4. DOP certification testing shall be observed and witnessed by an Owner’s agent/site representative.

Copies of DOP test results and certification must be submitted to Owner’s agent/site representative within 24 hours of the testing being performed.

5. All poly sheeting to be used for the construction of enclosures/containments must be fire retardant.

SDS information reflecting this requirement must be submitted prior to use.

6. All personnel used by the Contractor to conduct removal or handling of asbestos-containing waste El Portal Elementary School
2600 Moraga Road, San Pablo, CA
67 materials must possess a current accreditation certificate as a worker or contractor/supervisor as described in 40 CFR Part 763, Appendix C to subpart E, Asbestos Model Accreditation Plan.

7. The Contractor shall be responsible for all clean-up and costs associated with the decontamination of occupied spaces adjacent to any containment where removal of asbestos containing stucco/texture is conducted. The Contractor shall also be responsible for damage to building finishes and costs associated with removal of tape glue, staining of wall finishes, or destruction of wall surface integrity.

It is the responsibility of the Contractor to identify with the General Contractor all aspects of the project requirements pertaining to these types of damages.

Owner Responsibilities

1. The Owner shall provide the Contractor with access to the building during scheduled work hours through their representative. This representative is expected to be the General Contractor in charge of the site.

2. The Owner shall also provide the Contractor access to water and electrical hook-ups. However, the Contractor is responsible for all connections, electrical cords, GFCI’s, water hoses, and hose bibs necessary for attachment. GFCI’s are required to be used by the Contractor on all electrical circuits in use.

General Removal Instructions and Requirements

1. Removal of stucco/texture by any method and regardless of asbestos content shall be performed by personnel who are properly trained and accredited to perform Class I Work in public buildings, and are currently approved to conduct work on the project.

2. No personnel are allowed into the containment area for any reason during actual removal work without proper respiratory and personal protective equipment. At a minimum this shall include half- face negative pressure respirator if only hand scrapping is being performed. At a minimum this shall include full-face PAPR if air blasting methods are being employed. Regardless of the method used, full body coveralls, rubber boots, and gloves shall always be required while inside the containment.

No street clothes or shoes shall be worn by workers under full body coveralls or inside containment once removal has begun.

3. All openings, doors, hatches, voids, penetrations, etc. which may lead into the building shall be sealed with poly sheeting. No spray glue may be used on any exterior surface of a building.

4. Removal of stucco/texture regardless of asbestos content over a surface area greater than 25 square feet will require the construction and use of a three stage decontamination unit. This decontamination unit must be directly attached to the entrance of the containment and fully operable with working shower and hot water heater, as well as properly stocked with towels, soap, and shampoo. The clean room of any three stage decontamination unit must be at least 5' in width, 8' in length, and 8' in height. “Pop up” 3' X 3' style prefabricated units will not be allowed for this work. The filtration system must have at least a 1.0 micron particle size collection capability prior to release of the water into the treated water system.

5. Sufficient negative air units shall be installed which will provide a minimum of 4 air changes per hour and -0.03" air pressure differential. A manometer with digital readout capability must be installed and operational. Once these requirements have been met and the negative pressure has been established, the Contractor shall request a pre -start visual inspection from Owner’s agent/site representative.

6. When the Contractor has passed the pre-start visual inspection, removal of stucco/texture may be conducted.

7. Sufficiently wet materials to be removed with amended water prior to and during the removal phase of work, and place into waste containers for disposal.

8. Upon completing removal of all stucco/texture, the Contractor shall conduct wet wiping of all El Portal Elementary School
2600 Moraga Road, San Pablo, CA
68 remaining wall surfaces, poly barriers, scaffolding, etc. to remove settled dust from those surfaces.

Final Visual Inspection

1. Upon completion of all activities listed above, the asbestos contractor shall provide their own visual inspection prior to Owner’s agent/site representative, and shall be present during the inspection by Owner’s agent/site representative to remove any additional dirt and/or clean additional surfaces as needed, prior to encapsulation.

2. The final visual inspection will include an evaluation of all surfaces within the containment area, with emphasis placed on the completeness of materials removed. The Contractor shall thoroughly clean all equipment inside the containment, including all parts of the negative air units exposed to the work performed. New pre-filters shall be installed into all negative air units.

Final Lockdown-Encapsulation

1. Lock down-encapsulation of the containment shall be performed using one of two methods based on the needs of the project.

A. Hand Wipe Method: The needs of the project may require the remaining building component surfaces have no new film materials applied to them. If this is required the asbestos abatement contractor shall use clean wet cloths/towels to wipe existing surface dust off of remaining building components. These cloths/towels will be wetted with clean water and no chemicals or treatments will be added. All poly sheeting scaffolding and other components used to create the containment will be hand wiped with wetted cloths/towels which are treated with lock down-encapsulation chemicals to remove possible surface dust and lock down - encapsulate the surfaces of these items. This method can be used prior to the final visual to complete the final cleaning process.

B. Aerial Dispersal Method: The asbestos contractor shall lock down-encapsulate the entire containment area upon completion of the final visual inspection by the Owner’s agent/site representative, and acceptance of the work as complete.

Clearance Criteria (If Required)

1. All clearance air samples will be analyzed by transmission electron microscopy (TEM), and performed by a NIST/NVLAP accredited laboratory. The clearance criteria for releasing the Contractor is the A HERA Standard, with the average of all air samples less than 70 asbestos structures per square millimeter. Aggressive air sampling will be used, which includes using a leaf blower in conjunction with fans to dislodge any remaining dust within the containme nt.

Disposal Requirements

1. All waste containing less than 1% asbestos shall be properly disposed as a non-hazardous asbestos containing waste at an appropriate landfill. All waste containing greater than 1% asbestos shall be properly disposed as hazardous asbestos waste, in a landfill permitted to accept friable, hazardous ACM.

2. All waste containers shall have labeling in accordance with OSHA, DOT, EPA and DTSC requirements. All "Hazardous Waste" shall also include a Waste manifest with the generator's name, address, and Manifest Document number.

3. If bulk loading of waste into “burrito wrap” style bags is to be performed contractor is responsible for assuring the waste facility is aware of this type of bagging and will accept the waste upon its arrival.

Bulk loading of waste into large “burrito wrap” style containers will result in heavy stresses upon the poly sheeting. Contractor must submit written directions indicating the requirements to be used to create such waste containers. Contractor may not use these container bags until approved by Owner’s Representative.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA
69 Part 23.18 – Fire Debris Abatement Requirements
General Requirements

The demolition and disposal of "partially damaged" or "standing -but-unsafe-to-enter" structures are subject to Asbestos NESHAP requirements. All fire debris material regardless of amount shall be removed in a negative pressure enclosure/containment. The enclosure shall include critical barriers, two layers of plastic on walls if the walls are not being removed, a sufficient number of DOP tested negative air units to attain a level of at least -0.030" of negative air pressure within the containment, a digital recording manometer with a minimum of displaying three digits after the zero (0.000). At a minimum, a three -stage decontamination unit with an operational shower and water filtration system. The clean room of any three stage decontamination unit must be at least 5' in width, 8' in length, and 7' in height. The water filtration system must have at least a 1.0 micron pa rticle size collection capability. Documentation of this capability shall be provided to Owner’s agent/site representative.

When possible, the Contractor shall enclose multiple rooms within a building into a single containment.

Where rooms are joined by a common interior hallway or have a common exterior walkway, multiple spaces shall be joined together creating one containment using poly enclosures. The common work chamber shall be constructed of metal or wood studs and plywood sheeting for security purposes if outside of a building.

Decontamination units and joined “common areas” outside of a building shall have lockable doors or gates created with temporary fencing for security during off-hours.

Contractor Responsibilities

1. Except as amended here and in Section 24, Asbestos Specification/Procedures, all other Sections of this Specification shall be followed.

2. The Contractor shall provide all necessary notifications, equipment, tools, materials, lighting, labor, etc. to perform the work. Notification as appropriate to OSHA, EPA, or the delegated Air Quality Management District is the responsibility of the Contractor.

3. All HEPA equipment to be used on the project must be delivered to the site empty of all debris, clean, free of dust, and in full operating condition.

4. DOP certification testing shall be observed and witnessed by the Owner’s asbestos consultant.

Copies of DOP test results and certification shall be submitted to Owner’s agent/site representative within 24 hours of the testing being performed.

5. All poly sheeting to be used for the construction of enclosures/containments shall be fire rated. SDS information reflecting this requirement shall be submitted prior to use.

6. All personnel used by the Contractor to conduct removal or handling of asbestos-containing waste materials shall possess a current accreditation certificate as a worker or contractor/supervisor as described in 40 CFR Part 763, Appendix C to subpart E, Asbestos Model Accreditation Plan.

7. The Contractor shall be responsible for all clean-up and costs associated with the decontamination of occupied spaces adjacent to any containment where removal of asbestos-containing material is conducted. The Contractor will be responsible for damage to building finishes and costs associated with removal of tape glue, staining of wall finishes, or destruction of wall surface integrity.

Owner Responsibilities

1. The Owner shall provide the Contractor with access to the building during scheduled work hours through their representative. This representative is expected to be the General Contractor in charge of the site. The Owner shall also be responsible for arming and disarming alarm systems on buildings where work will be performed.

2. The Owner shall also provide the Contractor access to water and electrical hook-ups. However, the Contractor is responsible for all connections, electrical cords, GFCI’s, water hoses, and hose bibs necessary for attachment. GFCI’s are required to be used by the Contractor on all electrical circuits El Portal Elementary School
2600 Moraga Road, San Pablo, CA
70 in use.

General Requirements

1. Removal of fire debris by multiple methods and techniques shall be performed by personnel who are trained and accredited to perform Class I work in public buildings, and are currently approved to conduct work on the project.

2. No personnel are allowed into the containment area during actual removal work without proper respiratory and personal protective equipment. At a minimum this shall include half -face negative pressure respirators, full body coveralls, rubber boots, and gloves.

3. All doors, windows, and penetrations into the room(s) shall be sealed with poly sheeting. All ventilation systems shall be locked -out and sealed with critical barriers of either poly sheeting or plywood sheeting.

4. Full enclosure of the walls and ceiling with poly sheeting (as applicable) will be required, no matter what method of removal is used. Support of ceiling poly will be at the discretion of the Contractor.

Ceiling may be constructed of one layer of 4 mil poly sheeting. Walls shall be constructed o f two layers of 4 mil poly.

5. A three stage decontamination unit is required and shall be comprised of zippered doors between the chambers. Flapped doors will not be acceptable. The decontamination unit shall be cleaned daily of all debris, bags, tape, towels, etc. and shall remain clean during the day. The clean room of any three stage decontamination unit shall be at least 5' in width, 8' in length, and 7' in height. Multiple showers are required if the number of asbestos workers exceeds ten per Title 8 3366 Washing Facilities.

When there are less than five employees, the same shower may be used by both sexes if the shower room can be locked from the inside.

6. Since all asbestos workers will be required to shower upon leaving the work area, all workers shall wear a bathing suit under the full body coverall. The shower shall have hot and cold water, shampoo, soap and clean dry towels for drying. No street clothes or shoes shall be worn inside containment by the asbestos contractor employees during the removal process. The contractor cannot wear leather work boots in the shower, so steel toed rubber boots are required to be worn.

Rubber boots shall be left in the equipment room before entering the shower and they can be washed at the end of the work day and placed inside of asbestos waste bag, taped closed and removed.

7. Sufficient negative air units shall be installed which will provide a minimum of 4 air changes per hour and a minimum of -0.030" air pressure differential, while the zippered doors are opened for bag-out of waste. A digital manometer recording shall be made of all days when in use. The manometer tapes shall reflect the location, times, and dates of all measurements recorded. Once these requirements have been met and the negative pressure has been established, the Contractor shall request a pre- start visual inspection from Owner’s agent/site representative.

8. When the Contractor has passed the pre-start visual inspection by the asbestos consultant, removal of fire debris may be conducted.

9. Sufficiently wet fire debris to be removed with amended water prior to and during the removal phase of work, and place into waste containers for disposal. Acceptable me thods of containing the waste material include placing waste into a 6 mil poly bag and seal the bag using tape. This bag shall be moved to the waste load out shower, cleaned of all visible dust and deposited into a second 6 mil poly bag and sealed with tape using the “goose neck” method. This second bag must then be labeled with the appropriate asbestos warning labels for the regulated asbestos containing material (RACM). It is acceptable to have the waste manifest information placed inside of the second bag between the two bags as long as the writing on the waste manifest information can be read.

10. All fire debris removed on a shift shall be placed in waste containers. During asbestos removal, all floors of the containment shall remain wet by frequent wetting with amended water. At no time shall El Portal Elementary School
2600 Moraga Road, San Pablo, CA
71 the floor of the containment be dry.

11. The contractor shall clean all surfaces of the substrate using whatever tools to effectively clean and remove the material. Upon completing the removal of all fire debris, the Contractor shall conduct wet wiping on all remaining surfaces within the containment/enclosure. Use of an airless spray to detail clean the fluted openings is an acceptable cleaning technique.

Final Visual Inspection

1. Upon the completion of all activities listed above, the asbestos contractor shall provide their own visual inspection prior to Owner’s asbestos consultant shall be present during the inspection by Owner’s asbestos consultant to remove/clean additional surfaces as needed, prior to encapsulation.

2. The final visual inspection will include an evaluation of all surfaces within the containment area, with emphasis placed on the completeness of materials removed. Any three dimensional debris identified by the Owner’s asbestos consultant, shall be removed as directed with the use of a HEPA vacuum and other tools as necessary to remove the material. The Contractor shall thoroughly clean all equipment inside the containment, including all parts of the negative air units, and new pre-filters shall be installed into all negative air units.

Final Lockdown-Encapsulation

1. The asbestos contractor may encapsulate the entire containment area upon completion of the final visual inspection by the Owner’s agent/site representative, and acceptance of the work as complete.

Clearance Criteria

a. All clearance air samples will be analyzed by transmission electron microscopy (TEM), and performed by a NIST/NVLAP accredited laboratory. The clearance criteria for releasing the Contractor is the AHERA Standard, with the average of all air samples less than 70 asbestos structures per square millimeter.

Disposal Requirements

1. All fire debris waste shall be disposed as friable hazardous asbestos waste at a landfill permitted to accept friable, hazardous asbestos containing material.

SECTION 24. ASBESTOS SPECIFICATIONS/PROCEDURES

Part 24.1 - Contacts

Contact name, Company, and telephone number

Part 24.2 - Removal Locations

Refer to architectural drawings for this site identifying the buildings and work included in the project and scope of work outline. The General Contractor and his Sub-contractor are responsible for estimating the amount of asbestos-containing materials to be disturbed or removed as revealed on the mandatory bid walk, and provided in the project specifications and architectural drawings. The drawings will also provide the Contractor with locations where work is to be performed to allow computation of the quantities of materials to be impacted or removed.

The asbestos contractor shall provide a complete copy of this specification to their onsite competent person for reference while conducts work on the project. A copy of these specifications shall remain onsite by the asbestos contractor for the duration of the project.

Part 24.3 - Materials to be Abated

Refer to the architectural drawings and project specifications for designations and instructions pertaining to what materials are to be removed or impacted during this project. Directions pertaining to materials to be El Portal Elementary School
2600 Moraga Road, San Pablo, CA
72 impacted or removed during this project are NOT included in this Exhibit. This exhibit includes work practices and procedures for those materials that are impacted by the planned renovation/demolition.

Areas of roofs, walls, floors, and/or ceilings may require penetrations be made during the project which may involve asbestos containing materials (ACM) depending upon the location of penetrations. Prior to impacting any building materials which are listed as “suspect” for containing asbestos by the US EPA the Contractor should refer to Section 25, Asbestos Results List for information pertaining to specific Asbestos Containing Materials (ACM) or products known to exist on the site. Materials suspected of containing asbestos but which have not been tested are “assumed” to contain asbestos.

A hazardous materials inspection was conducte d by Atlas Technical Consultants of El Portal Elementary School in preparation of this project. The contractor shall refer to the Hazardous Mate rials Survey report prepared on April 12, 2023 which includes all suspect building materials that were sampled and analyzed for asbestos and included an assessment for lead in paint and ceramic products. The report also includes discussion on Freon, PCB in ballasts, fluorescent light tubes, mercury switches, radioactive tritium containing exit signs, crystalline silica and mold.

Materials commonly excluded from being suspected for containing asbestos include but are not limited to:
unwrapped pink and yellow fiberglass insulating materials or products, foam insulation, wood, metal, plastic, or glass. All other types of building materials or coatings on the materials listed above are commonly listed as “suspect” and must be tested prior to impact by a Contractor.

Attic spaces at this site may already be contaminated with asbestos roofing debris from prior roofing replacement projects, but is unknown. If ceiling systems are removed and it is discovered that suspect roofing debris is present, the contractor shall stop work and bring it to the attention of the project manager to assess the potential for asbestos.

Any instruction in the project specifications or architectural drawings designating the removal of VFT shall include the removal of the associated floor tile adhesive/mastic and base cove mastic as well. Both of these materials must be assumed to contain asbestos unless reported otherwise in Section 25 of this Exhibit.

Part 24.4 - Containment and Abatement Requirements

The general guidelines in these specifications shall be followed by the asbestos abatement contractor for all work on this project. All requirements of Cal/OSHA Section 1529 and US EPA AHERA regulations apply, and shall be followed, as well as, other applicable regulations.

The Contractor shall follow all requirements set forth in Section 23, Specific Procedures and Requirements when disturbing or removing specific asbestos containing materials.

All asbestos related work shall be performed within negative pressure work enclosures for any class of asbestos work. The term “containment” or “enclosure” shall be construed to mean a containment which is constructed to enclose a work area (as defined in Section 2), and meet all applicable requirements set forth in Sections 2 through 20 of this Specification and all governing regulatory agency requirements. Each containment shall be tailored to meet the needs of the “work area” to be enclosed and include all requirements as set forth in the above related sections and government regulations applicable to asbestos related work.

Sufficient negative air units shall be installed which will provide a minimum of 4 air changes per hour and a minimum of -0.030" air pressure differential, while the zippered doors are opened for bag -out of waste. A digital manometer recording shall be made of all days when in use. The digital recording manometer shall have at a minimum the ability of displaying three digit s after the zero (0.000). The manometer tapes shall reflect the correct location, times, and dates of all measurements recorded. Once these requirements have been met and the negative pressure has been established, the Contractor shall request a pre -start visual inspection from Owner’s asbestos consultant.

A three stage decontamination unit is required and shall be comprised of zippered doors between the chambers. Flapped doors will not be acceptable. The decontamination unit shall be cleaned daily of all debris, bags, tape, towels, etc. and shall remain clean during the day. The clean room of any three stage decontamination unit shall be at least 5' in width, 8' in length, and 7' in height. Multiple showers are required El Portal Elementary School
2600 Moraga Road, San Pablo, CA
73 if the number of asbestos workers exceeds ten per Title 8 3366 Washing Facilities. When there are less than five employees, the same shower may be used by both sexes if the shower room can be locked from the inside.

Part 24.5 - Contractor Assist Requirements

The asbestos contractor shall provide "contractor assist" services for electrical, plumbing, mechanical, and other trades as necessary and agreed to with the General Contractor, for work to be conducted in spaces such as attics, wall cavities, and mechanical rooms where asbestos contamination is present, or where ACM are to be disturbed in order to perform the work.

Contractor assist work shall require the asbestos contractor to construct a mini-cube enclosure, create access to the contaminated area, and wet wipe or HEPA vacuum all dust and debris from the immediate work area as needed to create a "clean" environment for the trade workers to work. All procedures specified in Section

23.3 Mini-Cube Enclosure Requirements shall be followed.

Part 24.6 - Worker Protection

At a minimum half-face respirators with P-100 (HEPA) cartridges, disposable coveralls, and hard sole shoes shall be used during the removal and disposal of all asbestos containing material. Full -face powered air purifying respirators (PAPR) with P-100 cartridges are required for all Class I work. Workers wearing tennis shoes, sandals, or soft sole type shoes will not be allowed to work on roofs or inside containments regardless of the activity being performed. Worker protection for all other work areas shall be in compliance with Cal/OSHA requirements and shall follow the respirator selection as specified in Title 8 section 5144.

Part 24.7 - Electrical and Water Hook-Ups

The Owner shall provide access for electrical and water hook-ups. The Contractor shall install a temporary electrical spider box to an existing electrical panel using a licensed qualified electrical contractor. The Contractor is responsible for all hook -ups, electrical cords, water hoses, and hose bibs necessary for attachment.

Part 24.8 - Visual and Air Clearance Criteria

The Contractor shall perform a pre-final visual of the removal area and adjacent surfaces prior to requesting that Owner’s asbestos consultant conduct a final visual inspection. The pre -final visual performed by the Contractor shall verify that all materials have been completely removed from the work area, and that the work area meets the requirements specified in Section 17.

Upon completion of the pre-final visual inspection by the Contractor, a final visual of the containment area will be performed by Owner’s asbestos consultant. The Contractor shall not be released to encapsulate the containment until receiving acceptance by Owner’s asbestos consultant confirming the removal area and the containment have met the criteria of Owner’s asbestos consultant for completeness of removal of asbestos materials and cleanliness of the containment barriers and surfaces.

Clearance air sampling will be performed following passing the visual inspection, encapsulation of the containment has taken place and a sufficient amount of time has passed to allow the encapsulant to dry. All clearance air samples will be analyzed by transmission electron microscopy (TEM), and performed by a NIST/NVLAP accredited laboratory. The clearance criteria for releasing the Contractor is the AHERA Standard, with the average of all air samples less than 70 asbestos structures per square millimeter.

Aggressive air sampling will be used, which includes using a leaf blower in conjunction with fans to dislodge any remaining dust within the containment.

Part 24.9 - Owner’s Responsibility

Not Used

Part 24.10 - Disposal Requirements

El Portal Elementary School
2600 Moraga Road, San Pablo, CA
74 Disposal of all friable hazardous asbestos containing waste must be tracked utilizing a current copy of a Uniform Hazardous Waste form. These forms are to be properly filled out by the Contractor and signed by an authorized Owner’s representative. All non-friable non-hazardous asbestos waste shall be tracked using a Bill of Lading or equivalent and signed by an authorized Owner’s representative. No individual or representative other than the Owner’s designated representative is permitted to sign Uniform Hazardous Waste forms or bill of Lading or equivalent for the Owner.

It shall be the responsibility of the Contractor to notify Owner’s agent/site representative and coordinate having a hazardous waste manifest properly signed by a Owner representative.

Part 24.11 - Work Periods

Work periods shall be scheduled with Owner’s agent/site representative at least 48 hours prior to the start of any shift. If weekend work is to be conducted, shift times are to be established and approved by Owner’s agent/site representative. All shifts are to consist of 8 hours and will begin at the time specified and agreed to by Owner’s agent/site representative and the abatement contractor.

PREPARED BY:

Matt Reilly
Senior Project Manager
CAC #18-6208

El Portal Elementary School
2600 Moraga Road, San Pablo, CA
75 Part 24.12 - Pre-Construction Submittal List

1. Copy of State of California - Contractor’s State License

2. Copy of State of California CSLB Active License

3. Copy of State of California CSLB Asbestos Certification

4. Copy of Department of Industrial Relations; Division of Occupational Safety and Health; Certificate of Registration for Asbestos-related Work

5. Copy of signed statement from company officer listing citations and pending proceedings against the Contractor, or if there have been no citations, a copy of the statement that no actions by regulatory agencies have occurred in the last three years signed by an officer of the company.

