and demonstrated success managing projects with diverse stakeholder groups.
4. Management Approach, Staffing Plan, and Rate Structure:
Qualifications of project staff (particularly key personnel such as the project manager), key personnel's level of involvement in performing related work, and the team's experience in
maintaining schedule and budget.
Points
Based
20 (20%
of Total)
5. References: Three references by former clients on similar projects.
Points
Based
15 (15%
of Total)
5. SPECIAL CONDITIONS
• Professional Services Agreement
The consultant selected shall use the City of San Rafael’s standard Professional Services Agreement. Submitting a Proposal is acceptance of the Professional Services Agreement as-is. Contractually required insurance coverage and endorsement information is shown in the body of the document.
• Reservations
The issuance of this RFP constitutes only an invitation to present responses. This RFP does not commit the City to award a contract, to defray any costs incurred in the preparation of a Proposal pursuant to this RFP, or to procure or contract for work. The City reserves the right, at its sole discretion, to determine whether or not any aspect of the response satisfactorily meets the criteria established in the RFP. • RFP as a Public Record
All Proposals submitted in response to this RFP become the property of the City and thus become public records and, as such, may be subject to public review. • Right to Cancel
The City reserves the right to cancel or change, for any or no reason, in part or in its entirety, this RFP, including but not limited to: selection schedule, submittal date, and submittal requirements.
• Business License
Prior to the selected consultant engaging in any operation or activity as a result of an award of a purchase contract, it must obtain a business license from the City of San Rafael. The business license must be kept in full force and effect during the term of the contract.
• Additional Information
The City reserves the right to request additional information and/or clarification from any or all respondents to this RFP, the right to confer with any respondent submitting a response and the right to reject any or all responses with or without cause. The City reserves the right, at its sole discretion, to waive any irregularities or informality. The City may conduct interviews with any respondent it deems necessary.
Request for Proposals - Capital Project Management Services Albert Park Library and Community Center
• Reasonable Inquiry
The City may conduct any reasonable inquiry to determine the responsibility of the proposer. The submission of a proposal constitutes permission by the proposer for the City to verify all information contained therein. If the City deems it necessary, additional information may be requested from any proposer. Failure to comply with any such request may disqualify a proposer from consideration.
• Public Information
Consultants who wish to release information regarding the consultant selection process, contract award, or data provided by the City at any public hearing/meeting, must receive prior written approval from the City before disclosing such information to the public.
ATTACHMENTS
A. Albert Park Library & Community Center Muni Code Section 3.42 B. City of San Rafael Professional Services Agreement Template A.
B.
C.
D.
E.
F.
Chapter 3.42 - PARCEL TAX FOR PLANNING AND CONSTRUCTION OF A NEW ALBERT PARK MAIN LIBRARY AND COMMUNITY CENTER
3.42.010 - Title.
This Chapter shall be known and may be cited as "Parcel Tax for Planning and Construction of a New Albert Park Main Library and Community Center." (Ord. No. 2044, § 3, 12-16-2024)
3.42.020 - Imposition.
A special non-ad valorem parcel tax (hereinafter the "Parcel Tax") is hereby established and shall be levied annually on the owner of each parcel of taxable real property located within the City of San Rafael (the "City"), unless the owner is by law exempt from taxation, in which case, the Parcel Tax shall be assessed to the holder of the possessory interest in such parcel, unless such holder is also by law exempt from taxation. The Parcel Tax is an excise tax on the use of property within the City.
The Parcel Tax shall hereby be established and levied each year, commencing July 1 after the Effective Date, on each parcel of taxable real property, improved or unimproved, within the boundaries of the City at the rate of fourteen and one-half cents ($0.145) per square foot of improved building area and seventy-five dollars ($75.00) per vacant parcel.
The collection of the Parcel Tax shall commence on July 1 after the Effective Date and continue for thirty (30) years thereafter or so long as bonds for the planning and construction of a new library and community center remain outstanding requiring debt service payments, whichever is longer.
The Parcel Tax shall be collected by the Marin County Tax Collector (the "Tax Collector") at the same time and in the same manner and shall be subject to the same penalties as ad valorem property taxes collected by the Tax Collector. The collection of the Parcel Tax hereunder shall not decrease the funds available from other sources of the City in any period from the Effective Date hereof.
For the purposes of this Chapter, a "parcel of taxable real property" shall be defined as any unit of real property located in the City which receives a separate tax bill for ad valorem property taxes from the Tax Collector. "Building" is defined as any structure having a roof supported by columns or walls and designed for the shelter or housing of any person or property of any kind. The word "building" includes the word "structure" and encompasses, without limitation, all residential, commercial and industrial structures. "Improved parcel" is defined as a parcel on which there exists any building. "Vacant parcel" is defined as a parcel on which no building exists.
The City shall be authorized to incur bonded indebtedness for eligible capital costs related to the planning and construction of a new library and community center as well as upgrades to San Rafael's branch libraries, utilizing the proceeds from the Parcel Tax to make principal and interest payments to service such debt.
st
st
G.
H.
A.
B.
1. 2.
All property that the Tax Collector has determined to be otherwise exempt from property taxes, or on which no ad valorem property taxes have been levied, in any year shall also be exempt from the Parcel Tax in such year. The Tax Collector's determination of exemption or relief for any reason of any parcel from taxation, other than the Senior Citizen Exemption (defined below), shall be final on the taxpayer for purposes of this Chapter. Taxpayers desiring to challenge the Tax Collector's determination should do so under the procedures established by the Tax Collector's Office, applicable provisions of the California Revenue and Taxation Code or other applicable law. Taxpayers seeking any refund of taxes paid pursuant to this Chapter shall follow the procedures applicable to tax refunds pursuant to the California Revenue and Taxation Code and any other generally applicable law.
An optional exemption (heretofore the "Senior Citizen Exemption") from the Parcel Tax will be made available annually to each individual in the City who attains 65 years of age prior to July 1 of the tax year, and who owns a beneficial interest in the parcel, and who uses that parcel as his or her principal place of residence, and who applies for such exemption to the City on or before June 1st of each tax year, or during the first year of the tax at a date to be determined by the Tax Collector. Any application for such exemption must be submitted to the Tax Collector, pursuant to any rules and regulations of the Tax Collector.
(Ord. No. 2044, § 3, 12-16-2024)
3.42.030 - Levy, collection, purpose.
The proceeds of the Parcel Tax shall be deposited into a special fund, maintained by the City, which proceeds, together with any interest and any penalties thereon, collected each fiscal year shall be used solely for the purposes set forth in this Section. The proceeds from the Parcel Tax shall be expended only for these purposes.
The proceeds collected by the levy of the Parcel Tax shall be used as follows:
The City shall be authorized to fund the planning, construction, equipping and furnishing of a new main library and community center, with associated parking lots, on City-owned property at Albert Park, located near 1 Street and B Street in Downtown San Rafael (the "Albert Park Main Library and Community Center"), and issue and sell bonds to provide financing for the specific capital projects listed below, subject to all of the accountability safeguards specified herein (hereinafter referred to as "Project" or "Projects").
The Albert Park Main Library and Community Center Project shall be sized to meet total citywide library square footage requirements appropriate for a city the size of San Rafael (~0.70 - 0.75 square feet per capita) not including associated parking, outdoor spaces, and landscaping. The majority of the building square footage needed to achieve the total required citywide square footage of library space shall be provided by the Albert Park Main Library and Community Center Project, but this Initiative shall not preclude adding additional library square footage to the branch libraries as part of the effort to achieve the aforementioned total citywide library square footage requirements of ~0.70 - 0.75 SF per capita. The community center Project component at Albert Park should be sized, at minimum, to meet the current community center uses in that location at the time the Project is planned for construction. st
3. 4.
5. 6.
7. 8.
C.
All designs and planning for the Albert Park Main Library and Community Center shall include the preservation or relocation of the existing Lonatese Gardens at Albert Park.
Provided that sufficient funding is available from the proceeds of the Parcel Tax to fund the planning and construction of a new Albert Park Main Library and Community Center, additional funding from the Parcel Tax may also be used to fund upgrades, renovations, remodeling, technology improvements, and furnishing/equipment improvements at Pickleweed Branch Library and Terra Linda Branch Library.
Each Project described herein is assumed to include its share of costs of bond issuance, architectural, engineering, legal and similar planning costs; litigation costs; construction management; Project bond consultants; staff development and training expenses associated with learning construction techniques and approaches and new equipment and systems; the furnishing and equipping of all Projects, including equipment to maintain facilities in a safe and clean condition; and a customary contingency for unforeseen design and construction costs. Payment of the costs of preparation of facilities planning and Project implementation studies, feasibility and assessment reviews, master planning, environmental studies, permit and inspection fees, studies and assessments, including ADA and seismic, and temporary housing and relocation costs for dislocated programs or activities caused or necessitated by Projects are permissible expenditures.
The final cost of each Project will be determined as plans are finalized and Projects are completed. Based on the final costs of each Project, certain of the Projects described above may be delayed or may not be completed. Necessary site preparation, grading or restoration may occur in connection with new construction, including ingress and egress, removing, replacing or installing irrigation, utility lines, trees and landscaping, relocating fire access roads and acquiring any necessary easements, leases, licenses or rights of way to the property.
Proceeds from the Parcel Tax shall be used only for the planning, construction, equipping and furnishing of the facilities and grounds identified in this section, and not for any other purpose, including administrator salaries and other operating expenses, in accordance with applicable law.
Where feasible, Projects may be completed in partnership with other public or private agencies on a joint use basis using Parcel Tax proceeds or related bonded indebtedness, subject to federal tax rules and regulations.
The purposes set forth in this Section shall constitute the specific purposes of this Chapter, which are specific and legally binding limitations on how the proceeds of the Parcel Tax may be spent. The proceeds of the Parcel Tax shall be used only for such purposes and shall not fund any purpose other than those set forth herein.
(Ord. No. 2044, § 3, 12-16-2024)
3.42.040 - City annual report.
The City shall prepare a report on at least an annual basis which shows the amount of funds collected and expended, and the status of any Project required or authorized to be funded, by the Parcel Tax. The City shall file each report with the Mayor, City Council and the oversight committee referenced in this Chapter.
A.
B.
(Ord. No. 2044, § 3, 12-16-2024)
3.42.050 - Parcel tax funds shall not replace existing funding.
The People of the City of San Rafael find and declare that, absent the Parcel Tax funds, the City would require more resources than are currently provided to plan, construct, equip and furnish a new library and community center. In adopting this Parcel Tax, the People of the City are providing new, additional City resources to complement, but not to replace or supplant, any or all pre-existing City, State, Federal or other funding for the planning, construction, equipping and furnishing of a new library.
Consistent with subsection (A), the People of the City of San Rafael specifically find and declare that their contributions to and disbursements from the special Parcel Tax fund authorized by this Chapter are discretionary expenditures by the City for the direct benefit of the residents of the City. In the event that the State attempts, directly or indirectly, to redistribute these expenditures to other jurisdictions or to offset or reduce State or Federal funding to the City because of the contributions to and disbursements from the special Parcel Tax fund authorized by this Chapter, the City shall transfer said monies that would otherwise be distributed each year from the special Parcel Tax fund to such other fund as the City Council may designate, to be spent for purposes which are substantially equivalent to the purposes set forth in this Chapter. (Ord. No. 2044, § 3, 12-16-2024)
3.42.060 - Increase in appropriations limit.
To the extent that the revenue from the Parcel Tax is in excess of the spending limit for the City, as provided for in applicable provisions of the California Constitution and State law, the approval of the Parcel Tax by the voters shall constitute approval to increase the City's spending limit in an amount equal to the revenue derived from the Parcel Tax for the maximum period of time as allowed by law. (Ord. No. 2044, § 3, 12-16-2024)
3.42.070 - Fiscal accountability protections and oversight.
Starting with the first operative year of this Chapter, the City shall establish an oversight committee comprised of San Rafael residents to submit a report on at least an annual basis to the Mayor and City Council evaluating whether the proceeds from the Parcel Tax are being properly expended for the purposes set forth in this Chapter. Proceeds from the Parcel Tax shall be subject to the City's generally applicable independent annual audit procedures and requirements.
(Ord. No. 2044, § 3, 12-16-2024)
3.42.080 - Preservation of Historic Carnegie Library.
The People of the City of San Rafael specifically find and declare that the historic Carnegie Library building constructed in 1909 in Downtown San Rafael is an essential element of the City's history, architecture and character and shall be preserved for future use. Within two (2) years of the Effective Date of this Measure, the San Rafael City Council shall initiate a public planning process related to the preservation of the historic San Rafael Carnegie Library building for ongoing civic, community or community-serving commercial uses. The planning process shall guide the development of a proposal, to be presented to the community, for the preservation and reuse of the historic Carnegie Library in Downtown San Rafael after the library vacates the building. (Ord. No. 2044, § 3, 12-16-2024)
v. Feb 2025 Page 1
CITY OF SAN RAFAEL
PROFESSIONAL SERVICES AGREEMENT
This Professional Services Agreement (“Contract”) is entered into by and between the City of San Rafael (“City”) and __________________________________________ (“Contractor”), a __________________________________________________ for __________________________________________________________, and is effective on _____________________ (“Effective Date”). City and Contractor may be referred to individually as a “Party” or collectively as the “Parties” or the “Parties to this Contract.”
RECITALS
A. City desires to secure professional services more fully described in this Contract, at Exhibit A, entitled “SCOPE OF WORK”; and
B. Contractor represents that it, and its subcontractors, if any, have the professional qualifications, expertise, and necessary licenses and desire to provide certain goods and/or required services of the quality and type which meet objectives and requirements of City; and
C. Contractor acknowledges that the execution of this Contract by the City is predicated upon the representations made in Contractor’s proposal dated _________________ submitted to the City; and
D. The Parties have specified herein the terms and conditions under which such services will be provided and paid for.
NOW, THEREFORE, the parties hereby agree as follows:
CONTRACT
1. WORK TO BE PERFORMED.
Except as otherwise may be expressly specified in this Contract, Contractor shall furnish all technical and professional services, including labor, material, equipment, transportation, supervision and expertise (collectively referred to as “Services”) to satisfactorily complete the work required by City at its sole risk and expense. Services to be provided to City are more fully described in Exhibit A entitled “SCOPE OF WORK.”. v. Feb 2025 Page 2
2. COMPENSATION.
In consideration for Contractor’s complete performance of the Scope of Work, City will pay Contractor in accordance with the rates and/or prices set forth in Exhibit A, up to the not-to-exceed amount of $_____________.
Contractor shall not increase its rates throughout the Term of this Contract, except that upon 60 day written notice, Contractor may adjust its rates no more than once annually at a maximum amount equal to the percentage change through December in the prior calendar year to the consumer price index (“CPI”) for California, All Urban Consumers, San Francisco-Oakland-San Jose areas, not to exceed five percent (5%).
Contractor will bill City on a monthly basis for work performed by Contractor during the preceding month, subject to verification by City. City will pay Contractor within thirty (30) days of City’s receipt of invoice.
3. TERM OF CONTRACT.
This Contract becomes effective upon the date listed as "Effective Date" and shall remain in effect until the completion of all obligations of both Parties hereto, or ___________________________ from the Effective Date, whichever comes first, unless terminated or amended as provided herein.
4. RELIANCE ON PROFESSIONAL SKILL OF CONTRACTOR.
Contractor represents that it has the necessary professional skills to perform the work required and the City shall rely on such skills of the Contractor to do and perform the work. In performing the work hereunder Contractor shall adhere to the standards generally prevailing for the performance of expert consulting services similar to those to be performed by Contractor hereunder.
Contractor represents that it has reviewed Exhibit A and that in its professional judgment the work to be performed under this Contract can be performed for a fee within the maximum amount set forth herein and within the times specified.
Contractor represents that it possesses all necessary training, licenses and permits to perform the Scope of Work and that its performance of the Scope of Work will conform to the standards of practice of a professional having experience and expertise in performing professional services of like nature and complexity of the Scope of Work working on similar, successfully completed projects.
The granting of any progress payment by City, or the receipt thereof by Contractor, or any inspection, review, approval or oral statement by any representative of City or any other governmental entity, shall in no way waive or limit the obligations in this Paragraph 4 or lessen the liability of Contractor for unsatisfactory work, including but not limited to cases where the defective or below standard work may not have been v. Feb 2025 Page 3
apparent or detected at the time of such payment, inspection, review or approval.
5. PROJECT COORDINATION.
A. City’s Project Manager. ________________________________ is hereby designated the Project Manager for the City and said Project Manager shall supervise all aspects of the progress and execution of this Contract.
B. Contractor’s Project Director. Contractor shall assign a single Project Director to have overall responsibility for the progress and execution of this Contract for Contractor. ___________________________________ is hereby designated as the Project Director for Contractor. Should circumstances or conditions subsequent to the execution of this Contract require a substitute Project Director, for any reason, the Contractor shall notify the City within ten (10) business days of the substitution.
6. TERMINATION.
A. The term of this Contract shall commence upon the date hereinabove written and shall expire upon completion of performance of work hereunder by Contractor.
B. Notwithstanding the provisions of (A) above, City may with or without cause, direct Contractorto suspend, delay or interrupt the work, in whole or in part, for such periods of time as City may determine in its sole discretion.
C. City may terminate this Contract in whole, or from time to time in part, for default, should Contractor commit a material breach of this Contract, or part thereof, and not cure such breach within ten (10) calendar days of the date of City’s written notice to Contractor demanding such cure, in which case Contractor shall be liable to City for all loss, cost, expense, damage and liability resulting from such breach and termination.
D. City may terminate this Contract in whole, or from time to time in part, for convenience, whenever City determines that such termination is in City’s best interests, in which case Contractor shall be entitled to recover its costs expended up to the termination date plus reasonable profit thereon to the termination date as this Contract would otherwise provide, but may recover no other cost, damage or expense. Contractor shall continue its work throughout the course of any dispute, and Contractor’s failure to continue work during a dispute shall be a material breach of this Contract.
E. Lack of Appropriation: If this Contract is a multi-year contract, subject to appropriation each fiscal year, the City may terminate this Contract immediately for lack of appropriation of funds.
F. Effect of Termination. Upon receipt of notice of termination, neither party shall incur additional obligations under any provision of this Contract without the prior written consent of the other.
v. Feb 2025 Page 4
G. Return of Documents. Upon termination, any and all City documents or materials provided to Contractor and any and all of Contractor's documents and materials prepared for or relating to the performance of its duties under this Contract, shall be delivered to City as soon as possible, but not later than thirty (30) days after termination.
7. INSURANCE REQUIREMENTS.
During the term of this Contract, and for any time period set forth in Exhibit B, Contractor shall procure and maintain in full force and effect, at no cost to City insurance policies with respect to employees and vehicles assigned to the performance of work under this Contract with coverage amounts, required endorsements, certificates of insurance, and coverage verifications as defined in Exhibit B.
