information, which must be distributed to all parties on a timely basis. The source of this information will cover the full spectrum including contracts, meeting minutes, drawings and specifications, submittals, requests for information (RFIs), pay requests, invoices, inspection reports, and so forth. Z&K, as CM, will act as the hub for the management of all information flow. Z&K has extensive experience providing document management solutions for its clients. Z&K’s approach to information management also includes building a communication framework to continually foster partnering and teamwork relationships for all the project stakeholders. Z&K builds this framework from the start of the project with an all-inclusive kick-off meeting where the lines of communication and project responsibilities will be clearly explained to all the project stakeholders.

The emphasis on project communication continues throughout the project with the weekly construction meetings. At each weekly meeting, all ongoing issues will be reviewed and discussed. All project stakeholders will be invited to the meetings.

An agenda of meeting topics will be distributed in advance and include items such as safety, old business, updated progress of the work, RFIs, submittals, testing and inspection reports, non-conformance notices, environmental monitoring, change orders, three-week-look-ahead schedule, pay requests, and so forth. Unresolved issues will be carried over to the next week’s meeting until a final resolution is obtained.

CODES & PROCEDURES MANAGEMENT | Z&K has a strong knowledge of the City, County, State, and Federal codes and procedures that are required to deliver a successful project. Z&K will ensure that all codes and procedures are properly followed for the City’s Project.

Some of the requirements are as follows:
o Project Construction Documents
o City Standards and Design Manuals
o California Building Code
o California Plumbing Code
o California Mechanical Code
o California Electrical Code
o California Building Energy Efficiency Standards
o Title 24, Part 2, 2.5, 3, 4, 5, 6, 11
o California Fire Code
o California Residential Code
o California Green Building Code
o California Disabled Regulations
o City Codes & Ordinances
o City Grading Code & Manual
o APWA “Greenbook” Standard Specifications for
Public Works Construction
o Caltrans Standards, Specifications, and
Procedures
o Caltrans Construction Manual
o Caltrans Safety Manual
o OSHA Construction Safety
Orders
o 10/30-hr OSHA Training
Certification
o Local Assistance Procedures
Manual (LAPM)
o State and Federal Building Codes (Site
Accessibility)
o County Procedures and Guidelines
o Work Area Traffic Control Handbook (WATCH)
Manual
o Manual of Uniform Traffic Control Devices
(MUTCD)
o Project Safety Plan (PSP)
o Site Health and Safety Plan
o Activity Hazard Analysis (AHA)

SCOPE OF SERVICES
Our Team’s relevant experience allows them to provide overall administration of the construction process based on their unique ability to fully understand the construction process, work proactively to identify problems early, and to mitigate each risk before it affects the project performance goals. Z&K has thoroughly reviewed the RFP; we confirmed our team will provide all scope of work tasks as outlined in the RFP scope of services. The Z&K Team will provide excellent Construction Inspection, services for the City of San Marino’s Street Rehabilitation Program. Z&K acknowledges our ability to meet the contract requirements for the work listed under the scope of services, along with any additional services that the City should require. The Z&K Team, at a minimum, will perform the following:

PRE-CONSTRUCTION PHASE
Preconstruction Conference | Z&K will schedule, coordinate, and conduct a pre-construction conference with the City, affected agencies, and the Contractor, as well as the design engineer, utilities and other agencies. An agenda will be prepared in advance to notify attendees of key items for discussion. At the pre-construction conference, we will discuss special contract and/or concerns, and establish the protocol to be used throughout the project. The meeting will highlight the contractor’s responsibility for items such as order of work, permit and environmental agreements, safety and access, progress pay requests, labor compliance, submittals, RFIs, CCOs, quality control, materials certification, schedule updates, and weekly meetings. Z&K will review the baseline schedule and verify that it meets all the required information prior to issuing the Notice to Proceed to the Contractor. Z&K will prepare and promptly distribute meeting minutes to all attendees.

Z&K has carefully selected this "A-Team" of and committed our most qualified staff for the duration of the contract to deliver a successful project. All assigned Z&K Inspectors and Construction Managers are committed to provide their services at all times required by the contract. Our proposed personnel have successfully provided construction management and inspection for a variety of projects. The Z&K Inspectors are on site daily to observe construction operations and materials and compare them with the project plans and specifications.

Page 18 ends

CONSTRUCTION PHASE
Construction Inspection Services | Z&K Inspectors have experience providing inspection services for numerous capital improvement projects, including storm drain and pipeline relocations, street improvements, traffic signal improvements, roadway widenings, striping, traffic control, and utility protection, and are well aware of how important project quality control is to the overall success of a project. Throughout each project, the inspectors will review contract documents, plans, and permits. Inspectors will monitor and enforce construction noticing requirements. The Z&K Inspectors will use their expertise to provide field conflict resolutions. The Inspectors’ primary duties will be to inspect and verify all work in place meets the requirements of the contract plans and specifications, traffic control plans, shop drawings, change orders, and O&M manuals as well as maintenance of project documentation. In addition to the construction activities, the project team must also review and enforce the requirements stipulated in the permits issued by regulatory and environmental agencies. Our team has extensive experience with working with the State Department of Fish and Wildlife, Department of Water Resources, and other state and federal agencies that may have input on the project.

Z&K Inspectors have the knowledge, skill, and experience to inspect all the anticipated construction operations that this contract may require. Inspectors will verify that all work in place meets the requirements of the contract plans and specifications, traffic control plans, shop drawings, change orders, and O&M manuals as well as maintenance of project documentation. Z&K will verify that all work conforms with the requirements and identify any issues of non-compliance with the applicable codes. Inspectors will meet with the project design team and City staff to work out any issues and resolve them quickly and efficiently. Z&K proposed staff will complete daily reports, including equipment, crews/personnel, and photos (before, during and after construction). The Construction Manager will review the inspectors’ daily reports and provide copies to the City upon project completion.

Z&K will review the contractor’s work for compliance with contract and environmental documents. Z&K will perform labor compliance tasks as needed, including verifying certified payroll reports, DBE utilization, subcontractor utilization, and labor interviews. Z&K will review the contractor’s submittals for compliance with contract documents. Z&K will review the contractor’s RFIs and either provide information from contract documents or route the request to the Engineer for resolution.

Z&K will review the contractor’s pay requests and recommendations to the City as to the acceptability of the requests.

Schedule Control | The Z&K Team will review and monitor the Contractor’s schedule and evaluate work in progress each week. All findings that may require enforcement or corrective actions will be reported to the City for consideration. These weekly work in progress status updates will be reflected in the master project schedule. Z&K will regularly update this schedule to reflect construction progress and provide updates on anticipated closure, detours, etc. The Team will also provide updates to the City on any other pertinent project information affecting the construction schedule. This update will show current conditions and revisions required by actual progress.

Daily Documentation | The Z&K proposed staff will complete and maintain field file bound workbooks including daily, weekly, and monthly reports logging any working day reports, change order documentation, equipment on site, crews/personnel, and photographs (before, during and after construction). A monthly Construction Manager progress report will include an overview of work accomplished during the previous month, an overview of work to be accomplished the following month, an updated schedule (based on the Contractor’s schedule of values), a list of problem areas, if any, and proposed corrective actions, and a bar graph comparing the monthly and cumulative invoiced amounts with the total authorized CM budget. These reports will be submitted via email and/or hardcopy.