6. General Liability Insurance Certificate

a) Occurrence
b) Asbestos/Lead Activities or Abatement Certificate c) Owner Named as Additional Insured
d) Consultant Named as Additional Insured

7. Auto Insurance

8. Workers' Compensation Insurance

9. Statement of Non-use of Sub-contractors or

a) Name of Each Sub-contractor
b) License Number for Each Sub-contractor
c) General Liability Insurance Certificate for Each Sub-contractor

1) Minimum Coverage of $1,000,000.00
2) Owner Named as Additional Insured
3) Consultant Named as Additional Insured

d) Auto Insurance Certificate for Each Sub-contractor e) Workers' Compensation Insurance Certificate for Each Sub-contractor

1) Owner Named as Additional Insured
2) Consultant Named as Additional Insured

10. Written Notification to CAL/OSHA

11. Written Notification to BAAQMD

12. Copies of City Permits (e.g. Parking or Waste container) or Statement That no Permits are Required

13. Statement That no Equipment Will be Rented for use With Asbestos or a Statement From Each Rental Company Acknowledging Their Equipment Will be Exposed to Asbestos

14. Non-Emergency Telephone Numbers

a) Local Police Department
b) Sheriff Department
c) Fire Department
El Portal Elementary School
2600 Moraga Road, San Pablo, CA
76 d) Emergency Medical Facility and Directions to That Facility From the Site

15. Written Emergency Plans

16. Written Work Plan

17. Written Schedule

18. Worker Documentation (Must Include at Least One Supervisor)

a) Training Records for Asbestos - AHERA (Supervisor and Worker)* b) Medical Examination Written Opinion Final Report for Each Employee* c) Respiratory Fit Tests for Each Employee*

19. Equipment list, SDS for all materials to be used on the project, including but not limited to, spray glue, encapsulants, wetting agents, mastic remover, etc.

20. Name of laboratory/person used for PCM analysis and copy of current NVLAP Certificate of Accreditation (if applicable), and most recent AIHA Proficiency Analytical Testing (PAT) Program results.

21. Written Statement That OSHA Monitoring Will be Performed During the Project

22. Manufacturers documentation of 5.0 micron filter capability required for waste water

23. Name of Transporter

24. Hazardous Waste Transporter Registration (if applicable) Is required only if work to be conducted involves the removal and disposal of “hazardous” asbestos waste as determined either by definition or designated within the Asbestos Abatement Specifications/Procedures and associated attached Exhibits.

25. Waste Facility Documentation

a) Name and Site Address
b) EPA Identification Number (if applicable)
c) Copy of Current Permit Authorizing Asbestos Waste Receipt and Disposal

26. Signed Copy of Competent Person Form Acknowledging Reading and Understanding the Specifications (Last Page of Forms Sections of Document) This must be signed by the asbestos Contractor/Supervisor who will onsite, not in the contractor’s office.

Note: Items 9, 12, 13, and 21 may be addressed in a single letter as applicable.

* No Contractor’s worker will be allowed to conduct asbestos related work, enter a containment, or regulated area prior to verification of AHERA, respirator, and medical documentation. This verification must either be onsite or faxed to Owner’s agent/site representative prior to entry.

Part 24.13 - Interim Construction Submittals

Upon request by the Owner or Owner’s Representative, the Contractor shall provide copies of documentation identified to be pertinent to the project.

Part 24.14 - Post Construction Submittal List

Contractor shall provide the following post-construction submittals to Owner’s Representative within thirty (30) days of the completion of asbestos abatement work.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA
77 1. Copies of revised notifications to regulatory agencies.

2. Information on all new workers not covered by the pre-construction submittals and not submitted during the project.

3. A copy of worker exposure monitoring results collected in compliance with DOSH regulations (Title 8 CCR, Section 1529) including daily/representative/full - shift/breathing-zone air samples, and 30-minute excursion samples.

4. A copy of the worker/visitor log showing the following for all persons entering the work area: date, name, social security number, entering, and leaving times, company or agency represented, and reason for entry. The Contractor's time records will not be accepted in lieu of a worker/visitor log.

5. Copies of all accident reports submitted during the course of work. If no accidents occur during the project this should be stated in writing by the Contractor.

6. Receipts from the landfill operator acknowledging the Contractor's delivery of wastes, including dat es, container types and quantities, tare weights or material delivered, and all appropriate signatures.

7. A complete record of the air filtration devices used certifying DOP testing (if performed) and a circular chart recording, indicating continuous operation and documenting differential air pressure.

8. Copies of DOP Testing Performed on HEPA Equipment not Previously Submitted

9. Manometer graphs identifying project name, date, and location.

10. A copy of the asbestos waste record showing dates, times, manifest numbers, quantities of wastes, types of containers removed from the work area, the hauler, and the signature of the recorder.

11. A Land Disposal Restrictions Notification and Certification

12. Completed Uniform Hazardous Waste forms

13. Other Documents as Requested

SECTION 25. ASBESTOS RESULTS LIST

Any material not specified on the following list which the Contractor encounters at this site must be considered as “suspect” and “assumed” to contain asbestos per US EPA. The only items excluded from this statement are; bare wood, glass, and metal.

Sample
Numbers Location Homogenous Material Approximate
Quantity
NESHAP
Category Asbestos Content
02-A-E Classrooms 24-28 Drywall and Joint
Compound 10,000 SF NA
Drywall
(NON-DETECTED)
Joint Compound
(0.25-0.50% Chrysotile)
Confirmed by 400 Point
Count
05-A-B Above Ceiling in
Classrooms 24-28 Air Cell Pipe Wrap 500 LF RACM 90% Chrysotile

SECTION 7800 ABATEMENT OF PCB

CONTAINING LIGHT BALLASTS AND MERCURY CONTAINING FLUORESCENT LIGHT TUBES C-21

SECTION II- LEAD

LEAD BASED COATING (LBC) & LEAD CONTAINING COATING (LCC)

ABATEMENT SPECIFICATIONS

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

REQUIREMENTS FOR DISTURBANCE OF

LEAD IN CONSTRUCTION

TABLE OF CONTENTS

Table of Contents
REQUIREMENTS FOR THE DISTURBANCE OF LEAD IN CONSTRUCTION PART 1.0 .. GENERAL REQUIREMENTS 1

1.1 Introduction .............................................................................................................................. 1

1.2 Definitions ................................................................................................................................ 2

1.3 Regulatory Compliance ............................................................................................................ 6

1.3.1 Environmental Protection Agency (EPA) ................................................................................. 6

1.3.2 Housing and Urban Development (HUD) ................................................................................. 7

1.3.3 California Department of Public Health (CDPH) ...................................................................... 7

1.3.4 California Occupational Safety and Health Administration (Cal/OSHA) .................................. 8

1.4 Lead-Work Pre-Job Notification Requirements........................................................................ 9

1.5 Lead Training Requirements .................................................................................................... 9

1.5.1 Minimal Training Required For All Workers Exposed To Lead ................................................ 9

1.5.2 Required Training For Those Exposed Over the Action Level Or Who Conduct Trigger Tasks ............................................................................................................................................... 10

1.5.3 Required Training For Those Who Are Reasonably Expected To Be Exposed Over The PEL And/Or Conduct Trigger Tasks On Over 100 Square Feet of Material .................................. 10

1.6 Required Submittal Documents ............................................................................................. 11

1.6.1 Submittals Prior To the Start Of Work .................................................................................... 11

1.6.2 Submittals Provided During the Work or Following Completion Of The Work If Applicable .. 14

1.7 Third-party Oversight ............................................................................................................. 15

1.8 Air Sampling By the Owner and/or Project Monitor................................................................ 15

1.9 Notification of Employers of Employees in Adjacent Areas ................................................... 15

1.10 Suspension of Work ............................................................................................................... 16

1.11 Pre-Start Meeting ................................................................................................................... 16 PART 2.0 MATERIALS AND EQUIPMENT ........................................................................................ 16

2.1 Fire Resistant Plastic Sheeting (Poly) .................................................................................... 16

2.2 Challenge Testing Of HEPA Filtration Systems ..................................................................... 16

2.3 Vacuum-Assisted Tools ......................................................................................................... 16

2.4 Power Washing ...................................................................................................................... 17

2.5 Personal Protective Equipment .............................................................................................. 17

2.6 Rental Equipment ................................................................................................................... 17 PART 3.0 EXECUTION....................................................................................................................... 18

3.1 Summary ................................................................................................................................ 18

3.2 Compliance with Requirements For The PEL and Action Level ............................................ 18

3.2.1 Personal Air Sampling ............................................................................................................ 18

3.3 Work Involving Whole Component Removal or Demolition Of Entire Structures .................. 19

3.4 Prohibited Work Practices ...................................................................................................... 19

3.5 Competent Person ................................................................................................................. 20

3.6 Work Site Preparation & Containment Requirements............................................................ 20

3.6.1 Exterior Work Site Preparation & Containment ...................................................................... 20

3.6.2 Interior Site Preparation & Containment ................................................................................ 21 El Portal Elementary School
2600 Moraga Road, San Pablo, CA

REQUIREMENTS FOR DISTURBANCE OF

LEAD IN CONSTRUCTION

TABLE OF CONTENTS

3.6.3 Additional Containment Requirements for Demolition of Ceramic Tile and Mechanical Disturbance or Blasting Of Lead-Containing Materials without A HEPA-Filtered-Vacuum Recovery System ................................................................................................................... 22

3.6.4 Decontamination Procedures ................................................................................................. 25

3.6.5 Avoiding Contamination of Adjacent Areas By Proper Decontamination .............................. 26

3.6.6 Approval Prior To Start Of Work ............................................................................................ 26

3.7 Wet Work Practices ................................................................................................................ 26

3.8 Prompt Cleanup of Debris ...................................................................................................... 26

3.9 Final Cleanup of The Work Area ............................................................................................ 26

3.9.2 Cleanup of Interior Work Areas .............................................................................................. 27

3.10 Final Inspection of The Work Area ......................................................................................... 27

3.11 Power Washing of Exterior Building Surfaces ....................................................................... 28

3.11.1 Waste Water Discharge Permits ............................................................................................ 28

3.11.2 Required Work Practices For Power Washing ....................................................................... 28

3.12 Lead Waste Management ...................................................................................................... 30

3.12.1 Lead Waste Testing ............................................................................................................... 30

3.12.2 Hazardous Waste Manifests .................................................................................................. 31

3.12.3 Waste Containers ................................................................................................................... 31

3.13 Alternative Work Plans ........................................................................................................... 32 PART 4.0 DOCUMENTATION SUBMITTAL REQUIREMENTS ............................................... 32 PART 5.0. LEAD RESULTS LIST ...................................................................................................... 36 El Portal Elementary School
2600 Moraga Road, San Pablo, CA

1 REQUIREMENTS FOR THE DISTURBANCE OF LEAD IN CONSTRUCTION PART 1.0 GENERAL REQUIREMENTS

1.1 Introduction

These specifications are designed to minimize and control potential lead hazards during the disturbance of materials that contain lead. These procedures and precautions apply to the distu rbance of lead that may result from the preparation of surfaces prior to painting, from the drilling into, cutting into, or removal of building components containing or covered with lead, or the demolition of buildings and/or structures that contain lead either in or on their surfaces.

The primary focus of these specifications is to address the work practices and procedures that the Contractor and/or other subcontractors must follow when conducting activities that may disturb lead in paint or other coatings or lead in ceramic tile glaze.

Given the age of the building on this project, lead in measurable amounts is common in paint, varnish, stains, and ceramic tile. Testing was conducted at the site to determine concentrations of lead on building surfaces or materials. Attached are the results of the testing. Interior and exterior painted, stained, varnished and glazed building surfaces were found to contain various concentrations of lead. The Contractor or other subcontractors may also encounter other building products such as lead sheeting, roof flashing or roof vents that may, in his or her judgement, be assumed to contain lead until proven otherwise.

The Contractor and other subcontractors working on this project must treat these suspect lead-containing products as containing lead unless the material is tested and proved to not contain lead by Atlas Technical Consultants LLC (Atlas). Unless tested, Cal/OSHA regulations will apply if any of these surfaces or materials will be disturbed during the project work.

Atlas anticipates enforcing Cal/OSHA and California Department of Public Health (CDPH) regulations regarding the training of workers disturbing lead and the containment and work practices utilized during that disturbance. The training requirements for workers and supervisors on this project are summarized in Part

1.5. Lead Training Requirements. The Contractor and other subcontractors disturbing lead must be familiar with the CDPH requirements regarding containment of lead debris and the Cal/OSHA lead in construction standard. Those requirements are summarized below in Part 1.3 Regulatory Compliance.

In summary, the Contractor and subcontractors shall utilize engineering controls to limit the release of lead dust or debris. These engineering controls may include, but are not limited to, using wet methods, using tools with vacuum recovery systems with High Efficiency Air Particulate (HEPA) filtration, using vacuums with HEPA filtration, using negative air pressure differential systems, and by the prompt cleanup of any lead-containing debris that the work might produce. Dry scraping, sanding, grinding, or abrading lead -containing materials is not permitted. All work that disturbs lead will require a containment. The containment may be as simple as plastic sheeting on the floor or ground when drilling minor penetrations or scraping paint on exterior surfaces. Or, for the demolition of ceramic tile and any painted wall systems, it is likely to require the Contractor construct a full containment for the area and utilize a negative air pressure differential system. The requirements for work practices and containment are described in Part 3.5 Work Site Preparation & Containment Requirements.

The requirements of this specification apply to all employers who have employees who may reasonably be exposed to lead on this project. This includes the Contractor, who will normally be an environmental contractor such as an asbestos abatement contractor, or a painting contractor utilizing CDPH lead certified workers and supervisors. In addition, this specification applies to all subcontractors conducting work on this El Portal Elementary School
2600 Moraga Road, San Pablo, CA

2 project who have employees who may disturb lead by drilling, cutting, scraping, or demolishing materials containing lead.

No Contractor shall begin work which will disturb known or suspect lead-containing surfaces or materials in a manner that may expose a worker to lead containing dust, create a potential for building contamination, or create possible lead containing waste, until all required pre-construction documentation has been reviewed and written approval has been received from the Owner and/or Project Monitor.

Activities expected to disturb lead-containing materials include, but are not limited to, painting preparation work such as scraping or sanding, penetration of painted surfaces through drilling or cutting, demolition of painted surfaces, removal of painted building components, and removal, drilling, or cutting of ceramic wall tiles. If the Contractor or subcontractors are observed conducting such activities without having written approval from the Owner and/or Project Monitor, they will be instructed to stop work. Work will not be allowed to resume until the Owner and/or Project Monitor provides approval for the work to begin.

This project involving potential disturbance of lead in the various painted materials is not considered a lead abatement project. The renovation project at this site would be considered “lead related construction work”; therefore, it is Atlas’ opinion the contractor is not required to submit a CDPH Form 8551 for this project.

1.2 Definitions

Action Level - Airborne exposure to lead at or above 30 µg/m3 over an eight-hour-time-weighted average as discussed in 8 CCR 1532.1. Typically, when employees are exposed over the Action Level, the employer must provide blood testing, training in compliance with 8 CCR 1532, and air sampling.

Air Filtration Unit - A portable exhaust system equipped with HEPA filtration and capable of maintaining a constant low velocity air flow into contaminated areas from adjacent uncontaminated areas. At a minimum, the air intake for the air filtration device must have a pre -filter on it which can be changed within the containment area. In most cases, air filtration devices will need to pass challenge testing by DOP before they are allowed to be used on site.

Airlock - A system for permitting ingress and egress with minimum air movement between a contaminated area and an uncontaminated area, typically consisting of two curtained doorways separated by a distance of at least three feet such that one passes through one doorway into the airlock, allowing the doorway sheeting to overlap and close off the opening before proceeding through the second doorway, thereby preventing flow- through contamination.

Air Monitoring - The process of measuring the content of a known volume of air collected during a specific period of time.

Blood Testing - Blood testing for lead and zinc protoporphyrin in compliance with the requirements for medical surveillance as listed in 8 CCR 1532.1.

Cal/OSHA - California Division of Occupational Safety and Health. A California agency that implements and enforces numerous health and safety standards regarding lead.

Certified Lead Supervisor and Worker - Supervisors and workers currently certified by the California Department of Public Health (CDPH).

Challenge Testing - Process used to verify that HEPA-filtered equipment does not leak or exhaust asbestos, lead, or other particulate. This testing must be done by a testing company, not affiliated with the Contractor, and approved by the Owner and Project Monitor. Challenge testing normally uses an oil mist as the challenge agent and measures how much, if any, of the agent is exhausted from the machine being tested.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

3 Clean Room - An uncontaminated area or room which is a part of the worker decontamination enclosure system with provisions for storage of workers' street clothes and clean protective equipment. The term also includes the uncontaminated area or room of a Waste Transfer Airlock.

Containment - Isolation of the work area from the rest of the building to prevent escape of lead in dust, debris or in the air.

Contractor - The Contractor is the person or entity identified as such in the Contract Documents as being responsible for the environmental work as done in response to and in accordance with this document.

References to the "Contractor" include the Contractor’s authorized representatives. The Contractor may be a sub-contractor to the Primary Contractor. The Contractor normally will be responsible for paint preparation work that disturbs lead, paint scraping done prior to the demolition of structures, or the demolition of ceramic tile. The Contractor will typically need to use CDPH certified lead workers and supervisors to conduct their work that disturbs lead. Those employers disturbing smaller amounts of lead such as through drilling, cutting, or small component removal are typically known as a subcontractor for the purposes of this specification.

Critical Barrier - Critical Barriers are used to restrict water and airflow. Critical Barriers are the barriers placed over openings in the walls and ceilings of a work area in order to ensure that lead dust cannot escape the work area via these openings. Unless otherwise specified in these Specifications, critical barriers shall be constructed of at least one layer of six-mil thick poly.

Curtained Doorway - A device to allow ingress or egress from one room to another while permitting minimal air movement between the rooms. These are typically constructed by placing two overlapping sheets of plastic over an existing or temporarily framed doorway, securing each along the top of the doorway, securing the vertical edge of one sheet along one vertical side of the doorway and securing the vertical edge of the other sheet along the opposite vertical side of the doorway. Other effective designs are permissible as long as they are approved by the Project Monitor.

Decontamination Enclosure System - A series of connected rooms, separated from the work area and from each other by air locks, for the decontamination of workers, conta iners, and equipment. This unit shall be constructed with at least two layers of six mil poly for the floors, walls, and ceiling. The floor of the dirty room shall consist of two layers of six mil poly plus a third layer of poly, four mil or thicker, to be used as a removable drop layer. Drop layer is to be removed as needed, but at least daily.

CDPH - California Department of Public Health. State agency that regulates the disturbance of lead in public buildings and on all structures in California. This agency and relevant regulations are primarily concerned with preventing childhood lead poisoning.

DOP - Dioctylphthalate particles, a testing agent for the efficiency of HEPA filters.

DOT - Department of Transportation, a Federal agency which has regulations and labeling requirements for the transportation of hazardous waste.

DTSC - Department of Toxic Substances Control, a department within the California Environmental Protection Agency charged with implementing and enforcing hazardous waste regulations.

Dust or Debris - Any visible dust or debris remaining in work area will be considered lead-containing residue.

Atlas – Atlas Technical Consultants LLC. This is the Lead Project Monitoring/Management Firm for this project, and is the employer of the Project Monitor used on this project.

EPA - U.S. Environmental Protection Agency, a Federal agency that developed and enforces various asbestos and lead regulations.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

4 HVAC - Heating, ventilation and air conditioning system.

HEPA Filter - A high efficiency particulate air filter capable of removing particles 0.3 microns in diameter from an air stream with 99.97% efficiency.

HEPA-Filtered-Vacuum Recovery System - This is a mechanical tool that has a shroud or covering over the area of a surface disturbed by a mechanical system in order to eliminate or significantly reduce the amount of dust released to the ambient air by the mechanical process. The shroud must be attached to a working vacuum with HEPA filtration.

HEPA Vacuum - A vacuum system equipped with HEPA filtration. Typically these units will need to be challenge tested before being allowed to be used inside of buildings on this project.

Lead-Based Paint - Materials meeting the definition of lead -based paint as defined by the California Department of Public Health and the United States Environmental Projection Agency. Currently defined as containing lead in concentrations equal to or greater than 1.0 mg/cm2, 5000 ppm, or 0.5% by weight.

Lead-Containing Material - Materials that contain measurable, quantifiable amounts of lead. The disturbance of these materials is regulated by Cal/OSHA.

Lead-Containing Hazardous Waste - Materials required by the State of California to be packaged, labeled, transported, and disposed of as a lead hazardous waste.

Lead-Containing Waste Material - Lead-containing waster material that does not need to be treated as a lead-containing hazardous waste.

Lead Project Management or Monitoring Firm – The firm hired by Owner to provide third-party oversight of the disturbance of lead performed on the Owner’s property by the Contractor or subcontractors. This firm is Atlas Technical Consultants.

Mil - A unit of length or thickness equal to one thousandth of an inch. Generally used when referring to the thickness of plastic (poly) sheeting used to contain the regulated area.

Movable Object - An unattached piece of equipment or furniture in the work area which can be removed from the work area.

Negative Air Machines - See Air Filtration Units.

NIOSH - The National Institute for Occupational Safety and Health. All respirators used on this project must be approved by NIOSH.

Outside Air - The air outside buildings and structures.

Owner - Property owner where the disturbance of lead will take place. For example, this may be a private building owner or manager, a government body such as a city or county agency, a military base, or a Owner district. This includes the Owner’s authorized representatives and employees.

PEL - Permissible Exposure Limit (as used in 8 CCR 1532.1)

Permissible Exposure Limit (PEL) - Airborne exposure to lead above 50 µg/m 3 over an eight-hour, time- weighted average as discussed in 8 CCR 1532.1. Typically, when employees are exposed over the PEL, the employer must provide blood testing, respirators, protective clothing, shower decontamination, CDPH certification, regulated areas, and air sampling.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

5 Poly - Flame-retardant polyethylene sheeting used to seal critical barriers, create cleaning barriers and drop layers, and to protect surfaces from damage or contamination.

Primary Contractor - The Contractor may not work directly for the Owner but instead subcontract with another contractor such as a general contractor or demolition contractor. The Primary Contractor is the entity responsible for hiring the Contractor if it is not the Owner.

Pre-start Meeting - Meeting held before the beginning of the project in which final details of the project are discussed and Contractor provides project monitor with pre-job submittal packet.

Project Monitor - An individual qualified by virtue of experience and education, designated as the Owner’s representative and responsible for overseeing the work that disturbs lead on this project.

Project Monitoring - Activities undertaken by the Project Monitoring Firm for the purpose of monitoring the work done by the Contractor on this project in regards to the disturbance of lead.

Regulated Area - Term used by Cal/OSHA in 8 CCR 1532.1 to indicate a work area where exposure to airborne lead might exceed the Permissible Exposure Limit or where “Trigger Activities” may be performed.

The area must be demarcated with signs and barriers designed to keep unauthorized people out of the area.

Additionally “Regulated Area” means any measure used to restrict access to an area where personnel impacting lead-containing materials are required to wear respiratory protection and/or protective clothing by the project specifications regardless of airborne concentration of lead.

Shower Room - A room between the clean room and the equipment room in the decontamination enclosure with hot and cold or warm running water controllable at the tap and suitably arranged for complete showering during decontamination. Unless specified elsewhere in these specifications, or determined otherwise by the program monitor, the shower shall be on a metal pan to contain water splashed, leaked or spilled out of the shower unit.

Specifications - These written requirements describing procedures the Contractor must follow for this project.

Subcontractor - Contractors working for the Primary (General) Contractor but who are not primarily responsible for environmental work. For example, they may be responsible for, demolition, electrical, plumbing, general construction, minor painting, or other special trades.

Submittals - Pre-construction, interim construction, and post construction documents submitted by the contractor to the Owner as indicated in General Requirements and Bidding Requirements.

Trigger Task - Term commonly used to describe the tasks described by Cal/OSHA in 8 CCR 1532.1 (d)(2).

These are tasks or activities that Cal/OSHA believes are expected to result in airborne exposures over the PEL until air monitoring proves otherwise. In brief, trigger tasks include manual demolition, scraping, sanding, using HEPA-attached equipment, using heat guns to remove lead paint, welding, torch cutting, and using other more aggressive techniques. (This is a summary list and does not list all tasks that are considered trigger tasks.) In addition, trigger tasks include any activity reasonably expected to result in airborne exposures to lead above the Permissible Exposure Limit.

View Ports - Clear windows into the regulated work area that allow authorized persons to view work activities inside the regulated area without entering the area. The view ports must be of sufficient number, constructed of materials of sufficient clarity, and be located in areas determined and/or approved of by the Project Monitor.

All regulated work areas including mini-enclosures will require view ports unless specifically determined not to be feasible by the Project Monitor.

Visible Emissions - Any emissions containing particulate material that are visually detectable without the aid El Portal Elementary School
2600 Moraga Road, San Pablo, CA

6 of instruments. For example, dust, debris, and water leaks are considered visible emissions.