8. INDEMNIFICATION.
A. Except as otherwise provided in subparagraph B of this section, Contractor shall, to the fullest extent permitted by law, indemnify, release, defend with counsel approved by City, and hold harmless City, its officers, agents, employees and volunteers (collectively, the “City Indemnitees”), from and against any claim, demand, suit, judgment, loss, liability or expense of any kind, including but not limited to attorney's fees, expert fees and all other costs and fees of litigation, (collectively “CLAIMS”), arising out of Contractor’s performance of its obligations or conduct of its operations under this Contract. The Contractor's obligations apply regardless of whether or not a liability is caused or contributed to by the active or passive negligence of the City Indemnitees.
However, to the extent that liability is caused by the active negligence or willful misconduct of the City Indemnitees, the Contractor's indemnification obligation shall be reduced in proportion to the City Indemnitees’ share of liability for the active negligence or willful misconduct. In addition, the acceptance or approval of the Contractor’s work or work product by the City or any of its directors, officers or employees shall not relieve or reduce the Contractor’s indemnification obligations. In the event the City Indemnitees are made a party to any action, lawsuit, or other adversarial proceeding arising from Contractor’s performance of or operations under this Contract, Contractor shall provide a defense to the City Indemnitees or at City’s option reimburse the City Indemnitees their costs of defense, including reasonable attorneys’ fees, incurred in defense of such claims.
B. Where the work to be performed by Contractor under this Contract are design professional services to be performed by a design professional as that term is defined under Civil Code Section 2782.8, then, to the extent permitted by law including without limitation, Civil Code sections 2782, 2782.6 and 2782.8, Contractor shall indemnify and hold harmless the City and its officers, officials, and employees (collectively City Indemnitees) from and against damages, liabilities or costs (including incidental damages, Court costs, reasonable attorney’s fees as may be determined by the Court, litigation expenses and fees of expert witnesses incurred in connection therewith and costs of investigation) to the extent they are caused by the negligence, v. Feb 2025 Page 5
recklessness, or willful misconduct of Contractor, or any sub Contractors, or subcontractor or anyone directly or indirectly employed by them, or anyone for whom they are legally liable (collectively Liabilities). Such obligation to hold harmless and indemnify any indemnity shall not apply to the extent that such Liabilities are caused in part by the negligence or willful misconduct of such City Indemnitee.
C. The defense and indemnification obligations of this Contract are undertaken in addition to, and shall not in any way be limited by, the insurance obligations contained in this Contract and shall survive the termination or completion of this Contract for the full period of time allowed by law.
9. PREVAILING WAGE.
If the work to be performed under this Contract is for services where prevailing wages are required by State law, Contractor shall pay prevailing wages to its employees on any contract in excess of $1,000.00, Copies of the general prevailing rates of per diem wages for each craft, classification, or type of worker needed to execute the Contract, as determined by Director of the State of California Department of Industrial Relations, are on file at the City’s Public Works Department upon request and may be obtained from the California Department of Industrial Relations website
[http://www.dir.ca.gov/OPRL/DPreWageDetermination.htm]. Contractor shall comply with the 8-hours per day/40 hours per week/overtime/working hours restrictions for all employees, pursuant to the California Labor Code. Contractor and all subcontractors shall keep and maintain accurate employee payroll records for Work performed under the Contract. The payroll records shall be certified and submitted as required by law, including Labor Code Sections 1771.4 (if applicable) and 1776, including to the Labor Commissioner no less frequently than monthly. Contractor shall comply fully with Labor Code Section 1777.5 in the hiring of apprentices for work relating to the Contract.
10. NOTICES.
All notices and other communications required or permitted to be given under this Contract, including any notice of change of address, shall be in writing and given by email, personal delivery, or deposited with the United States Postal Service, postage prepaid, addressed to the parties intended to be notified. Notice shall be deemed given as of the date of email, personal delivery, or if mailed, upon the date of deposit with the United States Postal Service. Notice shall be given as follows:
To City’s Project Manager:
[As identified in item 5.A]
___________________________
San Rafael, CA 94901
Email: ______________________
To Contractor’s Project Director:
[As identified in item 5.B]
___________________________
___________________________
Email: ______________________
v. Feb 2025 Page 6
11. LIABILITY OF CITY.
Except as provided in Exhibit A, Scope of Work to be Provided by Contractor and Exhibit B, Insurance, City's obligations under this Contract shall be limited to the payment of the compensation provided for in Paragraphs 1 and 2 of this Contract, Notwithstanding any other provision of this Contract, in no event shall City be liable, regardless of whether any claim is based on contract, tort or otherwise, for any special, consequential, indirect or incidental damages, lost profits or revenue, arising out of or in connection with this Contract, the Scope of Work, or the Project.
City shall not be responsible for any damage to persons or property as a result of the use, misuse or failure of any equipment used by Contractor, or by any of its employees, even though such equipment be furnished, rented or loaned to Contractor by City. The acceptance or use of such equipment by Contractor or any of its employees shall be construed to mean that Contractor accepts full responsibility for and shall exonerate, indemnify, defend and save harmless City from and against any and all claims for any damage or injury of any type, including attorneys' fees, arising from the use, misuse or failure of such equipment, whether such damage be to the Contractor, its employees, City employees or third parties, or to property belonging to any of the above.
Nothing in this Contract shall constitute a waiver or limitation of any right or remedy, whether in equity or at law, which City or Contractor may have under this Contract or any applicable law. All rights and remedies of City or Contractor, whether under this Contract or other applicable law, shall be cumulative.
12. MEDIATION.
Unless waived by the City, should any dispute arise out of this Contract, the parties shall meet in mediation and attempt to reach a resolution with the assistance of a mutually acceptable mediator. Unless the City waives this requirement, Contractor shall not be permitted to file legal action without first meeting in mediation and making a good faith attempt to reach a mediated resolution. The costs of the mediator, if any, shall be paid equally by the parties. If a mediated settlement is reached neither party shall be deemed the prevailing party for purposes of the settlement and each party shall bear its own legal costs.
13. GENERAL TERMS AND CONDITIONS.
This Contract includes, and the Contractor agrees to comply with the City’s General Terms and Conditions, which are set forth in Exhibit C, attached hereto and incorporated by reference.
[Signatures are on the following page.]
v. Feb 2025 Page 7
IN WITNESS WHEREOF, the parties have executed this Contract as of the day, month and year first above written.
CITY OF SAN RAFAEL:
_________________________________
________________________________,
_________________________________
Executed on:_______________________
APPROVED AS TO FORM:
Office of the City Attorney
_________________________________
________________________________,
_________________________________
ATTEST:
City Clerk
_________________________________
________________________________,
_________________________________
CONTRACTOR:
__________________________________
By: ____________________________
Name: ____________________________
Title: ____________________________
[If Contractor is a corporation, second
corporate officer signature required]
__________________________________
By: ____________________________
Name: ____________________________
Title: _____________________________
v. Feb 2025 Exhibit A
EXHIBIT A
SCOPE OF WORK
v. Feb 2025 Exhibit B-1
EXHIBIT B
INSURANCE REQUIREMENTS
During the term of this Contract, and for any time period set forth below, Contractor shall procure and maintain in full force and effect, at no cost to City insurance policies with respect to employees and vehicles assigned to the performance of work under this Contract with coverage amounts, required endorsements, certificates of insurance, and coverage verifications as defined in this Exhibit B.
A. Scope of Coverage. During the term of this Contract, Contractor shall maintain, at no expense to City, the following insurance:
1. Commercial general liability. A commercial general liability insurance policy in the minimum amount of one million dollars ($1,000,000) per occurrence/two million dollars ($2,000,000) aggregate, for death, bodily injury, personal injury, or property damage.
2. Automobile liability. An automobile liability (owned, non-owned, and hired vehicles) insurance policy in the minimum amount of one million dollars ($1,000,000) per occurrence.
3. Professional liability. If any licensed professional performs any of the work required to be performed under this Contract, a professional liability insurance policy in the minimum amount of one million dollars ($1,000,000) per occurrence/two million dollars ($2,000,000) aggregate, to cover any claims arising out of the Contractor's performance under this Contract. Where Contractor is a professional not required to have a professional license, City reserves the right to require Contractor to provide professional liability insurance pursuant to this section.
4. Workers’ compensation. If it employs any person, Contractor shall maintain workers’ compensation insurance, as required by the State of California, with statutory limits, and employer’s liability insurance with limits of no less than one million dollars ($1,000,000) per accident for bodily injury or disease. Contractor’s workers’ compensation insurance shall be specifically endorsed to waive any right of subrogation against City.
B. Other Insurance Requirements. The insurance coverage required of the Contractor in subparagraph A of this section above shall also meet the following requirements:
1. Except for professional liability insurance or workers’ compensation insurance, the insurance policies shall be specifically endorsed to include the City, its officers, agents, employees, and volunteers, as additional insureds (for both ongoing and completed operations) under the policies.
2. The additional insured coverage under Contractor’s insurance v. Feb 2025 Exhibit B-2
policies shall be “primary and noncontributory” with respect to any insurance or coverage maintained by City and shall not call upon City's insurance or self-insurance coverage for any contribution. The “primary and noncontributory” coverage in Contractor’s policies shall be at least as broad as ISO form CG20 01 04 13.
3. Except for professional liability insurance or workers’ compensation insurance, the insurance policies shall include, in their text or by endorsement, coverage for contractual liability and personal injury.
4. By execution of this Contract, Contractor hereby grants to City a waiver of any right to subrogation which any insurer of Contractor may acquire against City by virtue of the payment of any loss under such insurance. Contractor agrees to obtain any endorsement that may be necessary to effect this waiver of subrogation, but this provision applies regardless of whether or not City has received a waiver of subrogation endorsement from the insurer.
5. If the insurance is written on a Claims Made Form, then, following termination of this Contract, said insurance coverage shall survive for a period of not less than five years.
6. The insurance policies shall provide for a retroactive date of placement coinciding with the Effective Date of this Contract.
7. The limits of insurance required in this Contract may be satisfied by a combination of primary and umbrella or excess insurance. Any umbrella or excess insurance shall contain or be endorsed to contain a provision that such coverage shall also apply on a primary and noncontributory basis for the benefit of City (if agreed to in a written contract or agreement) before City’s own insurance or self-insurance shall be called upon to protect it as a named insured.
8. It shall be a requirement under this Contract that any available insurance proceeds broader than or in excess of the specified minimum insurance coverage requirements and/or limits shall be available to City or any other additional insured party.
Furthermore, the requirements for coverage and limits shall be: (1) the minimum coverage and limits specified in this Contract; or (2) the broader coverage and maximum limits of coverage of any insurance policy or proceeds available to the named insured; whichever is greater. No representation is made that the minimum insurance requirements of this Contract are sufficient to cover the obligations of the Contractor under this Contract.
9. Contractor agrees to ensure that subcontractors, and any other party involved with the performance of work under this Contract, who is brought onto or involved in the performance of the work by Contractor under this Contract, provide the same minimum insurance coverage required of Contractor, except as with respect to limits. Contractor agrees to monitor and review all such coverage and assumes all responsibility for ensuring that such coverage is provided in conformity with the requirements of this Contract. CONSUTLANT agrees that upon request by City, all v. Feb 2025 Exhibit B-3
agreements with, and insurance compliance documents provided by, such subcontractors and others engaged in the work under this Contract will be submitted to City for review.
10. Contractor agrees to be responsible for ensuring that no contract used by any party involved in any way with the Scope of Work reserves the right to charge City or Contractor for the cost of additional insurance coverage required by this Contract.
Any such provisions are to be deleted with reference to City. It is not the intent of City to reimburse any third party for the cost of complying with these requirements. There shall be no recourse against City for payment of premiums or other amounts with respect thereto.
C. Deductibles and SIR’s. Any deductibles or self-insured retentions in Contractor's insurance policies must be declared to and approved by the City and shall not reduce the limits of liability. Policies containing any self-insured retention (SIR) provision shall provide or be endorsed to provide that the SIR may be satisfied by either the named insured or City or other additional insured party. At City's option, the deductibles or selfinsured retentions with respect to City shall be reduced or eliminated to City's satisfaction, or Contractor shall procure a bond guaranteeing payment of losses and related investigations, claims administration, attorney’s fees and defense expenses.
D. Proof of Insurance. Contractor shall provide to the Project Manager all of the following: (1) Certificates of Insurance evidencing the insurance coverage required in this Contract; (2) a copy of the policy declaration page and/or endorsement page listing all policy endorsements for the commercial general liability policy, and (3) excerpts of policy language or specific endorsements evidencing the other insurance requirements set forth in this Contract. City reserves the right to obtain a full certified copy of any insurance policy and endorsements from Contractor. Failure to exercise this right shall not constitute a waiver of the right to exercise it later. The insurance shall be approved as to form and sufficiency by the City.
Failure to comply with these requirements shall be considered a material breach of contract.
v. Feb 2025 Exhibit C-1
EXHIBIT C
GENERAL TERMS AND CONDITIONS
1. COMPLIANCE WITH ALL LAWS.
Contractor shall observe and comply with all applicable federal, state and local laws, ordinances, codes and regulations, in the performance of its duties and obligations under this Contract. Contractor shall perform all work under this Contract in accordance with these laws, ordinances, codes and regulations. Contractor shall release, defend, indemnify and hold harmless City, its officers, agents and employees from any and all damages, liabilities, penalties, fines and all other consequences from any noncompliance or violation of any laws, ordinances, codes or regulations.
2. PROVISIONS DEEMED INSERTED.
Every provision of law required to be inserted in the Contract is deemed to be inserted, and the Contract will be construed and enforced as though such provision has been included. If it is discovered that through mistake or otherwise that any required provision was not inserted, or not correctly inserted, the Contract will be deemed amended accordingly.
3. SEVERABILITY.
If any provision of the Contract documents, or portion of a provision, is determined to be illegal, invalid, or unenforceable, the remaining provisions of the Contract documents will remain in full force and effect.
4. OWNERSHIP OF DOCUMENTS.
The written documents and materials prepared by the Contractor in connection with the performance of its duties under this Contract, shall be the sole property of City. City may use said property for any purpose, including projects not contemplated by this Contract.
5. INSPECTION AND AUDIT.
Upon reasonable notice, Contractor shall make available to City, or its agent, for inspection and audit, all documents and materials maintained by Contractor in connection with its performance of its duties under this Contract. Contractor shall fully cooperate with City or its agent in any such audit or inspection. Contractor shall maintain all Projectrelated records for a period of three (3) years from completion of the work.
6. ASSIGNABILITY.
The parties agree that they shall not assign or transfer any interest in this Contract nor the performance of any of their respective obligations hereunder, without the prior written consent of the other party, and any attempt to so assign this Contract or any rights, duties v. Feb 2025 Exhibit C-2
or obligations arising hereunder shall be void and of no effect.
7. WORKERS' COMPENSATION.
Contractor certifies that it is aware of the provisions of the Labor Code of the State of California which require every employer to be insured against liability for workers' compensation or to undertake self-insurance in accordance with the provisions of that Code, and Contractor certifies that it will comply with such provisions before commencing the performance of the work of this contract.
8. NONDISCRIMINATION.
Contractor shall not discriminate, in any way, against any person on the basis of sex, race, color, religion, ancestry, national origin, ethnic group identification, age, mental disability, physical disability, medical condition, genetic information, marital status, or sexual orientation in connection with or related to the performance of its duties and obligations under this Contract.
9. NO THIRD PARTY BENEFICIARIES.
City and Contractor do not intend, by any provision of this Contract, to create in any third party, any benefit or right owed by one party, under the terms and conditions of this Contract, to the other party.
10. INDEPENDENT CONTRACTOR.
For the purposes, and for the duration, of this Contract, Contractor, its officers, agents and employees shall act in the capacity of an Independent Contractor, and not as employees of the City. Contractor and City expressly intend and agree that the status of Contractor, its officers, agents and employees be that of an Independent Contractor and not that of an employee of City.
11. ENTIRE CONTRACT -- AMENDMENTS.
A. The terms and conditions of this Contract, all exhibits attached, and all documents expressly incorporated by reference, represent the entire Contract of the parties with respect to the subject matter of this Contract.
B. This written Contract shall supersede any and all prior contracts, oral or written, regarding the subject matter between the Contractor and the City.
C. No other agreement, promise or statement, written or oral, relating to the subject matter of this Contract, shall be valid or binding, except by way of a written amendment to this Contract.
D. The terms and conditions of this Contract shall not be altered or modified v. Feb 2025 Exhibit C-3
except by a written amendment to this Contract signed by the Contractor and the City.
E. If any conflicts arise between the terms and conditions of this Contract, and the terms and conditions of the attached exhibits or the documents expressly incorporated by reference, the terms and conditions of this Contract shall control.
12. SET-OFF AGAINST DEBTS.
Contractor agrees that City may deduct from any payment due to Contractor under this Contract, any monies which Contractor owes City under any ordinance, agreement, contract or resolution for any unpaid taxes, fees, licenses, assessments, unpaid checks or other amounts.
13. WAIVERS.
The waiver by either party of any breach or violation of any term, covenant or condition of this Contract, or of any ordinance, law or regulation, shall not be deemed to be a waiver of any other term, covenant, condition, ordinance, law or regulation, or of any subsequent breach or violation of the same or other term, covenant, condition, ordinance, law or regulation. The subsequent acceptance by either party of any fee, performance, or other consideration which may become due or owing under this Contract, shall not be deemed to be a waiver of any preceding breach or violation by the other party of any term, condition, covenant of this Contract or any applicable law, ordinance or regulation.
14. CITY BUSINESS LICENSE / OTHER TAXES.
Contractor shall obtain and maintain during the duration of this Contract, a City business license as required by the San Rafael Municipal Code, and Contractor shall pay any and all state and federal taxes and any other applicable taxes. City shall not be required to pay for any work performed under this Contract, until Contractor has provided City with a completed Internal Revenue Service Form W-9 (Request for Taxpayer Identification Number and Certification).
15. SURVIVAL OF TERMS.
Any terms of this Contract that by their nature extend beyond the term (or termination) of this Contract shall remain in effect until fulfilled and shall apply to both Parties’ respective successors and assigns.
16. GOVERNING LAW.
This Contract shall be deemed to have been executed in the County of Marin, California. The formation, interpretation and performance of this Contract shall be governed by the laws of the State of California, excluding its conflict of laws rules. Any suit or action initiated by either party shall be brought in the County of Marin, California unless the parties agree otherwise in a written amendment to this Contract. v. Feb 2025 Exhibit C-4
17. CONFLICT OF INTEREST.
Contractor, its employees, subcontractors and agents, may not have, maintain or acquire a conflict of interest in relation to this Contract in violation of any City ordinance or policy or in violation of any California law, including under Government Code section 1090 et seq. and under the Political Reform Act as set forth in Government Code section 81000 et seq. and its accompanying regulations. Any violation of this Section constitutes a material breach of the Contract.
18. AUTHORIZATION.
Each individual signing above warrants that they are authorized to do so by the party that they represent, and that this Contract is legally binding on that party. If Contractor is a corporation, signatures from two officers of the corporation are required pursuant to California Corporation Code section 313.
