CITY OF SANTA ANA FY 23/24CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The Bristol Street Improvements project was planned and designed to incorporate complete street concepts with storm drain quality features. The improvements include widening of the street from four lanes to six lanes, with bus turnouts, raised median, bike lanes, and sound walls. The project also brings native and organic landscaping that beautifies a fully developed urban area.
PROJECT NEED:
Bristol Street from Civic Center to Washington (Phase 3A) is part of the City's plan to widen Bristol Street from Warner Avenue to Memory Lane, which was approved by City Council in 1990 and reevaluated in 2015. Existing roadway has only 2 lanes in each direction and is operating at a LOS F. This widening is needed to improve traffic flow and create complete streets features.
PROJECT TITLE:
Bristol St Improvements & Widening:
Phase 3A - Civic Center-Washington
PROJECT CATEGORY:
Street Improvements
Street/Bridge Improvements &
Widening
LOCATION MAP
AGENCY: DIVISION: DATE:
Public Works CIP Engineering
CONTACT:
Jason Gabriel, Principal Civil Engineer 20-Feb-2024
PROJECT COSTS FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 Construction 5,444,992 - - - - - -
TOTAL 5,444,992 - - - - - -
SOURCE OF FUNDS FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 MEASURE M2 COMPETITIVE 5,444,992 - - - - - -
TOTAL 5,444,992 - - - - - -
EXHIBIT 3
CITY OF SANTA ANA FY 23/24CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The Bristol Street Improvements project was planned and designed to incorporate complete street concepts with storm water quality features. The improvements include widening of the street from four lanes to six lanes, with bus turnouts, raised median, bike lanes, enhanced storm drain system, and sound walls. The project also brings native and organic landscaping that beautifies a fully developed urban area.
PROJECT NEED:
Bristol Street from Warner Avenue to St. Andrew Place (Phase 4) is part of the City's plan to widen Bristol Street from Warner Avenue to Memory Lane, which was approved by City Council in 1990 and reevaluated in 2015. Existing roadway has only 2 lanes in each direction and is operating at a Level of Service (LOS) F. This widening is needed to improve traffic flow and create complete streets features.
PROJECT TITLE:
Bristol St Improvements & Widening:
Phase 4 - Warner -St Andrew
PROJECT CATEGORY:
Street Improvements
Street/Bridge Improvements &
Widening
LOCATION MAP
AGENCY: DIVISION: DATE:
Public Works CIP Engineering
CONTACT:
Jason Gabriel, Principal Civil Engineer 20-Feb-2024
PROJECT COSTS FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 Construction 12,227,342 - - - - - -
TOTAL 12,227,342 - - - - - -
SOURCE OF FUNDS FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 MEASURE M2 COMPETITIVE 12,227,342 - - - - - -
TOTAL 12,227,342 - - - - - -