Waste Load-out/Transfer System - A decontamination system utilized for transferring containerized waste from inside to outside of the work area. A series of connected rooms used for the load-out of lead-containing materials that have been properly containerized.

Waste Bags - Waste bags for lead -containing waste must be a minimum of six -mil thickness. In general, double bagging will be required.

Waste Containers - Waste containers are the containers into which lead-containing waste is placed. They may be bags of at least six-mil thickness, metal or fiber barrels, or other containers such as cardboard boxes approved by the Project Monitor. The Contractor is responsible for assuring that the type of container chosen is acceptable to the waste landfill to which the waste will be transported. Waste containers must be labeled according to the requirements of the California Department of Occupational Safety and Health (Cal/OSHA), Department of Toxic Substances Control (DTSC), Department of Transportation (DOT), and the Environmental Protection Agency (EPA).

Waste Transfer Airlock - A decontamination system utilized for transferring containerized waste from inside to outside of the work area.

Wet Cleaning - The process of eliminating lead contamination from building surfaces and objects by using cloths, mops, or other utensils which have been dampened with water and afterwards thoroughly decon - taminated or disposed of as lead-contaminated waste.

Work Area - Designated rooms, spaces, or areas of the project in which the disturbance of lead is to be undertaken or which may become contaminated as a result of such action. A contained work area is a work area which has been sealed off from adjacent areas.

Work Plan - Contractor’s written plan describing how the Contractor will perform the work in compliance with these specifications. The work plan shall include information on preparation of the work area, personal protective equipment, employee experience, training and assigned responsibilities during the project. It will also list decontamination procedures for personnel, work area and equipment, removal methods and proc- edures, required air monitoring program, procedures for handling and disposing of waste materials and procedures for final decontamination and cleanup.

Worker - A person who successfully meets the training requirements for the disturbance of lead as described in these specifications.

8 CCR 1532.1 - Chapter 8 of the Labor Code, California Code of Regulations, Section 1532.1: Lead (Known as the Lead Standard for the Construction Industry)

8 CCR 1544 - Chapter 8 of the Labor Code, California Code of Regulations, Section 1544: Respiratory Protection Standard.

1.3 Regulatory Compliance

Various agencies regulate work that disturbs lead -containing materials. The following is a summary of the most important agencies and regulations that apply during the disturbance of lead during construction work.

This list is not to be considered comprehensive. The Contractor is responsible for complying with all applicable federal, state, and local regulations that may apply to the specific work they are conducting.

1.3.1 Environmental Protection Agency (EPA)
Lead: Identification of Dangerous Levels of Lead; Final Rule (40 CFR Part 745 Subpart D)

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

7 The EPA defines lead-based paint as paint and coatings that contain lead in concentrations equal to or more than one milligram per square centimeter (1 mg/cm2), 5000 parts per million (5000 ppm), or one half of one percent (0.5%) by weight. EPA regulations apply to all housing and child -occupied facilities built before 1978. When the term “lead -based paint” is used in the context of these specifications, the term is used only to refer to paint that contains lead in concentrations equal to or greater than that defined by the EPA as lead-based paint. (This is to differentiate lead-based paint from the term “lead-containing paint” as used for compliance with Cal/OSHA.)

1.3.2 Housing and Urban Development (HUD)
Requirements for Notification, Evaluation and Reduction of Lead-Based Paint Hazards in Federally Owned Residential Property and Housing Receiving Federal Assistance (24 CFR Part 35)

The HUD Rule for Federal Housing (shortened name) applies to all residential properties built before 1978 that receive Federal financial assistance. This regulation uses the same definition of lead-based paint as the EPA. The work practices and procedures described in these specifications are designed to comply with occupant and worker protection regulations as mandated by OSHA and Cal/OSHA regulations for work that disturbs lead and are not designed to comply with all the requirements of 24 CFR Part 35. Should this project be covered by this regulation, the Owner may require additional practices and procedures in the scope of work for activities conducted in properties covered by the HUD Rule for Federal Housing.

1.3.3 California Department of Public Health (CDPH)
Accreditation, Certification, and Work Practices For Lead-Based Paint And Lead Hazards (Title 17, CCR, Division 1, Chapter 8, Sections 35000-361000)

This regulation primarily applies to residential and public buildings located in California. The definition of a public building is one that is “generally accessible to the public.” Some aspects of this regulation, particularly those that pertain to the definition of “presumed lead-based paint” and the containment requirements for disturbing lead-based paint apply to all structures in California.

This CDPH regulation definition of lead -based paint is identical to the EPA/HUD definition of 1 mg/cm2, 5000 ppm, and 0.5% by weight. In addition, this regulation requires all paint on structures in California to be treated as “presumed lead-based paint” unless the paint is on a home built after 1978 or an Owner built after 1992. Therefore, the paint in all owner’s buildings covered by this project that were constructed before 1993 must be treated as lead -based paint unless tested and proved otherwise as described elsewhere in these specifications.

The CDPH regulation differentiates between work that disturbs lead as part of renovation or maintenance work and work that disturbs lead as part of “abatement” work as defined in Title 17. The work practices and procedures described in these specifications are designed to comply with occupant and worker protection regulations as mandated by Cal/OSHA regulations for work that disturbs lead as part of renovation, demolition, and maintenance work. These specifications are not designed to comply with the requirements for abatement as defined in the CDPH Title 17 regulation.

Unless stated specifically otherwise in these specifications, the Owner does not anticipate any work being done as part of this projec t that meets the definition of abatement as used in Title 17.

Therefore, unless specifically directed otherwise by this specification or by the direction of the Owner and/or Project Monitor, the Contractor and/or subcontractors shall NOT submit Form 8551, “ABATEMENT OF LEAD HAZARDS,” to the CDPH since that form provides inappropriate notice for the work done on this project. The Contractor may be required to complete and submit this form should the scope of the work or the work practices change.

This regulation has significant penalties associated with the creation of “lead hazards.” Lead hazards are defined as: “...disturbing lead based paint or presumed lead-based paint without containment, or any other nuisance which may result in persistent and quantifiable lead exposure.” The requirements El Portal Elementary School
2600 Moraga Road, San Pablo, CA

8 discussed in Part 3.5 Work Site Preparation & Containment Requirements are designed to meet CDPH requirements. Should a Contractor and/or subcontractor conduct work without a containment or release lead-contaminated dust or debris outside of the containment, they are in violation of this regulation. The Project Monitor will stop all work, consider the Contractor and/or subcontractor to be in violation of these specifications and the contract documents. Work will not be allowed to begin again until the Contractor and/or subcontractor takes adequate steps to correct their violation and convinces the Owner and/or Project Monitor that the violation will not occur again.

1.3.4 California Occupational Safety and Health Administration (Cal/OSHA) Lead Standard for the Construction Industry (8 CCR 1532.1)

This standard regulates work done by employees who may disturb lead as part of demolition, construction, renovation or maintenance work. Painting activities that may disturb lead are covered by this standard. General construction work that disturbs lead is covered, as is the demolition of building components or entire structures.

Cal/OSHA regulates lead whenever lead is determined to exist in a material. When the term “lead- containing paint” is used in the context of these specifications, the term is used to refer to paint that contains lead in an amount equal to or above the reporting limit for the laboratory analysis or that detected by an X-ray Fluorescent Analyzer (XRF).

In addition, Cal/OSHA uses the EPA/HUD/CDPH definition of lead-based paint (1.0 mg/cm2, 5000 ppm, or 0.5% by weight) for their pre-job notification requirements discussed in Part 1.4 Lead-Work Pre-Job Notification Requirements.

The following information summarizes the significant requirements in the Cal/OSHA standard. This summary is not meant to substitute for the Contractor reading and being familiar with the Cal/OSHA requirements.

a. The Cal/OSHA lead standard is very complex. Cal/OSHA regulates lead in materials when a laboratory can quantify the amount of lead. This means materials are regulated even when they contain very small amounts of lead. The standard sets an “Action Level” for airborne lead at or above 30 µg/m3 over an eight-hour-time-weighted average. Typically, if employees are expected to be exposed to this airborne lead level, the employer must conduct air sampling, provide blood lead testing, and provide specialized training. The standard sets a “Permissible Exposure Limit” or “PEL” for airborne lead at or above 50 µg/m3 over an eight- hour-time-weighted average. The employer must continue the requirements needed at the Action Level but must now provide respirators, protective clothing, a shower decontamination system, and a written compliance program.

b. In 8 CCR 1532.1 (p), employers are required to notify Cal/OSHA before employees conduct a trigger task that will disturb more than 100 square or linear feet of material that contains lead in concentrations equal to or above 1.0 mg/cm 2, 5000 ppm, or 0.5% by weight. The notification also applies to welding or torch cutting that takes more than one hour in a shift.

Trigger tasks are described in 8 CCR 1532.1 (d)(2). In brief, they include manual demolition, scraping, sanding, using HEPA-attached equipment, using heat guns to remove lead paint, welding, torch cutting, and using other more aggressive techniques. This is a summary list and does not list all task that are considered trigger tasks.

c. The California standard defines lead -containing paint at the Consumer Product Safety Commission’s (CPSC) level of 0.06% by weight or 90 ppm for non -trigger tasks. The lead standard would not apply if the paint contains less than 90 ppm and the employees do not conduct trigger tasks. However if the employees do conduct trigger tasks, the entire standard applies.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

9 d. Cal/OSHA requires CDPH lead training and certification for any supervisors or workers who are “shown to be exposed” to airborne lead levels above the PEL in residential or public buildings. The Owner and Project Monitor believe that there is a reasonable expectation that those workers scraping paint prior to repainting, and those demolishing ceramic tile are likely to be exposed over the PEL. Therefore, on this project, that work must be done by CDPH certified workers and supervisors.

e. Cal/OSHA requires the supervisor to establish a “regulated area” whenever employees may be exposed to airborne lead over the PEL or if they will perform trigger tasks as defined in 8 CCR 1532.1 (d)(2). The establishment of regulated areas is discussed in Part 3.5 Work Site Preparation & Containment Requirements.

1.4 Lead-Work Pre-Job Notification Requirements

The Contractor is responsible for complying with the Lead-Work Pre-Job Notification as specified in 8 CCR 1532.1 (p). If notification is required for this project, the Contractor must provide the notification to Cal/OSHA and provide a copy of this notification to the Owner and/or Project Monitor as part of the Contractor’s pre-work submittal package.

Unless the material is tested as described elsewhere in these specifications, the Contractor and subcontractors must anticipate notifying Cal/OSHA if they plan to manually demolish or perform another type of trigger task (such as paint scraping or sanding) on any painted surface or ceramic wall surface on this project if the amount of material to be disturbed equals or is greater than 100 square feet.

Notification to Cal/OSHA is not required if the paint on the painted surface is primarily intact (not loose and peeling) and the painted material is removed in a manner that does not disturb the paint. For example, door or window frames may be removed without providing the notification if the paint or coating on the frames is intact and the building components can be removed without significantly disturbing the coating.

Unless stated otherwise in these specifications, or directed otherwise b y the Project Monitor, the Contractor and/or subcontractors shall NOT submit Form 8551, “ABATEMENT OF LEAD HAZARDS,” to the CDPH since that form provides inappropriate notice for the work done on this project since no lead “abatement” as defined by CDPH will be conducted as part of this project.

1.5 Lead Training Requirements

At a minimum, the Contractor and subcontractors must meet the lead training requirements as specified by 8 CCR 1532.1. This will include training all employees who drill, cut, scrape, abrade, remove, clean up debris, or in any other way are exposed to lead from painted surfaces or ceramic tile found on the buildings or structures covered by this project. The different types of training are summarized below for the typical types of work that are expected to disturb lead on this project.

1.5.1 Minimal Training Required For All Workers Exposed To Lead

This training will be sufficient for those who disturb lead in only minor ways. Those disturbing lead in more significant amounts will need to meet the training requirements stated in Part 1.5.2 or 1.5.3.

For example, this training applies to those workers who, for a total of less than one hour in an eight- hour shift, will drill or cut through painted surfaces, remove painted components (when the paint is intact), or remove ceramic tile significantly intact. (This time frame is guidance and not an official Cal/OSHA time frame. This time frame is suggested because it is thought that these tasks, done for such a short time frame, do not pose a realistic chance that workers will be exposed over the Action El Portal Elementary School
2600 Moraga Road, San Pablo, CA

10 Level based on an eight-hour time-weighted average.) In some cases, however, depending on the surface and type of work being conducted, the Project Monitor may determine that more training is needed even if the worker disturbs lead for less than an hour. In general, workers with this training conducting this type of minimal disturbance of lead will not need to wear respirators while conducting this work.

The training must comply with the training requirements as listed 8 CCR 1532.1(l)(1)(A). In summary, this training must comply with Hazard Communication Training for lead as discussed in 8 CCR 5194.

This training is also known as “hazard communication,” or “lead awareness” training and is usually done in less than hour depending on the work the employee will conduct.

The Contractor and subcontractors will need to provide the Owner and/or Project Monitor written proof that this training has been provided before workers will be allowed to conduct work that disturbs lead even in minimal amounts.

Proof of this training is not required if the employees are trained to the levels listed in Part 1.5.2 and/or

1.5.3. 1.5.2 Required Training For Those Exposed Over the Action Level Or Who Conduct Trigger Tasks

This training must be done for all those workers who conduct trigger tasks or are expected to be exposed above the Action Level. Typically, this training will be required for workers who conduct a trigger task such as paint scraping or manual demolition of painted components and the work will take more than one hour in an eight-hour shift. (This is a guidance and not an Cal/OSHA time frame.) The Project Monitor may determine that this training is needed for some workers who conduct tasks for even less than an hour.

The training must comply with the training requirements as listed 8 CCR 1532.1 (l)(1)(B) and (l)(2)(A- H). In summary, the standard requires the worker to be trained in series of subjects. The length of training depends on the experience and previous training of the worker, the type of work they will conduct, and whether or not they already have b een trained and approved to wear respirators.

Workers receiving this training and conducting this type of work will typically need to wear respirators and protective clothing while they conduct the work.

An environmental contractor, or a contractor with environmental work experience, previous training, and a written respiratory protection program generally conducts this type of work. The Owner and Project Monitor do not recommend subcontractors attempt this type of work. However, subcontractors will be allowed to conduct this type of work on this project if they can demonstrate proof of training and carry out the work according to these specifications.

The Contractor and subcontractors will need to provide the Owner and/or Project Monitor written proof that this training has been provided all workers conducting the tasks that require this training.

This training is not required if the employees are trained to the levels listed in Part 1.5.3.

1.5.3 Required Training For Those Who Are Reasonably Expected To Be Exposed Over The PEL And/Or Conduct Trigger Tasks On Over 100 Square Feet of Material

Workers and supervisors must be CDPH Certified Lead -Related Construction Workers or Supervisors if they will conduct trigger tasks or other work reasonably expected to exceed the PEL and/or conduct this work on over 100 square feet of material. (This is a guidance amount and not a Cal/OSHA regulatory requirement. However this amount of material and type of work is reasonably expected to potentially release airborne exposures over the PEL and thus trigger the CDPH certification requirement.) This includes work such as the manual demolition of painted surfaces, ceramic walls, paint preparation work (sanding and scraping), and other tasks as described in 8 CCR El Portal Elementary School
2600 Moraga Road, San Pablo, CA

11 1532.1 (d)(2). Proof of training will be a currently valid CDPH certification card. Workers who can show a completed course completion form and a completed application form for certification will be allowed to work pending their being fully certified.

Exception: Licensed asbestos contractors performing paint scraping work on the outside of buildings only for the purpose of removing loose and peeling paint prior to the demolition of the building, or the demolition of a structure, will not be required to have the workers or on -site supervisor be CDPH certified. They must, however, show proof of training in compliance with 8 CCR 1532.1 (l)(2) for employees who may be exposed above the Action Level. In s ummary they must meet the training requirements of this specification as stated in Part 1.5.2. In addition, however, the Contractor must have a CDPH certified supervisor approve the containment setup at the start of each shift that will disturb lead, approve the work practices and personal protective equipment worn by the workers, verify that proper air monitoring is being collected, must be able to return to the site within two hours if requested by the Project Monitor, and must approve the final clea nup of the work area prior to a visual inspection of the work area being conducted by the Project Monitor. The certified supervisor will always be required to approve the initial set up of the containment, personal protection, and work practices at the start of the job, but then depending on the quality of the work demonstrated, the Project Monitor may not require the certified supervisor to inspect the work site at the start of each shift. This exemption will be revoked should air sampling on this project demonstrate airborne lead levels above the Action Level on workers or supervisors.

1.6 Required Submittal Documents

While additional documents may be required by the scope of work for this project, at a minimum, the Contractor will be required to provide the Owner and/or Project Monitor with the following documents regarding the Contractor’s ability to safely disturb lead-containing materials.

1.6.1 Submittals Prior To the Start Of Work

All Contractors and subcontractors who will have employees disturb lead on this project must, at a minimum, provide proof of item number 1.6.1.e.1., lead hazard communication training in compliance with 8 CCR 1532.1 (l)(A)(1). This is the only submittal that must be provided by these employers as long as they do not disturb conduct more disturbance of lead than is described in Part 1.5.1.

The following submittals must be provided by all Contractors and subcontractors who will, at a minimum, have employees who will conduct trigger tasks for more than one hour per shift, will potentially be exposed above the Action Level, or will conduct other activities as determined by the Project Monitor that may result in significant exposure to lead.

a. A written lead compliance plan in compliance with 8 CCR 1532.1 must be provid ed that includes the following:

1. A description of equipment and materials, controls, crew size, job responsibilities, and operations and maintenance procedures for each activity in which lead is disturbed and potentially emitted;

2. A description of specific control methods (wet methods, engineering controls, etc.) that will be used to ensure workers are not exposed above the PEL;

3. Technology considered in meeting the Cal/OSHA permissible exposure level (PEL);

4. Air monitoring data documenting sources of lead emissions;

5. A detailed implementation schedule for the compliance plan, including the schedule El Portal Elementary School
2600 Moraga Road, San Pablo, CA

12 for inspections by a competent person;

6. A description of the lead work practice program which will be used to control worker exposures. This includes the use of protective work clothing, equipment, hygiene facilities and practices, and housekeeping practices;

7. A description of the steps the Contractor or subcontractor will take to minimize the generation of hazardous waste produced on this project. This includes, but is not necessarily limited to how the contractor will separate waste streams. For example, how will the Contractor or subcontractor keep potentially hazardous waste such as paint chips and dust from being disposed of with other potentially non-hazardous construction materials and debris?

Note: If a Contractor or subcontractor is found conducting lead-related work not specifically mentioned and described in the compliance plan, the work will be stopped until a compliance plan including that work is submitted, reviewed, and approved by the Owner and/or Project Monitor.

b. Copy of the Contractor or subcontractor’s written respirator program in accordance with the requirements of 8 CCR 1544.

c. Proof that all employees expected to wear respirators on this project have medical approval to wear a respirator.

d. Copies of respiratory fit-tests for all workers expected to wear a respirator on this project.

Fit testing must be done as required by and in accordance with 8 CCR 1544.

e. Proof of training required by Part 1.5 for type of work employee will do.

1. Proof of Hazard Communication Training for Lead done within the last calendar year for those exposed to lead or who will perform trigger tasks for less than one hour. (Proof may be a certificate or written statement stating training was completed and a list of names of those individuals who were trained. Proof of this training is not needed if employee provides proof of training required by items e. 2, or e 3.)

2. Proof of training in compliance with 8 CCR 1532.1 (l)(2) done within the last calendar year for all employees who will conduct trigger tasks as defined in 8 CCR 1532.1 (d)(2) for more than one hour or who will reasonably be expected to be exposed to lead above the Action Level. (Proof may be a certificate or written statement stating training was completed and a list of names of those individuals who were trained.)

3. Proof of CDPH lead certification for those workers who will conduct trigger tasks as defined in 8 CCR 1532.1 (d)(2) or will reasonably be expected to be exposed to airborne levels of lead above the PEL on projects that will disturb more than 100 square feet of lead-containing material. (Proof of certification will be a currently valid CDPH certification card as a worker or supervisor. Workers who can show proof of a valid course completion form and application being submitted to CDPH, will be allowed to work while awaiting full certification from CDPH.)

4. Proof of current CDPH certification as a lead supervisor for the on-site competent person for projects involving the conduction of trigger tasks or other activities reasonably expected to exceed the PEL on all projects that will disturb more than El Portal Elementary School
2600 Moraga Road, San Pablo, CA

13 100 square feet of lead-containing material. (Proof of valid certification will be a currently valid CDPH certification card a worker.)

5. If exception to requirement for CDPH certified supervisor listed in Part 1.5.3 is requested, then provide proof of CDPH certified supervisor who will verify containment, personal protection and work practices, and will be able to respond to the project within two hours of request by the Project Monitor.

f. Copies of all current SDS for chemicals used on this project.

g. Manufacturers' certifications that high efficiency particulate air (HEPA) vacuums, pressure differential units and other local exhaust ventilation equipment conform to ANSI Z9.2-79 for all HEPA -filtered equipment that will be used on this project. (This is proof that the equipment is actually HEPA filtered. This is separate from the challenge testing requirement needed for equipment used in interior spaces.)

h. Name and contact information of independent testing company who will challenge test all vacuums and air filtration devices used on this project (in interior spaces).

I. Statement regarding compliance with all Cal/OSHA exposure monitoring required for this project.

j. Name and contact information for laboratory who will analyze air samples or waste samples and documentation of their certification to conduct such analysis.

k. Name of Waste Transporter who will transport hazardous waste on this project and documentation that the Transporter is allowed to transport lead hazardous waste.

l. Name of Waste Landfill to which lead hazardous waste will be sent and documentation that such landfill is allowed to accept such waste.

m. Should waste water filtration be required on this project, submit manufactures documentation pertaining to the capability of waste water filters to filter particles of, at a minim um, five micrometers in size.

n. List of all rented equipment to be used within a lead regulated area, or a statement that no rental equipment will be used on this project.

1. If rental equipment is to be used, submit written statements from each rental company indicating the rental company's acknowledgment that the equipment is provided for and may be used in areas where airborne levels of asbestos and/or lead may be present.

o. Submit emergency plans. At a minimum submit the following:

1. Submit non-emergency telephone numbers, other then 911, for the appropriate Police, Sheriff, and Fire Departments.

2. Name, pager or cell phone numbers of the on -site supervisor and his immediate company supervisor.

3. Submit detailed written directions from the proj ect site to the medical facility to be used in case of an emergency. Also include a map which sufficiently shows the route to be taken from the site to the designated medical facility.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

14 4. Submit written emergency procedures pertinent to the work to be perfor med and which can be implemented by site personnel if the need arises.

p. Local sanitation district Wastewater Discharge Permit for Surface Washers (if required).

q. Cal OSHA Notification. This is required for this work on all projects that will disturb more than 100 square feet of lead-containing material.

The above listed documents must be provided prior to the start of work that will disturb lead. Under no circumstances will workers or supervisors be allowed to work on this project prior to the receipt, review, and acceptance of this documentation by the Owner and/or Project Monitor. In addition, documentation for rental equipment must be provided before the equipment may be used in a lead regulated area. All delays resulting from the failure of the Contractor and/or subcontractors to provide this information in the required time frame is solely the responsibility of the Contractor and/or subcontractor.

The Contractor must use the Pre-Work Submittal Checklist provided at the end of these specifications to provide the Owner and/or Project Monitor these submittals. Failure to use the form will likely lead to the rejection of the submittal package and a delay in the project that will be the sole responsibility of the Contractor and/or subcontractor.

The Contractor is responsible for maintaining current documents and resubmitting copies to the Owner and/or Project Monitor for any worker whose documents expire during the project. Any worker observed on a job site who either is not approved to conduct work by the Owner and/or Project Monitor or has been approved but documentation pertaining to training, medical evaluation, or respiratory fit testing has expired, will be instructed to stop work until these documents are received by the Owner and/or Project Monitor and the worker is approved to perform work that disturbs lead.