19. COUNTERPARTS AND ELECTRONIC SIGNATURE.
This Contract may be executed by electronic signature and in any number of counterparts, each of which shall be deemed an original, but all of which together shall constitute one document. Counterpart signature pages may be delivered by telecopier, email or other means of electronic transmission.
CITY OF SAN RAFAEL
Albert Park Library & Community Center
Capital Project Management Services
JULY 9, 2025
BURLINGAME COMMUNITY CENTER & WASHINGTON PARK
FOSTER CITY COMMUNITY CENTER
HALF MOON BAY LIBRARY
YORBA LINDA LIBRARY & CULTURAL ARTS CENTER
SALINAS EL GABILAN BRANCH LIBRARY C U P E R T I N O L I B R A R Y
EXPANSION
S A N T A C L A R I T A C A N Y O N
COUNTRY COMMUNITY CENTER
S A N T A C R U Z D O W N T O W N L I B R A R Y ,
HOUSING & MIXED-USE PROJECT
TABLE OF CONTENTS
1. Introductory Letter 1
2. Background on Firm & Statement of Qualifications 4
3. Project Understanding & Approach 20
4. Scope Of Work 22
5. Project Schedule 27
6. Firm References 29
7. Rate Schedule 33
8. Statements & Supplementary Information 37
CONFIDENTIAL. DO NOT RELEASE WITHOUT GRIFFIN STRUCTURES’ CONSENT & REDACTIONS California Civil Code § 3426.1 (d); California Evidence Code section 1040 and 1060; California Government Code section 6254(k); Freedom of Information Act, 5 U.S.C. § 552(b)(4) Why Griffin Structures?
Significant
experience with:
Libraries
Community Centers
Concept to Keys
Delivery
Public Outreach &
Communications
Large-Scale, HighProfile Projects
Sustainable Building
Practices, LEED
Certification & Net Zero
Energy
Unparalleled experience with both library
and community center facilities. Highlighted
Projects:
Half Moon Bay Library
Burlingame Community
Center
Salinas El Gabilan Branch
Library
Yorba Linda Library &
Cultural Arts Center
Cupertino Library
Expansion
Santa Clarita Canyon
Country Community
Center
Vast experience with sustainably
designed projects, including LEED
Platinum and Zero Net Energy.
Dedicated pre-development division
dedicated to supporting the City's early
planning efforts for this project.
BURLINGAME COMMUNITY CENTER
& WASHINGTON PARK
1. INTRODUCTORY LETTER
1. I ntro d uctor y L etter GRIFFIN STRUCTURES 1
1850 WARBURTON AVE, SUITE 120 | SANTA CLARA, CA | 408.955.0431 July 9, 2025
City of El San Rafael
1400 Fifth Avenue, Room 203, San Rafael, CA 94901
Attention: John Stefanski, Assistant City Manager
RE: Albert Park Library & Community Center, Capital Project Management Services Dear Mr. Stefanski & Evaluation Team,
We are pleased to submit our proposal to the City of San Rafael for this project. As you will discover, Griffin Structures is highly qualified to deliver this project given our vast portfolio inclusive of nationally recognized libraries, community centers, sustainably designed projects, and our founding as a public sector developer delivering projects from CONCEPT TO KE Y S .
For this project, we have assembled a seasoned team with the exact experience required to bring your project to successful completion. This includes key leadership comprised of the same individuals who led the delivery of the high-profile Half Moon Bay Library, Burlingame Community Center, Cupertino Library Expansion, Tustin Main Library, community centers for the cities of Lawndale, Fullerton and many additional noteworthy projects.
For this project, we have additionally engaged reputable firms with the exact expertise required to fulfill the City's public outreach and engagement goals for this project, as well as ensure the complete commissioning of its new facility. For this effort, we have teamed with long time partners Circlepoint and WSP in order to ensure the complete execution of these services.
Griffin Structures also maintains a strong presence within the bay area. This includes the MidPen Shirley Chisholm Educator Housing project in San Francisco, Tiburon Corporate Yard, San Leandro Shoreline Development, Alameda City Aquatic Center, multiple projects within the City of Oakland and more.
Griffin Structures takes great pride in providing both competitive pricing, and highly qualified personnel, going to great measures to ask ourselves, “What is our true value-added proposition to the City?” The answer is our people. Our people offer creative delivery options, solutions-based recommendations, and a true perspective of ownership that our competitors do not possess. This is our differentiator and the meaning behind our pledge to provide Excellence in Project Delivery.
We have reviewed the City's Professional Services Agreement and are prepared to sign the agreement asis. However, we have provided the comments on page 37 and humbly ask for the City's consideration and welcome the opportunity to review and discuss the comments with the City and its legal counsel. [ We hereby acknowledge receipt of all addenda ]
We look forward to the opportunity of serving you,
Jon Hughes, CCM, DBIA | President
P: 408.955.0431 x208
E: [email protected]
COVER LETTER: PART ONE
1. I ntro d uctor y L etter GRIFFIN STRUCTURES 2
How will the City be assured the project Architect
understands the scope of work, and will design a
facility that is both efficient and adequate to meet
the City’s needs?
We recognize the City has gone through multiple efforts to establish needs for this project, most recently in the reports developed by Group 4 in 2017 and Noll and Tam
in 2019. In reviewing these reports, it is clear the City went to great lengths evaluating the size and location
of the facility, and that the final decision was to move forward with a combined Library and Community
Center at Albert Park as detailed in the Noll and Tam
report.
Nevertheless, all of these reports describe a facility of “roughly 45,000 SF" but do not have a formal program
associated with this square footage or any formal
analysis to arrive at this number. Our team is prepared to dig into these numbers, meet with staff and
stakeholders, and develop a detailed project specific
program that breaks down exactly how the square
footage is developed, and what programming elements
are critical to the success of City operations. This will then serve as the primary baseline for developing
a design RFP as well as a total project budget and
schedule. We believe this level of detail and diversity of services exceed that of any other project management
firm. Accordingly, our team will ensure the City receives a well-designed, well-built facility that is the right fit programmatically and also within budget.
How will the City be assured the project will
not be negatively impacted via delays and cost
overruns due to marketplace supply chain issues?
There are several ways to mitigate challenges related
to supply chain issues. Key to determining the most
ideal will lie in an in-depth project delivery analysis.
We applaud the City for including project delivery
as a key deliverable to the City. At Griffin, we have
experience in all forms of delivery, including at-risk
alternative delivery options. Some of these options are better suited to mitigate against supply chain issues
or material cost overruns, while others are not. The
key discussion will rest on how willing the City will be to pursue alternative forms of delivery, or if a more
conservative approach is preferred. Such alternative
delivery options include Design-Build, Progressive
Design-Build, and CM At-Risk. These innovative
approaches allow for the City and the project team
to identify key systems and materials that may pose
a challenge and to pre-purchase the same when it is
financially advantageous. Should the City not wish to
move forward with alternative forms of delivery, there
are still opportunities to mitigate potential delays and impacts, though more limited in nature. Regardless,
our firm is the leading expert in Excellence in Project Delivery, and will be able to provide clear guidance
to the City to allow for a well informed and prudent
decision.
COVER LETTER: PART TWO
Strategic Considerations
Griffin Structures goes to great lengths to research and understand the challenges and opportunities for every pursuit.
As a result of this effort, we have prepared the following strategic considerations to demonstrate our approach and illustrate the value we offer. These considerations are prepared in a question-and-answer format for ease of reading.
1. I ntro d uctor y L etter GRIFFIN STRUCTURES 3
How will the City engage the community on this
project to ensure it garners and maintains public
support?
We believe a project is only as successful as it is
perceived successful by the public. Key to engendering
public support is quality communication and
consistency. It will be challenging to harness the myriad of stakeholder input into a single project approach, but we are confident that by utilizing our tried and tested approach, we can successfully deliver to the City what
its constituents require.
To achieve this, we will conduct a heavy outreach
campaign to generate interest and participation in
a myriad of outreach events. This communications
strategy will include developing a website, project
brand, regular social media updates, focused
engagement at community events, and active
participation with the community. Equally important
will be the incorporation of these comments into
the design documents to ensure that people are not
only heard, but that their comments are actually
incorporated into the design. Working closely with
our long-time and highly effective outreach partner,
Circlepoint, we are confident our approach will result
in the same level of success we have seen on multiple
surrounding projects.
In what ways will the Project Manager utilize
technology to provide enhanced services and
transparency to the project?
We believe the use of technology is essential to a
successful project. For this reason we employ a cloud
based document management system to organize
and manage the flow of all project documentation.
This system will accommodate all RFIs, submittals,
substitutions, daily reports, bulletins, permits, change orders, and SWPPP reports. This will in turn allow the
City to have access to all documents for the project at any time.
In addition to this, we will incorporate the use of
Building Information Modeling (BIM) as part of the
specifications to be managed by the HVAC trade
contractor. This will ensure that the overhead spaces
are adequately rendered allowing for maximum
efficiency of the overhead space.
Additionally, we utilize OpenSpace site photography
which allows for daily 360 photography of the whole
site, and will overlay these photographs onto the BIM
model. This too will ensure that systems being installed are properly coordinated and will mitigate potential
delays.
HALF MOON BAY LIBRARY
2. BACKGROUND ON FIRM & STATEMENT OF QUALIFICATIONS
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 4 Founded in 1981, Griffin Structures is a diversified
Owner's Representative / Program, Project and
Construction Management firm serving public, private,
non-profit, and institutional sectors.
A unique aspect of our firm rests not only
in our local and unparalleled library and
community center portfolio, but also in
our vast experience managing successful
delivery from Concept to Keys.
Griffin Structures maintains four decades of stability
in providing public sector, industry leading service to our clients. We offer a wealth of supportive resources
pertaining to specialists well-versed in the delivery of public amenities with direct experience local to the
City.
Firm Background
Size of Organization
Griffin Structures maintains a qualified roster of over 50 employees. This team includes seasoned Program and
Construction Managers whom are certified Construction
Managers on behalf of the Construction Management
Association of America, former Public Works Inspectors, Design-Build Institute of America (DBIA) Associates,
and individuals professionally trained in both design
and construction.
Location of Offices
1850 Warburton Avenue, Suite 120
Santa Clara, CA 95050
1 Technology Drive, Building i, Suite 829
Irvine, CA 92618
Years in Business
Griffin Structures has been serving the public, private and non-profit sector for 43 years.
Owners & Principal Parties
Roger Torriero, Chief Executive Officer
Jon Hughes, President
Mark Hoglund, Chief Financial/Operating Officer
Kelly Boyle, Executive Vice President
Korin Crawford, Executive Vice President
Dustin Alamo, Vice President
Robert Godfrey, Vice President
Deryl Robinson, Vice President
B U R L I N G A M E C O M M U N I T Y
CENTER & WASHINGTON PARK
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 5 Additional Skills & Experience
In direct response to the bullets contained within section 2, page 8 of the RFP, we have included the additional highlighted skills and relevant experience below for the City's review and consideration.
PUBLIC OUTREACH & COMMUNICATIONS
We understand the City wishes to further communicate and engage with the public for this project. For this reason, we have partnered with notable outreach firm, Circlepoint, to leverage participation in City-sponsored events, as well as make ample use of your social media presence, deploy an interactive web platform, e-newsletter, and more.
LARGE SCALE PUBLIC FACILITY & CIVIC BUILDINGS
At Griffin, we understand and can properly manage high-profile projects, having served in a similar capacity for the >$1B San Leandro Shoreline Development, $1.4B Great Park Framework Plan and the recently completed $400M+ County of Orange Civic Center delivered ahead of schedule and with returned savings to the County.
LIBRARY & COMMUNITY CENTER DESIGN & CONSTRUCTION
Unlike our competitors, Griffin Structures has led the delivery of virtually every project type. This includes leading library facilities and high-volume community centers for cities such as Half Moon Bay, Burlingame, Cupertino, Campbell, Foster City, Walnut Creek and over 70 additional, similar community facilities.
BUILDING SYSTEMS
At Griffin Structures we are trained as builders, but think like Owners. This extends to the experience of our team whom possess in-depth trade backgrounds including MEP, fire protection and more. We have team members who are licensed A and B Contractors, Professional Engineers, and hold additional noteworthy licensure.
SUSTAINABLE BUILDING PRACTICES & LEED CERTIFICATION
Within our extensive portfolio, we have completed several sustainably recognized projects, including LEED Platinum, Net Zero, AIA Top 10 COTE, and additional designations. This includes LEED Platinum and Net Zero Energy Half Moon Bay Library, Net Zero Energy Burlingame Community Center, and several others.
MUNICIPAL CLIENTS
Together, our team has delivered over 700 projects for public Clients from inception to completion. A specialty Program and Construction Management firm, we understand the complexities associated with public work and can forecast and mitigate potential causes for concern in real-time, providing trusted advisement from day one.
STRENGTH & STABILITY OF FIRM
Our firm has been successfully and continuously operating for 44 years, building an impeccable track record and reputation for quality and reliability. While we maintain a solid financial foundation, if necessary, we can provide a confirmation letter from our CPA, verifying our past and present financial standing, as part of the contract negotiation phase.
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 6 Organization
In order to offer the highest value to the City of San Rafael, we have included a highly experienced, comprehensive team of individuals and firms to provide specialty services for this project. All of our proposed team members are able to perform the services listed in the RFP.
With certifications from the Design-Build Institute of America (DBIA), Construction Management Association of America (CCM), and the U.S. Green Building Council (LEED AP), Griffin Structures employees are trained as Owner’s Representatives, are experienced and highly trained to provide exceptional services to our clients.
Hernan Munayco
Sr. Program &
Construction Manager
Jon Hughes
CCM, DBIA
President
Gary Chubb
LEED GA, DBIA
Project Executive
Robert Godfrey
CCM
Principal-In-Charge
PROJECT SUPPORT
HLCM
Cost Estimating
Circlepoint
Public Outreach
Dustin Alamo
CCM, LEED AP, DRE
#01930629
Pre-Development Mgr.
David Fields
CCM
Constructability Review
Specialist
Michael Baker
ICC
Quality Assurance
Inspector
WSP
Commissioning
Tempus
Scheduling
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 7 Jon Hughes
CCM, DBIA
President
EDUCATION
Bachelor of Science, Westmont College
CERTIFICATION
Certified Construction Manager (CCM)
Design Build of America Institute (DBIA)
Associate
AFFILIATIONS
NAVFAC and US Army Corps Construction
Quality Management (CQM) Program
YEARS OF EXPERIENCE
31 QUALIFICATIONS
President, Jon Hughes, offers a wealth of expertise in Program and Construction Management, contributing to the successful completion of many of California’s most prestigious properties. His tenure spans virtually every project type, including libraries, affordable housing projects, administrative headquarters, corporate yards/warehouses, community centers, recreational facilities, public safety and healthcare, as well as maintenance and infrastructure projects. Jon’s extensive background, coupled with his demonstrated early career experience in the field, further enhances his ability to guide our team in order to provide Excellence in Project Delivery to each client we serve.
REPRESENTATIVE EXPERIENCE
Half Moon Bay Library, CA
Burlingame Community Center & Washington Park, CA
Salinas El Gabilan Branch Library, CA
Salinas Hebbron Family Center, CA
Yorba Linda Library & Cultural Arts Center, CA
Cupertino Library Expansion, CA
Campbell Library Renovation, CA
Santa Ana Main Library Renovation + 3 Additional Libraries, CA Santa Cruz Downtown Library, Housing, Mixed-Use Project, CA Northeast Stockton Library & Community Center, CA
San Leandro Shoreline Park Master Plan, Monarch Bay Shoreline Development Project, CA
Eastvale Civic Center & Library, CA
Irvine Great Park Facilities Framework Plan & Library, CA Lillian Court & Bloomington Grove Library, CA (Related CA Project) Quartz Hill Library, CA
San Jacinto Civic Center, CA
San Jose Parkmoor (HUB) Housing & Community Center, CA
San Jose Dry Creek Crossing, CA
Jordan Downs Housing Redevelopment, Los Angeles, CA
Triada at Station District, Santa Ana, CA (Related CA Project) Alameda City Aquatic Center, CA
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 8
QUALIFICATIONS
Robert Godfrey brings more than 20 years of combined experience in construction management and planning. As a construction manager, he has been involved during all phases of development and construction. His responsibilities as a project/construction manager have entailed pre-construction services, public and stakeholder outreach, managing entitlement and plan check processes, obtaining building permits and coordinating inspections, and generating punch lists and overseeing project closeout. Robert has a proven record of project management involving effective communication with design team members, coordinating consultants, vendors and contractors - all to assure the client’s goals and objectives are achieved.
REPRESENTATIVE EXPERIENCE
Half Moon Bay Library, CA
Burlingame Community Center & Washington Park, CA
Salinas Hebbron Family Center, CA
Salinas El Gabilan Branch Library, CA
Yorba Linda Library & Cultural Arts Center, CA
Cupertino Library Expansion, CA
Campbell Library Renovation, CA
Santa Ana Main Library Renovation, CA
Santa Ana Newhope Library Renovation, CA
Santa Ana Delhi Center Library Branch, CA
Santa Ana Outdoor Library at Jerome Park, CA
Inglewood Main Library Renovation, CA
Escondido Public Library Critical Infrastructure & Modernization Project, CA
Irvine Great Park Facilities Framework Plan & Library, CA Foster City Recreation Center Replacement CA
San Jacinto Civic Center, CA
Midpen Shirley Chilsom Educator Housing, San Francisco, CA Linc Housing, Hifi Collective & SIPA HQ. Los Angeles, CA Linc Housing, Willow Way, El Monte, CA
San Jose Parkmoor (HUB) Housing & Community Center, CA
San Jose Dry Creek Crossing, CA
Jordan Downs Housing Redevelopment, Los Angeles, CA
Walnut Creek Aquatic & Community Center, CA
Alameda City Aquatic Center, CA
Robert Godfrey
CCM
Principal-In-Charge
EDUCATION
Bachelor of Science, Management, The
Georgia Institute of Technology, Atlanta
CERTIFICATIONS
Certified Construction Manager (CCM)
AFFILIATIONS
Construction Management Association of
America, Member
YEARS OF EXPERIENCE
23 2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 9
QUALIFICATIONS
In his capacity as Project Executive, Gary Chubb has overall responsibility and accountability for all aspects determining project success. He brings his considerable and varied professional experience to each client in providing continued excellence in client service. High-level industry executive with established 33-year career, Gary offers real estate solutions in both private and public sectors with focus on Public-Private Partnerships, Mass Timber, Progressive Design-Build, and Integrated Project Delivery. Proven exceptional skills in real estate development, strategic project management, education/teaching and extensive public speaking and outreach, general contractor operations, business planning, sales, alternative project delivery methods, pre-construction, entitlements, and project team outcomes.
