Att 1 - Contract Change Order Summary

San Mateo City Council
May 6, 2024

Document
Att 1 - Contract Change Order Summary
Meeting
May 6, 2024
Body
San Mateo City Council
Original file
135 KB
Text extracted from the city's file for reading and search. Open the original on sanmateo.primegov.com. That file is the official record.

Att 1 - Underground Flow Equalization System - Anderson Pacific - Contract Change Order Summary (as of 04/04/2024) Table 1. Contract Change Orders that Utilized Contengecy Reserve CCO ID Execution
Date
Price Details of Change
1 1/4/2021 $3,645.41 Addition of 9 Sensors to the tipping buckets 2 6/2/2021 $19,250.14 Additional temporary traffic control measures for the Event Center 3 7/20/2021 ($52,338.58) Additional actuator support beams for the Northern Diversion Structure and Credit for reduced dewatering, 5 9/23/2021 $45,466.22 Additional Electrical Breaker and installation of Baker tank 6 9/23/2021 $497,875.00 Addressing of Pipe buoyancy issues and unusual soil conditions during microtunneling 7 3/2/2022 $547,128.70 Additional manhole shoring, excavation and backfilling to avoid onsite utility conflicts at Delaware / 25th Ave. 8 5/16/2022 $264,129.00 Additional electrical upgrades, 20 ft of Microtunneling on Delaware and construction of additional Manhole and other minor changes
9 8/23/2022 $105,335.07 HVAC Equipment and Controls Modification, additional manhole installation 10 1/4/2023 $219,092.24 Differing subsurface site conditions, additional Level Sensor installation, additional CIPP lining, additional treated soil cost and other changes
11 1/4/2023 $1,044,154.39 Differring subsurface site conditions and additional Stormwater Bypass System 12 5/18/2023 $289,825.80 Additional work associated with foul air vent, additional combination air release valve and CIPP Price Escalation cost
13 5/31/2023 $125,739.67 Extension of Fiber Optic Conduit on 28th Ave 14 7/27/2023 $250,000.00 Additional Station 1 Landscaping restoration 15 8/24/2023 $95,140.97 Additional Force Main Re-routing and inspection and CCTV, resoration of fence and other changes 16 11/8/2023 $134,410.35 Additional Slide Gate Conduit and FRP Duct Support Hardware, Pump Rental 17 1/2/2024 $152,027.34 Traffic Signal Conduit Restoration and Rerouting 18 3/4/2024 $773,380.04 Additional porous concrete paving, additional Equipment Training, additional tree removal and disposal, and other changes
19 3/6/2024 $162,324.09 Additional excavation and other costs due to differing subsurface site conditions Total $4,676,585.85
Table 2. Contract and Change Orders that Did Not Utilize Contengecy Reserve CCO ID Execution
Date
Price Details of Change
Original Contract $55,277,330.00 UFES Construction contract CCO 4 8/18/2021 $3,877,875 Scope addition from Delaware Street Relief Sewer project Total $59,155,205.00 Revised UFES Construction contract