EXHIBIT 3
Construction Contract 1,433,200.00$
Contract Administration, Inspection and Testing 221,559.00$ Contingencies 143,320.00$
Additional Contingency (March 4, 2025) 380,000.00$
TOTAL ESTIMATED CONSTRUCTION COSTS 2,178,079.00$
CONSTRUCTION OF PROJECT NO. 22-9001: Legacy Square Transportation Improvements
COST ANALYSIS