CITY OF SANTA ANA FY 25/26CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The project features the installation of subsurface stormwater infiltration systems at the Santa Ana Zoo to capture and infiltrate approximately 67 acre-feet per year of stormwater and dry-weather runoff. The project will also include a new urban green space, bioswales, pervious pavement, seating, drought-tolerant landscaping and shade trees, and interpretive signage.
PROJECT NEED:
Stormwater infiltration provides multiple benefits, including improving water quality, enhancing local water supplies, and reducing flooding. The project will also feature a new urban green space in the zoo parking lot, which will provide recreational benefits to the surrounding community.
PROJECT TITLE:
Santa Ana Zoo Stormwater Capture and
Diversion Project
PROJECT CATEGORY:
Utility/Drainage/Lighting Improvements
Park Facility
LOCATION MAP
PROJECT COSTS FY 26/27 FY 27/28 FY 31/32
Construction - - -
TOTAL - - -
SOURCE OF FUNDS FY 26/27 FY 27/28 FY 31/32
Caltrans Cooperative
Implementation Agreement
- - -
TOTAL - - -
AGENCY: DIVISION: CONTACT: DATE:
Public Works Construction Engineering Craig Foster, NPDES Manager 04-Nov-2025