CITY OF SANTA ANA FY 24/25CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Reconstruction/resurfacing of existing pavement and
replacement/installation of missing or damaged, curbs, gutters, sidewalks, driveway approaches, and wheelchair ramps within along Civic Center between Shelton Street and Flower Street.
PROJECT NEED:
This segment of roadway has been identified as a high priority by the City's Pavement Management System. The pavement is deteriorating due to weather, age, and heavy usage. Some of the adjacent curbs, gutters, driveway approaches, curb ramps, and sidewalks are also in various states of disrepair and require replacement.
PROJECT TITLE:
Civic Center Rehab: Shelton -
Flower
PROJECT CATEGORY:
Street Improvements
Arterial Street Rehabilitation
LOCATION MAP
AGENCY: DIVISION: CONTACT:
Public Works CIP Engineering Alex Bangean, Senior Civil Engineer PROJECT COSTS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 Engineering 1,286,000 - - - - - -
TOTAL 1,286,000 - - - - - -
SOURCE OF FUNDS FY 24/25 FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 GENERAL FUND 1,286,000 - - - - - -
TOTAL 1,286,000 - - - - - -