Utility Coordination | The Z&K Team will provide ongoing coordination with public utilities to resolve any questions or conflicts, and to avoid any potential delays or additional costs to the project. Any conflicts with utilities will be reported to the utility company and Z&K will work to coordinate the relocation or removal of the utility. The resolution will be reported to the City. Our team will ensure that the Contractor is aware of all existing underground utilities by ensuring that Dig Alert tickets are current and up to date prior to excavation. We will keep track of hazardous and non-hazardous and conflicting utilities during our progress meetings. Additionally, we will communicate with utilities early since various utilities may need to be adjusted by the Owner and require utility coordination.

Communication | Z&K will establish coordination and a line of communication to be used among participants throughout the project. Our Construction Manager, Zack Faqih, PE will serve as the City’s representative in charge of project communication and coordination with Z&K, City staff, the design engineer, and the contractor throughout the construction phase. Z&K will document all necessary communications throughout the project and will ensure that all questions and inquiries are fulfilled in a timely manner. The emphasis on project communication continues throughout the project with the weekly construction meetings. At each weekly meeting, all ongoing issues will be reviewed and discussed. All project stakeholders will be invited to the weekly meeting. An agenda of meeting topics will be distributed in advance and include items such as safety, old business, updated progress of the work, request for information (RFIs), submittals, testing and inspection reports, non-conformance notices, contract issues, procedures, environmental monitoring, change orders (COs), look-ahead schedule for upcoming work, pay requests, and so forth. Unresolved issues will be carried over to the next week’s meeting until a final resolution is obtained. Z&K will prepare and promptly distribute meeting minutes.

Page 19 ends

Constructability Review | The Z&K Team is aware that prompt constructability reviews and implementation of value engineering methods allow for cost and schedule savings. Upon notice-to-proceed (NTP), the Z&K Team will conduct a thorough constructability review that will focus on anticipating issues in the field and resolve them through fast and flexible problem solving. This approach will result in timely completion of the work, claims avoidance, and the reduction of public inconvenience. The Z&K Team will maintain a master project schedule to include all completed and scheduled work. Z&K will provide updates on anticipated closure, detours, etc. The Team will also provide updates to the City on construction progress and any other pertinent project information.

Public Outreach | Z&K will assist the City in providing concierge-level services to impacted residents as it relates to their access into and out of their property, noise, dust, and general disruption to the neighborhood. Z&K will form and maintain good relations with residents and businesses in surrounding neighborhood by providing community outreach and a contact person to manage public relations for the duration of the project. At a minimum, the Z&K team will establish and manage a construction 24-hour hotline (toll free number), website, and email address for project stakeholders, property owners, interested parties, and the public to call with construction issues and concerns. All calls and public complaints will be documented and investigated, and a monthly report will be provided to the City.

Permitting Requirements | Throughout the project, the inspectors will review all required federal and state forms, permitting requirements, agency requirements, local regulations, and any other contract documents or plans to ensure the project’s compliance. Inspectors will monitor and enforce construction noticing requirements. The Inspectors’ primary duties will be to inspect and verify all work in place meets the requirements of the contract plans and specifications, traffic control plans, shop drawings, change orders, and O&M manuals as well as maintenance of project documentation. In addition to the construction activities, the project team must also review and enforce the requirements stipulated in the permits issued by any regulatory and environmental agencies involved in the project. Our team has extensive experience with working with the State Department of Fish and Wildlife, Department of Water Resources, and other state and federal agencies that may have input on the project.

Critical Path Method Schedule | The Team will review the Contractor’s critical path method schedule to monitor the project progress, define the critical path tasks, and provide, on a monthly basis, an update of accomplishments and projected project schedule goals for the following month. We will check the schedule for activities with start dates that did not begin during the review period. This proactive approach flags potential delay issues for further discussion. The Z&K Team has extensive experience in dealing with changes from unforeseen conditions, owner-initiated changes, and other types of delays. The Contractor will be required to submit a time impact analysis for any issue with the potential to delay the overall progress of the work. Z&K will mitigate the delay as the first course of action Weekly Progress Meetings | Z&K will schedule, coordinate, and conduct weekly construction meetings with City representatives, contractors, and other agencies related to the project. At each weekly meeting, all ongoing issues will be reviewed and discussed. All project stakeholders will be invited to the weekly meeting. An agenda of meeting topics will be distributed in advance and include items such as safety, old business, updated progress of the work, request for information (RFIs), submittals, testing and inspection reports, non-conformance notices, contract issues, procedures, environmental monitoring, change orders (COs), look-ahead schedule for upcoming work, pay requests, and so forth. Unresolved issues will be carried over to the next week’s meeting until a final resolution is obtained. Z&K will prepare and promptly distribute meeting minutes to all attendees.

Safety Compliance | Z&K Consultants take extreme pride for being a very safety conscious organization implementing a safe environment both in our offices and on our project sites. We monitor the Contractor and their subcontractors for safety compliance for meeting local, state, and federal safety requirements. We also ensure the trades and the Contractor are always safety conscious in everything they do in the Project. Z&K will review the Contractor’s compliance with workplace safety and health standards and notify the City of non-compliance. The Z&K Team is knowledgeable with the Caltrans Safety Manual and the Cal/OSHA Construction Safety Orders. The Inspectors will attend the Contractor’s Safety Meetings and promote safety throughout the life of our contract. Z&K will review, monitor, document and enforce contractor safety procedures for compliance with all safety laws and regulations. If any safety violations occur, Z&K will take immediate action to correct the issue and report any incidents to the City. All Z&K staff will observe construction safety, public safety and convenience. Z&K Inspection staff is knowledgeable with the Caltrans Safety Manual and the OSHA Construction Safety Orders.

Progress Payments | The Z&K staff bring a detailed understanding of the City processes for administering Contractor progress payments per the City’s standards & procedures. We will work closely under the direction of the City and with the contractor to verify that the contractor’s payments are processed, provide recommendations, and ensure they are executed promptly by the contract documents and City’s procedures. Z&K will reconcile the work done with the pay requests. Z&K will work with the Contractor on required corrections to the pay requests and ensure that they are in the format and forms required by the City. The pay requests will be submitted to the City with a statement that they have been reviewed. Z&K will keep accounts of all pay requests including amounts retained, dates submitted, dates paid, actual payments, changes in contract amounts, and any other pertinent information.

Page 20 ends

Document Control | Quality assurance includes quality of the constructed work as well as the quality of the Contractor’s document processes (such as the Contractor’s submittals and RFIs). In Z&K’s experience, lack of quality in the paperwork with items such as poor submittals and unanswered RFIs may lead to lack of quality in the constructed product. Deficiencies in submittal quality control by the Contractor often leads to incorrect or inferior equipment and materials being installed. Z&K will be proactive with the Contractor to ensure the quality of their submittals. Likewise, lax procedures for the processing of RFIs may lead to misunderstandings and delays. The Z&K CM will take a proactive approach with the Contractor and the Design Engineer to ensure the quality of the RFI process is maintained. Finally, Z&K regularly performs internal audits of its field operations to ensure the proper implementation of procedures for Z&K’s quality assurance program.

Z&K will ensure that the City complies with federal and state reporting requirements. Our team is experienced in complying with both state and federal grant reporting and filing requirements. We pay close attention to these requirements and deadlines so that project funding remains unaffected and so that file audits are conducted quickly and efficiently. Our team is also experienced in ensuring that project documents show compliance with DBE reporting requirements, DBE goals, and/or good faith effort documented. Z&K is extremely familiar with Federal-Aid implementation and the Caltrans’ Local Assistance Procedures. Proper Project documentation is key in audits conducted by the Federal Highway Administration (FHWA) and Caltrans.

