PROJECT DESCRIPTION:
The Bristol Specific Plan designated the parcel on the corner of Bristol Street and Tolliver Street as park land. This project will transform approximately
1.25 -acres of vacant, City-owned parcels
into a new neighborhood park. It will include features such as play equipment, adult fitness equipment and a basketball court.
PROJECT NEED:
This project will enhance recreational opportunities for the community.
PROJECT TITLE:
Bristol & Tolliver Park - Basketball
Court
PROJECT CATEGORY:
City & Park Facility Improvements
Park Facility
LOCATION MAP
AGENCY:
DIVISION:
CONTACT:
DATE:
Public Works
Parks, Fleet & Facilities
Mike Ortiz, Deputy PW Director / Parks, Fleet, and
Facilities
11-Jul-2025
PROJECT COSTS
FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
FY 31/32
Construction
291,000
-
-
-
-
-
-
TOTAL
291,000
-
-
-
-
-
-
SOURCE OF FUNDS
FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
FY 31/32
A & D District 4
115,000
-
-
-
-
-
-
CDBG Programs
176,000
-
-
-
-
-
-
TOTAL
291,000
-
-
-
-
-
-