REPRESENTATIVE EXPERIENCE
Tustin Library, CA
Environmental Nature Center, Newport Beach, CA
Discovery Cube Science Center, Santa Ana, CA
San Jose Parkmoor (HUB) Housing & Community Center, CA
San Jose Dry Creek Crossing, CA
Walnut Creek Aquatic & Community Center, CA
Rancho Santa Margarita Community Center, CA
Foster City Recreation Center, CA
Cypress Community Center Renovation / Expansion, CA
Fullerton Multi-Generational Community Center, CA
Alameda City Aquatic Center, CA
Laguna Beach Susi-Q Senior / Community Center, CA
Lawndale Community Center, CA
Elleven Condominiums, Los Angeles, CA
524 Belltown Mixed-Use Mass Timber, Seattle, WA
West Seattle Apartments, Seattle, WA
Redmond Apartments, Seattle, WA
Bellevue Apartments, Seattle, WA
Maui Apartments, Seattle, WA
University Place, Seattle, WA
USAA Multi-Family & Senior Living (5+ Projects), Seattle, WA Sustainable Living Innovations (SLI) Apartments, Seattle, WA Gary W. Chubb
LEED GA, DBIA
Project Executive
EDUCATION
Master of Science, Real Estate,
University of Denver
Bachelor of Science, Construction
Management, University of Washington
CERTIFICATIONS
Design-Build Institute of America (DBIA)
Associate
Commercial Real Estate Certificate, University
of Washington
Leadership in Environmental and Energy
Design, Green Associate (LEED GA)
AFFILIATIONS
Construction Industry Advisory Council, Vice
Chairperson, University of Washington
Design-Build Institute of America (DBIA)
U.S. Green Building Council (USGBC)
YEARS OF EXPERIENCE
34 2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 1 0 Hernan Munayco
Sr. Program & Construction
Manager
EDUCATION
Bachelor of Architecture, Southern California
Institute of Architecture (SCI-Arc)
CERTIFICATIONS / LICENSES
General Contractor License B
YEARS OF EXPERIENCE
24 QUALIFICATIONS
Hernan Munayco’s work includes in Building Types I,II,III & V with budgets exceeding $100M in both private and public, high-profile projects, including non-profit, commercial, mixed-use, ground-up buildings, civil work and adaptive re-use / tenant improvement, highlighted by international work experience. With over 20 years’ experience, he has been involved in the overall process through a variety of projects types and sizes, enabling him to provide cost/ schedule/project oversight, formally trained in architecture and as a licensed General Contractor.
REPRESENTATIVE EXPERIENCE
Cupertino Library Expansion, CA
Northeast Stockton Library & Community Center, CA
Santa Cruz Downtown Library, Housing & Mixed-Use Project, CA San Leandro Shoreline Park Master Plan, Monarch Bay Shoreline Development Project, CA
Salinas Hebbron Family Center & Recreational Facilities, CA Salinas El Gabilan Branch Library, CA
Santa Cruz County Crisis Childhood Center, CA
Stockton City Hall Renovations & Relocation, CA
Gregory Building Community Center, Hollywood, CA
Shonda Rhimes Performing Arts Center, Debbie Allen Dance Academy, Los Angeles, CA
Sunset & Gordon Mixed Use Highrise, Los Angeles, CA
LUMA Condominium Highrise, Los Angeles, CA
DTLA One Midnight Mission Homelessness Supportive Housing, Los Angeles, CA
CSI Housing Remodel, Hollywood, CA
24th Street Residences, Santa Monica, CA
Green Dot Oscar De La Hoya Charter High School,
Los Angeles, CA
Green Dot Animo Leadership Charter High School, Inglewood, CA Hawthorne High School Upgrades, CA
EC Hispanic Media Headquarters, Norwalk, CA
MHT Alloy Wheel Refinishing Plant, Rancho Dominguez, CA AO Hotel, Mexico City
Celebrity Center Hotel Improvement & Remodel, Hollywood, CA Studio B Golden Era Dance Centre, Hemet, CA
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 1 1 Dustin Alamo
CCM, LEED AP, DRE BROKER #01930629
Pre-Development Manager
EDUCATION
Bachelor of Architecture, University of
Colorado, Boulder
CERTIFICATION
State of California Licensed Real Estate
Broker
Certified Construction Manager (CCM)
LEED Accredited Professional
AFFILIATIONS
U.S. Green Building Council, Member
Construction Management Association of
America, Member
State of California Licensed Real Estate
Broker DRE #01930629
YEARS OF EXPERIENCE
20 QUALIFICATIONS
Dustin serves as the Vice President of Strategic Services for Griffin Structures, Inc. His primary responsibilities include the executive management of all needs assessment and master planning projects ranging by facility type, including library and cultural arts buildings, community and senior centers, public safety facilities, and many others. In addition, Dustin is skilled at developing long-term facility plans (ranging from $10M to $400M) which incorporate future space requirements, phasing considerations, and capital funding mechanisms. With a formal background in architecture, Dustin is knowledgeable in aspects of design. He understands the process and skill-set required for developing and building architectural programs, site plans, floor plans, elevations, and technical detailing.
REPRESENTATIVE EXPERIENCE
Inglewood Main Library Renovation, CA
Buena Park Library District Renovation, CA
Escondido Public Library Critical Infrastructure & Modernization Project, CA
Yorba Linda Library & Cultural Arts Center, CA
San Jacinto Civic Center & Library, CA
Half Moon Bay Library, CA
Burlingame Community Center & Washington Park, CA
Salinas El Gabilan Branch Library, CA
Bloomington Branch Library, CA
Cupertino Library Expansion, CA
Santa Cruz Downtown Library, Housing, Mixed-Use Project, CA San Leandro Shoreline Development & Library Project, CA Eastvale Civic Center & Library, CA
Irvine Great Park Facilities Framework Plan & Library, CA Hermosa Beach Library Pre-Development
Tustin Main Library, CA
Hermosa Beach Library Pre-Development, CA
El Centro Library Pre-Development, CA
Colton Civic Center City Hall & Library Pre-Development, CA San Jacinto Civic Center, CA
Anaheim Civic Center & Library Pre-Development, CA
Yucaipa Library Pre-Development, CA
Watsonville Civic Plaza, Library, Santa Cruz Superior Court, CA
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 12 David Fields
Constructability Review Specialist
EDUCATION
Bachelor of Science, Construction Engineering
& Management, Purdue University
Infantry Squad Leader, Combat Action
Veteran, US Marine Corps, Kaneohe Bay, HI
CERTIFICATION
California Contractor License, Class B
AFFILIATIONS
American Society of Civil Engineers, Associate
Member
YEARS OF EXPERIENCE
14 QUALIFICATIONS
David Fields brings a proven track record of providing strategic direction in all phases of building construction projects, including over 10 years of project management experience for nationally leading general contractors. David excels in overall project leadership, quality assurance, program management, financial management / forecasting, and scheduling. He has worked on and managed projects throughout California ranging from 1.5 billion to 1.5 million public and privately funded dollars.
David’s wealth of expertise includes, but is not limited to, risk management, financial management, constructability reviews, estimating, design management, construction monitoring, project controls, technology, sustainability, pre-construction, international procurement, scheduling and additional skillsets.
REPRESENTATIVE EXPERIENCE
Santa Ana Main Library Renovation, CA
Santa Ana Newhope Library Renovation, CA
Santa Ana Delhi Center Library Branch, CA
Santa Ana Outdoor Library at Jerome Park, CA
Escondido Public Library Critical Infrastructure & Modernization Project, CA
Eastvale Civic Center (City Hall, Library, Senior & Community Center, Police Station, Fire Station), CA
Pico Rivera Smith Park Aquatic Center Renovation, CA
Salesforce Transit Center, San Francisco, CA
Gate Improvements, Sony Pictures Entertainment, Los Angeles, CA Mosso Apartments, San Francisco, CA
AC + Moxy Hotel, Los Angeles, CA
Visalia Civic Center Ph2 Project (Public Safety Office Building, Evidence/Storage Building & Council Chambers), CA
High-End Office, Confidential Client, Irvine, CA
Bay Meadows Station 2, San Mateo, CA
Bay Meadows Station 4, San Mateo, CA
Fieldwork Brewing Beer Garden, San Mateo, CA
So-Fi Stadium Retail Complex, Los Angeles, CA
Data Center, Confidential Client, Irvine, CA
Trainee Barracks Phase 2 Complex 6, US Army Corps of Engineers, Ft.
Leonard Wood, MO
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 13
QUALIFICATIONS
Michael Baker has nearly 30 years of comprehensive inspection oversight experience as Inspector-of-Record with an emphasis on public works projects, program development, managing inspection operations and daily field inspection. A proven problem solver and team builder, Michael Baker is able to organize and manage multiple projects concurrently while maintaining a solid base of conformance to project specifications and program requirements. Mike Baker additionally holds several local, state, and federal government clearances and will utilize his background serving as an Inspector-ofRecord to bring your project to successful completion.
REPRESENTATIVE EXPERIENCE
East Bay Regional Park District, Improve Peralta Oaks North Project (Public Safety & Administrative Headquarters), Oakland, CA Alameda County Law Library & Training Center, Oakland, CA Google Bay View Campus, Mountain View, CA
Alameda County San Leandro Fire Station No.12, CA
Alameda County Hayward Fire Station No.23, CA
Alameda County San Leandro Fire Station No.6, CA
San Francisco International Airport, Courtyard 3 Connector, CA Alameda County Recorders Building, Oakland, CA
Santa Clara County Superior Court House Renovation, Santa Clara, CA Alameda County Superior Courthouse, Oakland, CA
Alameda County Sheriff’s Department New Offices, Oakland, CA Alameda County DNA Laboratory, Oakland, CA
Alameda County Juvenile Detention Facility, San Leandro, CA Alameda County Santa Rita Jail, Dublin, CA
Alameda County Regional Training Center, Dublin, CA
Alameda County Coroners’ Office, Oakland, CA
Alameda County Hospital, Fairmount Hospital, CA
California State Univ East Bay, Extensive Improvements, Hayward, CA Dublin New Two-Story Public Library, CA
Dublin 100 New Residential / Multi-Family Units, CA
Michael Baker
ICC
Quality Assurance Inspector
CERTIFICATION
ICC Combination Dwelling Inspector -
Uniform Codes
ICC Building Inspector
ICC Residential Combination Inspector
ICC Accessibility Inspector/Plans Examiner
ICC Spray-Applied Fireproofing Special
Inspector
ICC Plumbing Inspector
ICC Mechanical Inspector
ICC Combination Inspector
ICC Disaster Response
Electrical Inspector
Combination Dwelling Inspector
Certified Green Building Professional
Safety Assessment Program Coordinator
– SAP50073
State of California Registered Disaster Service
Worker
OSHA 30
YEARS OF EXPERIENCE
30 2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 14 Susan Harden
FAICP, CNUA, LEED AP
Outreach Specialist
EDUCATION
Master of Environmental Planning, Arizona
State University
Bachelor of Arts, Architectural Studies,
University of Kansas
Bachelor of Arts, Environmental Studies,
University of Kansas
AFFILIATIONS
American Institute of Certified Planners
(AICP)
Certified Main Street Manager, National Main
Street Center
Professional Certificate in Neighborhood
Revitalization, NeighborWorks America
Congress for the New Urbanism, CNU-A
Fellow, American Institute of Certified
Planners (FAICP)
U.S. Green Building Council, Member
YEARS OF EXPERIENCE
30 QUALIFICATIONS
Susan has a broad background in community development,
engagement, and planning. For over 25 years, she has built her career around community-based planning and visioning, striving to create healthier, more livable communities. Susan is able to oversee community design workshops, stakeholder meetings and presentations, pop-up events, social media management, newsletters, e-blasts, fact sheets, website content, press releases, updates for officials, and quarterly updates.
REPRESENTATIVE EXPERIENCE
Cupertino Library Expansion, CA
Santa Cruz Downtown Library, Housing & Mixed-Use Project, CA Yorba Linda Library & Cultural Arts Center, CA
Laguna Beach Village Entrance, CA
Shoreline Park Master Plan - Monarch Bay Shoreline Development Project, San Leandro, CA
Eastvale Civic Center (City Hall, Library, Senior & Community Center, Police Station, Fire Station)
Buena Park Fire Station No.61, CA
Communications & Graphic Design, Long Beach Water, Long Beach, CA
Rancho Cucamonga General Plan Update, CA
Channel Islands Harbor Vision Plan, CA
Campo Road Corridor Revitalization Plan, CA
Wildomar Town Center Master Plan, CA
Vista Civic Center Master Plan, CA
Poway Town Center Master Plan, CA
North Downtown Area Neighborhood Vision Plan, Lancaster, CA Imperial Downtown Master Plan, CA
Riverside Innovation District Vision Plan, CA
Pueblo Viejo Revitalization Plan, Coachella, CA
Richmond Park Neighborhood Concept Plan, Fullerton, CA
Garvey Avenue Corridor Mixed-Use Study, El Monte, CA
* Completed with Griffin Structures
Ryan Craven
CPE, CMIT
Cost Estimator
EDUCATION
Bachelor of Science, Construction
Engineering, National University, Costa Mesa
CERTIFICATION
Certified Public Estimator (CPE)
Construction Manager in Training (CMIT)
AFFILIATIONS
American Society of Plumbing Engineers
(ASPE)
CoreNet Global (Young Leaders Group)
YEARS OF EXPERIENCE
17 QUALIFICATIONS
Ryan is an expert in value engineering and construction cost estimating, including master planning, conceptual, schematic design development, and construction document phases. He is a skilled mediator, participating in change order preparation, validation, and negotiation. He has reconciliation experience with general contractors and subcontractors, and communicates well with all design team members, promoting open-door dialogue and effective project solutions.
REPRESENTATIVE EXPERIENCE
Inglewood Main Library Renovation, CA
Buena Park Library District Renovation, CA
Escondido Public Library Critical Infrastructure & Modernization Project, CA
Yorba Linda Library & Cultural Arts Center, CA
San Jacinto Civic Center & Library, CA
Half Moon Bay Library, CA
Burlingame Community Center & Washington Park, CA
Salinas El Gabilan Branch Library, CA
Bloomington Branch Library, CA
Cupertino Library Expansion, CA
Santa Cruz Downtown Library, Housing, Mixed-Use Project, CA San Leandro Shoreline Development & Library Project, CA Eastvale Civic Center & Library, CA
Irvine Great Park Facilities Framework Plan & Library, CA Hermosa Beach Library Pre-Development
Tustin Main Library, CA
Hermosa Beach Library Pre-Development, CA
El Centro Library Pre-Development, CA
Colton Civic Center City Hall & Library Pre-Development, CA San Jacinto Civic Center, CA
Anaheim Civic Center & Library Pre-Development, CA
Yucaipa Library Pre-Development, CA
Watsonville Civic Plaza, Library, Santa Cruz Superior Court, CA Mario Khalil
PE, PSP
Scheduler
EDUCATION
Master of Construction Management,
Politecnico Di Milano
Bachelor of Science in Civil Engineering, ElMinya University
CERTIFICATION
Professional Civil Engineer C87651
Planning & Scheduling Professional (PSP)
YEARS OF EXPERIENCE
17 QUALIFICATIONS
With over 15 years of public sector scheduling expertise, Mario has provided numerous baselines, updates and Time Impact Analyses, analyzed various claims and disputed issues during and after construction. He has extensive experience in scheduling with variety of delay analysis techniques, including time impact analysis, windows analysis, as-planned vs. as-built, and collapsed as-built using different software tools, including Microsoft Project, Primavera P3 & P6, SureTrak, Claim Digger, Schedule Analyzer and Acumen Fuse. He also offers training for public sector clients to better understand all aspects of scheduling methods.
REPRESENTATIVE EXPERIENCE
Carlsbad Police & Fire Headquarters Renovation, CA
Stockton City Hall Renovation & Relocation, CA
Rancho Cienega Sports Complex & Aquatic Facilities, Los Angeles, CA Albion Riverside Park, Los Angeles, CA
Machado Lake Ecosystem, Wilmington, CA
I-5 North Capacity Enhancement Project, LACMTA, Santa Clarita, CA Algin Sutton Pool Replacement, Los Angeles, CA
Forest Lawn Memorial Park, Woodlands Phase II, LA, CA
City of Los Angeles, Robertson Recreation Center, CA
LAUSD, Venice High School, CA
LAUSD, Elizabeth Learning Center, CA
LAUSD, McKinley Elem. School, CA
LAUSD, Shenandoah Elem. School, CA
City of Los Angeles, Machado Lake Ecosystem, CA
City of Los Angeles, Argo Drain Sub-Basin Facility, CA
CalTrans District 11, I-5 NCC Segment 2 & 3, CA
CalTrans District 11, I-5 North Coast Corridor Segment 1, CA CalTrans District 7, Route 47 Schuyler Heim Replacement, CA CalTrans District 7, I-10 HOV in Baldwin Park, CA
CalTrans District 11, Route 76 Mission to I-5, CA
CalTrans District 11, Imperial I-8 Pavement Rehabilitation, Segment, 4, CA
CalTrans District 11, Imperial I-8 Pavement Rehabilitation, Segment 2, CA
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 17 Charles Hutchinson
CXA, CCP, LEED AP
Commissioning Agent
Vice President
EDUCATION
Bachelor of Science, Mechanical Engineering,
New Mexico State University
CERTIFICATIONS / LICENSES
LEED Accredited Professional
ACG Certified Commissioning Authority, 2011
#411-796
Certified Commissioning Professional, 2015
BCA Certified Commissioning Professional
AFFILIATIONS
Building Commissioning Association, AABC
Commissioning Group
YEARS OF EXPERIENCE
31 QUALIFICATIONS
After more than a decade with WSP, Charles brings over 30 years of design and commissioning experience and is a recognized industry leader in the engineering and construction fields. Charles has a broad range of project experience in Fundamental and Enhanced Commissioning including Civic, Commercial, Educational, Retail, and Healthcare Facilities. He currently leads our Commissioning Division.
In addition to commissioning, Charles’ background includes Mechanical, Plumbing, and Fire Protection Engineering in a wide range of projects including Commercial, Municipal, Educational, and Retail projects.
REPRESENTATIVE EXPERIENCE
County of Orange Civic Center, Santa Ana, CA *
Yorba Linda Library & Cultural Arts Center, CA *
Quartz Hill Library, CA *
Inglewood Main Library Renovation, CA *
Fullerton Main Library Expansion, CA *
Great Park Ice & FivePoint Arena, CA *
San Bernardino County High Desert Government Ctr, Hesperia, CA * San Bernardino County Public Safety Operations Ctr, Hesperia, CA * Hesperia Civic Center, CA *
Lawndale Community Center, CA *
Westminster Corporate Yard, CA *
Riverside County Law Library Building, Indio, CA
Orange County Juvenile Hall Multi-Purpose Rehabilitation Center Commissioning, Orange, CA
Vanguard Student Center, Costa Mesa, CA
Cypress College Science Engineering Math Building, Cypress, CA Cypress College Student Activities and Veterans’ Resource Center Commissioning, Cypress, CA
* Completed with Griffin Structures
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 18 Andy Smith
CCP, CPMP, LEED AP O+M
Commissioning Agent
Assistant Vice President
EDUCATION
Mechanical Engineering, Santiago Canyon
Community College
CERTIFICATIONS / LICENSES
Certified Commissioning Process
Management Professional, Certified
Commissioning Professional
LEED Accredited Professional Operations &
Maintenance (LEED AP O+M)
YEARS OF EXPERIENCE
17 QUALIFICATIONS
Andy is involved with each phase of commissioning from early design development, executing design reviews through the construction phase, making regular site observations, and performing functional testing. Andy is our in-house cloud-based commissioning expert and manages projects with an owners/end user’s perspective to function and operate long after building turnover. With a construction background as a mechanical, electrical, and plumbing superintendent, Andy’s firsthand experience working from the other side of the table enables him to better lead a project from the design and construction phases through commissioning and occupancy.
