TOPIC: Euclid Street Corridor Traffic Signal Synchronization

AGENDA TITLE
Cooperative Agreement with the City of La Habra and Partnering Cities for the Euclid Street Corridor Traffic Signal Synchronization Project (Project 23-6721) (Non-General Fund)

RECOMMENDED ACTION
Authorize the City Manager to execute a cooperative agreement with the Cities of La Habra, Fullerton, Anaheim, Garden Grove, and Fountain Valley, identifying each city’s roles and responsibilities, including Santa Ana’s match requirement of $113,827, for the implementation of the Euclid Street Corridor Traffic Signal Synchronization Project, for a term beginning upon full approval of the agreement by all parties and ending December 31, 2028, with an option for extension upon written agreement by all parties (Agreement No. A-2024-XXX).

GOVERNMENT CODE §84308 APPLIES: Yes

DISCUSSION
On November 16, 2021, the City Council authorized staff to submit joint applications with participating agencies to the Orange County Transportation Authority (OCTA) to request funding consideration for the renewed Measure M2 Regional Traffic Signal Synchronization Program. The cooperative agreement for the Euclid Street Corridor Traffic Signal Synchronization Project (Euclid Street Project) would provide for inter- jurisdictional traffic signal synchronization and improvements along the corridor traversing the cities of Santa Ana, La Habra, Fullerton, Anaheim, Garden Grove, Fountain Valley, and Caltrans (Exhibit 1).

On March 9, 2022, the OCTA Board approved the Measure M2 funding request for the Euclid Street Project. While the City of La Habra will act as the lead agency for the project, a cooperative agreement is necessary to identify the roles and responsibilities of each participating agency to maintain inter-jurisdictional synchronization during the three-year grant period (Exhibit 2). Upon project completion, responsibility for ongoing signal maintenance will revert to the respective local agencies.

Euclid Street Corridor Traffic Signal Synchronization
April 2, 2024

Page 2 ends

4 1
4 1
The Measure M2 grant provides $4,961,013. The match commitments from the participating cities will provide a combined total of $1,240,253. The City of Santa Ana’s share of the matching funds is $113,827, of which $107,827 is cash and $6,000 is in- kind staff support.

FISCAL IMPACT
Funds for the City’s share of the project cost are budgeted and available in the Measure M2 Street Construction Fund (Account No. 03217662-66220; Project No. 23-6721) for expenditure in the fiscal years identified in the following estimated spending plan:

Fiscal Year Accounting
Unit-Account
#
Fund
Description
Accounting Unit,
Account
Description
Amount
2023-24
(April- June
2024
03217662-
66220
Measure M-
Street
Construction
Measure M2 Local
Fairshare St,
Improvements
Other Than
Building
$4,450
2024-25
(July 2024-
June 2025)
03217662-
66220
Measure M-
Street
Construction
Measure M2 Local
Fairshare St,
Improvements
Other Than
Building
$104,217
2025-26
(July 2025-
June 2026)
03217662-
66220
Measure M-
Street
Construction
Measure M2 Local
Fairshare St,
Improvements
Other Than
Building
$5,160
Total: $113,827
The current fiscal year funding is available in the FY 2023-24 budget and future fiscal year funding will be included in the proposed budgets for City Council consideration.

EXHIBIT(S)

1. Project Location Map

2. Cooperative Agreement
Submitted By: Nabil Saba, P.E., Executive Director – Public Works Agency Approved By: Tom Hatch, Interim City Manager