CITY OF SANTA ANA FY 24/25CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
To install and replace security lighting poles with concrete poles and new LED light structures at Angels Park, Centennial Park, and Delhi Park
PROJECT NEED:
Lighting in the parks are in need for improvement to enhance the safety of patrons and support evening activities.
PROJECT TITLE:
Park Lights at Three City Parks
PROJECT CATEGORY:
Utility/Drainage/Lighting
Improvements
Park Facility
LOCATION MAP
AGENCY: DIVISION: CONTACT: DATE:
Public Works Parks, Fleet & Facilities Mike Ortiz, Senior Civil Engineer 13-Nov-2024 PROJECT COSTS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 Construction 1,589,808 - - - - - -
Contingency 158,981 - - - - - -
TOTAL 1,748,789 - - - - - -
SOURCE OF FUNDS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 A & D District 2 298,789 - - - - - -
ARPA Funds 1,450,000 - - - - - -
TOTAL 1,748,789 - - - - - -
EXHIBIT 2