Our Inspectors know that a complete record of the project must include a full set of all contract drawings, addenda, specifications, change orders, logs, submittals, and RFI’s. Filing will include correspondence with all stakeholders and permit agencies, reports (daily, weekly, monthly) showing all day-to-day operations, the contractor's workforce, and equipment. In addition to the materials on hand, materials testing reports and sampling, copies of all permits, SWPPP plan, all reports, updates, and all other contract documents related to the construction of the project will be documented. Our internal QA/QC process is simple and does not require additional time demands of the City. Routinely, our Construction Manager or Inspectors will conduct independent reviews of the project records for their adherence to the required policies and procedures. Z&K will coordinate preparation of the as-built plans with the Design Engineer.

CLOSE-OUT PHASE
Our Construction Manager will take a proactive approach at processing close-out documentation by preparing a final punch list of items, which typically include guarantees/warranties, subcontractor liens, retention, and final acceptance/certificates of completion, orderly transfer of key records and documents, resolution of outstanding issues, final payment preparation and processing along with final acceptance or record drawings. Z&K will verify the completion of the final punch list when the contractor has certified and demonstrated the work is substantially complete. Upon completion of the project and all items on the final punch-list (including all warranties, guarantees, and operation and maintenance manuals, in addition to subcontractor liens, retention, and final acceptance/certificates of completion), Z&K will provide the City with both hard and electronic copies of project documentation. Z&K will conduct a final inspection and walk-through including City staff, Contractor, maintenance/service personnel, and project architect/design consultant.

Upon completion of the project and following the final inspection and walkthrough, Z&K will provide the City with both hard and electronic copies of project documentation, including a report stating that the installation of all improvements required by the project have been completed in accordance with the plans and specifications. Z&K will calculate the amount of final payment due to the prime Contractor and prepare the proposed final estimate. Z&K will also review and process the release of retention. Z&K will obtain evidence of certification of the release of all liens and stop notices. Z&K will obtain certification of delivery of record drawings to the City and design engineer. Z&K will advise the City when the Notice of Completion (NOC) should be filed.

Z&K will also provide the City with necessary data needed for acceptance of the project, such as release of retention, certification of release of all liens and stop notices, certification of delivery of record drawings.

Z&K will conduct a final inspection and walk-through including City staff, Contractor, maintenance/service personnel, and project architect/design consultant, and applicable agencies. Z&K will calculate the amount of final payment due to the prime Contractor and prepare the proposed final estimate. Z&K will also review and process the release of retention. Z&K will obtain evidence of certification of the release of all liens and stop notices. Z&K will obtain certification of delivery of record drawings to the City and design engineer. Z&K will advise the City when the Notice of Completion (NOC) should be filed.

Z&K will prepare the final punch list when the contractor has certified and demonstrated the work is substantially complete

Page 21 ends

SECTION 2:

FINANCIAL INFORMATION

Page 22 ends

FINANCIAL STATEMENTS
Financial Statements | Z&K Consultants, Inc. is financially qualified to undertake the Services defined by this RFQ/RFP.

We understand that to be considered qualified, the City may request from Respondent and any team member of any proposed consortium or joint venture, audited and/or reviewed financial statements for the most recently completed three fiscal years.

Z&K Consultants, Inc. does not have any financial, business, or other relationship with the City that may have an impact upon the outcome of this contract. Z&K Consultants, Inc. does not have any current clients who may have a financial interest in the outcome of this contract or any City construction project that may follow.

Z&K Consultants, Inc. is in a strong financial position and does not have any conditions that may impede our firm’s ability to provide the services requested in this proposal.

Z&K Consultants, Inc. accepts the terms and conditions for the City standard Professional Services Agreement. Z&K Consultants, Inc. does not have any proposed deviations or modifications to the agreement to note.

Demonstrating Financial Qualification: A Commitment to Transparency and Accountability In response to the financial and related information requirements outlined in the RFQ/RFP, we are fully prepared to demonstrate our financial qualification to undertake the Services defined therein. At Z&K, we recognize the critical importance of financial stability and transparency in ensuring the successful execution of projects.

Audited and/or Reviewed Financial Statements:

Z&K is prepared to provide audited and/or reviewed financial statements for the most recently completed three fiscal years upon the City’s request. These statements serve as a comprehensive snapshot of our financial standing, offering insight into our stability and capacity to fulfill project requirements.

Page 23 ends

CLAIMS AND LITIGATION HISTORY
Claims and Litigation History:

Z&K has ZERO (0) claims and litigation within the past five years, or since its incorporation. This disclosure, accompanied by a thorough explanation of the circumstances surrounding each claim or litigation, is not applicable.

Page 24 ends

CERTIFICATE OF INSURANCE

Page 25 ends

SECTION 3:

RESPONSE FORMS

Page 26 ends

ACCEPTANCE OF FORM OF PROFESSIONAL SERVICES AGREEMENT
Z&K hereby agrees to sign Professional Services Agreement substantially similar to the form of Professional Services Agreement attached to the RFP and has no proposed modifications to their RFQ/RFP Response.

Page 27 ends

SECTION 4:

DISCRETIONARY

SUPPLEMENTAL MATERIALS

Page 28 ends

SAMPLE DOCUMENTS

WEEKLY NEWSLETTER

INSPECTORS DAILY REPORT

Page 29 ends

EMPLOYEE INTERVIEW FORM WEEKLY STATEMENT

MONTHLY QUANTITY

OF WORKING DAYS
SHEET

CONTRACT CHANGE ORDERS

Page 30 ends

APPENDIX A: RESUMES
Mr. Faqih has 32 years of experience in the Construction Management, Construction Inspection, Project Management, and Contract Administration of capital imporvement and public works projects, and has successfully delivered over 40 street improvement projects including street improvements, slurry seal, pavement rehabilitation, traffic signal modifications, fiber communication, CCTV cameras, street lighting, intersection improvements, sewer and storm drain improvements, traffic signal improvements, curbs, gutters, sidewalks, bridge projects, and access ramps. He has extensive experience managing multiple projects in Los Angeles County and Orange County since 1999. Mr. Faqih’s experience extends to interfacing and coordinating with the Caltrans-Local Assistance Program, Counties, Cities, Funding Agencies. He has excellent skills in understanding construction contracts, review and control project cost and schedule, coordinate and assist in negotiating change orders, maintain project as-builts, managing multiple subconsultants and supervise inspection staff. Mr. Faqih excels in providing detailed constructability review of project plans and specifications, which minimizes the potential project delays and change orders and assists the client from pre-award to project close-out to ensure full funding reimbursement.

Relevant Project Experience
Irvine Great Park Neighborhood—Traffic, Mobility, Street Rehabilitation Capital Improvement Projects, Orange County, CA ($15M) | Senior Project Manager/Construction Manager: This project included 15 New Traffic Signal construction installations, street lighting, traffic signal modifications, and fiber communication /CCTV Cameras at all round-a-bout intersections throughout the neighborhood. Construction Cost: $15M Alton Parkway Extension Orange County Public Works Project, Orange County, CA ($22M) | Senior Project Manager/Construction Manager:

This is a roadway and utility improvement project. The Alton project and the adjoining County of Orange project were set up to join the existing Alton Parkway Road from Irvine Blvd. in the City of Irvine, through the County of Orange, connecting at the 241 Toll Road in the City of Lake Forest. The Alton project included overlapping construction of cutting-edge storm water facilities, such as 24 filterra boxes and a large gabion structure along with a complex arrangement of water and sewer pipelines, dry utilities, and (4) signalized intersections, traffic signal modifications, interconnect, and street lighting improvements. This work led to a million cubic yards of mass grading in order to construct a new six-lane 1.2-mile roadway along with a wildlife habitat area and new county jail fence. Construction Cost: $22M Los Angeles County Department of Public Works: Slauson Avenue and Firestone Boulevard Revitalization, Los Angeles, California (2019) ($3M) | Senior Project Manager/Construction Manager: This project includes resurfacing of roadway pavement tire rubber modified asphalt concrete, traffic signal modifications, reconstruction of curb and gutter, sidewalk, driveways, and curb ramps; construction of concrete pavement and crosswalks, and streetscape improvements; and the performance of other appurtenant work.

