Cities Index.
4.h-Rotary-Manor-Culvert-Replacement-Project

San Rafael City Council
February 20, 2024

Document
4.h-Rotary-Manor-Culvert-Replacement-Project
Meeting
February 20, 2024
Body
San Rafael City Council
Original file
119 KB
Text extracted from the city's file for reading and search. Open the original on storage.googleapis.com. That file is the official record.

____________________________________________________________________________

FOR CITY CLERK ONLY
Council Meeting:

Disposition:

Agenda Item No: 4.h
Meeting Date: February 20, 2024

SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Public Works
April Miller, Public Works Director
Prepared by: Theo Sanchez, Associate Civil Engineer City Manager Approval: __________ TOPIC: ROTARY MANOR CULVERT REPLACEMENT PROJECT
SUBJECT: ACCEPT COMPLETION OF THE ROTARY MANOR CULVERT REPLACEMENT PROJECT, CITY PROJECT NO. 11371, AND AUTHORIZE THE CITY CLERK TO FILE

THE NOTICE OF COMPLETION
RECOMMENDATION:

Accept completion of the Rotary Manor Culvert Replacement Project and authorize the City Clerk to file the Notice of Completion.

BACKGROUND:

Rotary Manor, located at 1821 Fifth Avenue, is a senior community housing facility. A culvert exists underneath this property and conveys flows along a historic waterway representing the upper reaches of present-day San Rafael Creek.

The corrugated metal pipe segment of this culvert needed replacement. On July 10th, 2023, the City Council awarded the construction contract to Maggiora & Ghilotti, Inc. in the amount of $788,700 and approved a construction contingency of $121,300 for a total appropriation of $900,000. Construction began on September 5th, 2023, and was completed on January 26th, 2024.

ANALYSIS:

Pursuant to Civil Code Section 3093, the City is required to record a Notice of Completion upon City acceptance of the improvements. This acceptance initiates a period during which project subcontractors may file Stop Notices seeking payment from the City from the funds owed to the Contractor for the project work.

FISCAL IMPACT:

No fiscal impact is associated with this report.

RECOMMENDED ACTION:

Accept completion of the Rotary Manor Culvert Replacement Project and authorize the City Clerk to file the Notice of Completion.

ATTACHMENTS:

1. Notice of Completion

← All documents from this meeting