Cities Index.
Staff Report

Santa Ana City Council
January 21, 2025

Document
Staff Report
Meeting
January 21, 2025
Body
Santa Ana City Council
Pages
2
Original file
142 KB
Text extracted from the city's file for reading and search. Open the original on santa-ana.primegov.com. That file is the official record.

Public Works Agency
www.santa-ana.org/pw
Item # 13
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
January 21, 2025
TOPIC: Final Tract Map 2020-01, County Tract Map No. 18178

AGENDA TITLE
Receive and File the Notification by the City Engineer of the Final Tract Map No. 2020- 01, County Tract Map No. 18178 at 1122 North Bewley Street (Applicant: XALT Developments LLC, a California Limited Liability Company) (No Fiscal Impact)

RECOMMENDED ACTION
Receive and file.

GOVERNMENT CODE §84308 APPLIES: No

DISCUSSION
In California, regulation and control of the division of real property is vested in the legislative bodies of local agencies by the Subdivision Map Act. In the City of Santa Ana, the regulations and processes are provided in Chapter 34 and 41 of the Santa Ana Municipal Code (SAMC), which pursuant to Section 34-127, includes the approval of tentative tract maps by the Planning Commission. However, if additional entitlements require approval such as Environmental Review and General Plan Amendment, then the Tentative Tract Map is approved by City Council.

Following the approval of the tentative map by the approving body, the property sub- divider prepares and submits a final map(s) to the City Engineer for approval. If the final map is in the correct form, prescribed by the Subdivision Map Act and Chapters 34 and 41 of the SAMC, and all conditions set forth in the tentative map are met, the final map shall be approved by the City Engineer.

On September 1, 2020, the Santa Ana City Council approved Tentative Tract Map 2020-01 (Orange County Map No. 18178) to allow the proposed subdivision of land into 10 condominium units and the construction of an attached townhome development. The approved tentative tract map (Exhibit 1) allows subdivision of the project site for condominium ownership purposes. The project is nearly fully constructed and the Developer has submitted a final map for approval.

The City Engineer is in the process of reviewing the final tract map (Exhibit 2) for technical accuracy and final approval. This action informs the City Council of the

Final Tract Map 2020-01, County Tract Map No. 18178
January 21, 2025

Page 2 ends

4 7
6 8
imminent approval of the referenced subdivision based upon the Subdivision Map Act and meeting all the conditions of approval set by the City. Pursuant to Section 34-183 of the SAMC, the City Engineer shall approve or disapprove this map within 10 days after the City Council meeting on January 21, 2025.

ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action.

FISCAL IMPACT
There is no fiscal impact associated with this action.

EXHIBIT(S)

1. Tentative Tract Map

2. Final Tract Map
Submitted By: Nabil Saba, P.E., Executive Director – Public Works Agency Approved By: Alvaro Nuñez, City Manager

← All documents from this meeting