REPRESENTATIVE EXPERIENCE
County of Orange Civic Center, Santa Ana, CA *
Yorba Linda Library & Cultural Arts Center, CA *
Inglewood Main Library Renovation, CA *
City of Pasadena Central Library Seismic Retrofit & Renovations, Pasadena, CA
Yorba Linda Adventure Playground, CA *
Great Park Ice & FivePoint Arena, CA *
Westminster Corporate Yard, CA *
University of California Los Angeles, Neuropsychiatric Replacement Hospital Commissioning, Los Angeles, CA
Riverside University Health System, Moreno Valley Medical Office Building Commissioning, Moreno Valley, CA
Veterans Affairs Long Beach Health Care Mental Health Inpatient Building, Long Beach, CA
Riverside County Law Library Building, Indio, CA
Orange County Juvenile Hall Multi-Purpose Rehabilitation Center Commissioning, Orange, CA
Foothill Transit Parking Structure, Azusa, CA
University of California Riverside Student Success Center Commissioning, Riverside, CA
Legacy Magnet School, Tustin, CA
Cypress College Commissioning Services, Cypress, CA
Cypress College Student Activities & Veterans’ Resource Center Commissioning, Cypress, CA
* Completed with Griffin Structures
2. B ackgroun d on F irm & S tatement of Q ualifications GRIFFIN STRUCTURES 19 Subconsultant Team
Public Outreach
Should the City wish to engaged enhanced
Public Outreach services, Circlepoint is ready to
provide public outreach advocacy (marketing and
communication tools) for the City’s project(s).
Located throughout the state of California, Circlepoint can provide services including, but not limited to:
Community design
workshops
Stakeholder presentations
Pop-up events
Social media mgmt.
Newsletters
E-blasts
Fact sheets
Website content
Press releases
Stakeholder updates
Quarterly updates
*Women Owned Business Enterprise
Commissioning
For Commissioning, WSP is ready to perform services
required to satisfy commissioning requirements of
the Owner, CalGreen/Title-24 and LEED Fundamental
and Enhanced. The WSP Commissioning team is
solely dedicated to building commissioning and will
advocate for the City, providing assurances for proper
installation and operation of the building systems.
WSP's summarized approach includes:
Understanding building systems design intent
Verifying test & balance reports
Reviewing operations & maintenance (O&M)
Managing processes via the cloud
Scheduling
Mario Khalil with Tempus Construction Services will
serve as our Scheduling consultant for this project.
In this role, Mario will review the baseline schedule
to ensure its logic and sequencing meets industry
standards, review all monthly schedule updates,
analyze any Time Impact Analyses (TIAs), and
support the team as it relates to any negotiations
for additional General Conditions related to schedule
delays.
Tempus has served alongside Griffin Structures for a
number of projects, including many similar to your
project.
*Small Business Enterprise
Estimating
HL Construction Management (HLCM) has provided
cost estimating services for the planning and
development of library and community center facilities
similar to your project. HLCM’s diverse team has
dedicated cost consultants with a background in a
range of project types. HLCM provides cost guidance
on scope and budget development, feasibility
studies, and milestone estimating. HLCM’s LEED
certified estimators also understand energy and
water efficiency goals, bringing enhanced stormwater
management techniques and a wealth of additional
expertise.
*Small Business Enterprise
SANTA CLARITA CANYON
COUNTRY COMMUNITY CENTER
3. PROJECT UNDERSTANDING & APPROACH
3. P roject U n d erstan d ing & A pproach GRIFFIN STRUCTURES 2 0 Project Understanding
The Albert Park Library and Community Center project is one of the largest capital improvement undertakings in the City's history. In passing Measure P, the City has demonstrated it strong commitment to seeing this project through successfully by ensuring the project will have adequate funding to achieve success. In light of that commitment, we understand this project will require a steady and experienced Project Manager to successfully shepherd the project from inception to completion.
It is clear that the existing Downtown Carnegie Library is far too limited in size and infrastructure to provide the services that a City of this size needs and deserves. In reviewing the Measure P documents, it is evident that this facility is highly valued by the community and is therefore protected from future removal due to its historic value. We are prepared to assist the City is evaluating the current library and make recommendations for future uses. Additionally, it is clear that the existing Community Center at Albert park is also unable to provide the level of service the community needs and deserves. We applaud the City in its wisdom to solve both of these challenges with a vision for a single project. We have found that Community Centers and Libraries often serve very similar purposes, much of which can be cross utilized in a single space, making the delivery of events and services more efficient and better deployed.
We feel uniquely suited to support the City with this project given our many years of providing needs assessments and programming for libraries and community centers around the state. Our team of experts are not just project managers, but also specialists in identifying the highest and best use of property, investigating and analyzing programmatic needs, and incorporating this information into a comprehensive program that provides the City with a “road map” on how to successfully plan for and deliver this project. This road map will then allow us to develop a budget and schedule for implementation for the remainder of the project.
One key aspect to the success of this project will be in the engagement of the myriad stakeholder groups. We understand the City has multiple constituents and stakeholders invested in this project, and we are deft at managing this collage of interest groups and harnessing their perspectives into a singular vision that is executable. This effort will involve extensive outreach, thoughtful synthesis, and a variety of contingency plans to ensure the overall objectives are achieved. We have performed these services for community centers, libraries, civic centers, public safety facilities, and complex capital improvement plans. Regardless of the product type, successful management of this project, with its complex set of stakeholders, will rely on expertise in the public development space, and deep understanding of public policy, expertise in public procurement, and a collaborative leadership approach that seeks to bring all team participants together to pull the project in the same direction. We will deploy this expertise to your project and deliver success to the community as we have done for decades, providing comprehensive project management oversight to ensure the achievement of the City's goals.
3. P roject U n d erstan d ing & A pproach GRIFFIN STRUCTURES 21 Griffin approaches projects with the perspective of an Owner, and the insight of an Architect and Contractor. Like an Owner, we approach each project as if i t is our own money, schedule, and facility that is being developed. Griffin provides Program Management and Construction Management (PMCM) based on our unique blend of experience as both a public agency PMCM and at-risk fee developers - uniquely enhancing our ability to provide unparalleled services to our clients and have included a summary of our available services below.
Approach
COMMUNICATION / DOCUMENT CONTROL
Standardized Communication and Document Management Protocols will be utilized for all project document controls. All RFIs, submittals, ASIs, CCDs, Deltas, daily reports, project photos, SWPPP reports, schedules, and closeout documents will be carefully integrated into the City’s third-party web-based Software-as-a-Service (SaaS).
SCHEDULE MANAGEMENT
A comprehensive master project schedule will be created to include all aspects of the project, including, but not limited to: design iterations & review times, permitting phases, pre-qualification, bidding, contracts & insurance, construction phasing, city installations, utility connections, IT installations, punchlist, commissioning, & contingency.
FINANCIAL CONTROLS
Effective financial controls depend on change management, timely invoices, claim mitigation & avoidance, commitment to value, clear documentation and legal comprehension. Our expertise in this category is best-in-class and includes an estimating team to serve as a reference point in developing budgets and change order negotiation.
QUALITY CONTROL OBSERVATIONS
Inspections, photography/technology such as recordings, photography, Bluebeam Technology to facilitate the communication of challenges in field for quick resolution & documentation, Building Information Modeling (BIM), and Field Observation Reports will be employed for Quality Control and Assurance.
At Griffin Structures, we see ourselves as an extension of staff. As such, we will take a leadership role in all project coordination and communication efforts and work closely with the City staff to do so in a consistent manner with your protocols. Nonetheless, some tasks will need to be performed by the City, specifically as it relates to items that only City staff employees can perform. These would include assistance and support from City departments, financial matters that only the City can execute, procurement processes, and staff dependent, decision-making, and final selection. In essence, Griffin Structures will lead the entire process and manage all team efforts, but we will also need the City to coordinate with us as it relates to these and other functions for which we do not have the authority or execute. And of course, the key to this success will be a single point of contact with the City to whom we will report.
CITY RESPONSIBILITIES
Please visit Section 5 of our proposal to view our proposed Project Schedule.
SCHEDULE
S A N T A C R U Z D O W N T O W N L I B R A R Y , H O U S I N G &
MIXED-USE PROJECT
4. SCOPE OF WORK
4. S cope O f W ork GRIFFIN STRUCTURES 22
TASK 1: PROJECT MANAGEMENT
Over the course of our long history providing Project
Management in the public sector, our team has
delivered nearly 30 libraries and 35 community centers, plus countless other projects of a similar nature. This experience gives us the unique ability to lead this effort from its inception through to completion. Serving the
City of San Rafael as Capital Project Manager for this
project, we will bring a “concept to keys” leadership
approach to the City. This will include everything listed in the scope of work in the RFP, plus additional scope
enhancements, particularly in the development of the
facility needs assessment and a project program for A/E use once on board. Below is a general description of
how we intend to deliver this scope of services.
TASK 2: PROJECT PLANNING
A. Initial Project Review
Griffin Structures will begin this project with an in
depth project review. The goal of this effort will be to get an understanding of existing documents, efforts,
and conditions in the field and to understand how the
project sits presently. Additionally, once this review is completed, we will identity and codify the key project
objectives that will help to guide project moving
forward.
B. Library & Community Center Programming
As part of our planning efforts, and based on the
objectives discovered during the initial project review, our team will prepare a comprehensive building
program for the library facility by first conducting
a benchmarking analysis of comparable libraries
serving communities of similar size, demographics,
and service needs. This will include evaluating industry best practices and current trends in library design
and programming. To ensure the building program
reflects the specific operational and community
needs of the City, we will conduct interviews with key
stakeholders, including library staff, members of the
Friends of the Library, and up to three targeted focus
groups representing priority programmatic uses (e.g.,
youth services, technology and media, and community
meeting space). These efforts will inform the
development of a data-driven, forward-looking space
program. Should the City desire broader community
engagement, our team—supported by Circlepoint—can
also facilitate additional outreach efforts (separately scoped), including community workshops, surveys,
or pop-up engagements to gather a wider range of
perspectives.
C. Project Delivery Analysis
Excellence in Project Delivery is our motto, and we pride ourselves in being regarded as experts in public project delivery throughout the state. As part of our initial
planning we will develop and present delivery options
that we believe are best suited for the success of the
project. These options will include, Design Bid Build,
Design Build, Progressive Design Build, CM at Risk and
other hybrid forms of Alternative Project Delivery. Once an approach is agreed upon, we will then work with
the City to develop a procurement strategy that is most suitable for the project.
Scope of Work
HALF MOON BAY LIBRARY
4. S cope O f W ork GRIFFIN STRUCTURES 2 3
D. Design Solicitation
Given our experience developing projects at risk,
Griffin has a robust design solicitation repository
that will select the project's best Design Team.
Some key features of this effort will be the request
and evaluation of past projects of a similar size
and character, the experience of the Design Team,
familiarity with libraries and community centers, and
park developments. As described above, we will include
a comprehensive program which establishes a baseline
of the design effort, and a clear delineation of scope
that will ensure the responses which are received are
comprehensive. Additionally, we will work with the
City to incorporate our RFP development plan into
existing City procurement procedures, if applicable. We will work closely with staff to ensure that the efforts employed are consistent with City regulations while also benefiting from our vast experience managing similar
efforts for other Clients.
T A S K 3 : P U B L I C I N F O R M A T I O N &
COMMUNICATION
E. Community Engagement
In coordination with the City, and working alongside our communications partner Circlepoint, Griffin will assist in soliciting direct feedback from the community on
programming and design priorities through a series of
small group meetings to be determined based on the
City's preference. Our experience has included reaching out to groups such as City staff, the internal Technical Advisory Committee, neighbors, local school staff, news media, and grassroots organizations, the business
community, religious organizations, and others to
obtain a section of the community which can represent
and support the development of the project. We will
work with the City and assist in the facilitation of
collaborative meetings with community members and
organizations on a variety of platforms including virtual and physical via Zoom or other conferencing media.
F. Regular Project Updates
Our team will work closely with the City to establish
the best methods for project updates. We are prepared
to develop a project specific website, social media
updates, flyers, and handouts. These efforts will be
closely coordinated with City staff and stakeholders
to occur at key milestones of the project. Our team
will also function as the representative of the project, providing updates to any and all commissions,
community presentations, council updates and technical
advisory committee updates.
T A S K 4 : C O M M U N I T Y E N G A G E M E N T ,
DESIGN & PLANNING
G. Conceptual Design
To initiate Conceptual Design it will be critical that
the Design team understand and the City validate the
existing needs assessment performed to date. For this
effort, the recently selected Design Team will need
to validate and incorporate this information into the
following key deliverables:
These concepts will then be evaluated by all
stakeholders and development team to ensure the
design meets the City’s needs, is appropriate for the
project site, and is within the City’s budget. To facilitate this review process, we typically require the design
team produce at least 3 different concepts for the
project and hold a council meeting or advisory meeting
for the decision making process. This will allow for the City to make an informed decision before going to far
into the design process.
4. S cope O f W ork GRIFFIN STRUCTURES 24
H. Design Management
Once Conceptual Design is approved, Griffin will use our proven project management approach to then take the
project through Schematic Design, Design Development,
Construction Documents and Permitting. We will
carefully review all approved programming and design
documents and ensure that the team is aligned on
project goals and requirements. We will prepare reports on probable cost, constructability, value analysis,
and operability. We will perform periodic checks on
the design progress to ensure that the design meets
all project goals including program, cost, schedule,
features, and quality; and we will issue reports on our findings. Griffin's track record for keeping change orders to a minimum is impressive. To minimize change orders,
we will focus extensively on the pre-planning and
design stages. Our critiques will help the design team
achieve the best possible facility, while adhering to the parameters established by policymakers.
I. Design Review Charrettes
In close coordination with the City, and as described
above, we are prepared to lead stakeholder and
community engagement charrettes to review key
planning and design concepts and incorporate
community feedback into the design process. This will
be a highly nuanced approach that will be developed
in close coordination with City staff. The goal will be to pull in as much community input as possible while
also maintaining a core focus on project objectives,
affordability, and timing.
J. Consultant Procurement & Management
Griffin will oversee the procurement of all necessary
consultant services to ensure the project moves forward expeditiously. During the development of the A/E RFP,
we will work closely with the City to determine which
services should be included within the A/E scope, and
which services are best provided as prime contracts
directly to the City. This would include, environmental investigations, geotechnical investigations, cultural
reviews, low voltage and audio visual considerations,
move management, preliminary abatement services. At
this stage it is not clear which of these services will be needed, but once our pre-planning efforts are complete, we will incorporate all necessary consultants in our
Master Budget and Master Schedule.
T A S K 5 : P R E - C O N S T R U C T I O N
SERVICES
K. Constructability Reviews
Our approach to managing cost and schedule during
the construction phase begins with our management
of the process during the preconstruction phase.
Specifically, we will focus on the quality and clarity of drawings and specifications, perform constructability
reviews, and provide cost estimating and reconciliation.
During the construction phase, conflicts and surprises
are minimized because of our proactive efforts
during the preconstruction phase. Griffin’s series of
constructability reviews will facilitate plan coordination and clarity, which ultimately minimizes the number
of contractors’ questions and change orders during
construction. This process results in contractor bids
which are not inflated to cover ambiguities.
4. S cope O f W ork GRIFFIN STRUCTURES 25
L. Albert Park Site Utilization
As part of our constructability review, our team will
also develop a site utilization and staging plan for
contractors to know how the site is to be used during
construction. The goal of this plan will be to maintain access and use of as much of Albert Park as possible
while also maintaining the most efficient use of the
site to maintain progress on the project. This plan will include temporary power, SWPPP access, traffic control
requirements, working hours, field office compound, and dust mitigation.
T A S K 6 : C O N T R A C T O R A D V E R T I S E &
AWARD
M. Contractor Bidding
Griffin is prepared to assist the City in this process
including the advertising process, bidders conference,
bid RFI’s and substitution requests, the issuance of
addenda, and support the City in the opening and
evaluation of the bids. We also recommend that the
City employ a Contractor prequalification effort to
ensure the bidders all have the necessary experience to deliver a project of this type.
T A S K 7 : C O N S T R U C T I O N
MANAGEMENT
N. Pre-Construction Conference
Griffin will organize and conduct the Pre-Construction
meeting and provide agenda and meeting minutes
accordingly. Griffin will ensure that all pertinent team members will be present to coordinate with City staff.
O. Submittal Procedures
Griffin will oversee the distribution of all shop drawings submittal reviews, RFIs, payment requests, change
orders, product data, material delivery dates, periodic reports, project logs etc. As described above, Griffin will use of Submittal Exchange for expedient distribution
and tracking of these documents. We will tailor this
effort to provide the exact level of detail expected from the City.
P. Meetings
Griffin will prepare the agendas and meeting minutes,
discuss the schedule updates and near-term activities;
work with the team to clarify or resolve problems;
coordinate with other Contractors; update the team
on the status of change orders, submittals, and RFI’s;
and review safety issues and other topics as they arise.
Griffin will assign action items to responsible parties along with the corresponding date the action requires
completion. These meetings will be reviewed for
concurrence and will be distributed to attendees within five calendar days.
Q. Quality Assurance / Quality Control (QA/QC)
Griffin Construction Managers are inherently
Construction Inspectors. Our Construction Manager/
Project Inspector will perform periodic inspections of
the project. We will review material deliveries, material types, installation methods, finished installations in
comparison to contract documents, and construction
code adherence. Additionally, we will coordinate the
timely execution of all specialty inspections including but limited to: geotechnical, building department,
special inspections, and materials testing, to ensure
the City receives the highest level of quality and
consistency with the plans and specifications as well as all standards and practices
4. S cope O f W ork GRIFFIN STRUCTURES 26
R. Maintain On-Site Records
Griffin will manage all project documentation via
our cloud-based document management system. As
such, we will maintain all shop drawings, product
data, samples, submittals, purchases, materials,
equipment, and applicable handbooks. All documents
will be maintained and turned over to the City at the
completion of the project.
S. Schedule of Values & Processing of Payments
Griffin will establish, or cause to be established by the Contractor, a comprehensive Schedule of Values for the
entirety of the project for approval by the City. Once
approved, this will serve as the basis for all progress payments, which Griffin will review for consistency with progress in the field and make recommendations to the
Contractor for correction. Once corrected, Griffin will make recommendations to the City for processing.
T. Evaluate Change Order Proposal Costs
Griffin will review all change orders and provide
supplemental information as needed to justify their
approval or rejection. Griffin will negotiate with the
Contractor on the City’s behalf and serve as the point
of contact for resolving issues and mitigating against
potential claims. Specifically, Griffin will seek to avoid claims as detailed above.
