1 0
0 9
1 CITY OF SAN MATEO
RESOLUTION NO.__ (2024)
RESOLUTION ADOPTING A LIST OF PROJECTS FOR FISCAL YEAR 2024-25 FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and Signed into law by the Governor in April 2017 to address the significant multi-modal transportation funding shortfalls statewide; and WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of our City are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and WHEREAS, the City will receive an estimated $2.70 million in RMRA funding in Fiscal Year 2024-25 from SB 1; and
WHEREAS, this is the 8th year in which the City is receiving SB 1 funding which will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and WHEREAS, the City used a Pavement Management System to develop the SB 1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the communities priorities for transportation investment; and WHEREAS, the proposed project list is part of the City’s Smooth Street Program which is endorsed by the San Mateo City Council through public process; and WHEREAS, the funding from SB 1 will help the City maintain, rehabilitate, and reconstruct twenty-one (21) roadway segments currently in poor or failed condition throughout the City this year; and
WHEREAS, the 2018 California Statewide Local Streets and Roads Needs Assessment found the City of San Mateo’s overall streets and roads are in a good condition, however some of the street segments in poor condition have not been addressed and this revenue will help us increase the overall quality of our entire road system over the next decade and bring our overall streets and roads into a better condition; and
1 0
0 9
1 WHEREAS, the SB 1 project list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-edge technology, materials and practices, will have significant positive co-benefits statewide; and
WHEREAS, the City affirms its commitment that the apportionments received will be used and reported on as required by statute and the Commission’s adopted program guidelines.
NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the City Council of the City of San Mateo, State of California, as follows:
1. The foregoing recitals are true and correct.
2. The following list of newly proposed projects will be funded in-part or solely with Fiscal Year 2024-25 Road Maintenance and Rehabilitation Account revenues:
Project Title: Citywide Street Reconstruction Phase 5
Project Description: Project work includes milling of pavement surface or removal of asphalt concrete and base, overlaying asphalt concrete or placement of asphalt concrete and base, upgrading curb access ramps, installation of pavement markings and striping and other incidental work.
Project Location: The following locations identified are subject to be changed:
Street From To
29th Ave Alameda de las Pulgas Juniper St
Bettina Ave City Limit 42nd Ave
Echo Ave Norfolk St Lodi Ave
High View Drive City Limit Newlands Ave
Idaho St Sunnybrae Blvd 10th Ave
Iowa Drive Parrott Dr Nevada Ave
Juniper Street 29th Ave 28th Ave
Juniper Street 30th Ave 29th Ave
Lula Bella Lane Hacienda St Flores St
Noe Ave ECHO S/S Norfolk St
Oregon Avenue St. John's Cemetery Bucknell Dr
Overland Drive 27' S of Woodberry Dr 55' S of Palos Verdes Dr Oxford Ave Hamlett St Norfolk St
Pierce Street Speers Ave Queens Ave
Rolling Hills Ave Alameda de las Pulgas Hacienda St
Rolling Hills Ave Hacienda St End
1 0
0 9
1 San Benito Street Antioch Dr San Miguel Way
Terrace Way Isabelle Ave Alameda de las Pulgas
Tilia Street Borel Ave Hobart Ave
Tulane Court Tulane Road End
29th Ave Alameda de las Pulgas Juniper St
Estimated Project Schedule: Construction is estimated to begin in Fall 2024 and be completed by Spring 2025.
Estimated Project Useful Life: The estimated useful life of the Project is average 20 years.
RESOLUTION NO. ____ PASSED AND ADOPTED by the City Council of the City of San Mateo, California, at a regular meeting held on this _______ day of _______, 2024, by the following vote: