CITY OF SAN MATEO
PUBLIC WORKS DEPARTMENT
330 WEST 20TH AVENUE
SAN MATEO, CA 94403
(650) 522-7300 CONTRACT CHANGE ORDER 2
PROJECT: WWTP BIOSOLIDS HAULING AND DISPOSAL
TO: SYNAGRO- WWT, INC.
CONTRACT CHANGE ORDER NO. 2 Page 1 of 1
Purchase Order No. PO-0001169 03/21/25
You are hereby directed to make the herein described changes from the plans and specifications or do the following described work not included in the plans and specifications on your contract.
DESCRIPTION OF WORK
The wastewater treatment process produces biosolids, which are hauled off-site for disposal on a routine basis at a cost of $78.90 per wet ton. Synagro-WWT, Inc. was awarded the contract to haul the WWTP’s biosolids in accordance with Municipal Code section 3.60.030, a competitive public process was used to obtain bids for this service.
Approve a change order to an agreement with Synagro-WWT Inc. for wastewater treatment plant biosolids hauling and disposal for an increase of $120,000 resulting in a total contract amount not to exceed $2,044,250.
Total cost of change not to exceed: $120,000
We, the undersigned contractor, have given careful consideration to the change proposed and hereby agree, if this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be noted above, and perform all services necessary for the work above specified, and will accept as full payment therefore the prices shown above.
By reason of this proposed change, ___ days extension of time will be allowed.
Date Accepted:
Contractor: SYNAGRO- WWT, INC.
By:
Title: Contracts Manager
DISTRIBUTION: Purchasing Department, Contractor, Construction Inspector, Project Manager/Project Analyst, Project File
STATEMENT OF ACCOUNT
Original Contract Price $1,824,250
Previous Change Orders $100,000
Total to date $1,924,250
This Change Order $120,000
Revised Contract Price $2,044,250
Date Approved:
By:
Matt Fabry, Director of Public Works
NOTE: This change order is not effective until approved by the Director of Public Works.