RESOLUTION 2023-###
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SAN PABLO AUTHORIZING
A TEMPORARY CONSTRUCTION EASEMENT FOR PACIFIC GAS & ELECTRIC COMPANY ON 1655 FOLSOM AVENUE & WILDCAT CREEK TRAIL FOR STAGING
FOR ITS GAS TRANSMISSION PROJECT
WHEREAS, Improve Public Safety is a Major Policy Goal under the FY 2023- 25 City Council Priority Workplan, effective May 1, 2023.
WHEREAS, this project is exempt from the provisions of CEQA as a minor alteration to land pursuant to Section 15304 of the CEQA Guidelines (14 Cal. Code Regs sec. 15304(e));
WHEREAS, Pacific Gas & Electric Company (PG&E) is strengthening its gas transmission systems to better serve communities;
WHEREAS, PG&E would like a temporary easement on the vacant lot located at 1655 Folsom Avenue and Wildcat Creek Trail;
WHEREAS, the proposed work and the use of the site will commence on A ugust 1, 2023 and will conclude on November 30, 2023, and under easement, PG&E has a right to extend the term on a month by month basis for up to three (3) months;
WHEREAS, PG&E will pay the City $4,100 as compensation for the temporary construction easement. If the term is extended beyond November 30, 2023, the City will receive $1,025 for each additional month;
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of San Pablo authorizes the City Manager to enter into a temporary construction easement for PG&E to use the site located at 1655 Folsom Avenue and Wildcat Creek Trail under the terms described above.
* * * * * * *
ADOPTED this 5
th day of June, 2023, by the following votes:
AYES: COUNCILMEMBERS:
NOES: COUNCILMEMBERS:
ABSENT: COUNCILMEMBERS:
ABSTAIN: COUNCILMEMBERS:
ATTEST: APPROVED:
_________________________________ _________________________________ Dorothy Gantt, City Clerk Abel Pineda, Mayor