Interstate Route I-215 / SR-60 Interchange Widening, Orange County, CA | Senior Project Manager/Construction Manager: Scope of work for this project includes widening the existing six lane highway to ten lanes, reconstruction of existing shoulder grades and installing a new median barrier wall. This project included new Ramp metering, Street lighting and fiber TMC communications from Central Ave. north to Rte 60- Day St.

LACDPW: Slauson Avenue Revitalization, Los Angeles County, CA | 02/2019 ($3M) | Senior Project Manager/Construction Manager: This project includes resurfacing of roadway pavement tire rubber modified

EDUCATION
» MSCE - Structures
Cal State Fullerton 2005
» BSCE - Civil /Transportation
Cal State LA 1985

LICENSES &

REGISTRATION
» Professional Engineer, P.E.

State of California (C57958)
» Certified Accessibility
Inspector/Plans Examiner
» Certified Building Official
» Certified Plans Examiner
» Certified Mechanical
Inspector
» Certified Plumbing
Inspector
» Certified Electrical Inspector
» SWPPP QSD & QSP
(#22055)
» OSHA 30 Hour
Construction Safety & Health
» State Certified HERS Rater
» Certified Emergency
Inspector
» C.G.B.P Certified Green
Building Inspector
» Certified Special Inspector
for Fireproofing
» Certified Special Inspector
for Structural Welding
» Certified Special Inspector
for Structural Steel
» Certified Special Inspector
for Reinforced Concrete
Zack Faqih, MSCE, PE, QSD/QSP, ICC, CBO
Senior Project Manager/Construction Manager
asphalt concrete, reconstruction of curb and gutter, sidewalk, traffic signal modifications, driveways, and curb ramps; construction of concrete pavement and crosswalks, and streetscape improvements.

LACDPW: Firestone Blvd. Street Rehabilitation, Los Angeles County, CA | 09/2019 ($2.4M) | Senior Project Manager/Construction Manager: This project includes resurfacing of roadway pavement tire rubber modified asphalt concrete, traffic signal modifications, reconstruction of curb and gutter, sidewalk, driveways, and curb ramps; construction of concrete pavement and crosswalks, and streetscape improvements.

City of Costa Mesa: Citywide Parkway Maintenance, Street Rehabilitation and Slurry Seal Project, No. 21-03, Costa Mesa, CA | Senior Construction Manager/Project Manager: This citywide street improvement program in the City of Costa Mesa involved mobilization, removal and reconstruction of curb and gutters, sidewalks, driveway approaches, spandrels, cross gutters, traffic signal modifications, ADA curb ramps, removal and reconstruction of existing pavement, milling and overlaying with new asphalt, adjustment of manholes and utility covers to grade, application of slurry seal, crack sealing, traffic signing, striping and markings, traffic markers and speed humps, installation of specialty and bicycle loop detectors, and implementation of traffic control.

City of Lake Forest: Street Resurfacing and Slurry Seal Program, Lake Forest, CA | Senior Construction Manager/Project Manager: This street resurfacing and slurry seal program for the City of Lake Forest involves street resurfacing of Glenn Ranch Road from Portola to El Toro, which required ARHM overlay, adjustments to storm drain manhole frame and cover, adjustments to sewer manhole, gas valve lid and can, water valve lid and can, removal and replacement of PCC sidewalk, removal and replacement of existing curb ramps, cold milling, signing and striping, adjustment of pull boxes to grade, installation of markers, installation of traffic loop detectors and bicycle lane detectors, crosswalk, and other street improvements.

City of Compton: Annual Residential Rehabilitation Project, Compton, CA | Senior Construction Manager/Project Manager: This project included street rehabilitation of seven major City streets. Scope of work consisted of cold mill, ARHM pavement, AC base course, aggregate base, full depth AC slot pavement, curb and gutters, sidewalks, cross gutter, alley intersection, driveway approach, curb ramps, signing, striping, markings, and pavement legends, speed hump, traffic signal loop, storm drain manhole, etc. Scope included fullservice construction management, reviewing traffic control plans, meetings, issues management, scheduling, cost control, labor compliance, reviewing RFIs and Submittals, change orders, dispute resolution, quality control/inspection, public relations, permits/environmental compliance, progress payments, monthly staff reports, site safety, as-builts drawings, final walkthrough, and project completion reports.

City of Torrance: Residential & Arterial Pavement Improvement, I-159/I-139, Torrance, CA | Senior Construction Manager/Project Manager: This project included slurry seal, cold mill and overlay and localized pavement repairs, tree removals/replacements, asphalt berm replacement, concrete repairs to curb, gutter, sidewalk, driveways, access and ramps. Mr. Faqih ensures construction quality assurance by supervising inspection and engineering, including oversight of excavation, compaction, subgrade inspection, backfill, paving, and inspection of structures, electrical, welding, drainage, and underground utilities. Mr. Faqih supervises the coordination geotechnical and materials testing, schedules and attends meetings with City representatives, contractors, and other agencies, prepares constructability reviews, and ensures compliance with project plans and specs, permits, agency requirements, and local regulations.

City of San Bernardino: Street Rehabilitation Program (30+ Major Streets), San Bernardino, CA | Senior Project Manager/Senior Construction Manager: This long-term, on-call contract involves concrete improvements and pavement improvements of over 30 major streets in the City of San Bernardino. The contract also includes the rehabilitation and resurfacing of various streets and intersections. Scope of work includes traffic signal modifications, full depth removal and replacement of asphalt concrete, slurry seal, grind and overlay, cold milling of existing asphalt concrete, removal and replacement of ramps, various ADA improvements, bike lane and bike trail, mobilization, traffic control, staging for major streets and intersections, removal of traffic striping, installation of traffic striping and pavement markers, installation of loop detectors and bicycle loop detectors, construction of cross walks, removal and replacement of sidewalk, driveways, ADA ramps, dig-outs, PCC curb and gutter, cross gutters, spandrels, curb ramps along both residential and commercial streets, manhole and utility vault adjustments, and preparation of SWPPP and erosion control plans.

City of Rosemead: Walnut Grove Ave. Resurfacing Project Phase I, Rosemead, CA | Senior Construction Manager/Project Manager: This project involves street resurfacing of Walnut Grove Ave., from Marshall St. to Grand Ave. in the City of Rosemead. In addition to street improvements, the project included intersection improvements, removal and replacement of existing AC pavement, cold mill and overlay, asphalt pothole repairs, replacement of PCC sidewalk, removal and replacement of ramps, ADA ramps, curb and gutter, bike lane and bike trail, traffic signal modifications, installation of medians, adjustment of manholes and utility covers to grade, installation of specialty and bicycle loop detectors, installation of speed humps, pedestrian crossings, and guardrail and roadway markers.