T A S K 8 : P O S T C O N S T R U C T I O N
SERVICES
U. As-Built Documents
Griffin Structures will maintain a complete and up to
date set of drawings for the duration of the project.
As such, we will use the CM set as the As-Built set
and require that all trade contractors mark up the
CM set which will allow for a complete set of AsBuilt documents be turned over to the City for record purposes.
V. Initial Start-Up & Testing
As part of the commissioning process, all installations will go through both a pre-functional testing protocol
and a functioning test protocol. These tests will be
managed and documented by the Commissioning Agent
and overseen by the Construction Manager/Project
Inspector.
W. Punch Lists
Griffin will coordinate the final punch walk to ensure
all improvements are per the plans and specifications.
Specifically, Griffin will employ a Field Observation
Log that will seek to identify quality issues observed
by the project team on an ongoing basis. This will
serve to function as an ongoing pre-punch list, and
therefore help to minimize the issues discovered at the final punch walk. Griffin will also oversee the follow up punch walks to confirm corrective action is resolved.
Once completed, Griffin will issue a comprehensive
punch list for completion by the Contractor. Griffin will oversee the completion of these items and ensure that
all deficiencies and corrections are completed to the
satisfaction of the City.
X. Conclusion
Griffin Structures takes pride in providing unparalleled construction management services. As described above,
Griffin will serve as the eyes and ears of the City. Our motto is “no surprises”. We achieve that by proper
management (avoiding the issues in the first place)
and clear and concise documentation (for defense and
resolution of unavoidable issues). Accordingly, Griffin will provide comprehensive construction management
and inspection services as detailed in the RFP.
SALINAS EL GABILAN BRANCH LIBRARY
5. PROJECT SCHEDULE
,,------
t
...
t
r
'T
.,,
~ "' ~ -~:__--- ~- -
5. P roject S che d ule GRIFFIN STRUCTURES 2 7
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
Design Solicitation
Conceptual Design
Concept Design Review
Schematic Design
Design Development
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
President - Jon Hughes 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 45 45 45 45 45 45 45 50 50 50 50 50 50 50 50 Needs Assessment / Programming - Dustin Alamo 45 45 45 45 10 5 Sr. Construction Manager - Hernan Munayco 10
Constructability Review Specialist - David Fields 10
Quality Assurance Inspector - Mike Baker
President - Jon Hughes $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,140 $ 1,140 $ 1,140 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 Principal In Charge - Robert Godfrey $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,200 $ 2,200 $ 2,200 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 Project Executive - Gary Chubb $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 11,925 $ 11,925 $ 11,925 $ 12,375 $ 12,375 $ 12,375 $ 12,375 $ 13,750 $ 13,750 $ 13,750 $ 13,750 $ 13,750 $ 13,750 $ 13,750 $ 13,750 Needs Assessment / Programming - Dustin Alamo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 11,925 $ 11,925 $ 11,925 $ 12,375 $ - $ - $ - $ - $ - $ - $ 2,750 $ 1,375 $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,600 $ - $ - $ - $ - Constructability Review Specialist - David Fields $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,600 $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Total $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 26,050 $ 26,050 $ 26,050 $ 27,030 $ 14,655 $ 14,655 $ 14,655 $ 16,030 $ 16,030 $ 16,030 $ 23,980 $ 17,405 $ 16,030 $ 16,030 $ 16,030 WEEKS
PROJECT PHASE 2025 2026
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
Design Solicitation
Conceptual Design
Conceptual Design Review
Schematic Design
Schematic Design Review
Design Development
Design Development Review
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
WEEKS
President - Jon Hughes 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 50 50 50 50 50 50 50 50 50 50 50 50 50 50 90 90 90 90 90 50 25 25 25 25 Needs Assessment / Programming - Dustin Alamo 10 5
Sr. Construction Manager - Hernan Munayco 20 10 40 10 90 172 172 172 172 172 172 Constructability Review Specialist - David Fields 20 10 40 10 Quality Assurance Inspector - Mike Baker 172 172 172 172 172 172 President - Jon Hughes $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 Principal In Charge - Robert Godfrey $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 Project Executive - Gary Chubb $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,750 $ 14,750 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 14,750 $ 7,375 $ 7,375 $ 7,375 $ 7,375 Needs Assessment / Programming - Dustin Alamo $ 2,850 $ 1,425 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 25,200 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 Constructability Review Specialist - David Fields $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 30,260 $ 23,435 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 38,210 $ 22,010 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 17,190 $ 17,190 $ 28,990 $ 28,990 $ 28,990 $ 54,190 $ 123,590 $ 111,790 $ 104,415 $ 104,415 $ 104,415 $ 104,415
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC PROJECT PHASE 2029 2030
PROJECT PHASE 2027 2028
Project Schedule
Please find our proposed schedule below. For more in-depth information, please visit Section 7 of our proposal.
5. P roject S che d ule GRIFFIN STRUCTURES 28
Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 50 50 50 50 50 50 50 50 50 50 50 50 50 50 90 90 90 90 90 50 25 25 25 25 Needs Assessment / Programming - Dustin Alamo 10 5
Sr. Construction Manager - Hernan Munayco 20 10 40 10 90 172 172 172 172 172 172 Constructability Review Specialist - David Fields 20 10 40 10 Quality Assurance Inspector - Mike Baker 172 172 172 172 172 172 President - Jon Hughes $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 Principal In Charge - Robert Godfrey $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 Project Executive - Gary Chubb $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,750 $ 14,750 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 14,750 $ 7,375 $ 7,375 $ 7,375 $ 7,375 Needs Assessment / Programming - Dustin Alamo $ 2,850 $ 1,425 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 25,200 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 Constructability Review Specialist - David Fields $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 30,260 $ 23,435 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 38,210 $ 22,010 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 17,190 $ 17,190 $ 28,990 $ 28,990 $ 28,990 $ 54,190 $ 123,590 $ 111,790 $ 104,415 $ 104,415 $ 104,415 $ 104,415
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
Design Solicitation
Conceptual Design
Conceptual Design Review
Schematic Design
Schematic Design Review
Design Development
Design Development Review
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
WEEKS
President - Jon Hughes 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 Needs Assessment / Programming - Dustin Alamo
Sr. Construction Manager - Hernan Munayco 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 Constructability Review Specialist - David Fields
Quality Assurance Inspector - Mike Baker 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 President - Jon Hughes $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 Principal In Charge - Robert Godfrey $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 Project Executive - Gary Chubb $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 Needs Assessment / Programming - Dustin Alamo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 Constructability Review Specialist - David Fields $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
2031 PROJECT PHASE
PROJECT PHASE 2029 2030
Design Solicitation
Conceptual Design
Conceptual Design Review
Schematic Design
Schematic Design Review
Design Development
Design Development Review
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
WEEKS Totals
President - Jon Hughes 4 4 4 264
Principal In Charge - Robert Godfrey 8 8 8 528
Project Executive - Gary Chubb 25 25 10 2,675
Needs Assessment / Programming - Dustin Alamo 210
Sr. Construction Manager - Hernan Munayco 172 172 50 5,734 Constructability Review Specialist - David Fields 90
Quality Assurance Inspector - Mike Baker 5,160
President - Jon Hughes $ 1,380 $ 1,380 $ 1,380 $ - $ - $ - $ - $ - $ - $ - $ - $ - 83,160 Principal In Charge - Robert Godfrey $ 2,680 $ 2,680 $ 2,680 $ - $ - $ - $ - $ - $ - $ - $ - $ - 161,040 Project Executive - Gary Chubb $ 8,125 $ 8,125 $ 3,250 $ - $ - $ - $ - $ - $ - $ - $ - $ - 635,275 Needs Assessment / Programming - Dustin Alamo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - 6,875 Sr. Construction Manager - Hernan Munayco $ 53,320 $ 53,320 $ 15,500 $ - $ - $ - $ - $ - $ - $ - $ - $ - 1,678,260 Constructability Review Specialist - David Fields $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - 24,200 Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - 1,455,120 $ 64,125 $ 64,125 $ 21,430 $ - $ - $ - $ - $ - $ - $ - $ - $ - 4,153,445 President - Jon Hughes $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 Principal In Charge - Robert Godfrey $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 Project Executive - Gary Chubb $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,750 $ 14,750 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 14,750 $ 7,375 $ 7,375 $ 7,375 $ 7,375 Needs Assessment / Programming - Dustin Alamo $ 2,850 $ 1,425 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 25,200 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 Constructability Review Specialist - David Fields $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 30,260 $ 23,435 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 38,210 $ 22,010 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 17,190 $ 17,190 $ 28,990 $ 28,990 $ 28,990 $ 54,190 $ 123,590 $ 111,790 $ 104,415 $ 104,415 $ 104,415 $ 104,415
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
Design Solicitation
Conceptual Design
Conceptual Design Review
Schematic Design
Schematic Design Review
Design Development
Design Development Review
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
WEEKS
President - Jon Hughes 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 Needs Assessment / Programming - Dustin Alamo
Sr. Construction Manager - Hernan Munayco 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 Constructability Review Specialist - David Fields
Quality Assurance Inspector - Mike Baker 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 President - Jon Hughes $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 Principal In Charge - Robert Godfrey $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 Project Executive - Gary Chubb $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 Needs Assessment / Programming - Dustin Alamo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 Constructability Review Specialist - David Fields $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
2031 PROJECT PHASE
PROJECT PHASE 2029 2030
NEWPORT BEACH MARINA PARK
COMMUNITY & SAILING CENTER
6. FIRM REFERENCES
I II
i/
/1 '
'l
'i 1/
1 l I
-- • -~ •. , ~· .. :;.....~~ ~ - - "'1:::';i:.!"~ ~: ... ~ .._ ~ - ~~·~ .. Y~~~
\
.-- ... ~~~-~ -:-~-. ·~ ..... ~"".': ::.-e--~ ... t:'"~, ~-~~I-_:: _, ~ ::.,. -:.. -
.~ -.~
6. F irm R eferences GRIFFIN STRUCTURES 2 9
PROJECT D ESCRIPTION & OUTCOME
Griffin Structures provided Construction Management and Value Engineering services for the new, 35,700 SF, twostory community center which is built over the footprint of the existing facility, expanding the existing space by nearly 11,000 SF.
The Center features an active lounge, community room,
classroom, music studio, tech shop, ceramics and fine arts workshops, teen center, fitness studio, and more.
Other components include the addition of new 35-stall
above-ground and underground parking structure adjacent to the new building, a newly relocated playground,
basketball court, and picnic area, and site improvements to the area surrounding the new Center.
VALUE + SIZE
$55,000,000 | 37,000 SF
D ATE OF CONTRACT + COMPLETION
2020 - 2022
CONTRACTING AGENC Y + CONTACT
City of Burlingame; Margaret Glomstad; Parks and
Recreation Director; (650) 558-7307;
[email protected]
CONSULTING PM + CONTACT
Griffin Structures; Jon Hughes; President; (949) 444-1615; [email protected]
AWAR D S
Peninsula Clean Energy Award
Net Zero Energy
TESTIMONIAL
“The Griffin team’s knowledge, professionalism, and
communication skills helped resolve some very difficult situations and kept the project on schedule and budget, which was no easy feat.”
- City of Burlingame
Burlingame Community Center & Washington Park
BURLINGAME, CA
6. F irm R eferences GRIFFIN STRUCTURES 3 0
PROJECT D ESCRIPTION & OUTCOME
Griffin provided Program and Construction Management
services for a new library in the City of Half Moon Bay. The project included demolition of an existing 7,825 SF library and construction of a new 22,000 SF library. Planning for the new $24 million library involved extensive community engagement and outreach. The contemporary design
includes a lobby; children’s and teen areas; study, literacy areas; as well as a roof deck, courtyard and atrium.
The project, which opened in August 2018, is a net-zero energy building (NZEB)–the first in San Mateo County. The library includes a large rooftop photovoltaic array that provides nearly all the electricity for the building. Site features include EV charging stations, drought-tolerant plantings, bioswales, and permeable pavers that allow
rainwater to be captured and filtered before it percolates into the ground, rather than flowing into storm drains.
VALUE + SIZE
$24,000,000 | 22,000 SF
D ATE OF CONTRACT + COMPLETION
2017 - 2019
CONTRACTING AGENC Y + CONTACT
John Doughty; Current Public Works Director, Gilroy; Former Public Works Director, Half Moon Bay; (831) 247-1088;
[email protected]
CONSULTING PM + CONTACT
Griffin Structures; Jon Hughes; President; (949) 444-1615; [email protected]
Griffin Structures; Robert Godfrey; Vice President;
(626) 840-8795; [email protected]
AWAR D S
LEED Platinum; Zero Net Energy; APWA Project of the Year; APWA National Project Award; San Mateo County Green
Building Award
TESTIMONIAL
“The CM services provided by Griffin throughout the design and construction process have been outstanding”
- City of Half Moon Bay
Half Moon Bay Library
HALF MOON BA Y , CA
6. F irm R eferences GRIFFIN STRUCTURES 3 1
NORTHEAST STOCKTON LIBRARY & COMMUNITY CENTER STOCKTON, CA
PROJECT DESCRIPTION & OUTCOME
This new Library and Community Center will feature library and reading areas, cafe and meeting rooms, makers space with sewing machines, and an educational culinary kitchen.
Athletic facilities include a full-size gymnasium, rockclimbing wall, and sports courts. Outdoor gathering event space and multi-use rooms will also be housed within the facility. All design elements will achieve LEED silver-level certification with low-impact design.
CONTRACTING AGENCY + CONTACT
City of Stockton; Mohammad Sadiq; Project Manager; (209) 937-8299; [email protected]
CONSULTANT PM + CONTACT
Griffin Structures; Hernan Munayco; Sr. Program & Construction Manager; (949) 375-0946; [email protected]
VALUE + SIZE
$15,000,000 | 20,000 SF
D A T E O F C O N T R A C T +
COMPLETION
2021 - Ongoing
CUPERTINO LIBRARY EXPANSION CUPERTINO, CA
PROJECT DESCRIPTION & OUTCOME
This project was envisioned to be a two-story addition at the southern end of the building. The existing 1,175 SF single story Children’s Book area was demolished and replaced
with a new 5,626 SF two-story addition that connects to the existing structure. In addition, this project expanded the size of the existing Story Room and created a multi-purpose Program Room. The new Program Room can be partitioned
into smaller rooms allowing for simultaneous use.
