CITY OF SANTA ANA FY
25/26
CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Install new LED lighting at Centennial Park (Fields
5 &
6 , and
Playground).
PROJECT NEED:
The installation of LED lighting will significantly improve visibility for players, coaches, and spectators during evening us, allowing the fields to support extended hours of operation and more programming. The lighting will illuminate a previously dark section of the park and pedestrian walkways.
PROJECT TITLE:
Centennial Park Lighting
PROJECT CATEGORY:
Utility/Drainage/Lighting
Improvements
Park Facility
LOCATION MAP
AGENCY:
DIVISION:
CONTACT:
DATE:
Public Works
Parks, Fleet & Facilities
Mike Ortiz, Deputy PW Director / Parks, Fleet, and
Facilities
12-Jan-2026
PROJECT COSTS
FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
FY 31/32
Construction
1,516,978
-
-
-
-
-
-
TOTAL
1,516,978
-
-
-
-
-
-
SOURCE OF FUNDS
FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
FY 31/32
CAPITAL OUTLAY/CELL
TOWER
186,978
-
-
-
-
-
-
GENERAL FUND
1,330,000
-
-
-
-
-
-
TOTAL
1,516,978
-
-
-
-
-
-