1.6.2 Submittals Provided During the Work or Following Completion Of The Work If Applicable

Depending on the document, these documents must be provided the Owner and/or Project Monitor on an ongoing basis during the work, or if appropriate following completion of the physical activities associated with the project. The documents must be received and approved by the Owner and/or Project Monitor before the work is considered complete. (Failure to provide these documents means the work is not complete, even though the physical activities may be completed.)

a. Daily sign-in sheet for each worker entering a lead regulated area.

b. The Contractor must provide the results of exposure sampling done to comply with the requirements of 8 CCR 1532.1 (d) and the requirements of this specification.

c. The Contractor must provide blood sampling and analysis results of lead (BLL) and zinc protoporphyrin (ZPP) levels for all workers who are represented by air monitoring results that exceed the Action Level. Typically, the Project Monitor will require blood lead sampling for all workers on a work shift if one or more air sampling results for that shift is above the Action Level.

The written results of the blood sampling analysis must be provided the Owner and/or Project Monitor within 21 days of the exposure over the Action Level or within 12 days of the completion of the project, whichever comes first.

d. Copies of job progress reports and project documentation. This must include the names of all employees onsite, the hours worked and a brief description of the work completed at the El Portal Elementary School
2600 Moraga Road, San Pablo, CA

15 site(s).

e. The Contractor must provide all waste disposal documentation.

1.7 Third-party Oversight

The Owner is utilizing the services of Atlas as an independent third -party consultant to provide oversight of all work that disturbs lead on this project. The Contractor shall treat this third -party consultant as a designated representative of the Owner. The third-party consultant for this project is known as the Project Monitor. The Project Monitor is expected to perform some or all of the following activities on this project, but may also conduct other activities as needed:

a. Visually monitor the work practices of the Contractor’s employees to determine that the work is being done in compliance with these specifications. The Project Monitor may conduct this activity on a continual basis or may make unannounced random visits to the project site to check on the Contractor’s performance.

b. Visually inspect for the presence of visible emissions suspected to contain lead.

c. Conduct personal and area air monitoring in accordance with accepted methods.

d. Collect bulk samples of relevant materials to determine the presence or absence of lead.

e. Visually inspect the work area for cleanliness after completion of the work.

1.8 Air Sampling By the Owner and/or Project Monitor

The Owner and/or Project Monitor may determine it appropriate to collect air samples to evaluate the effectiveness of the Contr actor’s engineering controls and work practices. The Contractor and/or subcontractors shall allow the Project Monitor to attach and collect personal air samples on the workers and shall instruct the workers to comply with the directions for that sampling as given by the Project Monitor.

Air sampling may also be used to verify the effectiveness of the Contractor’s containment system. The Project Monitor may choose to collect area air samples within the work area. These samples results may be used to generate an eight-hour, time-weighted average. The result of area samples in a lead work area should normally be far below what the workers are breathing. Therefore should the Project Monitor collect area air samples within the work area that result in exposures above half the Action Level (15 µg/m 3), the Project Monitor will require the Contractor and/or subcontractors to re -evaluate their work practices, engineering controls, and containment system.

The Project Monitor may also choose to collect area samples downwind, outside of the regulated work area.These sample results will be compared to background air samples upwind or samples collected prior to the beginning of work. Sample results indicating airborne lead emissions at or above 5 µg/m3 above background levels will be interpreted to mean that the Contractor and/or subcontractor’s containment or engineering controls are inadequate. This may result in the temporary stoppage of work until the Project Monitor is assured that airborne lead levels will signific antly diminish by the change in work practices or engineering controls.

1.9 Notification of Employers of Employees in Adjacent Areas

The Contractor and subcontractors who will disturb lead are responsible for ensuring that employers of employees in areas adjacent to the work being conducted have been notified that work disturbing lead will take place.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

16 Typically this notification is in addition to the posting of lead regulated area signs. In summary, this notice shall be provided to all other contractors and subcontractors in areas adjacent to the work. Those employers must be notified in advance of any upcoming work that will disturb or impact lead in a manner that may generate airborne levels of lead that could present a potential exposure to workers at or above the Permissible Exposure Limit (PEL) as defined in 8 CCR 1532.1©. This notice shall also provide information on the control measures being implemented and a warning that the employer’s employees are to remain outside of the posted regulated areas. The Contractor and/or subcontractors anticipating the need for such notification shall coordinate this notification with the Owner and/or Primary Contractor.

1.10 Suspension of Work

The Owner and/or Project Monitor may suspend all work that disturbs lead if any controls (such as barriers) fail, if debris known or suspected to contain lead is detected outside the containment, or if work is on the exterior of a structure and wind speeds are more than fifteen miles per hour, or if in the judgement of the Project Monitor, other factors exist that determine the work must be stopped because of the potential for the creation of lead hazards. For example, the Project monitor may conduct perimeter monitoring and discover that lead is being released in concentrations at 5 µg/m3 above background levels or work area air monitoring that is above half the Action Level. In either case, the Owner and/or Project Monitor may suspend work until more effective containment, work practices, and engineering controls are utilized.

1.11 Pre-Start Meeting

The Project Monitor typically recommends that there be a pre -start meeting with the Contractor or subcontractor’s representative and the Project Monitor approximately five days prior to the expected start of work. The Contractor will be expected to provide the majority of pre-work submittals described in Part 1.6.1 at that meeting. This meeting is designed to answer questions about the project and address issues of concern of either the Contractor, subcontractor, or Project Monitor. Shoul d this meeting be determined not to be necessary, the submittals must be delivered to the Owner and/or Project Monitor no later than five working days in advance of the work.

PART 2.0 MATERIALS AND EQUIPMENT

2.1 Fire Resistant Plastic Sheeting (Poly)

All plastic sheeting used on this project must be fire resistant whether used inside or outside of buildings.

2.2 Challenge Testing Of HEPA Filtration Systems

All HEPA -equipped vacuums and air filtration units to be used on this project in interior spaces during operations that may disturb lead must be challenge tested and meet ANSI requirements using DOP or an equivalent testing agent. Except for HEPA air filtration units used to create negative pressure differentials for the demolition of ceramic tile, this testing must take place within ten calendar days prior to their use and after replacement of any HEPA filter removed from previously tested equipment. Air filtration units used in conjunction with the demolition of ceramic walls must be challenge tested on site. They do not need to be retested as long as they remain on site. They will need to be retested if they are moved off site. Copies of all testing certifications must be provided to the Owner and Project Monitor prior to use of the equipment.

Exception: Subcontractors using HEPA vacuums for incidental cleanup of lead dust resulting from the minimal disturbance of lead as discussed in Part 1.5.1 are exempt from the challenge testing requirement unless, in the judgement of the Project Monitor, there is a reasonable expectation that the subcontractor’s HEPA vacuums are leaking.

2.3 Vacuum-Assisted Tools

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

17 When using power tools to disturb lead, the Contractor shall only use tools that have a HEPA-filtered-vacuum recovery system.

2.4 Power Washing

No high pressure or water blasting tools may be used if the spray will contact lead -containing paint.

For the purposes of this specification, power washing is defined as: The use of a low pressure “power washer” to rinse and/or wash stable, painted or coated surfaces to remove dust, dirt, grime, and other foreign matter in preparation for re-painting.” Under no circumstance may power washing be used to remove lead-containing paints or coatings from surfaces. Before using power washing, all areas of loose, peeling, cracking, or unstable coatings must first be prepared for re -painting using the appropriate methods and personnel protective equipment as specified by Cal/OSHA and CDPH regulations, and these specifications. Typically this means all loose and peeling paint must be removed by hand scraping and sanding or the use of mechanical tools equipped with HEPA filtration.

Should a Contractor or subcontractor use power washing in a manner that releases paint from the surface, and that paint also not be contained, the Contractor or subcontractor will be responsible for all costs associated with the Owner hiring and environmental contractor to clean up the area. The area to be cleaned will be determined by the Project Monitor and will extend past the point of visually apparent debris.

Prior to performing power wash operations the Contractor must determine if the local sanitation district requires a Wastewater Discharge Permit for Surface Washers. Should this permit be required, the Contractor is responsible for obtaining it, accurately completing it and adhering to the permit requirements.

2.5 Personal Protective Equipment

The Contractor shall use respirators and personal protective equipment as required by 8 CCR 1532.1 and as appropriate based on personal air monitoring results. All respirators must be approved by NIOSH.

Respirator fit test records and the respiratory protection program shall be retained on site as part of the project documentation if respiratory protection is used on this project. Disposable dust/mist respirators shall not be used.

At a minimum, half-face respirators with P-100 (HEPA) cartridges will be required during surface preparation where there is manual scraping or sanding that will take more than one hour to complete. Dry scraping or sanding, mechanical scraping, abrading, sanding, or similar actions will trigger the need for respirators regardless of the duration of the activity.

Regardless of the duration of the work, all workers scraping lead-containing paint or removing or demolishing ceramic tile must wear disposable protective clothing over their wear home clothes. Workers demolishing surfaces that contain ceramic tile must wear full body protective clothing including hoods and gloves.

At a minimum, the Contractor and subcontractors must ensure that no lead dust or debris is tracked out of the contained, regulated area. The Contractor and subcontractors must ensure that all those allowed into the regulated area wear adequate foot coverings that ensure that they will not track contaminated material out of the area when the leave.

2.6 Rental Equipment

Any equipment rented for the purpose of disturbing lead or used within a lead r egulated area must be accompanied with documentation verifying that the rental agency has been notified, and acknowledges receipt of notification that the equipment being rented will be used for work inside a lead regulated area. This documentation must be submitted to the Project Monitor prior to the equipment being used on the job site.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

18 PART 3.0 EXECUTION

3.1 Summary

Contractors and subcontractors conducting lead related construction work will be evaluated on a performance standard which includes, but is not limited to, cleanliness of work area, work practices as verified by exposure monitoring, containment set up, and ultimately, the cleanup of paint chips, dust, and debris.

Any work practice that creates paint chips, dust, glazed ceramic or painted debris must be conducted within a regulated area as defined in 8 CCR 1532.1 and within a containment at least as stringent as required by Title 17 and/or described in these specifications.

The containment system shall be designed and constructed to prevent visible dust or debris from escaping the work area as well as the escape of airborne lead emissions at or above 10 µg/m 3 above background levels. Should dust or debris generated by the work be found outside the containment, or the airborne lead outside the containment exceed background levels, the Project Monitor will determine that the containment is inadequate, in violation of Title 17 requirements, and work will be stopped until the Contractor and/or subcontractors redesign the containment to be more effective.

3.2 Compliance with Requirements For The PEL and Action Level

Contractors and subcontractors strictly adhering to the requirements listed in these specifications who conduct minimal disturbance of lead such as by the conduction of trigger task work amounting to less than one hour, may begin work assuming the Cal/OSHA Permissible Exposure Limit (PEL) will not be exceeded.

Contractors and subcontractors not strictly conforming to suggested work practices must start work assuming the PEL will be exceeded. This means they must comply with all OSHA requirements specified for work that results in exposures over the PEL. This will include, but is not limited to, complying with requirements for training, personal protection, regulated area developm ent, blood testing, personal air monitoring, the development of a written compliance plan, and the notification of employers in adjacent areas.

Contractors and subcontractors must assume the PEL will be exceeded each time they conduct trigger activities that will exceed one hour in duration. This will trigger the need to wear respirators and protective clothing, meet the training requirements specified earlier in these specifications, conduct personal air sampling, develop a written compliance plan and all other actions described as necessary by 8 CCR 1532.1 and these specifications.

3.2.1 Personal Air Sampling

The Contractor and subcontractors are responsible for conducting personal air monitoring during disturbance of lead in compliance with the requirements of 8 CCR 1532.1. At a minimum, Contractors and subcontractors shall conduct representative exposure monitoring on workers on a daily basis whenever those workers will conduct trigger task activities that will take longer than one hour to complete in an eight-hour shift. In addition, air sampling must be done for any work for which the Project Monitor believes has a reasonable potential for generating airborne lead at or above the Action Level. The Project Monitor will not allow work to proceed if the Contractor is not prepared to conduct the necessary air monitoring.

Sample information must include (but is not restricted to) the name of the individuals wearing the samples, the individuals’ Social Security Number or Company ID number, the date the samples were collected, identification by unique method of the area where the work is being performed, and identification of the work being performed. EXAMPLE: James Black, 000 -11-222, 06/25/03, Bill Jackson Elementary Owner, Building H, Classroom 5, East covered walkway, paint surface preparation work.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

19 Laboratory results shall be provided to the Owner and/or Project Monitor within 72 hours of sample collection. Paper copies must be received within 14 days of the Contractor receiving the results from the laboratory. Contractor and/or subcontractor must submit proof that laboratory has the required licenses to analyze air samples for lead.

Should they wish to make use of the exceptions to air sampling stated in 8 CCR 1532.1 (d)(3)© & (D), the Contractor and/or subcontractors must submit the required information to the Owner and/or Project Monitor and receive written approval from the Owner and/or Project Monitor prior to reducing the personal protection, containment, or engineering controls stated in this specification. In general, air sampling results that are intended for use to reduce personal protection requirements must be collected on this project. Air sampling results from other projects will not be allowed to create a negative exposure assessment for use on this project.

Contractor and/or subcontractors must submit a signed statement that they will conduct personal air sampling according to Cal/OSHA requirements for all work where that sampling is required by these specifications. Typically sampling will be required whenever the Contractor and/or subcontractor conduct a trigger task for more than one hour in an eight or more hour shift.

3.3 Work Involving Whole Component Removal or Demolition Of Entire Structures

Intact lead-containing paint on construction debris is generally not considered a hazardous waste in California.

However, loose and peeling paint on structures may result in all construction debris from that site being considered a hazardous waste.

Therefore prior to the demolition or removal of painted material and the disposal of that material, all loose, peeling or flaking paint must be removed. This includes objects such as fences, built-in furniture or cabinets, other similar structures, as well as entire structures being demolished.

Any paint debris generated during this work must be separated into appropriate waste streams and handled as a hazardous waste, or as deemed appropriate as discussed in Part 3.11 Lead Waste Management.

The manual demolition or removal of painted components involving over 100 square feet of material does not trigger the Cal/OSHA pre-work notification as stated in 8 CCR 1532.1 (p) if the paint is intact and will largely remain undisturbed by the removal or demolition process. For example, if door or window frames with intact paint are removed, and the amount of material is over 100 square feet, the Cal/OSHA notification does not need to be provided if the paint is intact and won’t be disturbed by the removal process.

3.4 Prohibited Work Practices

The following work activities are prohibited on the project:

a. Open-flame burning or torching.

b Machine sanding or grinding of lead materials or surfaces coated with lead unless the machine is equipped with a HEPA-filtered-vacuum recovery system.

c. Un-contained hydro-blasting or high-pressure washing.

d. The use of power washing to remove loose and peeling paint.

e. Abrasive blasting or sandblasting without a HEPA-filtered-vacuum recovery system or done outside of a negative pressure enclosure.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

20 f. Heat guns operating above 1,100 °F.
g. Dry scraping, except for limited areas where electrical hazards create a higher risk than lead or unless specifically approved by the Project Monitor.

h. Use of methylene chloride based paint strippers.

3.5 Competent Person

The Contractor and/or subcontractors disturbing lead shall have a competent person (as defined by Cal/OSHA for construction activities) onsite at all times to supervise and oversee all activities which may disturb materials containing lead. This person must be a CDPH Certified Lead Supervisor for all work that involves the conduction of trigger tasks on more than 100 square feet of lead-containing material.

The above requirement is not required for environmental contractors conducting work limited to the removal of loose and peeling paint on structures scheduled for demolition. In those situations, the on-site supervisor must meet the lead training requirements as stated in Part 1.5.2 Required Training For Those Exposed Over the Action Level Or Who Conduct Trigger Tasks. In addition, the Contractor must have a CDPH certified supervisor approve the containment setup at the start of each shift that will disturb lead, approve the work practices and personal protective equipment worn by the workers, verify that proper air monitoring is being collected, be able to return to the site within two hours if requested by the Project Monitor, and approve the final cleanup of the work area prior to a visual inspection of the work area being conducted by the Project Monitor. The certified supervisor will always be required to approve the initial set up of the containment, personal protection, and work practices at the start of the job, but then depending on the quality of the work demonstrated, the Project Monitor may not require the certified supervisor to inspect the work site at the start of each shift. This exemption will be revoked should air sampling on this project demonstrate airborne lead exposures to workers or supervisors are above the Action Level.

3.6 Work Site Preparation & Containment Requirements

The Contractor and/or subcontractor is required to contain the disturbance of lead in a manner that prevents lead-contaminated dust, debris, water, or air from leaving the regulated work area in an uncontrolled fashion.

The containment must be developed in compliance with the requirements of Title 17 and these specifications.

The presence of lead dust, debris, or air above background levels will indicate that the containment is inadequate. Work will be stopped and the Contractor and/or subcontractor must adjust work practices, engineering controls, or the containment in a manner that convinces the Project Monitor that the material will no longer be able to escape the regulated work area.

3.6.1 Exterior Work Site Preparation & Containment

The Contractor and subcontractors are responsible for ensuring that building occupants and those in adjacent areas are not exposed to lead dust or debris as they enter or exit buildings. The Contractor and subcontractors shall ensure that building occupants and others in the adjacent area do not enter the lead regulated area and have a safe means of access and egress to the building.

For exterior work site preparation, one layer of six-mil poly sheeting shall be placed on the ground extending at least ten feet beyond the perimeter of surfaces included in the work. This poly sheeting must be extended a minimum of twenty feet for a multistory building. Depending on wind conditions, the poly may need to be extended further than the ten and twenty foot minimums. The poly on the ground must be adequate to catch all lead -containing debris and water. For example, if the work involves the scraping of paint, all paint chips, dust, debris and water that is released by the work must be contained on the poly.

The poly must be secured to the side of the building or structure with tape, or other anchoring system, El Portal Elementary School
2600 Moraga Road, San Pablo, CA

21 so that there is no gap between the poly and the building or structure. The poly installed to cover ground or landscaping shall be installed in a manner to ensure that it will not blow away or billow from the wind. The use of weights such as wood is acceptable as long as the poly does not billow or blow in a manner that releases lead dust or debris off of it.

The exterior of all windows located within ten feet of any disturbance of lead must be sealed by covering them with at least one layer of six-mil thick poly sheeting. All ventilation machinery within 20 feet of the disturbance should be sealed by at least one layer of six-mil thick poly sheeting. Keep all windows within 20 feet of working surfaces closed, including windows of adjacent structures.

Should the disturbance of paint involve removing paint from the exterior of a window, then the Contractor or subcontractor must seal the inside of the window with two layers of six-mil thick poly.

The Project Monitor will typically waive the requirement to seal the inside of the window with two layers of poly if the disturbance of lead involves less than 5% of the painted surface area of an exterior window.

Those in adjacent areas must be kept a sufficient distance from any chance of encountering lead dust and debris. Therefore the Contractor shall erect barrier tape at a distance sufficient enough from the poly barriers to ensure that those passing by the area are not directly adjacent to the poly containment barriers. In general, the barrier tape should be at least five feet from the edge of the poly placed on ground surfaces if those surfaces are accessible to unauthorized persons. The area off the poly sheeting, but inside of the barrier tape, is still part of the regulated area however and is not allowed to have any lead dust or debris present at any time.

The Contractor and/or subcontractor must post the regulated area sign as described in 8 CCR 1532.1 (m) (WARNING, LEAD WORK AREA, POISON, NO SMOKING OR EATING.) The posting may be done by wording on the barrier tape or by suspending OSHA-approved signs with the wording on the tape barriers or on readily apparent surfaces visible to persons outside the area.

All those entering the regulated area must sign in on a roster that documents their presence in the area. This roster must be provided the Owner and/or Project Monitor on a daily or weekly basis as determined by the Project Monitor.

Work disturbing lead shall not be conducted on exterior surfaces if wind speeds are greater than 15 miles per hour or, in the judgement of the Project Monitor, pose a risk of blowing lead dust or debris out of the regulated area.

In addition, for work done on ladders or man lifts, the Project Monitor is likely to require the workers to scrape loose and peeling paint directly into a container, rather than let the loose debris float down and possibly off the containment barrier. Typically the Project Monitor will allow the workers to scrape loose and peeling paint into a cardboard box held in one hand while scraping with the other hand.

Work must stop and cleanup occur before rain begins.

The Contractor shall not leave debris or poly sheeting out overnight if work is not completed. The Contractor shall keep all debris in a secured area until final disposal.

3.6.2 Interior Site Preparation & Containment

For interior work site preparation, one layer of six-mil poly sheeting must be placed on the entire floor.

However, the entire floor area need not be covered by poly for large interior ar eas where the disturbance of lead is limited to the perimeter of the area. If the entire floor area is not covered with poly, the poly must extend out a minimum of ten feet from those areas where lead will be disturbed.

The poly sheeting must be secured to the wall using tape so there is no gap between the floor and the wall. The poly must also be secured to the floor.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

22 If individual rooms are being worked in, seal all doorways with a primitive airlock flap to prevent contamination of other areas of the building. Post the regulated area signs, as required by 8 CCR 1532.1 (m), at the entrance to the regulated area and all other entry points to the area.

All those entering the regulated area must sign in on a roster that documents their presence in the area. This roster must be provided the Owner and/or Project Monitor on a daily or weekly basis as determined by the Project Monitor.

If feasible, turn off all HVAC systems in the regulated work area. In addition, seal all ventilation systems in the regulated work area with a minimum of one layer of six -mil poly. Any exceptions to this requirement must be approved by the Project Monitor. Typically, the Project Monitor will require all ventilation system ducts and/or registers to be sealed with poly if they are within 20 feet of the disturbance of lead even if they are turned off. Seal all furniture or other equipment that must remain in place with a layer of four or six -mil poly. A minimum of six -mil poly is required for all work disturbing ceramic tile.

Small amounts of ceramic tile, such as covering less than two square feet, may be removed using this type of interior containment if the tiles are removed using hand tools and remain substantially intact during the removal process. Additional requirements for interior site preparation are required when surfaces covered by lead -containing ceramic tile are demolished. Those requirements are discussed in Part 3.6.3.

3.6.3 Additional Containment Requirements for Demolition o f Ceramic Tile and Mechanical Disturbance o r B lasting Of Lead -Containing Materials w ithout A HEPA -Filtered-Vacuum Recovery System

This part primarily addresses work that will involve the demolition of building surfaces covered by lead-containing ceramic tile. These requirements shall also apply shall the Contractor and/or subcontractors disturb lead-containing material, in an interior space, using mechanical or blasting methods without a HEPA-filtered recovery system approved by the Project Monitor.

In addition to the requirements stated in Part 3.6. 2, the demolition of ceramic tile that involves the breakage or cutting of the tile must be done inside a negative air pressure containment system. The negative air pressure must be generated using an air filtration unit that has been challenge tested on site as described in Part 2.2 Challenge Testing Of HEPA Filtration Systems.

Seal all critical barriers between the work area and the adjacent areas with a minimum of six-mil thick poly. Critical barriers are any openings in the surface areas of the regulated work area through which air, dust, or water might pass. This includes, but is not necessarily limited to all windows, doors, HVAC vents and units.

All objects or equipment that cannot be removed from the area must be covered and tape sealed with a minimum of six-mil thick poly. Any exceptions to this requirement must be specifically approved by the Project Monitor.

Typical decontamination requirements for paint scraping and most manual demolition are discussed in Part 3.6.4 Decontamination Procedures. However, the decontamination procedures surrounding the demolition of ceramic tile are much more stringent and are described below.

All regulated work areas where ceramic tile will be broken, or other tasks that will, in the opinion of the Project Monitor, generate significant amounts of lead dust, must include a personal decontamination area and the supervisor must ensure that, at a minimum, the following procedures are followed.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

23 a. Work That Disturbs Less Than 100 Square Feet Of Lead-Containing Material

Work involving the demolition of less than 100 square feet of lead -containing material, including ceramic tile, is not expected to result in airborne exposures over the PEL.

Therefore the personal decontamination system may, at a minimum, be a one stage decontamination system that separates the work area from the adjacent areas.

1. This must, at a minimum, include an airlock chamber between the work area and the adjacent areas. Each side of the air lock must be covered by poly curtains. At no time, including during the removal of waste containers, may the poly doors be open on both sides of this chamber at the same time. This chamber must be a minimum of three feet by three feet by six feet tall. There must be a clean poly drop cloth measuring at least five feet by five feet immediately outside this air lock onto which workers will step after exiting the air lock. This poly drop cloth must be kept visually clean of dust and debris at all times. This poly drop cloth shall be removed at the end of the work shift and replaced with a new clean poly drop cloth at the start of the next shift.

