TOPIC: Memory Lane and Flower Street Bikeway and Traffic Calming
AGENDA TITLE
Appropriation Adjustment and Capital Improvement Project Amendment for Memory Lane and Flower Street Bikeway and Traffic Calming (Project No. 23-6029)
RECOMMENDED ACTION
1. Approve an appropriation adjustment to recognize Traffic System Management Grant funds in the amount of $450,000 in the State Grant-Direct revenue account, and appropriate the same amount to the Active Transportation Program, Improvements Other than Buildings expenditure account. (Requires five affirmative votes)
2. Approve an amendment to the Fiscal Year 2023-24 Capital Improvement Project to include $450,000 of funding to the Memory Lane and Flower Street Bikeway and Traffic Calming (Project No. 23-6029) ATPL-5063(217).
GOVERNMENT CODE §84308 APPLIES: No
DISCUSSION
The City of Santa Ana received an Active Transportation Program (ATP) grant on January 26, 2024 for a traffic-calming project. This project will include the installation of various traffic calming and traffic safety improvements including rectangular rapid flashing beacons, curb extensions, a new bikeway, new/upgraded wheelchair ramps, raised crosswalks, sidewalks improvements, and median islands (Exhibit 1). The improvements will maintain the current restricted right turn at the intersection (Exhibit 2).
This project was not previously included in the FY 2023-24 Capital Improvement Program (CIP) due to funding being identified after the FY 2023-24 CIP program (Exhibit 3) had been finalized and approved, which is typical. Approval of this action will allow staff to commence work on the design phase for these projects in May 2024.
The United States Department of Transportation has fully executed the Program Supplement Agreement No. A456 (Exhibit 4) for project funding.
Memory Lane and Flower Street Bikeway and Traffic Calming April 16, 2024
4 1
8 5
ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action. The project will assess the environmental impact for compliance with the California Environmental Quality Act (CEQA).
FISCAL IMPACT
Approval of the requested Appropriation Adjustment will recognize Traffic System Management Grant funds in the amount of $450,000 in the State Grant-Direct, revenue account (No. 14817002-52025) and appropriate the same amount to the Active Transportation Program, Improvements Other than Buildings expenditure account (No. 14817613-66220).
With the approval of the amendment to the FY 2023-24 Capital Improvement Program, funds will be assigned, budgeted, and available for expenditure in FY 2023-24. Future phases of these projects will be budgeted in future Capital Improvement Programs.
The following table summarizes the funds budgeted and available for expenditure to deliver this project.
Fiscal
Year
Accounting Unit
- Account No.
(Project No.)
Fund
Description
Accounting Unit,
Account No.
Description
Amount
2023-24 14817613-66220
(23-6029)
Traffic
System
Management
Grant
Active Transportation
Program, Improvements
Other Than Buildings
$450,000
Total $450,000
EXHIBIT(S)
1. Conceptual Plan
2. Location Map
3. CIP Sheet Project 23-6029
4. Program Supplement Agreement No. A456
Submitted By: Nabil Saba, P.E., Executive Director – Public Works Agency Approved By: Alvaro Nuñez, Acting City Manager