CONTRACTING AGENCY + CONTACT
City of Cupertino; Roger Lee; Public Works Director (Ret.); (408) 234-8494; [email protected]
CONSULTANT PM + CONTACT
Griffin Structures; Hernan Munayco; Sr. Program & Construction Manager; (949) 375-0946; [email protected]
VALUE + SIZE
$8,000,000 | 10,000 SF
D A T E O F C O N T R A C T +
COMPLETION
2020 - 2022
Hernan Munayco
RECENT + RELEVANT LIBRARY / COMMUNITY CENTER EXPERIENCE
6. F irm R eferences GRIFFIN STRUCTURES 32
PROJECT NAME
01. Bloomington Branch Library
02. Campbell Library Renovation
03. Cupertino Library Expansion
04. Eastvale Civic Center & Library
05. Escondido Public Library Modernization
06. Fullerton Main Library
07. Half Moon Bay Library
08. Hesperia City Library
09. Inglewood Main Library Renovation
10. Irvine Great Park Framework Plan & Library
11. Newport Beach Donna & John Crean Mariners Library
12. Newport Beach Library, Witte Hall
13. Northeast Stockton Library & Community Center
14. Quartz Hill Library, County of Los Angeles
15. Salinas El Gabilan Branch Library
16. San Bernardino County Law Library Renovation
17. San Jacinto Civic Center & Library
18. San Leandro Shoreline Development & Library
19. Santa Ana Main Library Renovation
20. Santa Ana Newhope Library Renovation
21. Santa Ana Delhi Center Library Branch
22. Santa Ana Outdoor Library at Jerome Park
23. Santa Ana Zoo, Crean Family Farm
24. Santa Cruz Downtown Library, Housing & Mixed-Use Project
25. Tustin Main Library
26. Watsonville Civic Plaza & Library
27. Yorba Linda Library & Cultural Arts Center
28. Anaheim Civic Center & Library Pre-Development
29. Buena Park Library District Library Renovation Pre-Development PRE-DEVELOPMENT + PRE-CONSTRUCTION
Colton Civic Center & Library Pre-Development
El Centro Library Pre-Development
Hermosa Beach Library Pre-Development
Laguna Beach Facilities Master Plan & Library Pre-Development Willowbrook Library Pre-Development
07 27
15 03
Libraries
PROJECT NAME
01. Bakersfield MLK Jr Community Center & Park Revitalization
02. Buena Park Community Center
03. Burlingame Community Center & Washington Park
04. Carlsbad Pine Avenue Community Center & Gardens
05. Corona City Park Revitalization & Community Facilities
06. Cypress Community Center
07. Eastvale Civic Center & Community Facilities
08. Foster City Community Center
09. Fullerton Maple Community Center
10. Fullerton Multigenerational Community Center
11. Gardena Community Aquatics & Senior Center
12. Huntington Beach Community Senior Center
13. Irvine Great Park Framework Plan & Community Facilities
14. Jurupa Area Rec Park District, Skyview Event Center
15. Laguna Beach Community & Susi-Q Senior Center
16. Lake Forest Sports Park & Recreation Center
17. Lawndale Community Center
18. Newport Beach Marina Park Community & Sailing Center
19. Northeast Stockton Library & Community Center
20. Parkmoor Apartments & HUB Community Center
21. Quail Hill Community Center, Irvine
22. Rancho Cordova Mills Crossing
23. Rancho Palos Verdes Civic Center & Community Center
24. Rancho Palos Verdes, Ladera Linda Community Center & Park
25. Rancho Santa Margarita Civic Plaza & Community Center
26. Rancho Santa Margarita Community Center
27. Salinas Hebbron Family Center
28. San Bernardino County, On-Call Projects 2023
29. San Dimas Community Center
30. San Marino Community Center
31. Santa Ana Delhi Community Center & Community Park
32. Santa Clarita Canyon Country Community Center
33. Terra Lago Community Recreation Center
34. Walnut Creek Aquatic & Community Center
35. West Hollywood Plummer Park Community Center
03 18
08 32
Community Centers
Y O R B A L I N D A L I B R A R Y &
CULTURAL ARTS CENTER
7. RATE SCHEDULE
7. R ate S che d ule GRIFFIN STRUCTURES 33
POSITION 2025 2026 2027 2028 2029 2030 2031
Chief Executive Officer $320 $330 $340 $350 $360 $370 $370 Chief Financial Officer $295 $305 $315 $325 $335 $345 $355 President $285 $295 $305 $315 $325 $335 $345
Principal-In-Charge $275 $285 $295 $305 $315 $325 $335
Project Executive $265 $275 $285 $295 $305 $315 $325
Pre-Development Manager $265 $275 $285 $295 $305 $315 $325 Sr. Program & Construction Manager $250 $260 $270 $280 $290 $300 $310 Constructability Review Specialist $250 $260 $270 $280 $290 $300 $310 Program & Construction Manager $240 $250 $260 $270 $280 $290 $310 Inspector $240 $250 $260 $270 $280 $290 $310
Sr. Program Analyst $240 $250 $260 $270 $280 $290 $310
Estimator $240 $250 $260 $270 $280 $290 $310
Scheduler $240 $250 $260 $270 $280 $290 $310
Program Analyst $235 $245 $255 $265 $275 $285 $295
Accounting $230 $240 $255 $265 $275 $285 $295
Rate Sheet & Cost Proposal
7. R ate S che d ule GRIFFIN STRUCTURES 34
PRESIDENT PRINCIPAL IN
CHARGE
PROJECT
EXECUTIVE
PREDEVELOPMENT
MANAGER
EXECUTIVE
SR. PROGRAM &
CONST. MANAGER
CONSTRUCTABILITY
REVIEW SPECIALIST
Jon Hughes Robert Godfrey Gary Chubb Dustin Alamo Hernan Munayco David Fields 1 PROJECT MANAGEMENT Incl Incl Incl Incl Incl Incl
1A Lead role as Project Manager representing the City Incl Incl Incl Incl Incl Incl 2 PROJECT PLANNING 28 56 315 180 0 0
2A Review existing documents Incl Incl Incl Incl - -
2B Develop planning, design and project management plan Incl Incl Incl Incl - - 2C Define and maintain master schedule Incl Incl Incl Incl - - 2D Establish project controls and procedures Incl Incl Incl Incl - - 2E Assist in managing project budget Incl Incl Incl Incl - - 2F Provide monthly updates to schedule and budget Incl Incl Incl Incl - - 2G Assist in preparing staff reports and council presentations Incl Incl Incl Incl - 3 PUBLIC INFORMATION AND COMMUNICATION Incl Incl Incl Incl - - 3A Serve as primary point of contact for the project Incl Incl Incl Incl - - 3B Assist City with regular updates for public distribution Incl Incl Incl Incl - - 4 COMMUNITY ENGAGEMENT, DESIGN, AND PLANNING 88 176 1100 30 90 90 2H Constructability input to programming and budgeting efforts Incl Incl Incl Incl Incl Incl 4A Assist in developing project delivery method Incl Incl Incl Incl Incl - 4B Assist in selection of design team Incl Incl Incl Incl Incl - 4C Manage work of design team Incl Incl Incl Incl Incl - 4D Assist in public outreach of design team Incl Incl Incl Incl Incl - 4E Coordinate communication with relevant City departments Incl Incl Incl Incl Incl - 4F Assist in selection of consultants Incl Incl Incl Incl Incl - 4G Facilitate obtaining permits Incl Incl Incl Incl Incl - 4H Assist in developing strategies for Albert Park use Incl Incl Incl Incl Incl - 4I Coordinate plan check comments with Design Team Incl Incl Incl Incl Incl - 4J Provide input to ensure a functional and viable project Incl Incl Incl Incl Incl - 5 PRE-CONSTRUCTION SERVICES Incl Incl Incl Incl Incl -
5A Constructability review of plans and specifications Incl Incl Incl Incl Incl - 5B Manage project schedule on timelines and milestones Incl Incl Incl Incl Incl - 5C Assist in planning temporary facilities Incl Incl Incl Incl Incl - 5D Provide technical and report writing services as needed. Incl Incl Incl Incl Incl - 6 ADVERTISE AND AWARD 16 32 360 0 90 0
6A Advertise project in accordance with regulations Incl Incl Incl Incl Incl - 6B Utilize City's Bidexpress software system Incl Incl Incl Incl Incl - 6C Respond to bidder questions Incl Incl Incl Incl Incl - 6D Coordinate responses to bidder questions Incl Incl Incl Incl Incl - 6E Prepare addenda as needed Incl Incl Incl Incl Incl - 6F Arrange and attend pre-bid meeting Incl Incl Incl Incl Incl - 6G Review and evaluate bids and confer with the City Incl Incl Incl Incl Incl - 6H Assist in preparing recommendation for award to Council Incl Incl Incl Incl Incl - 7 CONSTRUCTION MANAGEMENT SERVICES 120 240 840 0 5160 0 7A Administer construction contracts Incl incl Incl Incl Incl - 7B Monitory quality control and costs Incl Incl Incl Incl Incl - 7C Prepare and coordinate project updates to City staff Incl Incl Incl Incl Incl - 7D Prepare and administer Commissioning Plan (WSP) Incl Incl Incl Incl Incl - 7E Conduct construction contract closeout activities Incl Incl Incl Incl Incl - 7F Formulate action plans to resolve issues and conflicts Incl Incl Incl Incl Incl - 7G Manage contract warranty period. Incl Incl Incl Incl Incl - 8 CONSTRUCTION MANAGEMENT SERVICES 12 24 60 0 394 0
8A Project closeout and issuane of substantial completion Incl incl Incl Incl Incl - 8B Assist with preparation of O&M plan Incl Incl Incl Incl Incl - 8C Facilitate transition to City maintenance staff
Total Hours 264 528 2675 210 5734 90
Subtotals $83,160 $161,040 $635,275 $6,875 $1,678,260 $24,200 PROJECT / CONSTRUCTION MANAGEMENT TOTAL No Charge $2,505,650 9 REIMBURSABLE COSTS $394,350
9A Insurance $24,350
9B Estimating (HLCM) ALLOWANCE $60,000
9C Scheduling Services (Tempus) ALLOWANCE $75,000
9D Cloud Based Document Management System (Autodesk) $40,000 9E Public Outreach (Circlepoint) ALLOWANCE $115,000
9F Misc. office supplies and printing $5,000
9G Commissioning (WSP) $75,000
GRAND TOTAL $2,900,000
ADD ALTERNATE - FULL TIME INSPECTOR DURING CONSTRUCTION $1,500,000 Item
No. PROJECT PHASE
Griffin Structures acknowledges and accepts the scope as described in the RFP and further refined below
PRESIDENT PRINCIPAL IN
CHARGE
PROJECT
EXECUTIVE
PREDEVELOPMENT
MANAGER
EXECUTIVE
SR. PROGRAM &
CONST. MANAGER
CONSTRUCTABILITY
REVIEW SPECIALIST
Jon Hughes Robert Godfrey Gary Chubb Dustin Alamo Hernan Munayco David Fields 1 PROJECT MANAGEMENT Incl Incl Incl Incl Incl Incl
1A Lead role as Project Manager representing the City Incl Incl Incl Incl Incl Incl 2 PROJECT PLANNING 28 56 315 180 0 0
2A Review existing documents Incl Incl Incl Incl - -
2B Develop planning, design and project management plan Incl Incl Incl Incl - - 2C Define and maintain master schedule Incl Incl Incl Incl - - 2D Establish project controls and procedures Incl Incl Incl Incl - - 2E Assist in managing project budget Incl Incl Incl Incl - - 2F Provide monthly updates to schedule and budget Incl Incl Incl Incl - - 2G Assist in preparing staff reports and council presentations Incl Incl Incl Incl - 3 PUBLIC INFORMATION AND COMMUNICATION Incl Incl Incl Incl - - 3A Serve as primary point of contact for the project Incl Incl Incl Incl - - 3B Assist City with regular updates for public distribution Incl Incl Incl Incl - - 4 COMMUNITY ENGAGEMENT, DESIGN, AND PLANNING 88 176 1100 30 90 90 2H Constructability input to programming and budgeting efforts Incl Incl Incl Incl Incl Incl 4A Assist in developing project delivery method Incl Incl Incl Incl Incl - 4B Assist in selection of design team Incl Incl Incl Incl Incl - 4C Manage work of design team Incl Incl Incl Incl Incl - 4D Assist in public outreach of design team Incl Incl Incl Incl Incl - 4E Coordinate communication with relevant City departments Incl Incl Incl Incl Incl - 4F Assist in selection of consultants Incl Incl Incl Incl Incl - 4G Facilitate obtaining permits Incl Incl Incl Incl Incl - 4H Assist in developing strategies for Albert Park use Incl Incl Incl Incl Incl - 4I Coordinate plan check comments with Design Team Incl Incl Incl Incl Incl - 4J Provide input to ensure a functional and viable project Incl Incl Incl Incl Incl - 5 PRE-CONSTRUCTION SERVICES Incl Incl Incl Incl Incl -
5A Constructability review of plans and specifications Incl Incl Incl Incl Incl - 5B Manage project schedule on timelines and milestones Incl Incl Incl Incl Incl - 5C Assist in planning temporary facilities Incl Incl Incl Incl Incl - 5D Provide technical and report writing services as needed. Incl Incl Incl Incl Incl - 6 ADVERTISE AND AWARD 16 32 360 0 90 0
6A Advertise project in accordance with regulations Incl Incl Incl Incl Incl - 6B Utilize City's Bidexpress software system Incl Incl Incl Incl Incl - 6C Respond to bidder questions Incl Incl Incl Incl Incl - 6D Coordinate responses to bidder questions Incl Incl Incl Incl Incl - 6E Prepare addenda as needed Incl Incl Incl Incl Incl - 6F Arrange and attend pre-bid meeting Incl Incl Incl Incl Incl - 6G Review and evaluate bids and confer with the City Incl Incl Incl Incl Incl - 6H Assist in preparing recommendation for award to Council Incl Incl Incl Incl Incl - 7 CONSTRUCTION MANAGEMENT SERVICES 120 240 840 0 5160 0 7A Administer construction contracts Incl incl Incl Incl Incl - 7B Monitory quality control and costs Incl Incl Incl Incl Incl - 7C Prepare and coordinate project updates to City staff Incl Incl Incl Incl Incl - 7D Prepare and administer Commissioning Plan (WSP) Incl Incl Incl Incl Incl - 7E Conduct construction contract closeout activities Incl Incl Incl Incl Incl - 7F Formulate action plans to resolve issues and conflicts Incl Incl Incl Incl Incl - 7G Manage contract warranty period. Incl Incl Incl Incl Incl - 8 CONSTRUCTION MANAGEMENT SERVICES 12 24 60 0 394 0
8A Project closeout and issuane of substantial completion Incl incl Incl Incl Incl - 8B Assist with preparation of O&M plan Incl Incl Incl Incl Incl - 8C Facilitate transition to City maintenance staff
Total Hours 264 528 2675 210 5734 90
Subtotals $83,160 $161,040 $635,275 $6,875 $1,678,260 $24,200 PROJECT / CONSTRUCTION MANAGEMENT TOTAL No Charge $2,505,650 9 REIMBURSABLE COSTS $394,350
9A Insurance $24,350
9B Estimating (HLCM) ALLOWANCE $60,000
9C Scheduling Services (Tempus) ALLOWANCE $75,000
9D Cloud Based Document Management System (Autodesk) $40,000 9E Public Outreach (Circlepoint) ALLOWANCE $115,000
9F Misc. office supplies and printing $5,000
9G Commissioning (WSP) $75,000
GRAND TOTAL $2,900,000
ADD ALTERNATE - FULL TIME INSPECTOR DURING CONSTRUCTION $1,500,000 Item
No. PROJECT PHASE
Griffin Structures acknowledges and accepts the scope as described in the RFP and further refined below
7. R ate S che d ule GRIFFIN STRUCTURES 3 5
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
Design Solicitation
Conceptual Design
Concept Design Review
Schematic Design
Design Development
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
President - Jon Hughes 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4
Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 45 45 45 45 45 45 45 50 50 50 50 50 50 50 50 Needs Assessment / Programming - Dustin Alamo 45 45 45 45 10 5 Sr. Construction Manager - Hernan Munayco 10
Constructability Review Specialist - David Fields 10
Quality Assurance Inspector - Mike Baker
President - Jon Hughes $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 1,140 $ 1,140 $ 1,140 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 $ 1,180 Principal In Charge - Robert Godfrey $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,200 $ 2,200 $ 2,200 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 $ 2,280 Project Executive - Gary Chubb $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 11,925 $ 11,925 $ 11,925 $ 12,375 $ 12,375 $ 12,375 $ 12,375 $ 13,750 $ 13,750 $ 13,750 $ 13,750 $ 13,750 $ 13,750 $ 13,750 $ 13,750 Needs Assessment / Programming - Dustin Alamo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 11,925 $ 11,925 $ 11,925 $ 12,375 $ - $ - $ - $ - $ - $ - $ 2,750 $ 1,375 $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,600 $ - $ - $ - $ - Constructability Review Specialist - David Fields $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 2,600 $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Total $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 26,050 $ 26,050 $ 26,050 $ 27,030 $ 14,655 $ 14,655 $ 14,655 $ 16,030 $ 16,030 $ 16,030 $ 23,980 $ 17,405 $ 16,030 $ 16,030 $ 16,030 WEEKS
PROJECT PHASE 2025 2026
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
Design Solicitation
Conceptual Design
Conceptual Design Review
Schematic Design
Schematic Design Review
Design Development
Design Development Review
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
WEEKS
President - Jon Hughes 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 50 50 50 50 50 50 50 50 50 50 50 50 50 50 90 90 90 90 90 50 25 25 25 25 Needs Assessment / Programming - Dustin Alamo 10 5
Sr. Construction Manager - Hernan Munayco 20 10 40 10 90 172 172 172 172 172 172 Constructability Review Specialist - David Fields 20 10 40 10 Quality Assurance Inspector - Mike Baker 172 172 172 172 172 172 President - Jon Hughes $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 Principal In Charge - Robert Godfrey $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 Project Executive - Gary Chubb $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,750 $ 14,750 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 14,750 $ 7,375 $ 7,375 $ 7,375 $ 7,375 Needs Assessment / Programming - Dustin Alamo $ 2,850 $ 1,425 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 25,200 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 Constructability Review Specialist - David Fields $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 30,260 $ 23,435 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 38,210 $ 22,010 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 17,190 $ 17,190 $ 28,990 $ 28,990 $ 28,990 $ 54,190 $ 123,590 $ 111,790 $ 104,415 $ 104,415 $ 104,415 $ 104,415
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
PROJECT PHASE 2029 2030
PROJECT PHASE 2027 2028
7. R ate S che d ule GRIFFIN STRUCTURES 36
President - Jon Hughes $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 Principal In Charge - Robert Godfrey $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 Project Executive - Gary Chubb $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,750 $ 14,750 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 14,750 $ 7,375 $ 7,375 $ 7,375 $ 7,375 Needs Assessment / Programming - Dustin Alamo $ 2,850 $ 1,425 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 25,200 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 Constructability Review Specialist - David Fields $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 30,260 $ 23,435 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 38,210 $ 22,010 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 17,190 $ 17,190 $ 28,990 $ 28,990 $ 28,990 $ 54,190 $ 123,590 $ 111,790 $ 104,415 $ 104,415 $ 104,415 $ 104,415
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
Design Solicitation
Conceptual Design
Conceptual Design Review
Schematic Design
Schematic Design Review
Design Development
Design Development Review
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
WEEKS
President - Jon Hughes 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 Needs Assessment / Programming - Dustin Alamo
Sr. Construction Manager - Hernan Munayco 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 Constructability Review Specialist - David Fields
Quality Assurance Inspector - Mike Baker 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 President - Jon Hughes $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 Principal In Charge - Robert Godfrey $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 Project Executive - Gary Chubb $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 Needs Assessment / Programming - Dustin Alamo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 Constructability Review Specialist - David Fields $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
2031 PROJECT PHASE
PROJECT PHASE 2029 2030
Design Solicitation
Conceptual Design
Conceptual Design Review
Schematic Design
Schematic Design Review
Design Development
Design Development Review
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
WEEKS Totals
President - Jon Hughes 4 4 4 264
Principal In Charge - Robert Godfrey 8 8 8 528
Project Executive - Gary Chubb 25 25 10 2,675
Needs Assessment / Programming - Dustin Alamo 210
Sr. Construction Manager - Hernan Munayco 172 172 50 5,734 Constructability Review Specialist - David Fields 90
Quality Assurance Inspector - Mike Baker 5,160
President - Jon Hughes $ 1,380 $ 1,380 $ 1,380 $ - $ - $ - $ - $ - $ - $ - $ - $ - 83,160 Principal In Charge - Robert Godfrey $ 2,680 $ 2,680 $ 2,680 $ - $ - $ - $ - $ - $ - $ - $ - $ - 161,040 Project Executive - Gary Chubb $ 8,125 $ 8,125 $ 3,250 $ - $ - $ - $ - $ - $ - $ - $ - $ - 635,275 Needs Assessment / Programming - Dustin Alamo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - 6,875 Sr. Construction Manager - Hernan Munayco $ 53,320 $ 53,320 $ 15,500 $ - $ - $ - $ - $ - $ - $ - $ - $ - 1,678,260 Constructability Review Specialist - David Fields $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - 24,200 Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - 1,455,120 $ 64,125 $ 64,125 $ 21,430 $ - $ - $ - $ - $ - $ - $ - $ - $ - 4,153,445 Constructability Review Specialist - David Fields 20 10 40 10 Quality Assurance Inspector - Mike Baker 172 172 172 172 172 172 President - Jon Hughes $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,220 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 $ 1,260 Principal In Charge - Robert Godfrey $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,360 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 $ 2,440 Project Executive - Gary Chubb $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,250 $ 14,750 $ 14,750 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 26,550 $ 14,750 $ 7,375 $ 7,375 $ 7,375 $ 7,375 Needs Assessment / Programming - Dustin Alamo $ 2,850 $ 1,425 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 25,200 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 Constructability Review Specialist - David Fields $ 5,400 $ 2,700 $ - $ - $ - $ - $ 10,800 $ 2,700 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 46,440 $ 30,260 $ 23,435 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 38,210 $ 22,010 $ 16,610 $ 16,610 $ 16,610 $ 16,610 $ 17,190 $ 17,190 $ 28,990 $ 28,990 $ 28,990 $ 54,190 $ 123,590 $ 111,790 $ 104,415 $ 104,415 $ 104,415 $ 104,415
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
Design Solicitation
Conceptual Design
Conceptual Design Review
Schematic Design
Schematic Design Review
Design Development
Design Development Review
Construction Documents
Permitting
Bidding and Award.
CONSTRUCTION
Mobilization
Construction
Punch List & Closeout
WEEKS
President - Jon Hughes 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 Principal In Charge - Robert Godfrey 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 Project Executive - Gary Chubb 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 25 Needs Assessment / Programming - Dustin Alamo
Sr. Construction Manager - Hernan Munayco 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 Constructability Review Specialist - David Fields
Quality Assurance Inspector - Mike Baker 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 172 President - Jon Hughes $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,300 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 $ 1,340 Principal In Charge - Robert Godfrey $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,520 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 $ 2,600 Project Executive - Gary Chubb $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,625 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 $ 7,875 Needs Assessment / Programming - Dustin Alamo $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Sr. Construction Manager - Hernan Munayco $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 $ 51,600 Constructability Review Specialist - David Fields $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Qualify Assurance Inspector - Mike Baker $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 48,160 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 49,880 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 108,185 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955 $ 111,955
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
PRECONSTRUCTION
Initial Project Investigation
Needs Assessment and Programming
2031 PROJECT PHASE
PROJECT PHASE 2029 2030
BURLINGAME COMMUNITY CENTER
& WASHINGTON PARK
8. STATEMENTS & SUPPLEMENTARY INFORMATION
8. S tatements & S upplementar y I nformation GRIFFIN STRUCTURES 37
CONFLICT OF INTEREST STATEMENT
Griffin Structures has no financial, business or other relationship with the City of San Rafael that may have an impact upon the outcome of the contract or the construction project.
