Text extracted from the city's file for reading and search. Open the original on santa-ana.primegov.com. That file is the official record.

Public Works Agency
www.santa-ana.org/public-works
Item # 13
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
April 16, 2024
TOPIC: Clean California Bus Stop Improvement Project

AGENDA TITLE
Appropriation Adjustment and Capital Improvement Project Amendment for the Bus Stop Improvement Project (Project No. 24-6985) (Non-General Fund)

RECOMMENDED ACTION

1.Approve an appropriation adjustment recognizing $398,000 in Clean California Local Grant Program grant funds in the Select Street Construction, State Grant-Direct revenue account, and appropriate the same amount into the Select Street Construction, Improvements Other than Buildings expenditure account. (Requires five affirmative votes)

2.Approve an amendment to the Fiscal Year 2023-24 Capital Improvement Project to include $398,000 of funding to the Bus Stop Improvement Project (Project No. 24- 6985).

GOVERNMENT CODE §84308 APPLIES: No

DISCUSSION
The Clean California Local Grant Program (CCLGP) is a competitive statewide program created to beautify and clean local streets and roads, tribal lands, parks, pathways, transit centers, and other public spaces. A total amount of $114.5 million was made available statewide for projects that reduce waste and debris, install measures to beautify and improve public spaces and mitigate the urban heat island effect, improve public spaces for walking and recreation, and advance equity for underserved communities.

The Public Works Agency submitted a successful application for $398,000 of funding for Orange County Transportation Authority (OCTA) bus stop facility improvements throughout the city (Exhibit 1). This project will provide one new bus shelter, 34 benches, 28 trash bins, two trees, and up to five selected sidewalk repairs. These improvements foster the District Transit Partnership’s primary objective of enhancing the cleanliness and attractiveness of bus stops within the city. The shelter and benches will afford transit users the ability to comfortably sit while waiting for bus arrivals and the new trash bins will decrease the amount of litter and debris at the bus shelters.

Clean California Bus Stop Improvement Plan
April 16, 2024

Page 2 ends

4 1
7 2
The City received a Notice to Proceed on January 8, 2024 in the amount of $398,000 from CCLGP (Exhibit 2). A resolution authorizing the Executive Director of the Public Works Agency (Exhibit 3) to enter into a Restricted Grant Agreement (RGA) with Caltrans was approved on December 19, 2023 (Exhibit 4). The Clean California Local Grant Program (CCLGP) can be applied to projects that beautify and clean local streets and roads, tribal lands, parks, pathways, transit centers, and other public spaces. These funds were granted and can be applied towards our Bus Stop Improvement Project due to the project providing new and improved benches, trashcans, and sidewalk at bus stops within the scope.

ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action. The project will assess the environmental impact for compliance with the California Environmental Quality Act (CEQA).

FISCAL IMPACT
Approval of the appropriation adjustment will recognize the receipt of $398,000 via the Select Street Construction, State Grant-Direct revenue account (No. 05917002-52025) and appropriate to the Select Street Construction, Improvements Other than Buildings, expenditure account (No. 05917660-66220).

The following table summarizes the funds budgeted and available in FY 2023-24 for expenditure to deliver this project. Any remaining balances not expended at the end of the current fiscal year will be presented to the City Council for approval to carry forward to FY 2024-25.

Fiscal
Year
Accounting Unit -
Account No.
(Project No.)
Fund
Description
Accounting Unit, Account
No. Description Amount
Appropriation Adjustment
2023-24 05917660-66220
(24-6985)
Select Street
Construction
Select Street Construction,
Improvements Other Than
Buildings
$398,000
Total $398,000

EXHIBIT(S)

1. CIP Sheet Project 24-6985

2. Clean California Transit Program Notice to Proceed

3. Executed Resolution

4. Executed Restricted Grant Agreement
Submitted By: Nabil Saba, P.E., Executive Director – Public Works Agency Approved By: Alvaro Nuñez, Acting City Manager