2. The workers must be able to remove their protective clothing and wash off their respirator before leaving the work area. The supervisor must ensure that they do not track lead containing materials out of the work area on their feet. Footwear worn out of the work area must have been covered by protective booties if worn in the work area. Following removal of the protective covering over the footwear, all footwear worn in the work are must be HEPA vacuumed before allowing it to be worn out of the regulated area. Footwear that can be washed before leaving the work area does not need to be covered by protective booties as long as the exterior of the footwear is thoroughly washed prior to being worn outside of the regulated area.

3. After they leave the decontamination chamber, workers must go directly to a nearby location where they must throughly wash their hands and face. Cal/OSHA specifically states that the supervisor must ensure this washing takes place.

4. Special attention must be given that workers do not track lead dust out of the work area on the soles of their feet or shoes.

5. Following the exit of workers from the work area, whether leaving for breaks or at the end of the day, the supervisor must visually inspect the area outside the decontamination system to verify that no dust or debris is being tracked out.

6. The Contractor shall not permit the storage or consumption of food and/or beverages inside the containment or within any of the decontamination chambers. Food or drink consumption within containment may result in the worker(s) dismissal from the site for the duration of the project.

7. Work will be stopped if the Project Monitor determines that the decontamination system is not kept in acceptable condition or used properly.

b. Work That Disturbs More Than 100 Square Feet Of Lead-Containing Material

For all work that disturbs more than 100 square feet of wall ceramic tile, the decontamination system must be a full, three -stage decontamination chamber with a shower as described below.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

24 1. The three-stage decontamination unit with shower must be contiguous with the containment unless determined infeasible by the Project Monitor.

2. The worker decontamination enclosure system shall consist of at least a clean room, a shower room, and an equipment room, separated from the work area by airlock chambers. The airlock chambers shall be at least three feet square in size. All fabricated units shall have, at a minimum, two layers of six-mil poly sheeting.

3. Entry and exit from all airlock chambers and the decontamination enclosure system chambers shall be through doorways designed to restrict air movement between chambers when not in use. The dirty side shall hav e an extra layer of six -mil poly sheeting on the floor as an extra drop cloth and it shall be replaced at least daily.

4. The clean room shall be sized and equipped to adequately accommodate the work crew. Lighting, heat and electricity shall be provided as necessary for comfort. This area must remain clean. If in the judgement of the Project Monitor, equipment storage or other activities taking place in this area affect the cleanliness of the area, the Contractor may be required to move that storage and those activities away from the designated clean area.

5. The shower room shall contain one or more showers as necessary to adequately accommodate workers and shall meet OSHA requirements for temporary shower facilities. The shower enclosure shall be constructed to ensure against leakage of any kind. In addition, the shower shall be a separate unit from the decontamination unit walls. The shower unit cannot be made from poly. Metal or hard plastic is acceptable. An adequate supply of soap, shampoo and towels shall be supplied by the Contractor and available at all times.

6. Shower water shall be drained, collected and filtered through a system with at least a five micrometer particle size collection capability. Filtered waste water shall be disposed of into a sanitary sewage system. Under no circumstances may it be released where it might enter a storm drain.

7. The shower chamber shall be, at a minimum, three feet by three feet wide by a minimum of six feet in height. The shower chamber shall be constructed so that no water from the shower can spray out of the chamber, nor any water run down the sides of the poly and escape the chamber system. The Contractor must have a back-up containment system to control leaks from the shower, connections and hoses. This can be either a secondary metal pan under the shower or a series of poly barriers, separate from the construction of the chamber, that are solely for the purpose of collecting water that might leak out of the shower system.

8. Each decontamination chamber shall have, at least, a four inch lip of poly from the floor up the wall to prevent possible transfer of water and debris between chambers.

Excess poly at the corners of this floor is to be fitted to the sides of the chamber by folding poly and taping, as opposed to cutting away excess poly and taping seams.

For some projects, particularly those where the decontamination chambers are located on surfaces needing special protection from water, the Project Monitor may determine additional precautions are neces sary such as requiring the shower chamber to have an overflow pan, in which the shower unit sits, that is capable of holding two inches of water. The filter system and any hose connections transferring contaminated water shall be located in a secondary containment, such as a metal pan. Any leakage shall be double-bagged or re-filtered. Should this requirement for an additional metal pan under the shower be required, it will be identified elsewhere El Portal Elementary School
2600 Moraga Road, San Pablo, CA

25 in these specifications and discussed at the bid walk.

9. Unless otherwise specified in these specifications, the minimum size of the decontamination chambers shall be the following:

Clean Change Room five feet x six feet x six feet high
Shower three feet x three feet x six feet high
Dirty Change Room five feet x six feet x six feet high
Air Lock Chambers three feet x three feet x six feet high

10. The Dirty Change Room may be part of the work area as long as a separate drop cloth is placed down before the entrance to the first airlock chamber and this drop cloth dust not contain significant quantities of debris from the work area.

11. There must be a clean poly drop cloth measuring at least five feet by five feet immediately outside the clean side airlock onto which workers will step after exiting the airlock. This poly drop cloth must be kept visually clean of dust and debris at all times. This poly drop cloth shall be removed at the end of the work shift and replaced with a new clean poly drop cloth at the start of the next shift.

12. Special attention must be given that workers do not track lead dust out of the work area on the soles of their feet or shoes. Footwear worn out of the work area must have been covered by protective booties if worn in the work area. Following removal of the protective covering over the footwear, all footwear worn in the work are must be HEPA vacuumed before allowing it to be worn out of the regulated area.

Footwear that can be washed before leaving the work area does not need to be covered by protective booties as long as the exterior of the footwear is thoroughly washed prior to being worn outside of the regulated area.

13. Following the exit of workers from the work area, whether leaving for breaks or at the end of the day, the supervisor must visually inspect the area outside the decontamination system to verify that no dust or debris is being tracked out.

14. The Contractor shall not permit the storage or consumption of food and/or beverages inside the containment or within any of the decontamination chambers. Food or drink consumption within containment may result in the worker(s) dismissal from the site for the duration of the project.

15. Work will be stopped if the Project Monitor determines that the decontamination system is not kept in acceptable condition or used properly.

3.6.4 Decontamination Procedures

Decontamination procedures shall be established by the Contractor and subcontractor depending upon the airborne concentrations of lead as well as the amount of dust and debris created by the work. At a minimum, the decontaminati on procedures shall be in compliance with 8 CCR 1532.1 (I)(1-5). As stated in 8 1532.1 (I)(1 -5), the Contractor shall assure that these decontamination facilities are used by the supervisor and workers.

For work that does not exceed the PEL, and/or does not include the disturbance of more than 100 square feet of material, the Contractor and/or subcontractor must assure that a hand-washing station is available and used by the supervisor and workers. For work that exceeds the PEL, or involves the breakage of ceramic tile in amounts over 100 square feet, the Contractor must ensure that workers shower, at a minimum at the end of the work shift as required by 8 CCR 1532.1.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

26 3.6.5 Avoiding Contamination of Adjacent Areas By Proper Decontamination

Should the Owner and/or Project Monitor discover that an occupant of the regulated area left the regulated area without properly decontaminating, the Contractor will be required to clean the adjacent areas that in the opinion of Project Monitor may have been exposed to lead dust or debris from this action. Failure to properly decontaminate is demonstrated by wearing protective clothing outside the regulated area that was previously worn in the area or by wearing footwear outside the regulated area that was not properly covered and/or decontaminated. The failure to adequately decontaminate will trigger the following cleaning. In all areas determined necessary by Project Monitor, the Contractor will be required to HEPA vacuum, then wet wash, then HEPA vacuum again all potentially contaminated areas and items to the satisfaction of the Project Monitor. The Project Monitor will not need to demonstrate the need for this cleaning by the presence of visible dust and will not need to collect settled dust samples in order to require the Contractor to implement the cleaning routine.

3.6.6 Approval Prior To Start Of Work

The Project Monitor shall visually inspect any regulated area for compliance with this specification before the contractor and/or subcontractor may begin work that may disturb lead. The contractor and/or subcontractors may not begin work disturbing lead without approval from the Project Monitor.

The contractor and/or subcontractor must contact the Project Monitor sufficiently in advance of needing the visual inspection and coordinate with the Project Monitor in order to minimize any delays resulting from the need for this visual inspection.

Typically, once the Project Monitor has reviewed the contractor and/or subcontractors regulated work area set up, the work site supervisor will be told that they may start work at future regulated work areas without prior authorization from the Project Monitor as long as they assure the Project Monitor that the containment and work practices will be implemented as approved by the Project Monitor.

3.7 Wet Work Practices

Unless determined infeasible by the Project Monitor, all disturbance of lead-containing materials must utilize wet methods for dust suppression.

3.8 Prompt Cleanup of Debris

Removed lead-containing material shall be kept wet and promptly placed in the type of waste containers required by this specification. The Contractor and subcontractors are encouraged to place debris in containers shortly after it has been removed. However, at a minimum, all bulk debris must be containerized before any work stoppages such as for breaks, lunch, or the end of a shift. Bulk debris must be kept adequately wet until it is containerized. The Contractor must plan only to disturb amounts of material that can be cleaned up and containerized before the next work stoppage. Delays and additional costs incurred by the Contractor for failing to adequately calculate the amount of time needed to clean up debris will be the sole responsibility of the Contractor. For example, if a crew must work overt ime to containerize debris before ending the shift, those additional costs are the sole responsibility of the Contractor.

The Contractor and/or subcontractor must not allow excessive amounts of dust and debris to gather on the floor containment barriers. If in the opinion of the Project Monitor, too much debris is being allowed to gather on the floor poly, the Project Monitor will require the Contractor or subcontractor to either assign a worker to conduct continual cleanup, or the workers scraping paint or conducting other work disturbing lead will have to contain the debris before it falls to the ground. Typically this is done by scraping paint directly into a cardboard box held by the worker as he or she scrapes off the loose and peeling paint.

3.9 Final Cleanup of The Work Area
El Portal Elementary School
2600 Moraga Road, San Pablo, CA

27 3.9.1 Exterior Work Areas

The Contractor and/or subcontractor must HEPA vacuum up all visible dust and debris off containment barriers. Then gently roll and/or fold poly barriers in on themselves in order to avoid releasing any remaining dust to adjacent areas during this process.

The final step will be to vacuum up any visible dust or debris in the work area or regulated area that is suspected to contain lead. The area must be visually clean of all lead-related dust and debris, and all poly barriers must be removed before the workers leave the job site. The regulated area barrier tape and/or signs must be taken down. Critical barriers erected on windows and HVAC systems may be left in place if work will take place in those same areas during the next work shift. Otherwise those barriers must also be removed before the workers leave at the end of the shift.

3.9.2 Cleanup of Interior Work Areas

All cleanup of the interior work area shall be performed using a HEPA vacuum and wet washing techniques. All surface areas in the work area that reasonably could have been exposed to airborne lead must be HEPA vacuumed and/or wet washed. This includes wall surfaces when the work included ceramic tile demolition. Ceilings must also be cleaned if the ceilings are less than five feet above the area where ceramic tiles were disturbed. For example, if the ceramic tile wainscoting extended six feet up the wall, and the ceiling is at eleven feet or lower, the ceiling will need to be vacuumed. If, however, the ceiling is above eleven feet, it will not need to be cleaned. This is based on the assumption that lead dust is unlikely to migrate up more than five feet. If in the judgement of the supervisor or Project Monitor the ceiling may be contaminated, the ceiling shall be cleaned regardless of how far it is above the disturbance of the tile.

3.10 Final Inspection of The Work Area

The Project Monitor will inspect work areas for visual signs of dust and debris related to the disturbance of lead. The Project Mon itor will not inspect or evaluate the quality of paint preparation work such as paint scraping. The contractor who will be painting the prepared surfaces is responsible for the quality and workmanship of the surface preparation. However, if the work involves the removal of loose and peeling paint prior to the demolition of a structure, the Project Monitor will evaluate the completeness of that work.

For exterior work, the Project Monitor will visually inspect the work area to determine that there is no visible dust or debris still in the area that is reasonably expected to have been generated by the work. All poly barriers (except for on critical barriers in areas needed for the next shift) and barrier tape and signs must be removed.

Until told otherwise by the Project Monitor, the supervisor must notify the Project Monitor in advance of the end of the shift in order for the Project Monitor to visually inspect the work area prior to the workers leaving for the day. Typically this will not be required after the workers demonstrate that they consistently properly clean the work area before leaving.

For interior work, the Project Monitor will conduct a thorough visual inspection for dust and debris that may be related to the disturbance of lead. All surface areas must be clean. Residue dust will be assumed to contain lead and must be cleaned.

Until told otherwise by the Project Monitor, the supervisor shall notify the Project Monitor when the supervisor believes the work is complete and ready for a visual inspection. Prior to calling the Project Monitor for the visual inspection, the supervisor must personally inspect the area and determine that it is clean and ready for a final inspection.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

28 The Project Monitor typically will not collect dust wipe sa mples to verify the cleanliness of an area unless specifically stated otherwise elsewhere in these specifications. However, dust wipes may be collected in either of the following circumstances. In both cases the supervisor will be told of the possibility o f the collection of dust wipes and encouraged to conduct extra cleaning of the areas.

a. Ceramic Tile Removal Closely Adjacent To Kindergarten Classrooms, Daycare Facilities, or Food Preparation Areas Including Kitchens and Eating Areas.

The Project Monitor is likely to conduct dust wipe sampling on the floor in the area between the decontamination unit and occupied areas of the property where children under the age of six routinely may be present. The supervisor will be told in advance that this testing will take place and is encouraged to clean the area between the decontamination area and where the sample will be collected. This sample will be collected within 20 feet of the decontamination chambers unless the Project Monitor believes that poor work practices or decontamination procedures have contaminated the area as discussed below.

b. Failure To Comply With Work Practices, Engineering Controls, Or Decontamination Procedures

If in the judgement of the Project Monitor, the Contractor and/or subcontractor has not followed the requirements of this specification regarding work practices, engineering controls, and decontamination procedures, the Project Monitor will collect dust wipe samples in areas believed contaminated by the Contractor or subcontractors’ actions. The supervisor of the project will be told in advance if such testing will be conducted and given time to clean those areas. For example, Part 3.6.5. descri2bes actions that will lead to additional cleaning by the Contractor.

Should dust wipe sampling be necessary, the Project Monitor will conduct such testing with the specified intent of verifying whether the containment process and decontamination processes used by the Contractor and/or subcontractor were adequate in preventing the release of lead dust from the work area. The samples will be collected according to the procedures required in Title 17. The containment will be judged appropriate if the results of the samples do not indicate a dust lead hazard for floors as specified in Title 17.

3.11 Power Washing of Exterior Building Surfaces

For the purposes of this procedure power washing is defined as the use of a low pressure “power washer” to rinse and/or wash stable, painted or coated surfaces to remove dust, dirt, grime, and other foreign matter in preparation for re-painting. In no circumstance is this to be construed as water blasting, and is not intended nor shall be used to remove lead-containing paints or coatings from surfaces. Loose and peeling paint must be removed by the other methods described in this specification before power washing may be conducted.

Should power washing begin to release paint from the substrate, the Contractor must stop the power washing process and remove the loose material following the procedures described in these specifications.

3.11.1 Waste Water Discharge Permits

Many local sanitation districts require the completion and submission of a waste discharge permit prior to allowing the use of power washers. Therefore, prior to performing power- wash operations, the Contractor must obtain a Wastewater Discharge Permit for Surface Washers, if required, from the local Sanitation District, Water Quality Division; Industrial Waste Section, and adhere to the permit requirements. It is the Contractor’s responsibility to obtain and properly fill out a current copy of this permit if it is required.

3.11.2 Required Work Practices For Power Washing
El Portal Elementary School
2600 Moraga Road, San Pablo, CA

29 Where power washing of exterior surfaces of buildings coated with lead-containing paint(s) or seal coats is specified, or in those areas where the Contractor opts to use power washing to prepare surfaces, all of the following conditions must be met prior to uncontrolled washing without waste water control/collection measures. The following test is conducted prior to allowing the beginning of full power washing in order to verify that measurable amounts of lead are not being released by the washing process. Once it is determined that the washing process does not release lead, the Contractor will be allowed to proceed with power washing with only minimal additional requirements.

a. The Contractor in coordination with the Project Monitor shall select a minimum of one test area typical of the surfaces to be power washed. This area shall be 100 or more square feet in area. On some sites where the building surfaces are different, the Project Monitor may require more than one area to be tested.

b. The Contractor shall construct a floor containment for the test areas. The containment must be designed to capture and collect all wash water and any paint chips generated during the assessment. Typically the Contractor simply needs to use poly on the ground to create a basin like effect which will capture the spray water.

c. The Project Monitor will first collect a sample of source water such as from the hose tap. The Contractor will then be asked to power wash the test area in a similar manner as to how the building as a whole will be power washed. Work shall be halted if the washing process causes delamination of paint from the test area surfaces. Modifications to the methods and work practices shall be made prior to resumption of power washing and these modifications must be approved by the Project Monitor prior to their implementation.

d. The Project Monitor will collect one or more samples of the water runoff that was captured by the Contractor following power washing the test area. As long as there are no visible paint chips in the water and/or the amount of water is not excessive, the Contractor may release the captured water as long as it is absorbed by landscaping or will evaporate. No waste water resulting from power washing operations may be allowed to drain into any storm drain as required by the State of California.

e. The Project Monitor will send these samples to a laboratory for lead in water analysis. The sample results for the source water will be compared to the water runoff sample. If similar amounts of lead are present in each, the Project Monitor will reach the conclusion that the power washing process is unlikely to release lead into the water or surrounding area during the power washing process. Typically the power washing process does not release lead as long as loose and peeling paint was removed prior to the start of power washing.

f. The Owner will pay for the collection of these water samples and their laboratory analysis.

g. The Project Monitor will notify the Contractor as soon as the results of the testing process are known. Typically the Contractor will be given permission to begin power washing. The Project Monitor and the Contractor will need to discuss alternatives to power washing in the unlikely situation that the water test shows lead contamination in the runoff water.

h. The Contractor shall assume that the testing and water analysis process will take a total of three work days. For example, if the test is done on the morning of the first day, the water samples will arrive at the laboratory on the morning of the second day. The results of the sampling process will be available on the afternoon of the third day. Since no power washing will be allowed until this testing process shows acceptable results, the Contractor must build this testing process into the work schedule. The Contractor may choose to accelerate the testing process but this will mean that the Contractor, rather than the Owner, will pay for the El Portal Elementary School
2600 Moraga Road, San Pablo, CA

30 transportation of the samples to the laboratory and for the rush laboratory analysis. Even under “rush” conditions, it is very unlikely that the entire process could be completed in one day. The Contractor may want to schedule the testing process prior to the completion of other paint preparation work in order to have the results by the time the paint preparation work is complete.

I. Upon receiving approval to begin power washing, the Contractor will be allowed to proceed power washing the building. The Contractor must, however, notify the Project Monitor 24 hours in advance of the beginning of power washing in order for the Project Monitor to monitor the process should he or she feel that is appropriate.

j. Employee protective measures such as disposable clothing and respirators will not be required as power washing is not likely to result in airborne exposures of lead above the Action Level.

k. Waste water produced from power washing operations which does not contain chips of paint may be allowed to soak into the ground below the area being washed. If the area located below or around the surface to be washed does not allow for absorption into the ground, the water must be directed toward an area on the property that will allow for absorption into the ground or evaporation. The Contractor must take steps to ensure that no waste water enters storm drains. This is State and Federal law. This runoff cannot go into a storm drain regardless of the lead content of the water.

3.12 Lead Waste Management

Proper testing and disposal of all waste material is the responsibility of the Contractor.

The Contractor must plan the work in order to minimize the generation of hazardous waste during the disturbance of lead-containing materials. The Contractor must create separate waste streams as necessary.

This particularly includes the separation of any loose paint chips or flakes or ceramic tile debris from other construction debris. All waste streams must be identified by the Contractor before the work begins and separated during the course of the project to minimize costs of disposal.

The Contractor is responsible for all costs associated with the testing, removal, packing, loading, shipping, and disposal of lead containing waste generated during this project. This does not include waste water testing done to determine if power washing is permitted. The cost of that testing will be covered by the Owner.

The Contractor is required to comply with all regulations in Title 8 Section 1532.1 Lead in Construction and Cal/EPA Title 22 for waste classification and disposal.

3.12.1 Lead Waste Testing

The Contractor must conduct appropriate waste stream characterization testing and/or filtering prior to disposal of waste products such as water, sand, paint chips, vacuum debris, and filters generated during surface preparation activities. Once completed, the test analysis results must be submitted to the Owner and/or Project Monitor for review. The Contractor is responsible for all costs associated with waste stream testing. Contractors may choose to avoid some waste testing by presuming that the waste is a lead hazardous waste. Waste must be tested if the Contractor wishes to treat it as a non-hazardous waste.

The Contractor may not remove or dispose of the identified materials from the job site until this review has been completed and the Contractor has been informed by the Owner and/or Project Monitor of their concurrence that the materials have been properly tested and meet the requirements allowing the materials to be classified as non-hazardous.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

31 3.12.2 Hazardous Waste Manifests

For all hazardous waste that requires an EPA manifest, the Contractor must coordinate with the Owner for signature of the manifest. In general, the Contractor must notify the Owner a minimum of 24 hours in advance of the need for a signature. Hazardous waste cannot be transported without an authorized signature so it is the responsibility of the Contractor to coordinate with the Owner the time waste transporters will need the signature. Delays resulting from the failure of the Contractor to obtain an authorized signature from the Owner will be the sole responsibility of the Contractor, unless the Owner was provided 24 hour in advance notice and the transporter arrived on time during the regular work hours of the Owner.

3.12.3 Waste Containers

All debris generated in the regulated work area shall be placed in containers approved by the Project Monitor. The containers shall be leak tight and meet the requir ements as stated in these specifications. Bags and other containers shall not be overfilled.

If in the judgement of the Project Monitor, the Contractor’s method of containerizing debris is inadequate and either results in the release of dust or debris or is reasonably expected to result in such a release, the Contractor will be forbidden to continue waste containerization or load out until the containers meet the approval of the Project Monitor. This may result in the Contractor being required to change from one type of container to another. It must be understood that the Contractor is responsible for proper containerization of waste and therefore, will be required to provide for adequate and appropriate containers regardless of cost incurred due to failu re of one system of containerization being required over another.

When utilizing bags to contain lead hazardous waste, two bags at least six-mil in thickness must be used. The inner bag may be sealed with adequate amounts of tape necessary to secure the opening of the bag. Only the second or final bag must be gooseneck sealed.

Regardless of the wastes characterization or designation as construction debris or hazardous waste, all waste containers shall be stored in designated and secure areas separate from the work area prior to testing and/or disposal.

The Contractor is responsible for proper storage and labeling of all hazardous waste containers while they are being used as storage and before they leave the job site according to the requirements of DTSC and DOT.

Building components such as wood with loose and flaking paint must, at a minimum, be wrapped in one layer of six-mil poly and adequately sealed with tape to secure the containerized material.

Concentrated lead waste such as sludge from paint stripping operations, lead containing paint chips and/or dust, HEPA vacuum contents and filters must be assumed to be hazardous waste until properly tested and must, at a minimum, be placed in poly lined, DOT approved steel drums.

Hard edged materials such as floor tile, gypsum board, plaster, stucco, ceramic tile, and other materials that may tear bags must be assumed to be hazardous waste until properly tested and must, at a minimum, be placed in poly lined, ridged -walled containers such as fiber drums or cardboard boxes as the final container.

Sharp edged components with peeling, blistering or flaking paint (e.g., nails, screws, metal lath, tin sheeting, door frames, etc.) must, at a minimum, be wrapped in one layer of six-mil poly sheeting, or a single six-mil thick bag and adequately sealed with tape to secure the containerized material.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

32 3.13 Alternative Work Plans

The Contractor and/or subcontractors may submit alternate work plans to the suggested work practices and containment strategies as stated in these specifications. These alternate work plans or containment strategies must be approved by Owner and/or Project Monitor prior to their implementation.

PART 4.0 DOCUMENTATION SUBMITTAL REQUIREMENTS

Pre-Start Submittals

Please attach submittals in the order listed below. Please check off each item that is submitted. Write NA in spaces for which you believe the requirement is Not Applicable.

