Exhibit 5

Santa Ana City Council
January 20, 2026

Document
Exhibit 5
Meeting
January 20, 2026
Body
Santa Ana City Council
Original file
256 KB
Text extracted from the city's file for reading and search. Open the original on santa-ana.primegov.com. That file is the official record.

FY 25/26 FY 28/29 FY 29/30 FY 30/31
1,389,000 1,500,000 1,500,000 1,500,000
111,000 - - -
1,500,000 1,500,000 1,500,000 1,500,000
FY 25/26 FY 28/29 FY 29/30 FY 30/31
1,500,000 1,500,000 1,500,000 1,500,000
1,500,000 1,500,000 1,500,000 1,500,000

CITYWIDE
AGENCY: DIVISION: CONTACT: DATE:

Public Works CIP Engineering Jason Gabriel, Principal Civil Engineer 11-Dec-2025 TOTAL 1,500,000 1,500,000 1,500,000
SOURCE OF FUNDS FY 26/27 FY 27/28 FY 31/32
GENERAL FUND 1,500,000 1,500,000 1,500,000
TOTAL 1,500,000 1,500,000 1,500,000
PROJECT COSTS FY 26/27 FY 27/28 FY 31/32
Construction 1,500,000 1,500,000 1,500,000
Engineering - - -
CITY OF SANTA ANA FY 25/26CIP

CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:

This project will provide for the removal of existing damaged pavement and reconstruction with Portland Cement Concrete (PCC) for alleys citywide.

PROJECT NEED:

The Citywide network of Portland Cement Concrete (PCC) and asphalt alleys is in extreme state of deterioration with the presence of numerous potholes, cracking, spalling, and uplifting. PCC pavement will eliminate the drainage problems associated with the asphalt pavement and provide a longer life for the alleys.

PROJECT TITLE:

Alley Improvement Program
PROJECT CATEGORY:

Street Improvements
Alley Rehabilitation

LOCATION MAP