CITY OF SANTA ANA FY 23/24CIP

CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:

This project provides for the application of crack seal and slurry seal to various streets citywide with minor coldmill and removal and replacement of asphalt concrete pavement.

PROJECT NEED:

The City's Pavement Management Program has been developed to identify the preventative maintenance requirements for the City's street network. The application of a surface seal to streets with improvements constructed in the last 10 years will ensure a high level of service for years to come.

PROJECT TITLE:

Local Street Preventative
Maintenance
PROJECT CATEGORY:

Street Improvements
Local Street Resurfacing

LOCATION MAP

CITYWIDE
AGENCY: DIVISION: CONTACT:

Public Works CIP Engineering Jason Gabriel, Principal Civil Engineer PROJECT COSTS FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 Construction 2,778,000 2,778,000 2,778,000 2,778,000 2,778,000 2,778,000 2,778,000 Engineering 222,000 222,000 222,000 222,000 222,000 222,000 222,000 TOTAL 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 SOURCE OF FUNDS FY 23/24 FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 M2 LOCAL FAIRSHARE 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 TOTAL 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 3,000,000 27