REGULATORY ACTIONS OR LITIGATION
Griffin Structures hereby confirms we have no regulatory actions or legal issues to disclose.
SUPPLEMENTARY INFORMATION: PROPOSED COMMENTS
We have reviewed the City's Professional Services Agreement and are prepared to sign the agreement as is. However, we have provided the comments below and humbly ask for the City's consideration and welcome the opportunity to review and discuss the comments with the City and its legal counsel. Thank you. • Section 1 Work to Be Performed, 4th line between the words “City” and “at” insert “as expressly set forth in this Agreement”. • Section 4 Reliance on Professional Skill of Contractor, 4th line, strike the word “export” and replace with “professional.” • Section 6 Termination, Paragraph C, 4th line, between the words “case” and “Contractor” insert “Contractor shall be entitled to recover its costs expended up to the termination, subject to offsets as…” • Section 8 Indemnification, Paragraph A, 2nd and 3rd lines, strike “defend with counsel approved by City” and “agents.” Also strike final sentence of paragraph A beginning with “In the even the City Indemnities are made a party to any action….” • Section 9 Prevailing Wage, at the end of section, add the sentence “The obligations set forth in this Section 9 only apply to the extent applicable to Contractor and/or the Services.”
• Section 11, Liability of City, 2nd paragraph, first line, between words “shall” and “City” insert the words “either Contractor or..” • Section 11, Liability of City, 4th paragraph, 3rd line, at the end of sentence after the word “law” add “except as expressly stated in this Agreement.”
• Exhibit B, Scope of Coverage A, Professional Liability, 3rd line, strike “occurrence” and replace with “claim.” Also, 4th line of same paragraph, add “professional negligence” between the words “any” and “claims.” • General Terms and Conditions, 1. Compliance with Laws, 4th line, after the word “regulations” insert “in accordance with Contractors standard of care.” Also, same paragraph, at the end of the last sentence add “in violation of Contractor’s standard of care.”
• General Terms and Conditions, 4. Ownership of Documents, add the following “If Contractors Services include preparation of any design documents, then the design professionals will be deemed the authors and owner of their work product, and the city will be granted non-exclusive, fully paid license to use such work product only on this project. Additionally, notwithstanding anything in this section, any intellectual property owned, created, made, conceived, reduced to practice, or developed prior to, or independent of, performance of Services under this contract (“Prior Intellectual Property”) will remain the property of Contractor, and Contractor grants city a non-exclusive, fully-paid license to use such work product only on this project.” [ Please note we have consolidated tabs 8-10 within this page in order to satisfy the page count. Thank you. ]
SOUTHERN CA OFFICE
1 TECHNOLOG Y D RIVE
BUIL D ING I SUITE 829
IRVINE, CA 92618
949 497 9000
NORTHERN CA OFFICE
1850 WARBURTON AVE
SUITE 120
SANTA CLARA, CA 95050
408 955 0431
BURLINGAME COMMUNITY CENTER & WASHINGTON PARK
FOSTER CITY COMMUNITY CENTER
HALF MOON BAY LIBRARY
YORBA LINDA LIBRARY & CULTURAL ARTS CENTER
SALINAS EL GABILAN BRANCH LIBRARY C U P E R T I N O L I B R A R Y
EXPANSION
S A N T A C L A R I T A C A N Y O N
COUNTRY COMMUNITY CENTER
S A N T A C R U Z D O W N T O W N L I B R A R Y ,
HOUSING & MIXED-USE PROJECT
____________________________________________________________________________________
FOR CITY CLERK ONLY
Council Meeting: _______________________
Disposition: ___________________________
Agenda Item No: 7.b
Meeting Date: October 6, 2025
SAN RAFAEL CITY COUNCIL AGENDA REPORT
Department: Fire Department
Prepared by: Kate Anderson,
Wildfire Mitigation Program
Manager
City Manager Approval: ______________
TOPIC: WILDFIRE PREVENTION EFFORTS IN SAN RAFAEL FROM 2019-2025 SUBJECT: INFORMATIONAL REPORT ON THE 38-POINT WILDFIRE PREVENTION AND
PROTECTION ACTION PLAN
RECOMMENDATION:
Staff recommends that the City Council accept the informational report on the Wildfire Prevention and Protection Action Plan and proposed revision.
BACKGROUND:
In 2019, the City of San Rafael adopted the 38-Point Wildfire Prevention and Protection Action Plan (“38- Point Plan”) to guide policies, programs, and community investments aimed at reducing wildfire risk to the City of San Rafael. The plan was developed after a yearlong public input process with numerous meetings with the City Council, and the Wildfire Advisory Committee (comprised of 15 community members and former Mayor Phillips and Councilmember Bushey). The 38-Point Plan was designed as a living framework that outlined short-, medium-, and long-term actions, ranging from defensible space inspections and vegetation management to public education, emergency preparedness, and infrastructure hardening. The 38-Point Plan has served as a foundational roadmap, guiding San Rafael’s efforts on countywide initiatives under the Marin Wildfire Prevention Authority (MWPA), which is funded by Measure C.
Since adoption, the City has made significant progress implementing many of the strategies, and staff have provided periodic updates to the City Council in previous years. Highlights include:
• Establishment of the San Rafael Wildfire Mitigation Team with dedicated staff and funding source through Measure C, a 10-year wildfire prevention parcel tax. • Expanded defensible space and home hardening inspections, with 17,623 out of the City’s 17,847 total properties inspected and 28,918 total inspections to date. Staff have inspected 100% of parcels zoned as single-family residential and are working to engage all residents in multi-family dwellings by 2026.
• Updates to San Rafael Municipal Code (SRMC) Chapter 4.12 expand vegetation management standards citywide. Each zone, or distance from a structure, has a unique set of requirements in alignment with fire science and best practices.
SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 2
• Development of resources available to support residents in mitigating wildfire hazards and preparing for wildfires. This includes grants, direct assistance, and education. Grants and direct assistance programs are focused on the most critical risk reduction work, including creating a zone free of vegetation around homes (zone zero) and removing large amounts of vegetation. • Evaluation of San Rafael’s evacuation routes and implementation of multiple programs to solve evacuation challenges. This includes the completion and maintenance of roadside vegetation clearance, as well as the clarification of safe parking areas. • Completion and maintenance of several key fuel reduction and shaded fuel break projects in highrisk areas. These areas have included San Rafael’s fire road network to improve emergency responder access and slow fire spread before it reaches the community, as well as the defensible space zone in open space adjacent to residential development. • Launch of community engagement and education initiatives, including Firewise neighborhood support and multilingual outreach.
Community engagement and input were a key piece of developing the 38-Point Plan and continue to be a cornerstone of this program’s success. Staff remain committed to engaging with and informing the public of efforts to mitigate and adapt to climate change. Since 2019, staff have observed an increased awareness and deepening understanding on a community level about the risk of wildfire in our community, which may be attributed to the wildfire team’s year-round presence and engagement in the community. This has been accomplished through community meetings, virtual and in-person trainings, direct mail campaigns, door-to-door defensible space evaluations, signage, and coordination with community and neighborhood leaders. Additionally, staff provide updates to the City website and social media channels.
ANALYSIS:
Since 2020, with the passage of Measure C and the establishment of the Marin Wildfire Prevention Authority (MWPA), the City has made significant progress in most areas of the 38-Point Plan, largely driven by increased tax revenue. The 38-Point Plan has served as a guide for developing an annual MWPA work plan that includes projects and programs supporting wildfire preparedness and adaptation at the community level, tailored to the needs of San Rafael, and enhancing the safety of our neighboring communities.
Projects have included shaded fuel breaks, defensible space, and fire road vegetation management, evacuation route vegetation clearance, and safe parking clarifications, including the parking box program, as well as numerous ongoing programs that support public education and outreach, a citywide defensible space program, grants and other financial assistance options for residents, and alerts and notification sign-ups and systems. Since October of 2024, $200,000 of reimbursement grants have been distributed to 102 San Rafael property owners. A summary of the status and actions relating to each item in the 38- Point Plan is provided in Attachment 1.
The 38-Point Plan has served as a valuable starting point for making significant impacts on our community’s safety. However, as the wildfire risk landscape continues to evolve and new policies are being developed at the state level, it is timely to revisit the structure and content of the 38-Point Plan.
Several factors prompt the potential need for an update, including changes in the risk environment, new and upcoming regulatory guidance, and recognition of progress made on many key items.
Evaluation of current and future priorities is crucial as the City navigates a changing risk environment characterized by drought cycles, increased fire weather, longer fire seasons, and shorter but more intense winters. This also includes incorporating new scientific findings related to fire science, home hardening and building construction, climate change, and social impacts of wildfire. The State is also changing and developing policies that include Zone Zero regulations and the introduction of the California SAN RAFAEL CITY COUNCIL AGENDA REPORT / Page: 3
Wildland-Urban Interface Code, which provides opportunities for San Rafael to apply and enforce codes in a manner that supports the City’s goals and objectives.
Over 85% of the 38 initiatives are either completed (4 items) or transitioned to an ongoing maintenance cycle (8 items), or are ongoing supported programs (21 items). Two initiatives are in progress and will be completed by the end of the fiscal year. Three initiatives are pending or have not yet been completed.
Item 12, calling for a review of the WUI map, may be unnecessary as codes are applied more universally.
Item 17, calling for Citywide adoption of 7A may be resolved in the upcoming adoption of the new California Wildland Urban Interface code. Item 37, which would require two gates for all fences, has not been started pending further research and impact analysis. An update to the 38-Point Plan will enable staff to close out completed items, consolidate those achieved through the same project or program, and introduce new and emerging priorities. The 38-Point Plan was also drafted and approved before the formation of the MWPA and could benefit from closer alignment with Measure C’s five goals and associated metrics.
To ensure the 38-Point Plan remains a current, value-added guiding document, staff are in the process of evaluating and updating the 38-Point Plan. In addition, the City Council’s 3-Year Strategic Plan includes a goal and objective (Goal C – Objective C.2.2 – Wildfire Action Plan Implementation; “Continue implementing the Wildfire Action Plan and evaluate the need for revisions including focusing on zone zero (0-5 feet) from homes and structures.” This process will include community engagement and exploration of numerous new programs or projects that could be added, as well as any items that should be removed.
The 38-Point Plan will remain a standalone document, with an updated format and action items that illustrate the current work being performed, such as continuing programs, maintenance projects, new projects, policy, and advocacy work, etc.
The update to the 38-Point Plan will provide an opportunity to reorganize the plan’s content to reflect and incorporate county-wide wildfire mitigation goals, while maintaining and honoring the original vision of the 38-Point Plan and providing a useful structure to support the implementation of existing and new action items.
COMMUNITY OUTREACH:
Community engagement was not completed before this 38-Point Plan status update. However, staff will conduct community outreach and engagement throughout the process of updating the plan.
FISCAL IMPACT:
There is no direct fiscal impact associated with this informational report.
OPTIONS:
Staff suggest the following options to be considered on this matter:
1. Accept the report.
2. Provide an alternative direction.
RECOMMENDED ACTION:
Staff recommends that the City Council accept the informational report on the 38-Point Wildfire Prevention and Protection Action Plan.
ATTACHMENTS:
1. 38-Point Wildfire Prevention and Protection Action Plan Progress Update
Attachment 1 - Wildfire Prevention and Protection Action Plan Progress Update Status Description Summary
• Complete: The action has been completed as described. • In Progress: The action is actively underway.
• Maintenance Stage: The action has been completed; however, continuing work is needed to preserve the result. • Not Started: This action has not been started because it was either deemed unnecessary or additional analysis is needed. • Ongoing: There is a continuing need for this action; there is no fixed completion date. • Pending: The action is still planned, but it relies on another action or event to proceed. # Action Summary Status Next Steps/ Notes
1 Eliminate highly flammable
vegetation
Maintenance Stage Ordinance No. 1988 was adopted in 2021 to prohibit and require the removal of Juniper, Bamboo, Acacia, and Italian Cypress. Enforcement of outstanding issues and continued support for residents to facilitate hazard mitigation.
2 Establish citywide
standards
Complete Citywide vegetation standards were updated in 2021. Grants, education, and enforcement are ongoing to achieve compliance.
3 Reduce ember ignition in
the immediate zone
Ongoing Ordinance No. 1988 was adopted in 2021, which includes specific standards for the immediate zone. Analyze the potential impacts of changes to California law regarding defensible space zones. Provide additional grant support for Zone Zero mitigation. Ongoing need for enforcement. 4 Expand Goat Grazing Maintenance Stage Multi-year contract in place to cover over 150 acres. 5 Establish more fuel
interruption zones
Ongoing All San Rafael lands have been evaluated, and strategic areas are being added to the MWPA work plan as budget permits. Staff are coordinating with high-risk landowners on additional project sites, with long-term maintenance plans.
6 Improve Public Education Ongoing Expanded outreach events and engagement activities to reach different populations, including increased Spanish language materials and events.
Continued coordination with Fire Safe Marin and neighborhood or community leaders. Defensible space evaluations offer residents one-onone educational opportunities. 7 Establish more
Firewise communities
Ongoing The City hosted a meeting for new leaders in March 2025, providing ongoing support for both new and established communities.
# Action Summary Status Next Steps/ Notes
8 Develop an abatement
process for private
unimproved parcels
Ongoing Staff are working with the City Attorney’s Office to determine a fair and sustainable abatement process. Resident resources, such as grants and direct assistance, have generally avoided the need for significant forced abatement. The goal remains to avoid the need for abatement. 9 Effective debris removal Ongoing Debris Management is handled on a site-specific basis. Further research into biomass options is ongoing.
10 Engage volunteers in fire
prevention
Ongoing Re-engaged volunteers in 2025 after new staff were onboarded. Volunteer training is referenced in Public Resources Code (PRC) 4291.6. 11 Volunteer broom pulls Ongoing Staff support dozens of events each year with broom pullers, debris management, safety training, site identification, and outreach. 12 Review and update the
wildland urban interface
(WUI) map
Pending Further analysis to be conducted during WUI code update. 13 Consider the Adoption of
PRC 4290 and 4291
Complete The City considered becoming a Fire Risk Reduction Community (PRC 4290.1) and completing the map of limited egress streets (PRC 4290.5). The City’s ordinance is more restrictive than what is required under PRC 4291; therefore, this action was deemed unnecessary.
14 Develop new resources Ongoing This action was largely addressed by the passage of Measure C, which supports wildfire prevention efforts. However, the City will continue to seek grants and cost recovery for the abatement of private property, and to pursue Measure A wildfire funds through the partnership with the Marin County Open Space District.
15 Seize ignition sources and
remove encampments in
open space
Ongoing The City adopted Chapter 19.50 of the San Rafael Municipal Code to address camping on public property.
16 Reduce the likelihood of
ignition in undeveloped
land
Ongoing Open Space signs have been updated. The San Rafael Municipal Code was updated in 2022 through Ordinance No. 2008. The Red Flag warning processes are outlined. Ongoing education and enforcement are needed. 17 Uniform application of
Chapter 7A building
materials
Pending Chapter 7A of the California Building Code, which addresses building materials and construction for wildfire exposure, is being replaced with Chapter 5 in the new draft California Wildland Urban Interface Code (CWUIC). This will be addressed through the Code update and adoption process.
# Action Summary Status Next Steps/ Notes
18 Eliminate Wood Shake
Roofs
Ongoing In 2022, the Building Code was amended to require the replacement of wood shake roofs by May of 2027. Grants are available to support property owners with the costs of replacing their shake roofs.
19 Vegetation mapping and
risk analysis
Ongoing The Marin County Community Wildfire Protection Plan (CWPP) is scheduled for an update in 2026, which will include an updated analysis. 20 Analysis of fire roads and
fuel breaks
In Progress The fire road inventory project is contracted for completion in 2025. Staff are connecting the analysis with the trails plan.
21 Increase hardened homes Ongoing- expanding This effort is supported through ongoing education programs, grants, and property inspections.
22 Vegetation Management
Plans and Resilient
Landscape Templates
Ongoing The Vegetation Management Plans process is streamlined. Resilient Landscape Templates have not been developed in their original concept, as other guidance meets similar needs.
23 Increase inspections Maintenance Stage The entire City was inspected. Staff are entering a three-year return cycle process with options for resident-scheduled visits and continued enforcement inspections.
24 Education via signs In progress New Open Space signs are installed, and the Public Safety Center sign installation is scheduled to be completed by the end of 2025. Red Flag Signs are in progress.
25 Reduce risk in short-term
rentals
Maintenance Stage Short-term rentals must display fire safety and evacuation information for all guests. Owners must also complete and submit annual vegetation selfinspection checklists. 26 Hire additional staff Complete Fixed-term roles have transitioned to regular career positions. Wildfire Mitigation Specialists and Emergency Management Coordinators are in place.
27 Police Ranger Staffing Ongoing The San Rafael Police Department is working to hire adequate Ranger staff. 28 Reduce Fuels along
roadways
Maintenance Stage Primary routes are complete and in ongoing maintenance. 29 Parking Box Program Ongoing The City plans to complete installation in all hillside areas by the end of 2025.
30 Improve Alerting Ongoing Purchased portable long-range acoustic devices (LRADs). The County Alert system has been upgraded, and a draft MOA is in place.
# Action Summary Status Next Steps/ Notes
31 Increase early warning and
detection
Complete Cameras were installed on San Rafael Hill and San Pedro Hill. 32 Evacuation Plans and
Drills
Ongoing Publish Fireclear Maps. Continue to host neighborhood drills and safety fairs.
33 Assure Safe and resilient
infrastructure
Maintenance Stage Vegetation is maintained along fire roads, cell phone towers, fire stations, and water towers.
34 Assure staff can send and
receive alerts
Maintenance Stage The City maintains a third-party vendor and has a redundant MOU with the County and its Duty officer. Training is ongoing to ensure an adequate number of people are trained.
35 Assure staff can
communicate
Maintenance Stage Staff work to ensure communication redundancies and offer training and drills to enhance preparedness.
36 Garage Door Battery BackUpOngoing Power failures, impacting the functionality of automatic garage doors, can make evacuation by car impossible during an emergency. Residents are offered grants and education to address this concern.
37 Dual gate requirement to
prevent entrapment
Not started The action recommends updating the Building Code to require new and replacement fences to have two gates. Further analysis is required to determine the benefit and feasibility of this program.
38 Agency Coordination and
Collaboration
Ongoing Staff meet regularly with partners and seek ways to develop collaborative projects and share best practices.