Att 3 - Construction Management Services Current Cost Estimates

San Mateo City Council
July 20, 2026

Document
Att 3 - Construction Management Services Current Cost Estimates
Meeting
July 20, 2026
Body
San Mateo City Council
Original file
358 KB
Text extracted from the city's file for reading and search. Open the original on sanmateo.primegov.com. That file is the official record.

Tanner Pacific Contract Award: June 21, 2022
Approved End Date (per Amendment No.3): January 1, 2027 Description Amount
Original Agreement: $3,000,000
Amendment No. 1: $0
Amendment No. 2: $2,000,000
Approved Task Order 1 (Basin A): -$940,070
Approved Task Order 2 (IAP 3): -$1,433,124
Approved Task Order 3 (Basin A Add'l) -$394,590
Approved Task Order 4 (WWTP Digester Pumps) -$181,781
Approved Task Order 5 (Basin C): -$632,210
Approved Task Order 6 (IAP 3 Add'l) -$671,605
Amendment No. 3: $1,000,000
Task Order 7 (Digester Transfer Pump Impts Add'l) -$64,528 Task Order 8 (3 Wat Pump Ferric Chlo Constructability) -$8,346 Task Order 9 (MCC Replacement Constructability) -$8,765 Task Order 10 (IAP 3 add'l No. 2) -$679,756
Task Order 11 (3-Water pumping and Ferric Chloride) -$424,473 Task Order 12 (Basin C add'l) -$142,498
Available Funds: $418,254
Future Task Orders to be Added Amount
Biogas and Biosolids Evalulation: Digester 1 Cleaning $155,250 Polymer Injection System $97,750
MCC Replacement - Constructability Review $10,080
IAP3 Extension $480,976
Total Future Task Orders: $744,056
Total Funds Needed Amount
Current Available Funds $418,254
Total Future Task Orders $744,056
Additonal Funds Needed for Amendment No. 4: $325,802
Recommended Additional Funding Request (Rounded): $350,000 AƩ 3 – ConstrucƟon Management Services Current Cost EsƟmates Townsend Management Incorporated Contract Award: June 21, 2022 Approved End Date (per Amendment No.3): January 1, 2027 Description Amount
Original Agreement: $3,000,000
Amendment No. 1: $0
Amendment No. 2: $2,000,000
Approved Task Order 1 (Delaware): -$655,844
Approved Task Order 2a (ECR Constructability Review): -$10,703 Approved Task Order 2b (Basin E): -$525,793
Approved Task Order 3 (EC Relief): -$830,429
Approved Task Order 4 (Basin B): -$496,564
Approved Task Order 5 (ECR Constructability Review 2): -$18,926 Approved Task Order 6 (Lift Stations): -$1,238,760
Amendment No. 3: $1,000,000
Task Order 7 (Basin B Closeout): -$59,982
Available Funds: $2,162,999
Future Task Orders to be Added Amount
Basin D $865,000
El Camino Real & Large Diameter $280,000
Total Future Task Orders: $1,145,000
Total Funds Needed Amount
Current Available Funds $2,162,999
Total Future Task Orders $1,145,000
Total Predicted Amount Remaining upon Contract Completion: $1,017,999 ​Att 3 – Construction Management Services Current Cost Estimates​