Construction Contract 3,808,800$
Construction Administration 230,000$
75,000$
87,128$
115,000$
176,000$
Contingencies 380,880$
TOTAL ESTIMATED CONSTRUCTION COSTS 4,872,808.00$
CONSTRUCTION OF PROJECT NO. 24-6600: Bristol-Tolliver Street Urban Greening Project
COST ANALYSIS
Inspection
Testing
Basketball Court Change Order (to be performed under existing construction contract)
Remainder of Basketball Court (to be performed by others under separate Federal contract)