All Contractors and subcontractors who will have employees disturb lead on this project must, at a minimum provide proof of item number 1.6.1.e.1., lead hazard communication training in compliance with 8 CCR 1532.1 (L)(A)(1). This is the only submittal that must be provided by these employers as long as they do not disturb more lead than is described in Part 1.5.1.

The following submittals must be provided by all Contractors and subcontractors who will, at a minimum, have employees who will conduct trigger tasks for more than one hour per shift, will potentially be exposed above the Action Level, or will conduct other activities as determined by the Project Monitor that may result in significant exposure to lead.

a. A written lead compliance plan in compliance with 8 CCR 1532.1 must be provided that includes the following:

1. A description of equipment and materials, controls, crew size, job responsibilities, and operations and maintenance procedures for each activity in which lead is disturbed and potentially emitted;

2. A description of specific control methods (wet methods, engineering controls, etc.) that will be used to ensure workers are not exposed above the PEL;

3. Technology considered in meeting the Cal/OSHA permissible exposure level (PEL);

4. Air monitoring data documenting sources of lead emissions;

5. A detailed implementation schedule for the compliance plan, including the schedule for inspections by a competent person;

6. A description of the lead work practice program which will be used to control worker exposures. This includes the use of protective work clothing, equipment, hygiene facilities and practices, and housekeeping practices;

7. A description of the steps the Contractor or subcontractor will take to minimize the generation of hazardous waste produced on this project. This includes, but is not necessarily limited to how the contractor will separate waste streams. For example, how will the Contractor or subcontractor will keep potentially hazardous waste such as paint chips and dust from being disposed of with other potentially non-hazardous construction materials and debris.

b. Copy of the Contractor or subcontractor’s written respirator program in accordance with the requirements of 8 CCR 1544.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

33 c. Proof that all employees expected to wear respirators on this project have medical approval to wear a respirator.

d. Copies of respiratory fit-tests for all workers expected to wear a respirator on this project.

Fit testing must be done as required by and in accordance with 8 CCR 1544.

e. Proof of training required by Part 1.5 for type of work employee will do.

1. Proof of Hazard Communication Training for Lead for those exposed to lead or who will perform trigger tasks for less than one hour. (Proof may be a certificate or written statement stating training was completed and a list of names of those individuals who were trained. Proof of this training is not needed if employee provides proof of training required by items e. 2, or e. 3.)

2. Proof of training in compliance with 8 CCR 1532.1 (l)(2) for all employees who will conduct trigger tasks as defined in 8 CCR 1532.1 (d)(2) for more than one hour or who will reasonably be expected to be exposed to lead above the Action Level. (Proof may be a certificate or written statement stating training was completed and a list of names of those individuals who were trained.) Not required if providing proof of training required in item e.3 and/or item e.4.

3. Proof of CDPH lead certification for those workers who will conduct trigger tasks as defined in 8 CCR 1532.1 (d)(2) or will reasonably be expected to be exposed to airborne levels of lead above the PEL. This is required for this work on all projects that will disturb more than 100 square feet of lead -containing material. (Proof of certification will be a currently valid CDPH certification card as a worker or supervisor. Workers who can show proof of a valid course completion form and application being submitted to CDPH, will be allowed to work while awaiting full certification from CDPH.)

4. Proof of current CDPH certification as a lead supervisor for the on -site competent person for projects involving the conduction of trigger tasks or other activities reasonably expected to exceed the PEL. This is required for this work on all projects that will disturb more than 100 square feet of lead -containing material. ( Proof of valid certification will be a currently valid CDPH certification card)

5. If exception to requirement for CDPH certified supervisor listed in Part 1.5.3 is requested, then provide proof of CDPH certified supervisor who will verify containment, personal protection and work practices, and will be able to respond to the project within two hours of request by the Project Monitor. (Only applicable for paint scraping work done prior to the demolition of buildings or structures.)

f. Copies of all current SDS for chemicals used on this project.

g. Manufacturers' certifications that high efficiency particulate air (HEPA) vacuums, pressure differential units and other local exhaust ventilation equipment conform to ANSI Z9.2-79 for all HEPA -filtered equipment that will be used on this project. (This is proof that the equipment is actually HEPA filtered. This is separate from the challenge testing requirement needed for equipment used in interior spaces.)

h. Name and contact information of independent testing company who will challenge test all vacuums and air filtration devices used on this project (in interior spaces).

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

34 I. Statement regarding compliance with all Cal/OSHA exposure monitoring required for this project.

j. Name and contact information for laboratory who will analyze air samples or waste samples and documentation of their certification to conduct such analysis.

k. Name of Waste Transporter who will transport hazardous waste on this project and documentation that the Transporter is allowed to transport lead hazardous waste.

l. Name of Waste Landfill to which lead hazardous waste will be sent and documentation that such landfill is allowed to accept such waste.

m. Should waste water filtration be required on this project, submit manufactures documentation pertaining to the capability of waste water filters to filter particles of, at a minimum, five micrometers in size.

n. List of all rented equipment to be used within a lead regulated area, or a statement that no rental equipment will be used on this project.

1. If rental equipment is to be used, submit written statements from each rental company indicating the rental company's acknowledgment that the equipment is provided for and may be used in areas where airborne levels of asbestos and/or lead may be present.

o. Submit emergency plans. At a minimum submit the following:

1. Submit non-emergency telephone numbers, other then 911, for the appropriate Police, Sheriff, and Fire Departments.

2. Name, pager or cell phone numbers of the on-site supervisor and his immediate company supervisor.

3. Submit detailed written directions from the project site to the medical facility to be used in case of an emergency. Also include a map which sufficiently shows the route to be taken from the site to the designated medical facility.

4. Submit written emergency procedures pertinent to the work to be performed and which can be implemented by site personnel if the need arises.

p. Local sanitation district Wastewater Discharge Permit for Surface Washers (if required).

q. Cal OSHA Notification. This is required for this work on all projects that will disturb more than 100 square feet of lead-containing material.

The above listed documents must be provided in the time specified in the project documents prior to the start of work that will disturb lead. Under no circumstances will workers or supervisors be allowed to work on this project prior to the receipt of this documentation by the Owner and/or Project Monitor. In addition, documentation regarding rental equipment, but must be provided before the equipment may be used in a lead regulated area. All delays resulting from the failure of the Contractor and/or subcontractors to provide this information in the required time frame is solely the responsibility of the Contractor and/or subcontractor.

The following documents must be provided the Owner and/or Project Monitor following completion of the physical activities associated with the project. The following documents must be received and approved by the Owner and/or Project Monitor before the work is considered complete. (Failure to provide these El Portal Elementary School
2600 Moraga Road, San Pablo, CA

35 documents means the work is not complete, even though the physical activities may be completed.)

a. Daily sign-in sheet for each worker entering a lead regulated area.

b. The Contractor must provide the results of exposure sampling done to comply with the requirements of 8 CCR 1532.1 (d) and the requirements of this specification.

c. The Contractor must provide blood sampling and analysis results of lead (BLL) and zinc protoporphyrin (ZPP) levels for all workers who are represented by air monitoring results that exceed the Action Level. Typically, the Project Monitor will require blood lead sampling for all workers on a work shift if one or more air sampling results for that shift is above the Action Level.

The written results of the blood sampling analysis must be provided the Owner and/or Project Monitor within 21 days of the exposure over the Action Level or within 12 days of the completion of the project, whichever comes first.

d. Copies of job progress reports and project documentation. This must include the names of all employees onsite, the hours worked and a brief description of the work completed at the site(s).

e. The Contractor must provide all waste disposal documentation.

This specification was developed by:

Matt Reilly
Senior Project Manager
CDPH I/A/S #4855 and #4854

SECTION 7800 ABATEMENT OF PCB

CONTAINING LIGHT BALLASTS AND MERCURY CONTAINING FLUORESCENT LIGHT TUBES C-22
SECTION III –OTHER HAZARDOUS MATERIALS
(PCB CONTAINING LIGHT BALLAST, UNIVERSAL WASTE LAMP,

MERCURY SWITCHES, SMOKE DETECTORS,

MOLD CONTAMINATED BUILDING MATERIALS,

FREON AND CRYSTALLINE SILICA)

ABATEMENT SPECIFICATIONS

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

Page 1 of 7 ends

OTHER HAZARDOUS MATERIALS

POLYCHLORINATED BIPHENYLS (PCB’s) LIGHT BALLAST HANDLING PROCEDURES

The Contractor may be instructed to remove light fixtures which contain light ballasts during demolition/ renovation activities specified in the contract documents . These light ballasts may contain PCBs in the oil used as coolant and lubricant. Any ballast containing PCBs is to be considered a “Hazardous Waste”, and the Contractor is respons ible for ensuring personnel who perform PCB related work (inspection, removal, clean-up) are trained and qualified to do so. All workers must also follow current OSHA regulations including 29 CFR 1910.120 and 8 CCR 5192, as well as other applicable federal, state and local laws and regulations.

PCB Light Ballasts

All light ballasts manufactured through 1978 are magnetic ballasts which contain PCBs. Installation of ballasts manufactured prior to 1978 continued for several more years. As a result it can be expected that any building constructed before 1980 which has not had a complete lighting retrofit is likely to have PCB containing ballasts. Therefore, unless the ballast is electronic (this type is PCB free), determined by testing not to contain PCBs, or the manufacturers label on the ballast states “No PCBs”, it is assumed all light ballasts on this site contain PCB’s, and must therefore be handled as a hazardous waste by the Contractor. The Contractor may have other options for disposal of any light ballasts found not to contain PCB’s.

Light Ballast Inspection

Contractor should disconnect all power and de -energize all electrical equipment to be impacted prior to performing inspection of electrical devices scheduled for removal or replacement. This de-energizing should be performed by or under the supervision of a licensed electrician. Contractor shall inspect each ballast prior to its removal to determine if the ballast is leaking, if oily residue is present on the exterior of the ballast or the ballast has been damaged resulting in a leak. Upon discovering and prior to removal of any oil coated, leaking, or damaged ballast Contractor shall contact Owners representative to discuss work procedures, waste requirements, etc.

Handling Work Practices of Undamaged Light Ballasts

Handling of ballasts shall be consistent with existing ballast conditions. While a ballast may not initially indicate any damage or leakage to be present, it may become damaged or begin to leak for any number of reasons during the removal and handling process. Any skin contact will probably constitute overexposure to PCBs since they are easily absorbed through the skin. It is recommended any personnel who will perform PCB related work should at a minimum wear protective clothing, including chemically -resistant gloves, goggles, boots, and disposable coveralls.

Handling Work Practices of Damaged Light Ballasts

Handling of damaged ballasts shall be performed in a manner consistent with existing and current feder al, state and local laws and regulations. Clean -up of spills, or contaminated surfaces will require the use of specifically trained and properly protected personnel utilizing state of the art work practices, removal equipment, and materials. The Owners representative must be notified prior to the performance of this type of work.

PCB Containing Waste

All PCB containing light ballasts, removed by the Contractor, shall be placed in leak tight approved containers (metal barrels) until they are removed from the site by a waste transporter permitted to haul hazardous materials. Barrels must not be loaded in excess of their approved capacity. For most barrels this is 750 El Portal Elementary School
2600 Moraga Road, San Pablo, CA

Page 2 of 7 ends

pounds. No other materials except, a sufficient amount of absorbent packing material, shall be included with the light ballasts.

The Contractor should contact their waste hauler prior to the start of work for information pertaining to recommendations or the waste haulers stated requirements for packing PCB containing ballasts. However, at a minimum, the absorbent packing material should be added to the bottom of the waste barrel prior to the first ballast. Absorbent packing material should then be added intermittently as necessary to encase the ballasts as the waste barrel is being filled. When the waste barrel is filled, or no more light ballasts will be added, additional absorbent packing material should be added to completely cover the ballasts and the container then sealed.

Contractor is also responsible for appropriate labeling of waste barrels and securing of lids to meet federal and/or state requirements while being stored on the site.

All leaking or damaged ballasts must be handled in accordance with federal and state disposal requirements and shall be separated from undamaged ballasts in preparation for incineration at an appropriately licensed facility.

The Contractor is responsible for all costs associated with the removal, packing, loading, shipping, and disposal of each barrel of waste generated during this project. The Contractor is also responsible for obtaining and properly completing any Uniform Hazardous Waste Manifests needed for the disposal of PCB waste.

However, the Contractor SHALL NOT sign any Uniform Hazardous Waste Manifests for the Owner.

Non-PCB Light Ballasts

Non-PCB light ballasts are considered a hazardous waste in California and the contractor is responsible for collection, packaging, labeling, and holding this waste stream for proper disposal. Non-PCB light ballasts shall be shipped for disposal or recycle by the Contractor.

UNIVERSAL WASTE LAMP HANDLING PROCEDURES

The Contractor may be instructed to remove light fixtures which contain lamps which are designated as “Universal Waste” during demolition/renovation activities specified in the contra ct documents. If the Contractor is instructed to remove such fixtures the following handling procedures shall be followed.

Universal Wastes

Universal wastes are hazardous wastes that are more common and pose a lower risk to people and the environment than other hazardous wastes. Federal and State regulations identify universal wastes. The regulations, called the “Universal Waste Rule,” are in the California Code of Regulations (CCR), title 22, division 4.5, chapter 23.

Universal Waste Lamps

Universal Waste Lamp, also referred to as “lamp” is defined as the bulb or tube portion of an electric lighting device. A lamp is specifically designed to produce radiant energy, most often in the ultraviolet, visible, and infra-red regions of the electromagnetic spectrum. Examples of common universal waste electric lamps include, but are not limited to, fluorescent, high intensity discharge, neon, mercury vapor, high pressure sodium, and metal halide lamps. Any lamp which is not spent and has been designated to be reused is not classified as a waste and does not meet the requirements of a hazardous waste or a universal waste.

Mercury-added lamps

Mercury-added lamps (effective February 9, 2004): Fluorescent tubes and several other types of lamps (not incandescent light bulbs) contain a small amount of mercury that is necessary for their operation. Currently, most fluorescent lamps contain enough mercury to be a hazardous waste.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

Page 3 of 7 ends

Universal Waste Lamp Disposal

Spent lamps typically contain concentrations of mercury exceeding the established Total Threshold Limit Concentration and/or the Soluble Threshold Limit Concentration values. Therefore, these lamps must be sent to an authorized recycle facility, or to a universal waste consolidator for shipment to an authorized recycling facility.

At a minimum the lamps must be packaged in boxes/packages/containers which are structurally sound, adequate to prevent breakage, and compatible with the content of the lamps. These packages must remain closed and be free of damage which could cause leakage under reasonably foreseeable conditions.

Each container shall be labeled or marked clearly with one of the following phrases: “Universal Waste – Lamp(s),” or “Waste Lamp(s).” or “Used Lamp(s)”.

Documentation in the form of a log, invoice, manifest, bill of lading or other shipping document is required to be submitted to the Owner’s Representative for each shipment of waste from the project site. This documentation shall include: name and address of generator and address of site wa ste is generated on, quantity of lamps to be shipped, date of shipment, name and address of hauler, and name and address of waste facility receiving the waste.

Hazardous Waste Designation

Any lamp which is not designated for recycling or continued use in a different fixture for which the lamp is manufactured for use in must be handled, managed, and disposed of as a hazardous waste in accordance with Cal/EPA Title 22. Since all spent lamps are required to be recycled the Owner will not approve of the disposal of lamps as hazardous without consultation and review of the specific circumstances which warrant this change in designation.

MERCURY SWITCHES

Thermostat switches that contain mercury are considered a hazardous waste if removed and disposed.

Where the contract requires removal of thermostat switches, the contractor shall follow all requirements for packaging and disposal of these mercury containing wastes.

SMOKE DETECTORS WHICH MAY CONTAIN A RADIOACTIVE ELEMENT

The Contractor shall be responsible for the removal of any and all smoke detectors which may contain a radioactive element, which may be present in any building or corridor prior to the demolition of any building included in this project. These types of detectors are easily identified by reviewing the label which is usually found on the back of the detector. Older units may display the international radiation symbol (three bladed propeller) and the radioactive content. Newer units state the radioactive content and their Nuclear Regulatory Agency (NRC) license number.

The Contractor shall be responsible for contacting the manufacturer of any smoke detector with a radioactive element present to determine their return policies. The California Department of Toxic Substance Control (DTSC) has stated that it is a condition of the manufacturers NRC license that they must accept returned units for disposal. The Contractor shall be responsible for all costs associated with removing, packaging, and shipping of the detectors in compliance with the manufacturers policies and procedures.

Contractor shall submit to the Owner a letter from the m anufacturer which includes the number of units received, date received, and acceptance of the shipment for disposal by that manufacturer.

Additional Waste Management Requirements

The Contractor is responsible for managing lamps in a manner which prevents release of any universal waste or component of a universal waste to the environment. The Contractor is also responsible for the immediate El Portal Elementary School
2600 Moraga Road, San Pablo, CA

Page 4 of 7 ends

clean up of materials (mercury or other hazardous constituents) released by a lamp broken during removal or otherwise damaged while being handled into a container or containers designed to accommodate the resulting waste and its contents.

The Contractor is responsible for training employees in proper handling, packaging, storing and labeling the universal waste, as well as, how to respond to releases (66273.13). This may be accomplished by providing employees written instructions or posting these instructions in the area where the universal waste lamps are being stored.

The Contractor is responsible for all costs associated with the removal, packing, loading, shipping, clean up and disposal of hazardous materials removed during this project, and any waste generated due to breakage during this project. The Contractor is also responsible for obtaining and properly completing any Uniform Hazardous Waste Manifests needed for the disposal of lamp waste. However, the Contractor SHALL NOT sign any Uniform Hazardous Waste Manifests for the Owner.

The following information will be required when completing a Uniform Hazardous Waste Manifest used to dispose of hazardous waste generated at this site during this project.

Project Site Name: El Portal Elementary School

Block #1 (Generator’s US EPA ID No.)

XXXXXXXXXX

Block #3 (Generator’s Name and Address) and Block #4 (Generator’s Phone Number)

City of San Pablo, 1000 Gateway Avenue, San Pablo, California 94806

Block #15 (Special Handling Instructions and Additional Information)

2600 Moraga Road, San Pablo, California 94806

It SHALL be the responsibility of the Contractor to contact the Owner in advance of the scheduled pick up time and date so the waste materials can be visually inspected for proper packing, and to have the Uniform Hazardous Waste Manifest properly signed by an Owner representative.

MOLD CONTAMINATED BUILDING MATERIALS

During the course of conducting the construction related project, the contractor may discover water damaged building components which may also have visible or suspect mold on building materials. Mold can be harmful to humans depending upon the amount of exposure and type of exposure; therefore, it is incumbent of the contractor to take precautions in the event of the discovery of mold contaminated building materials.

If mold contaminated building materials are discovered on the project, it should be brought to the attention of the project manager. In addition, any structural wood members should also be closely examined for possible dry rot and decay and brought to the attention of the project manager. Precautions should be implemented by the contractor to protect his/her employees from exposures to mold from both skin contact and inhalation exposures. Employees should be trained in accordance with the Cal/OSHA Hazard Communication Standard for mold hazards.

If this project involves asbestos related work, the work practices and worker protection for asbestos is very similar to mold related work. Workers performing asbestos related demolition of building components are required to be protected in accordance with Cal/OSHA Title 8 1529 Asbestos in Construction regulations.

Workers performing asbestos related work are required to wear respirators with P -100 (HEPA) filters, and whole body disposable coveralls while removing the building materials within negative pressure HEPA filtered work enclosures. These same asbestos work practices defined in Title 8 1529 and in other specifications for El Portal Elementary School
2600 Moraga Road, San Pablo, CA

Page 5 of 7 ends

this project shall apply to any mold contaminated building materials.

Any mold contaminated building materials shall be removed from the work environment in sealed bags. If the building materials have been determined to contain asbestos, the default criteria for handing, packaging, labeling, and disposal of the waste material shall be the Cal/OSHA, Federal EPA, and D.O.T. regulations for asbestos waste. If the mold impacted materials have been determined not to contain asbestos, the materials shall be placed in sealed six mil plastic bags and can be disposed as non -hazardous waste. If the mold impacted building components are painted, lead in the paint may be the determinant for disposal. Refer to the Lead in Construction specifications for handling of painted components for lead waste issues.

FREON

All refrigerant systems at the buildings containing Freon and other fluorocarbon products associated with heating, ventilating, and air-conditioning (HVAC) systems, or freezers, refrigerators, etc. if removed in the planned renovation or demolition project, shall be removed from the mechanical systems and recycled in accordance with Cal/EPA requirements.

CRYSTALLINE SILICA

Cal/OSHA Title 8 1532.3. Occupational Exposures to Respirable Crystalline Silica require all employers to control employee exposures to silica dust during construction related activities. The contractor is responsible for following all of the requirements in the silica regulations established by Cal/OSHA in Title 8 section 1532.3.

Below are some of the key components related to engineering controls specific to different tasks. Below are excepts from the silica standards; however, the contractor shall familiarize themselves with all of the requirements in this regulation.

(C) Specified exposure control methods. (1) For each employee engaged in a task identified on Table 1, the employer shall fully and properly implement the engineering controls, work practices, and respiratory protection specified for the task on Table 1, unless the employer assesses and limits the exposure of the employee to respirable crystalline silica in accordance with subsection (d).

All employers shall refer to “Table 1 - Specified Exposure Control Methods When Working With Materials Containing Crystalline Silica” which identify the specific Equipment/Task, required Engineering and Work Practice Control Methods, and the required respiratory protection based on number of hours for the specific tasks. The contractor shall implement at least one of the work practices and control measures for the work activity they chose to implement.

(3) Where an employee performs more than one task on Table 1 during the course of a shift, and the total duration of all tasks combined is more than four hours, the required respiratory protection for each task is the respiratory protection specified for more than four hours per shift. If the total duration of all tasks on Table 1 combined is less than four hours, the required respiratory protection for each task is the respiratory protection specified for less than four hours per shift.

(2) When implementing the control measures specified in Table 1, each employer shall:

(A) For tasks performed indoors or in enclosed areas, provide a means of exhaust as needed to minimize the accumulation of visible airborne dust;

(B) For tasks performed using wet methods, apply water at flow rates sufficient to minimize release of visible dust;

(C) For measures implemented that include an enclosed cab or booth, ensure that the enclosed cab or booth:

1. Is maintained as free as practicable from settled dust;

2. Has door seals and closing mechanisms that work properly;

3. Has gaskets and seals that are in good condition and working properly;

4. Is under positive pressure maintained through continuous delivery of fresh air;

5. Has intake air that is filtered through a filter that is 95% efficient in the 0.3-10.0 ìm range (e.g., MERV-16 El Portal Elementary School
2600 Moraga Road, San Pablo, CA

Page 6 of 7 ends

or better); and

6. Has heating and cooling capabilities.

(d) Alternative exposure control methods. For tasks not listed in Table 1, or where the employer does not fully and properly implement the engineering controls, work practices, and respiratory protection described in Table 1:
(1) Permissible exposure limit (PEL). The employer shall ensure that no employee is exposed to an airborne concentration of respirable crystalline silica in excess of 50 ìg/m3, calculated as an 8-hour TWA.

(2) Exposure assessment.

(A) General. The employer shall assess the exposure of each employee who is or may reasonably be expected to be exposed to respirable crystalline silica at or above the action level in accordance with either the performance option in subsection (d)(2)(B) or the scheduled monitoring option in subsection (d)(2)(C).

(B) Performance option. The employer shall assess the 8-hour TWA exposure for each employee on the basis of any combination of air monitoring data or objective data sufficient to accurately characterize employee exposures to respirable crystalline silica.

(C) Scheduled monitoring option.

1. The employer shall perform initial monitoring to assess the 8-hour TWA exposure for each employee on the basis of one or more personal breathing zone air samples that reflect the exposures of employees on each shift, for each job classification, in each work area. Where several employees perform the same tasks on the same shift and in the same work area, the employer may sample a representative fraction of these employees in order to meet this requirement. In representative sampling, the employer shall sample the employee(s) who are expected to have the highest exposure to respirable crystalline silica.

2. If initial monitoring indicates that employee exposures are below the action le vel, the employer may discontinue monitoring for those employees whose exposures are represented by such monitoring.

3. Where the most recent exposure monitoring indicates that employee exposures are at or above the action level but at or below the PEL, the employer shall repeat such monitoring within six months of the most recent monitoring.