Mr. Dawson has over 28 years of experience providing quality control and quality assurance with extensive experience on of numerous major capital improvement projects including street improvements, traffic signal improvements, roadway widenings, bridges, transmission mains, new wells, tanks, reservoirs, water and wastewater treatment plants, pipelines, lift stations, booster pump stations, retaining walls, dewatering, parks and facilities, landscaping and irrigation improvements, utility installation, roadway widenings, grade separations, masonry walls, storm drain projects, roadway projects, street rehabilitations, and large-scale water and wastewater projects.

He has provided construction inspection services for numerous local agencies.

He has extensive Public Works Inspection experience and understands the expectations of the City since he has worked in the public and private sectors.

He will integrate seamlessly with City staff to successfully deliver the City’s citywide projects. He has a depth of resources to support him on this project.

Relevant Project Experience
City of Fullerton: Raymond Avenue Grade Separation at Raymond Ave and BNSP Railway | Senior Construction Inspector: As part of the OC Bridges program, the City of Fullerton and the Orange County Transportation Authority designed and constructed a new roadway underpass at the intersection of Raymond Ave and the BNSF Railway. The roadway was lowered between Santa Fe Avenue to the north to approximately 500 feet south of Valencia Drive to the south. The project required extensive utility coordination and relocation of 20 different facilities including water, sewer, drainage, and telecommunications. The underpass greatly improved safety and traffic operations at the rail line that carries more than 70 trains per day, with train lengths reaching a mile long. The Raymond Ave Grade Separation benefited from the excellent relationships developed between the design and construction teams, the railroad, and utilities. Coordination and approvals were required by BNSF, as the owner of the rail facility. The construction of the project could not impact rail traffic and customer service. The project required close coordination with BNSF for the development of the shoofly, as well as construction sequencing. Rail construction was coordinated based upon the availability of the track machine.

Additionally, the railroad was expanding from two to three tracks during the construction of the grade separation.

This project continued the strong working relationship established with BNSF that was developed through the delivery of the neighboring OC Bridges projects. There was extensive coordination with local utility providers.

The roadway lowering involved protecting in place or relocating 20 utilities and established a utility corridor. This required coordination with City of Fullerton utilities, Orange County Sanitation District (OCSD), Orange County Water District, SCE, Southern California Gas, and multiple telecommunication purveyors. The utility corridor included water, sewer, storm drain, and joint trench for dry utilities. In addition to the functional improvements provided by the new grade separation, the project provided an opportunity to enhance the aesthetics of the corridor through the rail crossing. The project includes a landscaped median, decorative retaining walls and bent caps, and attractive and safe lighting in the underpass for bikes and pedestrians.

City of Torrance: Residential and Arterial Pavement Improvement, I-159/I-139 | Senior Construction Inspector: This project involved pavement improvements to a residential neighborhood as well as four arterial streets. Improvements include asphalt preservation and repair methods including application of slurry seal, cold mill and overlay and localized pavement repairs, as well as tree removals and replacements, asphalt berm replacement, concrete repairs to curb, gutter, sidewalk, driveways, access ramps, and cross gutters.

City of San Marino: Street Rehabilitation Program Project No. 21-9271| Senior Construction Inspector:

Annually, San Marino rehabilitates up to 40 street segments with treatment methods including slurry sealing, thin/thick overlays and full reconstruction. Work includes full-time construction inspection services of the actual construction
Thomas Dawson, CBO, ICC Certified
Senior Supervising Inspector

LICENSES &

REGISTRATION
» International Code
Counsel Certifications
» Building Plan Examiner
» California Commercial Combination Inspector
» California Commercial Plumbing Inspector
» California Commercial Mechanical Inspector
» California Commercial Mechanical Inspector
» California Commercial
Electrical Inspector » California Residential
Electrical Inspector
» California Residential
Plumbing Inspector
» Certified Building Official
» CLB License No. 674861
» OSHA 30 Hr.

City of Lake Forest: Street Resurfacing and Slurry Seal Program, Lake Forest, CA | Senior Construction Inspector: This street improvement program involves resurfacing of Glenn Ranch Road from Portola to El Toro, as well as pre-construction inspection services for the slurry seal of Zone F and arterial slurry seal of Jeronimo and Muirlands from Los Alisos to Bake. This program required pavement improvements, street resurfacing, asphalt repairs, slurry seal, cold mill and overlay, pavement repairs, adjustments to storm drain manhole frame and sewer manhole, removal and replacement sidewalk, existing curb ramps, signing and striping, installation of markers, installation of traffic loop detectors and bicycle lane detectors, crosswalk, and other street improvements.

City of Corona: Magnolia Avenue Grade Separation, (RCTD) | Roadway Construction Inspector: The project scope was to construct railroad grade separation at the BNSF Railroad and Magnolia Avenue at Grade crossing including a new four-lane overhead structure (bridge) over existing BNSF tracks supported by 9 bents and 2 abutments. Both bridge approaches are supported by Retaining Walls/MSE Walls systems on both ends, multiple walls systems for pedestrian and vehicular support. Project involved concrete paving, AC, JPCP, CRCP, drainage improvements, guard rail installation, staging, traffic control procedures, shoring and casing support system to facilitate construction of CIDH piling. Mr. Dawson performed inspection of roadway and bridge construction operations to ensure compliance with applicable codes, regulations, construction drawings, traffic, and erosion control/water quality plans, attended all progress and special meetings, prepared daily reports, maintained project records, and coordinated field sampling and testing of materials throughout the project. He coordinated with Caltrans inspectors to obtain approval on rebar, formwork, falsework.

City of Temecula: Pavement Rehabilitation Program – Winchester Road (Jefferson Avenue to Ynez Road) | Senior Construction Inspector: The City of Temecula pavement rehabilitation program. The work for this project generally includes pavement Improvements along Winchester Road from Jefferson Avenue to Ynez Road. Improvements Include: centerline rumble strips, flashing stop signs, guardrails, remove and replace existing asphalt pavement, reconstruction of traffic loops, adjust existing manholes and valves for different utilities, and installation of striping and pavement markers.

City of Irwindale: 2021-2022 Resurfacing Project | Senior Construction Inspector: This project involved general street improvements, in addition to street resurfacing, for multiple streets in the City of Irwindale, including Ayon Avenue, Calle del Norte, Pat Miranda Lane, Calle de Paseo, Allen Drive, Progress Lane, Central Street, and Peppertree Lane. The project’s scope included centerline rumble strips, flashing stop signs, roadway widening, sidewalk improvements, curb and gutter reconstruction, addition of travel lanes, addition of bike lanes, reconstruction of ADA-compliant sidewalks and pedestrian ramps, storm drain improvements, and utility relocation. Mr. Dawson provided full time construction inspection services, coordinated and attended weekly construction progress meetings with staff, and coordinated materials testing services.

City of Chino: Slurry Seal Program (Various Locations Citywide) | Senior Construction Inspector: This Project which includes street rehabilitation and slurry seal of various streets, including, Pipeline Ave from City Limits to City Limits, Chino Ave from City Limits to City Limits and Schaefer Ave from City Limits to City Limits.

Scope of work includes pavement improvements, street resurfacing, crack sealing, slurry seal, localized digouts, striping removal/install, and traffic loop detectors. He provided preparation of submittal packages, scheduling, mark outs, meetings, cost control, reviewing RFIs, preparing change order proposals, permits, progress billings, subcontractor coordination, as-built drawings, and final walkthrough/closeout.

