CITY OF SANTA ANA

PROPOSAL
PROJECT NO.: 25-6033

TRAFFIC SIGNAL MODIFICATION AT SEGERSTROM AVENUE & RAITT STREET AND

SEGERSTROM AVENUE & FLOWER STREET
PROJECT NO.: 22-6018

PEDESTRIAN HYBRID BEACON INSTALLATION AT EDINGER AVENUE AND

TOWNER STREET

BID PROPOSAL
TO: CITY COUNCIL OF THE CITY OF SANTA ANA
FROM: Elecnor Belco Electric, Inc.

REQUIREMENT:

The undersigned bidder declares that they have carefully examined the location of the proposed work, that they have examined the Contract Documents in its entirety and hereby proposes to furnish all material and do all the work required to complete the said work in accordance with said plans (if any) and the specifications for the unit price(s) or lump sum(s) set forth in the following schedule:

Item Description Qty Unit Unit Price Amount
1 Traffic Signal Modification at 1 LS $ $
Segerstrom Avenue and Raitt 379,702
Street 379,702
Traffic Signal Modification at 1 LS $ $
Segerstrom Avenue and Flower
Street 260,088 260,088
Pedestrian Hybrid Beacon 1 LS $ $
Installation at Edinger Avenue
and Towner Street 225,401 225,401
* Install 2" PVC Conduit 100 LF $ 32 $3,200
5 * Install 3" PVC Conduit 3375| LF $55 $185,625
6 * Install 4" PVC Conduit 820 LF $ g4 $
68,880
7 Install No. 5 Pull Box 1 EA 51, 066 $1,066
8 Install No. 6 Pull Box 21 EA
51,258 $26,418
9 Install No. 6E Pull Box 10 EA $
$1,500 15,000
10 Install N40 Pull Box 1 EA $ $
5,000 5,000
P-1 of P-19

CITY OF SANTA ANA

PROPOSAL
PROJECT NO.: 25-6033

TRAFFIC SIGNAL MODIFICATION AT SEGERSTROM AVENUE & RAITT STREET AND

SEGERSTROM AVENUE & FLOWER STREET
PROJECT NO.: 22-6018

PEDESTRIAN HYBRID BEACON INSTALLATION AT EDINGER AVENUE AND

TOWNER STREET
Item Description Qty Unit Unit Price Amount
IP Communication System 1 LS $ $
34,300 34,300
12 * Install 12 Strand SMFO Cable 350 LF $ $1,050
3 13 * Install 144 Strand SMFO 4075 LF $
Cable 5 $20,375
14 T* Fusion Splice Strands of 144 EA $
SMFO 44 $6,336
15 Fiber Optic Splice Enclosure 3 EA $
1,728 $5,184
16 Signing and Striping 1 LS $47,860 $47,860
17 * Pothole Pole Locations for 16 EA $
Utility Conflicts 1, ISS 18,480
18 Temporary Overhead Wiring 1 LS $ $22,106
22,106
19 PCC Sidewalk (T=4") 250 SF $22.80 $5.700
20 PCC Curb Ramp 250 SF $ $

56.90 14,225
21 CCTV Inspection of Existing 1 LS $ $
ewer Main and Laterals (Pr 10,000 10,000
nd Post Construction
22 Project Advertising Sign(s) 3 EA $ $
1,100 3.300
23 | Construction Permit 1 LS $ 8,000 $8,000
P-2 of P-19

CITY OF SANTA ANA

PROPOSAL
PROJECT NO.: 25-6033

TRAFFIC SIGNAL MODIFICATION AT SEGERSTROM AVENUE & RAITT STREET AND

SEGERSTROM AVENUE & FLOWER STREET
PROJECT NO.: 22-6018

PEDESTRIAN HYBRID BEACON INSTALLATION AT EDINGER AVENUE AND

TOWNER STREET
TOTAL BASE BID- ITEMS 1-23 $ 1,367,296.00

ADD ALTERNATE BID
24 Install GTT Opticom EVP System at 1 TLS $ $
Segerstrom Avenue and Raitt Street 16,266 16,266
Install GTT Opticom EVP System at 1 LS $15,122 $15,122
Segerstrom Avenue and Flower Street
TOTAL ALTERNATE BID - ITEMS 24-25 $ 31,988
The lowest responsible bidder shall be selected based on the total base bid. The City reserves the right to award the Base Bid, and any, all, or none of the add-alternate bid items (if any). * The quantity for this bid item is shown for bid comparison only. This bid item shall not be subject to the "25%" limit as stated in Section 7-3.5 of the Standard Specifications. The actual amount for this item will be dictated by the actual quantity used, and the Agency reserves the right to increase or decrease the quantity of this item accordingly. + This bid item is considered a Specialty Item per Section 3-2 of the Standard Specifications.

TIME FOR COMPLETION OF IMPROVEMENTS AND LIQUIDATED DAMAGES The undersigned bidder hereby proposes to complete the Work for the total base bid amount shown above, within One Hundred Twenty (120) working days after the commencement date stated in the Notice to Proceed. Upon issuance of the Notice to Proceed, Contractor shall immediately place order for long-lead time items (i.e. Traffic Signal Poles, Electrical Meter Pedestal and Fiber Optic Cable). The absolute maximum time of completion of improvement (including time extensions. weather, and material procurement) shall not exceed 365 calendar days.

The liquidated damages amount, in lieu of the amount specified in Subsection 6-9 of the Standard Specifications, shall be $4,200 per calendar day.

Name of Firm Elecnor Belco Electric, Inc.

Signature of BIDDER
all individual co-partners composing the firm. If a corporation, state legal name of corporation, and names of President, Secretary, Treasurer and Manager, thereof.) P-3 of P-19