4. Where the most recent exposure monitoring indicates that employee exposures are above the PEL, the employer shall repeat such monitoring within three months of the most recent monitoring.

5. Where the most recent (non-initial) exposure monitoring indicates that employee exposures are below the action level, the employer shall repeat such monitoring within six months of the most recent monitoring until two consecutive measurements, taken seven or more days apart, are below the action level, at which time the employer may discontinue monitoring for those employees whose exposures are represented by such monitoring, except as otherwise provided in subsection (d)(2)(D).

Prepared By:

Matt Reilly
Senior Project Manager
Atlas Technical Consultants

2600 Moraga Road Abatement & 2022 Form ATTACHMENT A – CONSTRUCTION Demolition Project WASTE MANAGEMENT
0501 Page 90
Attachment A – Construction Waste Management Form

2600 Moraga Road Abatement & 2022 Form ATTACHMENT A – CONSTRUCTION Demolition Project WASTE MANAGEMENT
0501 Page 91

NO

CONSTRUCTION & DEMOLITION DEBRIS RECYCLING

APN: Buildin g Permit #:________________________J#_________________ (if applicable) Owner Name: Owner Mailing Address: Phone ( ) Jobsite Contact: Company: Phone ( )
Jobsite Address: Building Type: SF Res.-New NonRes-New NonRes-Addt./renov. Multifamily

Non-
residential
 Any new construction project that requires a permit
 Any demolition projects that require a permit
 Additions equal to or greater than 1,000 square feet
 Alterations equal to or greater than $200,000
Residential  Any new construction project that requires a permit  Any demolition projects that require a permit
 Any additions or alterations that increase the building’s conditioned area, volume, or size

Will you use a Richmond
Sanitary Service debris box?
Will you haul your construction &
demolition waste yourself?
When setting up service, tell Richmond Sanitary Service this is for “C&D Recycling.” When scheduling final inspection, bring in or send in receipts and weight tickets from the transfer station showing that your waste material went to “C&D Recycling.” Remember, never put garbage in construction waste! At final inspection, show receipts and weight tickets from the transfer station showing that your waste material went to “C&D Recycling.” Remember, never put garbage in construction waste! YES

Fill out the next page.

YES
Does your project meet any
of the below criteria?
YES Fill out the front of the rest of this form. If no, check this box: The below criteria do not apply to my project.

NO
1 2
3 4
Pre-Construction Waste Management Plan (WMP) Instructions

Effective January 1, 2014, certain residential and non-residential building construction and demolition projects must meet Title 24 California Green Building Standards Code (CALGreen). For these projects, 50% of all waste generated must be recycled.

Specify in the table below the types and quantities of materials expected to be generated in your project. Indicate whether they will reused on-site, recycled or disposed by completing the form below.

Material Reuse Recycle Dispose Fac ility/Service Providers to be used Asphalt
Brick
Cardboard
Carpet
Concrete/Shotcrete
Dirt/Clean Fill
Gypsum Dry Wall **
Job office paper, glass & plastic bottles,
cans – Collect separately

Metals
Plant/ Tree Debris
Roofing – asphalt composition shingle, tile, wood
shake, tar or gravel
Rock/Stone
Wood (Pallets, lumber) **
Other

Construction Waste Management Report – Post Construction/Demolition Final Inspection will not be scheduled until completed plan is submitted

APN: Buildin g Permit #:________________________J#_________________ (if applicable) Owner Name: Owner Mailing Address: Phone ( ) Jobsite Contact: Company: Phone ( )
Jobsite Address: Building Type: SF Res.-New NonRes-New NonRes-Addt./renov. Multifamily Identify which materials were reused, recycled or disposed by completing the table below. If the materials were reused on site, describe the reuse application under the facilities/service providers’ column. Salvaged materials from deconstruction should be designated as reuse. Further instructions are on the back of form.

Material Reuse Recycle Dispose Actual Fac ility/Service Providers Used Weight (tons) Asphalt
Brick
Cardboard
Concrete/ Shotcrete
Dirt/Clean Fill
Gypsum Dry Wall
Job office paper, glass & plastic bottles,
cans, other

Metal
Plant /Tree Debris
Roofing - asphalt composition shingle, tile, wood
shake, tar or gravel

Rock/stone
Wood (pallets, lumber, etc)
Other
Other
Material Recovery Summary
Total tons of materials disposed (not recycled):

Total tons of materials salvaged, reused, or recycled:

Percentage of materials recycled/reused: % Calculate pounds disposed per square footage of project _____________

I certify that I have read the CalGreen Title 24 Building Code and understand the requirements of Section 4.408, 5.408, 301.1.1 and 301.3. The information I have provided is accurate to the best of my ability and meets the regulations.

Contractor signature:_________________________________________Date:_________

Contractor license #:__________________________

Construction Waste Management Report (CWMR) Post-Construction/Demolition Instructions

CWMR (Post-Construction/Demolition):

This form must be filled out if contractor does not use Richmond Sanitary Service debris box service.

 Indicate the types and quantity of debris that were actually generated from the project (tons).  Specify whether each material was reused, recycled or disposed  Provide the name of each facility or service that was actually used for each type of material  Attach receipts or gate-tags for all materials to verify their destination including subcontractors loads  If using the “Waste Stream Reduction Alternative” method, add together all waste disposed and divide by the square footage of project. Residential projects must be less than 4lbs/sf and non-residential and high rise buildings (4 stories or more) must be less than 2 lbs/sf.  Provide any additional information (including photographs) that are relevant to determining compliance with the code  Sign at the bottom

Upon completion of construction and demolition activities, but before the final inspection, the person responsible for the project shall submit the CWM Report and the required documentation (listed above) to demonstrate achievement of the diversion requirement. Submit the report to the building department for approval.

The CWM Report will be reviewed and a determination made as to whether the project manager achieved the diversion requirement and demonstrated compliance with the code. Questions can be directed to the city’s building department.

Mixed C&D materials are sorted, recycled, and reused if garbage is kept separated.

Metals Cardboard

Sheetrock Wood

2600 Moraga Road Abatement & 2022 Form ATTACHMENT E – STATE Demolition Project WAGE RATE
0501 Page 92

Attachment B – State Wage Rate

2600 Moraga Road Abatement & 2022 Form ATTACHMENT E – STATE Demolition Project WAGE RATE
0501 Page 93

2600 Moraga Road Abatement & 2022 Form ATTACHMENT E – STATE Demolition Project WAGE RATE
0501 Page 94
State:

Please refer to the following web link for the State General Prevailing Wage Rate Determination:

https://www.dir.ca.gov/OPRL/DPreWageDetermination.htm

2600 Moraga Road Abatement & 2022 Form ATTACHMENT F – CHANGE Demolition Project ORDER FORM
0501 Page 95

Attachment C – Change Order Form

2600 Moraga Road Abatement & 2022 Form ATTACHMENT F – CHANGE Demolition Project ORDER FORM
0501 Page 96

Contractor: Contractor Name
Contract Execution Date: mm/dd/yyyy
ORIGINAL CONTRACT AMOUNT: $0.00
CHANGE ORDER #1 TOTAL: $0.00
CHANGE ORDER #2 TOTAL: $0.00
CHANGE ORDER #3 TOTAL: $0.00
CURRENT CONTRACT AMOUNT (PRIOR TO THIS CHANGE ORDER): $0.00 0 $0.00 LS $0.00
0 $0.00 N/A $0.00
$0.00
REVISED CONTRACT AMOUNT: $0.00
ADJUSTMENT OF CONTRACT TIME OF COMPLETION: # working days CCO item
#
NET CHANGE IN CONTRACT COST:
<PROJECT TITLE>
B. CHANGES IN THE CONTRACT DOCUMENTS
This change order formalizes various instruction bulletins (IB’s), field orders, authorized RCO’s and extra work/ force account items. All of the work items described below are in progress or have been completed.

ITEM # UNIT
QTY.

UNIT

PRICE UNIT NET CHANGE

TO CONTRACT
PROJECT # <###>
CONTRACT CHANGE ORDER NO. #<##>

DESCRIPTION
mm/dd/yyyy
In accordance with Article 6 of the General Conditions of the Contract Documents, you are hereby directed to make the herein described changes to the plans, specifications, or scope of work contracted for within the terms of the subject Contract.

DESCRIPTION OF CHANGE
CCO item
# DESCRIPTION
A. EXISTING CONTRACT
P:\CIP\0_CIP_Forms & Guidelines\03 Const Phase\
Contract Change Order (CCO#) Template

Page 1 of 2 ends

PROJECT # <###>
CONTRACT CHANGE ORDER NO. #<##>
Action / Title Signature Date
Contractor Acceptance by:

Contractor Acceptance Date
Action / Title Signature Date
*Necessary if contingency funds are needed and the Change Order exceeds City Council approved contract value.

Attachments: <Title of Contractor Document>
Distribution:

Original: City Clerk
cc: Contractor
Engineering
Finance - increase PO #<###> b
y: $0.00
Project Inspector/ Construction Manager
Notes: City Council approved a contract value on mm/dd/yyyy of $###,### and 15% contingency of $##,###.

Contract value including this CO/Authorized Contract: 0 / 0 = #DIV/0! as this indicates less than a 15% increase.

Matt Rodriguez, City Manager
Funding Approval*
Allan A. Panganiban, PW Director / City Engineer
Scope Approved
C. APPROVAL SECTION
“The undersigned Contractor certifies under penalty of perjury that its statements and representations in this Change Order request are true and correct. Contractor warrants that this Change Order request is comprehensive and complete as to the Work or changes referenced herein, and agrees that any known or foreseeable costs, expenses, or time extension requests not included herein, are deemed waived. Contractor understands that submission of claims which have no basis in fact or which Contractor knows to be false may violate the False Claims Act, as set forth in Government Code sections 12650 et seq., and Chapter 3.17 of the San Pablo Municipal Code.”
Name, Title
Funding in approved capital project budget account (###-####-#####-###) is adequate to cover this change order.

CCO Template Updated 10/12/20
Signature
Project Manager, Title
Recommended
P:\CIP\0_CIP_Forms & Guidelines\03 Const Phase\
Contract Change Order (CCO#) Template

Page 2 of 2 ends

2600 Moraga Road Abatement & 2022 Form ATTACHMENT H – NOTICES Demolition Project Page 97
0501

Attachment D – Asbestos Results List

2600 Moraga Road Abatement & 2022 Form ATTACHMENT H – NOTICES Demolition Project Page 98
0501

El Portal Elementary School
2600 Moraga Road, San Pablo, CA
77 1. Copies of revised notifications to regulatory agencies.

2. Information on all new workers not covered by the pre-construction submittals and not submitted during the project.

3. A copy of worker exposure monitoring results collected in compliance with DOSH regulations (Title 8 CCR, Section 1529) including daily/representative/full - shift/breathing-zone air samples, and 30-minute excursion samples.

4. A copy of the worker/visitor log showing the following for all persons entering the work area: date, name, social security number, entering, and leaving times, company or agency represented, and reason for entry. The Contractor's time records will not be accepted in lieu of a worker/visitor log.

5. Copies of all accident reports submitted during the course of work. If no accidents occur during the project this should be stated in writing by the Contractor.

6. Receipts from the landfill operator acknowledging the Contractor's delivery of wastes, including dat es, container types and quantities, tare weights or material delivered, and all appropriate signatures.

7. A complete record of the air filtration devices used certifying DOP testing (if performed) and a circular chart recording, indicating continuous operation and documenting differential air pressure.

8. Copies of DOP Testing Performed on HEPA Equipment not Previously Submitted

9. Manometer graphs identifying project name, date, and location.

10. A copy of the asbestos waste record showing dates, times, manifest numbers, quantities of wastes, types of containers removed from the work area, the hauler, and the signature of the recorder.

11. A Land Disposal Restrictions Notification and Certification

12. Completed Uniform Hazardous Waste forms

13. Other Documents as Requested

SECTION 25. ASBESTOS RESULTS LIST

Any material not specified on the following list which the Contractor encounters at this site must be considered as “suspect” and “assumed” to contain asbestos per US EPA. The only items excluded from this statement are; bare wood, glass, and metal.

Sample
Numbers Location Homogenous Material Approximate
Quantity
NESHAP
Category Asbestos Content
02-A-E Classrooms 24-28 Drywall and Joint
Compound 10,000 SF NA
Drywall
(NON-DETECTED)
Joint Compound
(0.25-0.50% Chrysotile)
Confirmed by 400 Point
Count
05-A-B Above Ceiling in
Classrooms 24-28 Air Cell Pipe Wrap 500 LF RACM 90% Chrysotile El Portal Elementary School
2600 Moraga Road, San Pablo, CA
78 Sample
Numbers Location Homogenous Material Approximate
Quantity
NESHAP
Category Asbestos Content
06-A-B Classroom 25 9”x9” Red Vinyl Floor Tile
with Black Mastic 950 SF CAT I
9”x9” Red Vinyl Floor Tile
(5% Chrysotile)
Black Mastic
(NON-DETECTED)
08-A-C Classroom 26 and 27 9”x9” Brown Vinyl Floor
Tile with Black Mastic 1,900 SF CAT I
9”x9” Red Vinyl Floor Tile
(5% Chrysotile)
Black Mastic
(2% Chrysotile)
09-A-B Classrooms 24-28 Brown Mastic behind Tag
Board 1,000 SF CAT II Brown Mastic
(2% Chrysotile)
11-A-C Classroom 27 Wall Texture 1,550 SF NA
Wall Texture
(0.25-0.50% Chrysotile)
Confirmed by 400 Point
Count
13-A-B Computer Lab 12”x12” Tan Vinyl Floor
Tile with Black Mastic 1000 SF CAT I
12”x12” Tan Vinyl Floor
Tile
(2% Chrysotile)
Black Mastic
(5% Chrysotile)
14-A-E Computer Lab and
Classrooms 20-23
Drywall and Joint
Compound 10,000 SF NA
Drywall
(NON-DETECTED)
Joint Compound
(0.25% Chrysotile)
Confirmed by 400 Point
Count
18-A-B Classroom 20 9”x9” Gray Vinyl Floor
Tile with Black Mastic 950 SF CAT I
9”x9” Gray Vinyl Floor
Tile
(5% Chrysotile)
Black Mastic
(NON-DETECTED)
19-A-B
Above Ceiling in
Classrooms 20-23 and
Computer Lab
Air Cell Pipe Wrap 500 LF RACM 90% Chrysotile
20-A-B Women’s Restroom
4”x4” Pink Ceramic Tile
with Grout and
Underlayment
300 SF CAT II
4”x4” Pink Ceramic Tile
(NON-DETECTED)
Grout
(NON-DETECTED)
Underlayment
(4% Chrysotile)
Mastic
(15% Chrysotile)
21-A-B Men’s Restroom
4”x4” Green Ceramic Tile
with Grout and
Underlayment
300 SF CAT II
4”x4” Green Ceramic Tile
(NON-DETECTED)
Grout
(NON-DETECTED)
Underlayment
(4% Chrysotile)
Mastic
(NON-DETECTED)
El Portal Elementary School
2600 Moraga Road, San Pablo, CA
79 Sample
Numbers Location Homogenous Material Approximate
Quantity
NESHAP
Category Asbestos Content
23-A-B Men’s & Women’s
Restroom
Drywall and Joint
Compound 980 SF NA
Drywall
(NON-DETECTED)
Joint Compound
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
24-A-C Men’s & Women’s
Restroom Texture 980 SF NA
Texture
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
25-A-B Classroom 9 and 10 9”x9” Gray Vinyl Floor
Tile with Black Mastic 1,900 SF CAT I
9”x9” Gray Vinyl Floor
Tile
(5% Chrysotile)
Black Mastic
(5% Chrysotile)
26-A-B Above Ceiling in
Classrooms 24-28 Air Cell Pipe Wrap 500 LF RACM 80% Chrysotile 27-A-E Classrooms 9-13 Drywall and Joint
Compound 10,000 SF NA
Drywall
(NON-DETECTED)
Joint Compound
(0.25-0.50% Chrysotile)
Confirmed by 400 Point
Count
29-A-C Classrooms 9-13 4” Base Cove with Mastic 800 LF CAT II 4” Base Cove
(4% Chrysotile)
Black Mastic
(2% Chrysotile)
Brown Mastic
(NON-DETECTED)
Yellow Mastic
(NON-DETECTED)
33-A-B Classroom 11 9”x9” Gray Vinyl Floor
Tile with Black Mastic 950 SF CAT I
9”x9” Gray Vinyl Floor
Tile
(5% Chrysotile)
Black Mastic
(2% Chrysotile)
34-A-B Classroom 12 and 13
12”x12” Brown Vinyl
Floor Tile with Black
Mastic
1,900 SF CAT I
12”x12” Tan Vinyl Floor
Tile
(2% Chrysotile)
Black Mastic
(5% Chrysotile)
37-A-C Classroom 13 Knockdown Texture 980 SF NA
Knockdown Texture
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
38-A-B Classrooms 3-7 Air Cell Pipe Wrap 500 LF RACM 90% Chrysotile 39-A-B Classroom 3 Flooring 9”x9” Gray Vinyl Floor
Tile with Black Mastic 950 SF CAT I
9”x9” Gray Vinyl Floor
Tile
(5% Chrysotile)
Black Mastic
(NON-DETECTED)
El Portal Elementary School
2600 Moraga Road, San Pablo, CA
80 Sample
Numbers Location Homogenous Material Approximate
Quantity
NESHAP
Category Asbestos Content
40-A-E Classrooms 3-7 Walls Drywall and Joint
Compound 10,000 SF NA
Drywall
(NON-DETECTED)
Joint Compound
(0.50% Chrysotile)
Confirmed by 400 Point
Count
42-A-B
Classrooms 3 & 5
Restroom Walls and
Men’s and Women’s
Restroom Walls
4”x4” Green Ceramic Tile
with Grout and
Underlayment
500 SF CAT II
4”x4” Green Ceramic Tile
(NON-DETECTED)
Grout
(NON-DETECTED)
Underlayment
(5% Chrysotile)
Mastic
(NON-DETECTED)
43-A-B
Classrooms 3 & 5
Restroom Walls and
Men’s and Women’s
Restroom Walls
4”x4” Green Ceramic Tile
with Grout and
Underlayment
500 SF CAT II
4”x4” Pink Ceramic Tile
(NON-DETECTED)
Grout
(NON-DETECTED)
Underlayment
(5% Chrysotile)
Mastic
(NON-DETECTED)
49-A-B Classrooms 4-5 Walls Knockdown Texture 3,000 SF NA Joint Compound
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
51-A-B Classroom 5 & 7
Brown 12”x12” Vinyl
Floor Tile with Black
Mastic
1,900 SF CAT I
12”x12” Tan Vinyl Floor
Tile
(<1% Chrysotile)
Black Mastic
(5% Chrysotile)
57-A-G Covered Walkway
Roofing
Built up Roof with Silver
Paint 15,000 SF CAT I
Silver Paint
(<1% Chrysotile)
Built Up Roof
(8% Chrysotile)
58-A-B Classroom Building
24-28 Plaster Wall 4,500 SF NA
Plaster
(NON-DETECTED)
Tan Paint
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
59-A-B
Computer Lab,
Classroom 20-23 and
Admin Building
Plaster Wall 8,500 SF NA
Plaster
(NON-DETECTED)
Tan Paint
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
60-A-B Classroom Building
9-13 Plaster Wall 5,000 SF NA
Plaster
(NON-DETECTED)
Tan Paint
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
El Portal Elementary School
2600 Moraga Road, San Pablo, CA
81 Sample
Numbers Location Homogenous Material Approximate
Quantity
NESHAP
Category Asbestos Content
61-A-B Classroom Building
3-7 and Auditorium Plaster Wall 13,200 SF NA
Plaster
(NON-DETECTED)
Tan Paint
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
62-A-B Classroom Building
1 & 2 Plaster Wall 3,000 SF NA
Plaster
(NON-DETECTED)
Tan Paint
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
63-A-B Classroom Building
24-28 Roof
Built up Roof with Silver
Paint 6,500 SF CAT I
Silver Paint
(<1% Chrysotile)
Built Up Roof
(3% Chrysotile)
64-A-B
Computer Lab,
Classroom 20-23 and
Admin Building Roof
Built up Roof with Silver
Paint 10,000 SF CAT I
Silver Paint
(<1% Chrysotile)
Built Up Roof
(2% Chrysotile)
65-A-B Classroom Building 9-
13 and Library Roof
Built up Roof with Silver
Paint 9,500 SF CAT I
Silver Paint
(<1% Chrysotile)
Built Up Roof
(2% Chrysotile)
66-A-B Classroom Building 3-
7 and Auditorium Roof
Built up Roof with Silver
Paint 9,700 SF CAT I
Silver Paint
(<1% Chrysotile)
Built Up Roof
(3% Chrysotile)
67-A-B Classroom Building
3-7 Roof Asphaltic Roofing 4,300 SF CAT I
Asphaltic Roofing
(NON-DETECTED)
Roofing Felt
(NON-DETECTED)
Tar
(2% Chrysotile)
69-A-B Classroom 1 & 2
Flooring
12”x12” Brown Vinyl
Floor Tile with Black
Mastic
4,000 SF CAT I
12”x12” Brown Vinyl
Floor Tile
(2% Chrysotile)
Black Mastic
(5% Chrysotile)
71-A-E Classroom 1 & 2 Wall Knockdown Texture 3,000 SF NA Knockdown Texture
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
72-A-B Classroom 1 & 2 Wall Drywall with Joint
Compound 3,000 SF NA
Drywall
(NON-DETECTED)
Knockdown Texture
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
El Portal Elementary School
2600 Moraga Road, San Pablo, CA
82 Sample
Numbers Location Homogenous Material Approximate
Quantity
NESHAP
Category Asbestos Content
73-A-B Classroom 1 & 2
Restroom Wall
4”x4” Pink Ceramic Tile
with Grout and
Underlayment
200 SF CAT II
4”x4” Pink Ceramic Tile
(NON-DETECTED)
Grout
(NON-DETECTED)
Underlayment
(5% Chrysotile)
74-A-B Classroom 1 & 2
Restroom Wall
4”x4” Green Ceramic Tile
with Grout and
Underlayment
200 SF CAT II
4”x4” Pink Ceramic Tile
(NON-DETECTED)
Grout
(NON-DETECTED)
Underlayment
(5% Chrysotile)
78-A-B Classroom Building
24-28 Roof Black Roof Patch 2,200 SF CAT I Black Roofing (4% Chrysotile)
79-A-B Auditorium Kitchen
Floor
9”X9” Brown Vinyl Floor
Tile with Mastic 2,500 SF CAT I
9”x9” Gray Vinyl Floor
Tile
(5% Chrysotile)
Black Mastic
(NON-DETECTED)
80-A-B Auditorium Floor 12”x12” Vinyl Floor Tile
with Mastic 5,200 SF CAT I
12”x12” Brown Vinyl
Floor Tile
(2% Chrysotile)
Black Mastic
(3% Chrysotile)
81-A-B Auditorium Wall Drywall with Joint
Compound 16,000 SF NA
Drywall
(NON-DETECTED)
Knockdown Texture
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
82-A-E Auditorium Wall Knockdown Texture 16,000 SF NA
Knockdown Texture
(<0.25% Chrysotile)
Confirmed by 400 Point
Count
84-A-B Above Ceiling Kitchen
Area Air Cell Pipe Wrap 500 LF RACM 50% Chrysotile
85-A-B Above Ceiling Kitchen
Area TSI Pipe Wrap 500 LF RACM 35% Amosite
5% Chrysotile
87-A-B Auditorium Kitchen
Wall
4”x4” Brown Ceramic Tile
with Grout and
Underlayment
600 SF CAT II
4”x4” Brown Ceramic Tile
(NON-DETECTED)
Grout
(NON-DETECTED)
Underlayment
(6% Chrysotile)
88-A-B Classroom 1 & 2
Building Roof Built Up Roof 4,800 SF CAT I
Silver Paint
(<1% Chrysotile)
Built Up Roof
(7% Chrysotile)
NA Auditorium Fire Debris and Ash 5,000 SF RACM NA
NA Administration and
Library Building Fire Debris and Ash 5,500 SF RACM NA
El Portal Elementary School
2600 Moraga Road, San Pablo, CA
83 Sample
Numbers Location Homogenous Material Approximate
Quantity
NESHAP
Category Asbestos Content
NA Administration and
Library Building
Floor Tile and Mastic-
Assumed to Exist
Beneath Thick Layer of
Ash and Debris.
5,500 SF RACM NA

Note 1.: Category I Non -friable ACM is asbestos -containing packings, gaskets, resilient floor covering, and asphalt roofing products containing more than one percent asbestos by area.

