Att 1 - Dale Ave Pump Station Improvements - Contract Change Order Summary

San Mateo City Council
November 6, 2023

Document
Att 1 - Dale Ave Pump Station Improvements - Contract Change Order Summary
Meeting
November 6, 2023
Body
San Mateo City Council
Original file
452 KB
Text extracted from the city's file for reading and search. Open the original on sanmateo.primegov.com. That file is the official record.

Att 1 - Dale Ave Pump Station Improvements - Anvil Builders - Contract Change Order Summary (as of 10/27/2023) CCO # Execution
Date Price Details of Change
1 6/25/2020 34,336.13$ Provide two new surge tanks for operation under full vacuum conditions 2 11/12/2020 143,160.81$ Add lifting handles to metal plates; elevator cost split; 36" pipe connections to wetwells; and RCP force main coupling
3 2/8/2021 413,991.93$ Force main and influent junction box shutdowns and plug installations; and force main dewatering 4 4/7/2021 39,973.38$ 4 month power fluctuation monitoring to determine if there are impacts to pump operations 5 7/20/2021 429,433.45$
SCADA hardware modifications; Force main #1 groundwater and pipe liquid mitigation; Force Main #2 joint pressure test; Force Main liner access pit relocations; Elevator cab modifications; switchboard surge protection device; grit cleanup; sump pump relocation; slide gate plate; force main wall penetration; and wet well crack repair
6 10/25/2021 225,359.53$ HVAC monitoring panel, horn, strobe, pressure switches, and control wires 7 4/19/2022 37,369.00$ PLC upgrades, programming, and control wiring modifications to correct pump stop logic 8 4/19/2022 228,176.24$ Sump pump conduit wiring; HVAC redesign; and force main 1 pipe conflicts 9 5/4/2022 95,251.54$ Fiber connection change; surge tank demo of underground vault for pile construction; wet well crack repair; street light repair; sump pump guide rails; antenna transmission capabilities; and infill plates 10 7/11/2022 162,843.78$ Temporary generator through June 2022 due to Air District Permit issue with permanent generator 11 9/26/2022 188,747.97$
Work hour waiver; antenna pole; temporary generator; smith blair grout packing; pipe lining delay charges; fan reconfiguration; force main penetration leaks; electrical changes; and SCADA antenna conduit
12 11/13/2022 202,693.78$
Reroute MCC wires; flowmeter install; exhaust beam supports; temporary generator extension; additional structural calculations for elevator; emergency feeder conduit/roof drain; UPS power monitoring; gas monitoring system repair; jacket water heaters; stairway light switches; generator silencer; rotating valves bonnets; and elevator abandonment 13 11/13/2022 1,115,403.92$ Tier 4 generator procurement, shipping, assembly, emmission abatement equipment, wiring, controls, and submittals
14 7/30/2023 46,209.60$
MAS Devicenet modifications; cover elevator openings; weather tower radio conduit removal; elevator pit leak repair; old gas sensor replacement; air compressor repair service; temporary generator swap; elevator equipment removal and de-scoping; and air compressor block heater install
15 10/23/2023 55,159.58$ Generator parapet enclosure; and pump drain bleed valve install 16 10/23/2023 39,734.00$ Elevator electrical changes TOTAL 3,457,844.64$