• cognizant
Project Change Order #8
December 13 2024
Contents
Project change order ...3
Summary ....3
Request Description. 4
Business Purpose / Reason for Change ... ....4
Impact Assessment 5
Payment Terms.. .... 6
Assumptions.. ....6
Authoriza..

Project change order
This Change Order form is used for requesting, documenting and approving changes to the change from the originally planned Workday deployment or applicable service offering.

Summary
Client: City of San Mateo
SOW/Project Name: PROJ_54648/ Cty of San Mateo, CA - HCM/Pay - Phase 2 Change Order#: C08
Project Manager (Client): Pete Owen, City of San Mateo
Project Sponsor (Client): Pete Owen, Director of IT
Engagement Manager: Ken Clark, Cognizant
Acceptance Due Date: 1/31/2025
Change Type: Term Extension additional hours added)
Impact Assessed by: Jane Davis, Ken Clark, Neil Brosnan, Sarah Gardner, Randy Ustianowski, Laurie Bledsoe, Kelton Wheatley, Gaurav Sethi, Laura MacInnes, Rachel Taylor, Pete Owen,
Priority: High
Billing: Change #1: The project extension scope will be billed under current project.

Contract Line Type: The project extension scope will be Fixed Fee.

Is new PO# required? No new PO# needed
Request Description
Change #1: This Change Order extends the projecttimeline 12 weeks and set the anticipated Go-Live date to March 16, 2025. No new scope items. All work will be focus on resolving open items and payroll impacting issues which will be managed by the project PMO.

Go-Live Push Items Change Order Price
Extension of Resources for all Functional areas $259,922.00 including the EM
Sub Total $259,922.00
Cognizant Investment $60,000.00
"Go-Live" Change Order Amount $199,922.00
Change #2: The following projects end dates will also be revised:

City of San Mateo, CA - HCM/Pay - Phase 2 - New project end Date June 27, 2025 • City of San Mateo - Change Order #6 - Staff Aug on current project (Testing staff augmentation is under this project) New Project End Date March 31, 2025 • City of San Mateo P2 HCM/Pay Change Order 7 - Proj. Extension & Addtl. OC&T New Project End Date March 31, 2025
Business Purpose / Reason for Change
Change #1: The client required more time to complete internal training, close out remaining open items, reduce the payroll variances & have conversations with their unions related to payroll impacts. Therefore, the project go-live date will move to 3/16/2025 from 12/22/2024 (CO#7). As a result of the extension of the project go-live date, the extended post production support for Integrations and payroll support, as stated under CO#6, end date will change from 4/11/2025 to 6/27/2025
Change #2: Need to align all projects end dates to ensure work can continue.

Impact Assessment
Project Activities Timeline as a result of this change order Affected:

Deliverables Timeline
Affected:

Project Schedule Schedule impact will indude:

Impact: • Project extension of 12 weeks
• Current Go-Live Date 12/22/2024
• New Go-Live Date 3/16/2025
Current Project end date 4/11/2025
• Revised project erd date 6/27/2025
Current Timeline
Total 134 weeks
4 12 16 63 20 4 15
Current Plan Stage Architect Configuration Testing Payroll Deploy Post Stage & Prototype Parallel + Production
UES
Start 9/12/2022 10/10/2022 1/2/2023 4/24/2023 | 7/8/2024 11/25/2024 12/24/2024 End 10/7/2022 1/1/2023 4/23/2023 7/7/2024 11/24/2024 12/23/2024 4/11/2025 Revised Timeline
Total 135 weeks
4 12 16 63 20 16 15
Revised Plan Stage Architect Configuration Testing Payroll Deploy Post Stage & Prototype Parallel+ Production
UES
Start 9/12/2022 10/10/2022 1/2/2023 4/24/2023 7/8/2024 11/25/2024 3/16/2025 End 10/7/2022 1/1/2023 4/23/2023 7/7/2024 11/24/2024 3/16/2025 6/27/2025 Change 0 0 12
Payment Terms
Change #1: The total amount $199,922.00 will be split amongst the current milestone payment schedule. Payments for this change order will be made according to the milestone payment schedule below:

Fixed Fee and Invoicing
Invoice Current Revised
Event Invoice Amount (After
Date C08 c08)
Amount
Plan Stage: Delivery of Plan Artifacts 10/7/2022 $124,314.00 N/A $124,314.00 Architect Stage: Sign off 1/01/2023 $251,529.75 N/A $251,529.75 Tenanure Stage: Delivery of End to End 4/23/2023 $385,603.09 N/A $385,603.09 Test Stage: Delivery of End to End - 2 10/02/2023 $499,280.00 N/A $499,280.00 Tenant
Test Stage: Completion of End to End 6/7/2024 $587,756.55 N/A $587,756.55 Test
Test Stage: Completion of Parallel Test 9/30/2024 $519,774.61 N/A $519,774.61 Deploy Stage: Completion of Push to 12/23/20:4 $310,785.00 $99,961.00 $410,746.00 Production (Go Live) 3/16/2025
Post Production Support: Completion of 4/11/2024 $155,757.00 $99,961.00 $255,718.00 Project 6/27/2025
Total Payments $2,834,800.00 $199,922.00 $3,034,722.00
Assumptions
• No new scope items or major configuration changes (and if they do arise, would be subject to a new change order). All work wll be focus on resolving open items and payroll impacting issues.

Any future MOU changes will be handled by The City of San Mateo after go-live. : All Assumptions from the SOW dated 21 Fabruary 2022 apply to this change Order • No additional tenant build will be required.

No additional Payroll Parallel testing cycles
• Workstream meetings will reduce to an "As needed" basis. • The appropriate San Mateo City team staff will be available to complete the work required to go live.
• Any item marked as of today and going forward as a post go-live item, will become an item for CVS to addressed.

Authorization
City of San Mateo Cognizant Authorization Signature
Name Name
Job Title Job Title
Date Date