Foothill/Eastern SR 133/261/241 Transportation Corridor Toll Roads, Orange County, CA | Senior Construction Inspector: Project included all facets of electrical construction, Toll Plaza buildings, Traffic Signals, Street Lighting, Sign Lighting, Bridge Electrical/ Communication installation, Directional Boring & Trenching. Fiber Optic Installation & Fusion Splicing, Network Integration for Intelligent Transportation Systems, CCTV & Access Control.

Beach Blvd Bridge at Fullerton Channel City of Buena Park, CA | Senior Construction Inspector: During the 1994/1995 Flood season, Beach Boulevard in Buena Park, CA (Beach Boulevard is also known as State Route 39) was washed out at Fullerton Creek creating two sink holes of 120 ft X 75 ft on both sides of the bridge; leaving the bridge vulnerable to failure. In addition, in coordination with Caltrans Sacramento Structural Section, He designed a retaining wall system to provide protection for the existing bridge piles and to rebuild the Channel.

He kept both Caltrans and the City of Buena Park advised of the project progress. Due to the emergency that the sink holes created, he was able to exempt the project from all the required environmental permits from the Army Corp of Engineers, United States Fish and Wildlife, and the California Fish and Game.

Mr. Davalos has over 25 years of experience in public works inspection, construction management, contracting, quality control, construction inspection, and management of large-scale capital improvement projects, and has successfully delivered over 35 street improvement projects, involving street improvements, intersection improvements, median improvements, ADA ramp improvements, bike lanes and bike trails, conduit installation, traffic signal improvements, asphalt overlay, construction staging, traffic control, clearing and grubbing, SWPPP preparation, manholes and utility covers, loop detectors, PCC sidewalk, speed humps, and pedestrian crossings. Mr. Davalos’s expertise extends to his familiarity with Caltrans, Federal Department of Labor and State of California Division of Labor Standards Enforcement, and equal employment opportunity compliance monitoring.

Relevant Project Experience
City of Chino: Ramona Ave. and Walnut Ave. Traffic Signal Modifications and Street Improvements Project | Senior Construction Inspector: for a series of projects for the City of Chino Ramona Ave and Walnut Ave Traffic Signal Modifications Project. The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other. Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection.

Kimball/El Prado/Central Traffic Signal Improvement Project | Senior Construction Inspector: The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other. Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, drainage improvements, landscaping improvements, AC base course, ARHM pavement, concrete repairs to curb, gutter, sidewalk, driveways and driveway approaches, and replacing markings and striping on concrete and asphalt.

City of Chino: 11th St. Traffic Signal Modifications, Pavement Reconstruction Alley, and Intersection Accessibility Project | Senior Construction Inspector: The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other.

Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection. The scope also involved drainage improvements, landscaping improvements, AC base course, ARHM pavement, concrete repairs to curb, gutter, sidewalk, driveways and driveway approaches, and replacing markings and striping on concrete and asphalt.

City of Compton: Annual Residential Rehabilitation Project (Phases 1 & Phase 2A), Compton, CA | Senior Construction Inspector: Scope of work consisted of construction of cold mill, ARHM pavement, AC base course, aggregate base, full depth AC slot pavement, curb and gutters, sidewalks, cross gutter, alley intersection, driveway approach, curb ramps, signing, striping, markings, and pavement legends, speed hump, traffic signal loop, adjust to grade existing sewer manhole, water valve, water meter, and storm drain manhole.

Eddie Davalos
Senior Construction Inspector

LICENSES &

REGISTRATION
» Citrus College, Covina,
CA, Public Works/Earth
Work
» OSHA 30 Hour
Construction
Safety & Health
» Sexual Harassment
Prevention Training
» Defensive Driving
Training
» Caltrans Roadway
Safety
Training
» Bridge Inspector
Training
» Metro Rail Safety
Training
Mr. Davalos’s responsibilities included construction inspection, reviewing traffic control plans, issues management, cost control, labor compliance, dispute resolution, quality control/inspection, public relations, and ensuring site safety.

City of San Marino: Street Rehabilitation Program, San Marino, CA (Phase 1 and Phase 2) | Senior Construction Inspector: Improvements include cold-milling asphalt concrete pavement and re-paving with HMA and ARHM, clearing and grubbing, localized pavement repairs, replacing impacted traffic striping, markings, pavement legends, loop detectors, curb painting, replacing damaged curb and gutter, curb ramps, cross gutters, sidewalks, driveways and driveway approaches, inspection and replacement of sewer manholes, coordinating with local utilities, preparation and implementation of SWPPP and BMPs, and providing temporary traffic control in conformance with the contract documents and applicable permits. Mr. Davalos’s responsibilities included construction inspection, reviewing traffic control plans, issues management, cost control, labor compliance, dispute resolution, quality control/inspection, public relations, and ensuring site safety.

City of Alhambra: FY 19-20 & FY 20-21 SB1 Street Rehabilitation Projects, Alhambra, CA (Phase 1 and Phase 2) | Senior Construction Inspector: This program consists of pavement and street rehabilitation of 23 local street segments located south of mission road, west of Garfield Avenue, east of Atlantic Boulevard, and north of Valley Boulevard. Pavement improvements include intersection improvements, slurry seal treatment, varying depths of cold milling and overlay, and full depth removal and reconstruction. The project also includes concrete improvements such as removal and replacement of broken and off-grade sidewalk, ADA ramps, median installation, sidewalks, and driveway approaches, that need updating, broken and off-grade curb and gutter, driveway aprons, cross gutter, and traffic signing striping, and markings.

City of Rosemead: Walnut Grove Ave. Resurfacing Project Phase I, Rosemead, CA | Senior Construction Inspector: This project involves street resurfacing and widening of Walnut Grove Ave., from Marshall St. to Grand Ave. in the City of Rosemead. Improvements included roadway widening, intersection improvement, pavement improvements, ADA improvements, sidewalk repairs, traffic signal modification, storm drain improvements, sewer main improvements, and addition of bike lanes. Mr. Davalos provided full-time inspection, attended weekly progress meetings, prepared daily diaries, filled out incident reports, made assessments of exiting pavement conditions, coordinated with and provided direction for materials and geotechnical testing services, ensured successful completion and submission of the as-constructed plans and final punch list, reviewed traffic control plans, and performed regular labor compliance interviews on site.

City of Irwindale: 2021-2022 Resurfacing Project, Irwindale, CA | Senior Construction Inspector: This project involves general street improvements, in addition to street resurfacing, for multiple streets in the City of Irwindale, including Ayon Avenue, Calle del Norte, Pat Miranda Lane, Calle de Paseo, Allen Drive, Progress Lane, Central Street, and Peppertree Lane. The project’s scope included roadway widening, sidewalk improvements, curb and gutter reconstruction, addition of travel lanes, addition of bike lanes, reconstruction of ADA-compliant sidewalks and pedestrian ramps, storm drain improvements, sewer main improvements, and utility relocation. Mr. Davalos provided full time construction inspection services, coordinated and attended weekly construction progress meetings with city staff, coordinated materials testing services, and documented daily progress through written daily diaries and photos.