Note 2.: Category II Non -friable ACM is any material, excluding Category I non -friable ACM, containing more than one percent asbestos, which is non-friable such as transite and other concrete based products.

Note 3.: Regulated Asbestos-Containing Material (RACM) is any friable material, any Category I non-friable ACM which has become friable, any Category I non-friable ACM which will be or has been subjected to sanding, grinding, cutting, or abrading, any Class II non-friable ACM that has a high probability of becoming or has become crumbled, pulverized, or reduced to a powder by the forces expected to act on the material in the course of demolition or renovation operations.

Note 4.: Asbestos Containing Construction Materials (ACCM) is a manufactured construction material containing greater than 0.1% asbestos by weight by the PLM method.

Note 5.: The terms “assume” and “presume” mean the named material is considered positive for containing asbestos and must be treated accordingly, until properly sampled in compliance with 40 CFR, Part 763 Asbestos-Containing Materials in Schools; Final Rule and Notice.

Competent Person

The Cal/OSHA standard for asbestos related construction work, found in 8 CCR, 1529, outlines specific duties and qualifications of the “Competent Person.” Find below a n overview of these qualifications and responsibilities. The competent person must be authorized by their employer to take prompt corrective measures to eliminate hazards on the job and protect their workers safety. The competent person must be the Supervisor onsite who is capable of:

• Identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees.

• Identifying existing asbestos hazards in the work place and selecting the appropriate control strategy for asbestos exposure.

The duties of the competent persons include, but are not limited to:

• Frequent and regular inspections of the job site, materials, and equipment. • Supervise or perform the set-up of the regulated area and/or containment. • Ensure the integrity of the regulated area and/or containment. • Set up procedures to control entry to and exit from the regulated area and/or containment. • Supervise all employee exposure monitoring and assure it is conducted according to regulatory requirements.

• Ensure that employees working within the regulated area(s) wear respirators and protective clothing as required by regulation.

El Portal Elementary School
2600 Moraga Road, San Pablo, CA
84 • Ensure that employees working set up, use, and remove engineering controls, use work practices and personal protective equipment in compliance with the regulations.

• Ensure that employees use hygiene facilities and observe the decontamination procedures specified in the regulation.

• Ensure through continuing onsite surveillance that engineering controls are functioning properly and employees are using proper work practices.

• Ensure that notification requirements of the regulation are met.

Additionally, the EPA requires the competent person to be trained in the Federal NESHAP regulations, the means to comply with them, and be on site during all removal operations.

2600 Moraga Road Abatement & 2022 Form ATTACHMENT H – NOTICES Demolition Project Page 99
0501

Attachment E – Lead Results List

2600 Moraga Road Abatement & 2022 Form ATTACHMENT H – NOTICES Demolition Project Page 100
0501

El Portal Elementary School
2600 Moraga Road, San Pablo, CA

36 PART 5.0. LEAD RESULTS LIST

Any material not specified on the following list which the Contractor encounters at this site must be considered as “suspect” and “assumed” to contain Lead per US EPA. The only items excluded from this statement are; bare wood, glass, and metal.

Sample
Number Material Location Condition Lead Content
(% by weight)
Approximate
Quantity
01-PB White Paint
on Drywall
Interior of Classroom 24-28
Building Walls Fair 0.098 10,000 SF
02-PB White Paint
on Drywall
Interior Classroom 21-23 and
Computer Lab Building on
Drywall Walls
Fair 0.29 10,000 SF
03-PB White Paint
on Drywall
Interior of Classroom 9-13
Building on Drywall Walls Fair 0.16 10,000 SF
04-PB White Paint
on Drywall
Interior of Classroom 3-7
Building on Drywall Walls Fair 0.048 10,000 SF
05-PB Gray Paint
on Plaster
Exterior of Classroom 3-7 and
Auditorium Building on Plaster
Walls
Fair 0.025 13,200 SF
06-PB Gray Paint
on Plaster
Exterior of Classroom 9-13
Building on Plaster Walls Fair 0.20 5,000 SF
07-PB Gray Paint
on Plaster
Exterior of Classroom 20-23
and Admin Building on Plaster
Walls
Fair 0.035 8,500 SF
08-PB Gray Paint
on Plaster
Exterior of Classroom 24-28
Building on Plaster Walls Fair 0.24 5,000 SF
13-PB White Paint
on Drywall Interior Auditorium Wall
Loose
and
Peeling

0.12 16,000 SF
15-PB
Green Paint
on Wood
Trim
Exterior of Classroom Building
1&2
Loose
and
Peeling

0.55 350 LF
16-PB
Green Paint
on Wood
Trim
Exterior of Classroom 3-7
Building and Auditorium
Building
Loose
and
Peeling

0.68 800 LF
17-PB
Green Paint
on Wood
Trim
Exterior of Classroom 9-13
Building and Library
Loose
and
Peeling

0.73 600 LF
18-PB
Green Paint
on Wood
Trim
Exterior of Classroom 20-23
and Admin Buildings
Some
Loose
and
Peeling

0.58 700 LF
19-PB
White Paint
on Wood
Trim
Exterior of Classroom 24-28
Building
Some
Loose
and
Peeling

0.29 500 SF
El Portal Elementary School
2600 Moraga Road, San Pablo, CA

37 Sample
Number Material Location Condition Lead Content
(% by weight)
Approximate
Quantity
20-PB
White Paint
on Wood
Trim
Exterior of Classroom 20-23
Building
Some
Loose
and
Peeling

0.33 700 LF
21-PB
White Paint
on Wood
Trim
Exterior of Classroom 20-23
and Admin Buildings
Some
Loose
and
Peeling

0.70 700 LF
22-PB
White Paint
on Wood
Trim
Exterior of Classroom 3-7 and
Auditorium Building
Some
Loose
and
Peeling

0.70 800 LF
23-PB
White Paint
on Wood
Trim
Exterior of Classroom 1&2
Building
Some
Loose
and
Peeling

0.55 350 LF

A total of five (5) ceramic glaze samples were collected during this inspection and submitted to EMSL. These samples were analyzed by Total Threshold Limit Concentration (TTLC). EMSL is accredited by the California Department of Public Health’s Environment al Laboratory Accreditation Program Branch to perform this analysis.

Results of the analysis are listed in the following table:

Sample
Number Material Location Condition
Lead
Content
(mg/Kg)
Approximate
Quantity
09-PB
4”x4” Salmon
Colored
Ceramic Tile
Glaze
Women’s Restroom Wall in
Classroom 3 Good 14,000 500 SF
10-PB
4”x4” Green
Colored
Ceramic Tile
Glaze
Men’s Restroom Wall in
Classroom 2 Good 2,300 500 SF
11-PB
4”x4” Salmon
Colored
Ceramic Tile
Glaze
Women’s Restroom Wall in
Classroom 20-23 Building Good <40 300 SF
12-PB
4”x4” Green
Ceramic Tile
Glaze
Men’s Restroom Wall in
Classroom Building 20-23 Good 1,300 300 SF
14-PB
4”x4” Brown
Ceramic Tile
Glaze
Kitchen Auditorium Wall Fire
Impacted 290 600 SF

2600 Moraga Road Abatement & 2022 Form ATTACHMENT H – NOTICES Demolition Project Page 101
0501

Attachment F – Notices

2600 Moraga Road Abatement & 2022 Form ATTACHMENT H – NOTICES Demolition Project Page 102
0501

2600 Moraga Road Abatement & 2022 Form NOTICE OF POTENTIAL AWARD Demolition Project Page 103
0501
[Copy onto City letterhead]

Sent via _______________ <insert delivery method, e.g., certified mail or FedEx>

<Date>

<Contractor representative name and title>
<Contractor business name>
<Contractor address>
<Contractor fax or email>

Re: NOTICE OF POTENTIAL AWARD
<Project Title>Project

Dear <Contractor representative name>:

The City of San Pablo (“City”) is pleased to inform you that City staff intends to recommend that the San Pablo City Council or its authorized designee award the Contract for the above-referenced Project (“Project”) to <_______________> (“Contractor”) for the Contract Price of $<_____________>, based on Contractor’s Bid Proposal submitted on <____________, 20__>.

A copy of the Contract accompanies this Notice. Contractor must execute <___> copies of the enclosed Contract and return the wet-inked copies to my attention, accompanied by the required Payment Bond, Performance Bond, and insurance certificates and endorsements, no later than ten days from the date of this Notice of Potential Award, above.

Failure to execute and return the enclosed Contract and required bonds and insurance documentation within the specified time could result in forfeiture of Contractor’s bid security. This Notice of Potential Award does not bind the City to award the Contract. The City, acting through its City Council or authorized designee, reserves the right to reject any or all bids, and the right to decline to award the Contract, notwithstanding any staff recommendation.

Unless expressly authorized or required to engage in any pre-construction activities, such as preparing submittals, Contractor must not commence Work until directed by the Notice to Proceed and will not be entitled to compensation or credit for any Work performed before the date specified in the Notice to Proceed.

Please acknowledge receipt of this Notice of Potential Award by signing the attached Acknowledgement of Notice of Potential Award, as indicated, and transmitting the Acknowledgement to my office at: <Fax number or email address>. Do not hesitate to contact me if you have any questions in this regard.

Sincerely,

< Name>
< Title>

Enclosure

2600 Moraga Road Abatement & 2022 Form NOTICE OF POTENTIAL AWARD Demolition Project Page 104
0501
Acknowledgement of Notice of Potential Award

On behalf of <Contractor company name> (“Contractor”), I acknowledge receipt of the Notice of Potential Award for the <Project Title>Project:

s/_________________________________

Name: _____________________________

Title: ______________________________

Date: ______________________________

2600 Moraga Road Abatement & 2022 Form NOTICE TO PROCEED Demolition Project Page 105
0501
[Copy onto City letterhead]

Sent via _______________ <insert delivery method, e.g., certified mail or FedEx>

<Date>

<Contractor representative name and title>
<Contractor business name>
<Contractor address>
<Contractor email>

Re: NOTICE TO PROCEED
<Project Title>Project

Dear <Contractor representative name>:

By this letter <______________________________> (“Contractor”) is notified to proceed with its Work for the above-referenced Project (“Project”), as required by the Contract Documents. Contractor and its first-tier Subcontractors must attend a mandatory pre-construction conference on <date> at <time> at <address/location>. The following document(s) must be submitted to the Project Manager at ___________ <email address>, no later than <_______, 20__>: ____________________________ <list required documents, e.g., baseline schedule, subcontracts, submittal schedule, schedule of values, etc.>

Contractor should start the Work on or before <Date> (“Start Date”), and must achieve Final Completion within <# Days> calendar days from the Start Date.

A copy of the fully executed Contract is enclosed for your files.

Please acknowledge receipt of this Notice to Proceed by signing the attached Acknowledgement of Notice to Proceed, as indicated, and transmitting the Acknowledgement to my office at: <__________>@sanpabloca.gov. Please do not hesitate to contact me if you have any questions in this regard.

Sincerely,

< Name>
< Title>

Enclosure

2600 Moraga Road Abatement & 2022 Form NOTICE TO PROCEED Demolition Project Page 106
0501
Acknowledgement of Notice to Proceed

On behalf of <Contractor company name>(“Contractor”), I acknowledge receipt of the Notice to Proceed for the <Project Title>Project:

s/_________________________________

Name: _____________________________

Title: ______________________________

Date: ______________________________

2600 Moraga Road Abatement & 2022 Form NOTICE OF COMPLETION Demolition Project Page 107
0501
Recording Requested By:

The City of San Pablo

When Recorded Mail To:
_____________________ <name, title>
_____________________ <street address>
_____________________ <city, state and zip>

EXEMPT FROM RECORDING FEES PER
GOVERNMENT CODE § 27383

SPACE ABOVE THIS LINE IS FOR RECORDER’S USE

NOTICE OF COMPLETION
Civil Code §§ 8182, 8184, 9204, and 9208

NOTICE IS HEREBY GIVEN THAT:

1. The undersigned is the agent of the owner of the Project described below.

2. Owner’s full name is City of San Pablo (“City”)

3. City’s address is 1000 Gateway Avenue, San Pablo, California 94806

4. The nature of City’s interest in the Project is:
__ Fee Ownership __ Lessee _ _ Other:__________________

5. Contract was awarded by City Council on: <Date of Contract Award>

6. Construction work on the Project performed on City’s behalf is generally described as follows: <Project title and description>

7. The Project is located at: <Location / address>

8. The name of the original Contractor for the Project is: <Contractor company name> located at <Contractor company address>

9. The Project was accepted as complete on: <Final Completion date>

Verification: In signing this document, I, the undersigned, declare under penalty of perjury under the laws of the State of California that I have read this notice, and I know and understand the contents of this notice, and that the facts stated in this notice are true and correct.

__________________________ ________________________________ Date and Place Signature

________________________________
Name and Title

EXEMPT FROM NOTARY ACKNOWLEDGMENT REQUIREMENTS PER
GOVERNMENT CODE § 27287 AND CIVIL CODE § 9208

2600 Moraga Road Abatement & 2022 Form ATTACHMENT H – NOTICES Demolition Project Page 101
0501
Attachment G – Site Photos
2600 Moraga Road Abatement & 2022 Form
Demolition Project
ATTACHMENT G – SITE
PHOTOS Page 102
0501

2600 Moraga Road Abatement & 2022 Form ATTACHMENT G – SITE Demolition Project 051 PHOTOS Page 102
2600 MORAGA ROAD - SITE PHOTO 1

2600 Moraga Road Abatement & 2022 Form ATTACHMENT G – SITE Demolition Project 051 PHOTOS Page 102

2600 MORAGA ROAD - SITE PHOTO 2

2600 Moraga Road Abatement & 2022 Form ATTACHMENT G – SITE Demolition Project 051 PHOTOS Page 102

2600 MORAGA ROAD - SITE PHOTO 3

2600 Moraga Road Abatement & 2022 Form ATTACHMENT G – SITE Demolition Project 051 PHOTOS Page 102

2600 MORAGA ROAD - SITE PHOTO 4

CITY OF SAN PABLO
Public Works Department

1000 Gateway Avenue ● San Pablo, CA 94806
Main: 510-215-3060 ● Fax: 510-215-3013
www.SanPabloCA.gov

July 17,2023

SUBJECT: ADDENDUM NO. 1
2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 (File Number 0501)

To Prospective Bidders:

The following are changes to the contract specifications and plans for the above referenced project:

This addendum is hereby made a part of the contract documents to the same extent as if they were originally included therein. Receipt of this addendum shall be acknowledged with the bid for the 2600 Moraga Road Abatement & Demolition Project.

Note There are several Attachments to this document: and these should be located behind the existing attachments in the Bid documents,

Attachment H: El Portal School Site Plan
Attachment I: El Portal School As-Built Plans
Attachment J: BAAQMD J Permit

BID OPENING:

1. Bid opening remains unchanged. Date: July 25, 2023

QUESTIONS: Answers are presented in bold and italic

2. During work is the Prime Contractor required to supervise all subcontractors or can Supervision by subcontractor sufficient? Prime Contractor must be available to respond to site and be knowledgeable of daily event but, subcontractor supervision can be delegated to subcontractor. All Supervisors must provide contact information to inspection team.

3. Qualification requirements note that bidders must have completed 6 recently completed public works projects, can experience by key personnel’s past experience be used to comply with this requirement? If the proposer can document how both the Project Manager has 6 public works projects in a capacity of Project Manager and the Superintendent has 6 public works projects of which they were the Superintendent, then that will be acceptable.
2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 – ADDENDUM No. 1_

Page 2 of 3 ends

P:\CIP\_PW ACTIVE PROJECTS\0501 S.P.A.R.C. Project\15 Bid\02 Addendum\Demo\Formal Bid\Demolition Addendum #01.docx

4. Can drywall with tape joint compound and plaster walls which have been identified as having a point count of less than 1% be left in place and demolished with the building structure? Yes, if work is performed by a DOSH certified demolition contractor.

5. Are the burned buildings (Gymnasium and Administration Buildings) that have asbestos materials to be demolished using water control measures with lined waste bins and labeled friable waste, and does this include the burned out classroom structures as well. Yes, both the Gymnasium and the Administration buildings to be demolished using wet methods, the class room structures on the south west to be demolished in same method.

6. Are as-built drawings available? As Built drawings are limited in scope and do not convey utility information nor elevations of the buildings see attached El Portal School PDF.

7. If no as-built drawings are available, what size should the bidders assume for the below grade concrete. Assume 6-inch slab, 3-ft deep footings x 12-inches wide.

8. What is the thickness of the asphalt pavements and does the asphalt contain petromat? Assume 4-inches. Assume no petromat. Assume Limit is 3’ beyond existing structures with the parking lot to remain. Assume temporary fencing to remain but can be relocated to perform work.

9. Do existing slabs have wire mesh or rebar? Assume both.

10. The asbestos and lead surveys list room numbers for the various materials, please provide a drawing with room numbers so bidders know where the materials are located. See Attached PDF files for room numbering.

11. The portable building on the North west corner of the north most building to be demolished? Yes, the portable building on site should be demolished but the shipping container to be located to the front parking lot.

12. Are the pavers and random building materials on site are they to be removed by others prior to work? No, demolition contractor to include these materials in their removal costs.

13. Is there any backfill or compaction required? No compaction requirements. No backfill requirements.

14. Is the SWPP installation limited to straw waddles at the perimeter? Yes. Plus SD inlet protection.

15. No underground utilities have been identified, does the work exclude the removal of underground utilities? No removal of UG utilities. Just capping sewer line and crimping water line. City crews shall turn water off at meter.

16. If underground utilities are to be removed please identify type, location, and depth. USA will need to be utilized to identify underground Utility location. Assume hand dig to verify depth.

17. Will the City perform the required utility disconnects, caps, and safe-offs? We can coordinate with utility companies later on.

18. Is there a source of water on site for dust Control? Yes. I believe there is a fire hydrant close by.

19. When will the work start? Early to Mid-August Assume work to be completed prior to October 15 2023.
2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 – ADDENDUM No. 1_

Page 3 of 3 ends

P:\CIP\_PW ACTIVE PROJECTS\0501 S.P.A.R.C. Project\15 Bid\02 Addendum\Demo\Formal Bid\Demolition Addendum #01.docx

20. Will the city provide the necessary demolition permit? Yes. J-number and bldg. demo permit # is attached.

21. Is the limit of work as shown on the Demolition Site Plan? Assume Limit is 3’ beyond existing structures with the parking lot to remain. Assume temporary fencing to remain but can be relocated to perform work.

22. Do you want the concrete hauled off site of crushed and left on site? Hauled off.

23. Is Saw cutting required at demolition limits? No, saw cutting is not required.

24. Contractor to get City Business License. Yes, Contractor to get Business License.

25. Is a BAAMD permit required? Yes, City has obtained J number from BAAMD see Attached

26. Traffic Control Plans required? Yes, Contractor will need to provide a Traffic Control Plan. Access is limited to Moraga Road

27. Hazardous Materials to be removed? See bid documents for Asbestos, Lead, PCB and other compounds.

28. Some rooms have old appliances are these to be included in scope of work? Yes, all freon containing appliances to be removed prior to demolition with Freon to be reclaimed in a manner consistent with BAAQMD and State and EPA guidelines.

29. Number of working days is 40 is that calendar or working days? Working Days

30. Liquidated Damage Cost? The LD is $2500 per calendar day.

If you have any questions regarding this addendum, please contact Matt Brown, Senior Civil Engineer at (510) 215-3061.

Sincerely,

MATTHEW A BROWN, P.E.

Senior Civil Engineer/ Acting Public Works Director

RTH/MB

2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 – ADDENDUM No. 1_

Page 5 of 5 ends

07/17/23
P:\CIP\_PW ACTIVE PROJECTS\0501 S.P.A.R.C. Project\15 Bid\02 Addendum\Demo\Formal Bid\Demolition Addendum #01.docx
Attachment H: El Portal School Site Plan

Page 5 of 13 ends

2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 – ADDENDUM No. 1_

Page 6 of 5 ends

07/17/23
P:\CIP\_PW ACTIVE PROJECTS\0501 S.P.A.R.C. Project\15 Bid\02 Addendum\Demo\Formal Bid\Demolition Addendum #01.docx
A
ttachment I: El Portal School As-Built Plans

Page 7 of 13 ends
Page 8 of 13 ends
Page 9 of 13 ends
Page 10 ends

13 (D Ct-M.612.00M$
@)HEA�R 1<coH
@-JANl10R
. @ S1�A6>E
@ 'SHEL-iEFZ­
@ WAL¥-i-1AY

EL PORTAL SCHOOL
DATE: SP-lA EXISTING
11>'7 •� PAGE5 OF S
CD
4-<!? :A'--o':: 1�•--0•
lf,4'- •
-Sl"Z.E-
-----·
� x(34 1--0' 'f.. zej-o'J ;-(?4!..-3• Y.'2$-d)
( I0-0' '>< 14 Lo")
(16'-d' ;< 141-0'�

1.. i- ( IS'-3' x 't)-cJ•)-+ (,t'· o''� 1.�'-o")
'2,. "-(&J'-7'' X 17 1-0') X ,!5
('B'-d x 7t-cl')-t(<o'-dx /7te.,'-3'�-i­
Lf:J'-d x G:,'81-01 x . 6
-rorAL
�Ii:.
. 14-0
25'2
llexg
112
l'Uo5
CHESTER BOWLES, JR., ARCHITECT C.3.806
RICHMOND UNIFIED SCHOOL DISTRICT INTERACTIVE RESOURCES, INC. · RICHMOND, CALIFORNIA THOMAS KING BUTT, ARCHITECT C7369

Page 11 of 13 ends

2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 – ADDENDUM No. 1_

Page 7 of 5 ends

07/17/23
P:\CIP\_PW ACTIVE PROJECTS\0501 S.P.A.R.C. Project\15 Bid\02 Addendum\Demo\Formal Bid\Demolition Addendum #01.docx
A
ttachment J: BAAQMD J Permit

Page 13 of 13 ends

CITY OF SAN PABLO
Public Works Department

1000 Gateway Avenue ● San Pablo, CA 94806
Main: 510-215-3060 ● Fax: 510-215-3013
www.SanPabloCA.gov

July 19, 2023

SUBJECT: ADDENDUM NO. 2
2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 (File Number 0501)

To Prospective Bidders:

The following are changes to the contract specifications and plans for the above referenced project:

This addendum is hereby made a part of the contract documents to the same extent as if they were originally included therein. Receipt of this addendum shall be acknowledged with the bid for the 2600 Moraga Road Abatement & Demolition Project.

BID OPENING:

1. Bid opening remains unchanged. Date: July 25, 2023

SPECIFICATIONS:

2. Reference: NOTICE INVITING BIDS- Time for Completion, Page 1

The Time of completion has been modified and the following sentence shall be deleted:

Time for Completion. The Project must be completed within 40 working days from the start date set forth in the Notice to Proceed.

And replaced with:

The Project must be completed within 50 working days from the start date set forth in the Notice to Proceed.

QUESTIONS: Answers are presented in bold and italic

3. Will the brick walls at the admin building and library must be disposed as RACM? As most of the brick is in burned areas it should be considered Regulated Asbestos Containing Material (RACM).
2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 – ADDENDUM No. 1_

Page 2 of 2 ends

P:\CIP\_PW ACTIVE PROJECTS\0501 S.P.A.R.C. Project\15 Bid\02 Addendum\Demo\Formal Bid\LTR Addendum #02 2600 Moraga Demo.docx

4. Will Power to the site be provided by the City or by the contactor? By the Contractor.

If you have any questions regarding this addendum, please contact Matt Brown, Senior Civil Engineer at (510) 215-3061.

Sincerely,

MATTHEW A BROWN, P.E.

Senior Civil Engineer/ Acting Public Works Director

RTH/MB

2600 Moraga Road Abatement & Demolition Project, CIP Project No. 0501 – ADDENDUM No. 1_

Page 3 of 1 ends