Construction Contract 4,482,892.00$
Contract Administration, Inspection and Testing 667,108.00$ Contingencies 1,075,000.00$
TOTAL ESTIMATED CONSTRUCTION COSTS 6,225,000.00$
CONSTRUCTION OF PROJECT NO. 22-1341: First Street Slope Stabilization
UPDATED COST ANALYSIS