City of Torrance: Residential & Arterial Pavement Improvement Project, Torrance, CA | Senior Construction Inspector: Mr. Davalos provided inspection for improvements including application of slurry seal, cold mill and AC overlay, clearing and grubbing, removal and disposal of existing pavement, localized pavement repairs, as well as tree removals and replacements, asphalt berm replacement, AC base course, concrete repairs to PCC curb, gutter, PCC sidewalk, driveways, access and ramps. Other relevant features include adjustment of storm drains and sewer manholes to grade, reconfiguration of sewer piping, mobilization, traffic control, removal and replacement of existing traffic striping/markings and signage, and irrigation. Mr. Davalos provided full-time inspection, prepared daily diaries, filled our incident reports, provided digital images of progress to the City, reviewed compliance with the SWPPP and installation of BMPs, ensured successful completion and submission of the as-constructed plans and final punch list.

City of Lake Forest: Street Resurfacing of Glenn Ranch Road from Portola to El Toro, Lake Forest, CA | Senior Construction Inspector: This street improvement program involves resurfacing of Glenn Ranch Road from Portola to El Toro, as well as pre-construction inspection services for the slurry seal of Zone F and arterial slurry seal of Jeronimo and Muirlands from Los Alisos to Bake.

Mr. Martin has more than 27 years of construction management and inspection experience on major capital improvement projects and is a certified ICC and ACI. Jimmy has been performed senior construction inspection services for various projects including pavement rehabilitations, traffic signal improvements, slurry seal projects, roadway widenings, intersection improvements, new intersections, bridges, interchanges, street improvements, traffic signal modifications, retaining walls, sound walls, MSE walls, sewer pipeline projects, water pipeline projects, water treatment facilities, wastewater treatment facilities, pipeline projects, and lift stations and has successfully delivered over 25 street improvement projects.

Jimmy’s public works inspection responsibilities include the ability to review improvement plans, inspect public improvements construction, negotiate and administer contracts, and prepare and maintain a variety of reports. Jimmy values safety as a top priority and is acutely aware of security protocol and adherence to regulatory requirements. Jimmy proficiently surveys, inspects and evaluates production environments to determine fulfillment of safety and security standards. Jimmy possesses strong leadership capabilities that consistently lead to project productivity and profitability. His ability to supervise various levels of personnel and increase each team member’s performance contribute to the overall success of program goals and client satisfaction. His proven track record of meeting company and agency objectives are direct results of his team-oriented, dependable and professional approach.

RELEVANT PROJECT EXPERIENCE
City of Torrance, Residential/Arterial Pavement Improvements | Senior Construction Inspector: This project included street rehabilitation and slurry seal of various streets, including, Cranbrook Ave, Kornblum Ave, Felbar Ave, Van Ness Ave, Madrona Ave, Harpers Wy, Gramercy Pl, Manhattan Pl, Yukon Ave, and Ainsworth Ave. Scope of work included pavement improvements, street resurfacing, crack sealing, slurry seal, localized digouts, Hot-mix Asphalt pavement, striping removal, curb and gutter, ADA access ramps, alley intersections, driveway approaches, cross gutters, traffic loop detectors and adjustment of utilities. Scope included preparation of submittal packages, scheduling, project management, meetings, cost control, reviewing RFIs, preparing change order proposals, permits, progress billings, subcontractor coordination, as-built drawings, and final walkthrough/closeout.

City of Torrance, Anza/Vista Montana/Pacific Coast Highway Intersection Improvements | Senior Construction Inspector: The Anza/Vista Montana/Pacific Coast Highway Intersection Improvements Project consists of construction of the Pacific Coast Highway/Anza Intersection Improvements with appurtenances as shown on City of Torrance Plan No.’s ST-1019/SD-517/C- 2019-8/TS-2019-2/ST-1019-TC; curb, gutter, sidewalk, catch basins, curb ramps, raised medians, striping, traffic signal replacement; grind and overlay, and AC pavement; and all other incidental work.

City of Chino, Slurry Seal Program (Various Locations Citywide) | Senior Construction Inspector: This Project which includes street rehabilitation and slurry seal of various streets, including, Pipeline Ave from City Limits to City Limits, Chino Ave from City Limits to City Limits and Schaefer Ave from City Limits to City Limits.

Scope of work includes pavement improvements, street resurfacing, crack sealing, slurry seal, localized digouts, striping removal/install, and traffic loop detectors. Z&K provided preparation of submittal packages, scheduling, mark outs, meetings, cost control, reviewing RFIs, preparing change order proposals, permits, progress billings, subcontractor coordination, as-built drawings, and final walkthrough/closeout.

City of Chino, Alley/Sanitation Rehabilitation Project | Senior Construction Inspector: This Project which includes removal of existing alley pavement and base section to construct new AC pavement section and ribbon gutter in multiple alleys in the City of Chino. Scope of work includes new PCC drive and alley approaches, curb and gutter, 4’ PCC alley gutter, new AC pavement section over compacted crushed miscellaneous base, and the construction of several block walls. Z&K is providing preparation of submittal packages, scheduling, project

LICENSES &

REGISTRATION
» ICC Soils Special Inspector
» ICC Reinforced Concrete
Inspector
» Caltrans Various
Certifications » Nuclear
Gauge Certification
» ACI Field Technician Grade
1 » 30 Cal/OSHA
» Confined Space Training
» Traffic Control Technician
and Traffic Control Flagger
» Certified California
Journeyman Laborer (AGC)
» Pervious Concrete
Technician (NRMCA)
» Carpentry
» Cement Mason
» Fall Protection
» Traffic Control Safety
Jimmy Martin, ACI, ICC Cert.

Senior Construction Inspector (Alternate)
management, meetings, cost control, reviewing RFIs, preparing change order proposals, permits, progress billings, subcontractor coordination, as-built drawings, and final walkthrough/closeout.

City of Temecula, Pavement Rehabilitation Program – Winchester Road (Jefferson Avenue to Ynez Road) | Senior Construction Inspector: The City of Temecula pavement rehabilitation program. The work for this project generally includes pavement Improvements along Winchester Road from Jefferson Avenue to Ynez Road. Improvements Include, remove and replace existing asphalt pavement, reconstruction of traffic loops, adjust existing manholes and valves for different utilities, and installation of striping and pavement markers.

City of Chino, Various Arterial Streets (e.g., Central Ave, Edison Ave, Riverside Dr, Eucalyptus Ave, Chino Ave, Ramona Ave) | Senior Construction Inspector: Completed over 9 linear miles of roadway widening and asphalt pavement rehabilitation. Roadway widening consisted of the addition of vehicle lanes, curb & gutter, sidewalk, and landscape area. Pavement rehabilitation consisted of selective deep lift removals, cold mill existing AC pavement 3” below surface and pave back section (in kind). Removal and replacement of all substandard curbs, gutters, sidewalks, and ADA curb ramps. Replacement of traffic signal loops.

City of Indio, Highway 111 - Young’s Lane Median Improvements Project | Senior Construction Inspector Demolition of existing AC paving, street structural section, decorative PCC curb, decorative cobble pavers and median landscaping. Complete reconstruction of all improvements, with modified horizontal alignment.

Repair/replacement of all existing lighting and automatic irrigation systems. Placement of 60,000 SF of type II Emulsion Asphalt Slurry. Coordinated road closures and traffic detours with local businesses. Installation of new traffic signage and striping. Inspected installation of work area traffic control for compliance with approved plans.

City of Corona, Citywide Sidewalk Improvements | Senior Construction Inspector: Assessment and prioritization of 80,000 sf of existing deteriorated or damaged sidewalks, throughout the city. Marked and created photo documentation of locations that required sidewalk replacement. Utilizing GPS mapping software, obtained the exact location of all sidewalk repair locations. Inspected construction activities during sidewalk demolition and replacement. Coordinated with a certified arborist to assure proper root pruning and stabilization of mature trees. Confer with property owners, contractors, project engineers and other City departments regarding scheduling work, gathering data and resolving complaints. Performed inspection of sidewalk demolition and replacement including temporary traffic control, site maintenance, root pruning, and compliance with City and Greenbook Standards.

