EXHIBIT 4
Construction Contract 562,868.00 $
Contract Administration, Inspection and Testing 84,430.20$ Contingencies 56,286.80 $
TOTAL ESTIMATED CONSTRUCTION COSTS 703,585.00$
CONSTRUCTION OF PROJECT NO. 23-7539: Traffic Signal Modification at Warner Avenue and Wright Street
COST ANALYSIS