CITY OF SANTA ANA FY 24/25CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Transform the City of Santa Ana Courtyard outside of City Hall into an ADA compliant Public Health Plaza. The project will include ADA enhancements including new pavement and ADA compliant public restrooms.
PROJECT NEED:
The outdoor Public Health Plaza will be utilized for a variety of purposes, including but not limited to the following: host COVID-19 vaccination clinics; staging area for COVID testing; space for health, wellness programming and training; public communication efforts;
community gatherings and meeting space. The Public Health Plaza is located in a HUD designated Qualified Census Tract and is Walking distance to several disadvantaged communities.
PROJECT TITLE:
Civic Center Public Health Plaza
PROJECT CATEGORY:
City & Park Facility Improvements
Facility
LOCATION MAP
AGENCY: DIVISION: DATE:
Public Works CIP Engineering
CONTACT:
Sean Thomas, Principal Civil Engineer 17-Sep-2024
PROJECT COSTS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 Construction 746,928 - - - - - -
Contingency 74,693 - - - - - -
Engineering 62,039 - - - - - -
TOTAL 883,660 - - - - - -
SOURCE OF FUNDS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 ARPA Funds 883,660 - - - - - -
TOTAL 883,660 - - - - - -
EXHIBIT 6