City of Irwindale, 2021-2022 Resurfacing Project | Senior Construction Inspector: This project involved general street improvements, in addition to street resurfacing, for multiple streets in the City of Irwindale, including Ayon Avenue, Calle del Norte, Pat Miranda Lane, Calle de Paseo, Allen Drive, Progress Lane, Central Street, and Peppertree Lane. The project’s scope included roadway widening, sidewalk improvements, curb and gutter reconstruction, addition of travel lanes, addition of bike lanes, reconstruction of ADA-compliant sidewalks and pedestrian ramps, storm drain improvements, sewer main improvements, and utility relocation. Martin provided full time construction inspection services, coordinated and attended weekly construction progress meetings with city staff, and coordinated materials testing services.

City of Hawthorne, Prairie Ave Improvement Project Phase II, Hawthorne, CA | Senior Construction Inspector: This arterial street improvement project consists of excavation and removal of existing pavement, installation of storm drain, sewer improvements, ADA access ramps, driveways, curb and gutter, traffic signal relocations, signage and striping, adjustment of storm drain and sewer manholes. Mr. Martin provided full-time project management, preparing submittal packages, coordination with subcontractors, scheduling, quantity tracking and monthly billing, cost control, field coordination, meetings, RFIs, change order proposals, T&M tracking, and final project closeout.

City of Commerce, Atlantic Blvd Corridor Improvement Project, Commerce, CA | Senior Construction Inspector: This street improvement project provided the beautification of Atlantic Blvd from Washington Blvd to The I5 FWY. This project consisted of the resurfacing of Atlantic Blvd, improving mobility of pedestrians, ADA compliant access ramps, PCC bus pads, bus shelters, PCC medians, landscaping, installation of City monument, adjustments of storm drain manhole frames and sewer manholes, installation of traffic signal upgrades, and traffic loop detector installation.

City of Hawthorne, Local Street Improvement Project, Hawthorne, CA | Senior Construction Inspector:

This local street improvement project consists of cold mill, excavation, and removal of existing pavement, ARHM pavement improvements, ADA curb ramps, installation of speed humps, curb and gutter, localized pavement reconstruction, traffic signal detectors and bicycle loop detectors, and signage and striping. Mr. Martin provided full-time project management, coordination with City and subcontractors, monthly progress billing, cost control, RFIs, change orders, scheduling, onsite crew management, and project closeout.

Ms. Duhn has extensive experience in project management, office engineering, contract administration, document control, labor compliance oversight, and construction management, and has successfully delivered over 20 street improvement projects, involving street improvements, intersection improvements, ADA ramp improvements, bike lanes and bike trails, conduit installation, traffic signal improvements, asphalt overlay, construction staging, traffic control, clearing and grubbing, SWPPP preparation, coldmill and overlay, manholes and utilty covers, loop detectors, PCC sidewalk, speed humps, and pedestrian crossings. These are great testaments of Ms. Duhn’ managerial and oversight project experience. She gained tremendous experience in the design, operations, and maintenance by working closely with various stakeholders. Ms. Duhn has thorough knowledge of submittals, RFIs, and CCO review, project filing, daily reporting, quantity tracking, and project coordination. She is experienced in developing and maintaining project files, processing progress payments, and maintaining various logs, including submittals, RFIs, and correspondences. She is proficient with various construction computer software.

Relevant Project Experience
11th St. Traffic Signal Modifications, Pavement Reconstruction Alley, And Intersection Accessibility Project, City of Chino | Project Manager/Office Engineer: The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other. Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection. The scope also involved drainage improvements, landscaping improvements, AC base course, ARHM pavement, concrete repairs to curb, gutter, sidewalk, driveways and driveway approaches, and replacing markings and striping on concrete and asphalt.

City of Compton: Annual Residential Rehabilitation Project (Phases 1 & 2A), Compton, CA | Project Manager/Office Engineer: Scope of work consisted of construction of cold mill, ARHM pavement, AC base course, aggregate base, full depth AC slot pavement, curb and gutters, sidewalks, cross gutter, alley intersection, driveway approach, curb ramps, signing, striping, markings, speed hump, traffic signal loop, water valve, water meter, and storm drain manhole. Scope included full-service construction management, pre-construction, management information system, reviewing traffic control plans, meetings, issues management, scheduling, cost control, labor compliance, reviewing RFIs and Submittals, change orders, dispute resolution, quality control/inspection, public relations, permits/environmental compliance, progress payments, monthly staff reports, site safety, as-builts drawings, and final walkthrough/ City of Torrance: Residential and Arterial Pavement Improvement, I-159/I-139, Torrance, CA | Project Manager/Office Engineer: This project involves pavement improvements to a residential neighborhood and four arterial streets. Improvements include clearing and grubbing, cold mill and overlay, AC base course, aggregate base, concrete repairs to sidewalk, replacement of pavement markings and striping on concrete and asphalt, installation of speed humps, traffic signal loops, water valves and water meters, sewer manholes and storm drain manholes. Ms. Duhn coordinated and conducted the preconstruction conference and progress meetings, maintained the management information system, reviewed submittals, RFIs, and change orders, monitored the contractor’s schedule weekly, monitored the project funding, and ensured labor compliance by reviewing certified payrolls and verifying prevailing wages.

City of Costa Mesa: Citywide Parkway Maintenance, Street Rehabilitation and Slurry Seal Project, No. 21-03, Costa Mesa, CA | Project Manager/Office Engineer: This citywide street improvement program in the City of Costa Mesa involved mobilization, removal and reconstruction of curb and gutters, sidewalks, driveway approaches, spandrels, cross gutters, ADA curb ramps, removal and reconstruction of existing pavement, milling and overlaying with new asphalt, adjustment of manholes and utility covers to grade, application of slurry seal, crack sealing, traffic signing, striping and markings, traffic markers and speed humps, installation of specialty and bicycle loop detectors, and implementation of traffic control.

City of Chino: Ramona Ave. And Walnut Ave. Traffic Signal Modifications and Street Improvements Project | Project Manager/Office Engineer: for a series of projects for the City of Chino Ramona Ave and Walnut Ave Traffic Signal Modifications Project. The project consisted of traffic signal improvements, street and pavement improvements, as well as traffic signal improvements, to a residential neighborhood and four arterial streets for one project, and intersection improvements and lane upgrades for the other. Improvements include street and pavement rehabilitation, intersection improvement, clearing and grubbing, slurry seal, cold mill and AC overlay, utility coordination, as well as electrical and lighting improvements, including traffic signal hardware replacement, pedestrian countdown signal hardware installation, replacement and testing of fiber optic communication equipment, boring inspection. The scope also involved drainage improvements, landscaping improvements, AC base course, ARHM pavement, concrete repairs to curb, gutter, sidewalk, driveways and driveway approaches, and replacing markings and striping on concrete and asphalt.

EDUCATION
» BSCE – Civil Engineering California State Polytechnic University, Pomona

LICENSES & REGISTRATION
» Professional Engineer, P.E.

State of California, #91078
» SWPPP (QSD) & (QSP)
Certificate # 22055
» OSHA 30 Hour Construction
Safety and Health
Brittany Duhn, PE, QSD/QSP
Project Manager/Office Engineer

← All documents from this meeting