Cities Index.
01_City Of San Marino 25012201-35

San Marino City Council
February 28, 2025

Document
01_City Of San Marino 25012201-35
Meeting
February 28, 2025
Body
San Marino City Council
Original file
124 KB
Text extracted from the city's file for reading and search. Open the original on cityofsanmarino.primegov.com. That file is the official record.

14555 Titus Street ● Van Nuys, CA 91402
(800) 780-0201 phone ● (818) 780-7993 fax
Contractor's License #589431 (D03 Awnings)
www.SuperiorAwning.com Document No.

Revision No.

Proposal Date

CONSTRUCTION CONTRACT
You are entitled to a fully completed copy of this agreement, signed by both you and the contractor before work is started.

Customer/Contact: Phone:

Billing Address: Site Address:

E-Mail:

Description of the Project, Significant Materials to be Used and Product to be Installed:

Width: 32 0 Projection: 32 0 $33,676.36 x 1 33,676.36
feet inches feet inches unit price quantity Product Option Adjustments:

Material: Additional Specifications: 0.00
Frame: 0.00
Binding: 0.00
Valance: 0.00

0.00 12500.00
Item Subtotal: $ 46,176.36
0 0 0 0 $0.00 x Qty 0.00
feet inches feet inches unit price quantity Product Option Adjustments:

Material: Additional Specifications: 0.00
Frame: 0.00
Binding: 0.00
Valance: 0.00

0.00 2500.00
Item Subtotal: $ 2,500.00
0 0 0 0 $0.00 x Qty 0.00
feet inches feet inches unit price quantity Product Option Adjustments:

Material: Additional Specifications: 0.00
Frame: 0.00
Binding: 0.00
Valance: 0.00

0.00 0.00
Item Subtotal: $ 0.00
Subtotal Primary Items $ 48,676.36
Quantity Discount Amount: $ 0.00
Accessories: Qty Extension
$ 0 $
0 0 Total Accessories: $ 0.00
0 Subtotal Pre-Tax: $ 48,676.36
Sales Tax: $ 3,082.84
Total Contract Price Including Sales Taxes: $ 51,759.20 Start of work commences with the above design layout. Down Payment/Schedule of Progress Payments as follows:

Completion estimated to be 2-4 Weeks from deposit date. Execution of this contract requires payment made now in the amount of:-----------------------> $ 18,815.34 Representing initial deposit in accordance with contract regulation plus progress payment for design layout and custom materials procurement. via check or credit card #
Final payment of remaining contract balance is due upon installation. exp.

Billing zip code
Superior Awning, by: X Date:

ACCEPTANCE: I, the undersigned, acknowledge that I have read and understood the terms of this agreement including the Terms, Conditions & Notices enclosed herewith.

Cost/Unit
Christopher Garcia (818) 512-9769 [email protected] 1/0/1900 0 Permits and related fees and drawings are not included unless expressly and separately itemized. Gore™ Tenara® thread carries a lifetime warranty against defect or deterioration and all steel is galvanized and rust resistant. Other warranties as itemized above. See warranty literature for details/limitations. 0 0
0 0.00

0.00 0
Custom Product (see specs)
0 0
0 0
0 0
---------------------------------> $
City Of San Marino (Chris Gutierrez)
25012201-35
1/22/2025
---------------------------------> $
0 0
0 2200 Huntington Dr San Marino Ca.
[email protected]
ppv240405GLA
Aluminum Patio Cover - Freestanding
(626) 476-7057
White 12" Pans
0 0
0 Standard Roof
0 Installation Included
0 0
Fabricate and install an aluminum carport using customers existing 6x steel posts and 7" I-beams. Order with extra rigid W pan to cantilever 12' beyond existing 32' W x 20' P frame (See BH) no additional posts will be needed.
0 Product Description
0 0
0 0
0 0
0 0
0 0
Prevailing Wage
0 Priced as prevailing wage
0 0
Demo and disposal of existing 32'x 20' aluminum patio
0 0
0 0
0 0
---------------------------------> $
0 0
0 0
0 0
Purchaser Signature: X ___________________________________ Date: ________________

← All documents from this meeting