CITY OF SANTA ANA FY 25/26CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The project features the installation of a subsurface stormwater infiltration system, catch basin inlets, pre-treatment devices, and Bioretention Basins at the new park at 10th St & Flower St.
PROJECT NEED:
Stormwater infiltration provides multiple benefits, including improving water quality, enhancing local water supplies, and reducing flooding.
PROJECT TITLE:
10th and Flower Stormwater Capture
PROJECT CATEGORY:
Utility/Drainage/Lighting
Improvements
Storm Drain/Water Quality
LOCATION MAP
AGENCY: DIVISION: CONTACT: DATE:
Public Works Construction Engineering Craig Foster, NPDES Manager 1-July-2025 PROJECT COSTS FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32 Construction 600,000 - - - - - -
TOTAL 600,000 - - - - - -
SOURCE OF FUNDS FY 25/26 FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32 MEASURE M2 COMPETITIVE 600,000 - - - - - -
TOTAL 600,000 - - - - - -