FY2025-26 CIP
Project Status Update
Project Type Project Name Project Balance
(As of 01/12/26) Status
Construction
Contract Award
Date
Estimated
Completion or
Construction
Duration
Facilities Car Wash Improvements 286,614 In construction 7/9/2025 12/30/2026 Facilities Computer SW Fueling Station 292,360 In construction 7/1/2025 12/30/2027 Facilities Corporate Yard Facility Maintenance 35,681 Design phase funding only Design Complete 6-9 months Facilities Digital Media Billboard 375,000 Expected to advertise April 2026 Design Complete 2-3 months Facilities Electric Feeder & Panel Upgrades 1,000,000 In construction. 10/16/2025 12/30/2026 Facilities Fire Station 71 Storage Tank 824,365 In construction 2/17/2026 10/31/2026 Facilities Fire Station 74 Storage Tank 1,207,239 In construction 1/20/2026 8/31/2026 Facilities Jail Access Control 131,398 Expected to advertise July 2026 Planning Phase 9-12 months Facilities Law Library Deck Modification 450,210 Design phase funding only; Design 25% complete. Design Phase 9-12 months
Facilities Modernization SA Civic Center 4,492,909 Design phase funding only; Design 25% complete. Planning Phase 9-12 months
Facilities Natural Gas Fueling Station 22,030 Design phase funding only Design Complete 3-6 months Facilities SARTC 2nd & 3rd Floors Restroom 434,686 In construction 10/28/2025 4/30/2026 Facilities Cypress Fire Station 4,066,332 In construction 10/22/2025 11/30/2026 Library Main Library Children's Exhibit 764,807 In construction 12/18/2024 4/1/2026 Library Main Library Park Improvements 584,594 In construction 8/6/2024 7/15/2026 Library Main Library Renovation 15,997,871 In construction 8/6/2024 6/16/2026 Library Newhope Library Windows 179,185 In construction 9/17/2024 3/24/2026 Library Parking Lot Main Library 37,350 In construction 8/6/2024 12/30/2026 Parks 10th And Flower Park 491,586 In construction 10/15/2024 2/9/2026 Parks Bristol Recreation Corridor 274,697 Design phase funding only; Design 95% complete. Design Phase 3-6 months
Parks Centennial Park Restrooms 423,321 In construction 12/9/2024 3/31/2026 Parks Cool Pavement Treatment 200,000 Expected to advertise February 2026 Design Complete 7/31/2026 Parks Corbin Center Improvements 52,026 Design phase funding only; Design 90% complete. Design Phase 6/30/2026
Parks Dog Park @ Centennial 2,281,545 In construction 3/18/2025 3/5/2026 Parks Lillie King Basketball Court 200,000 Expected to advertise February 2026 Design Complete 2-4 months Parks Logan/Chepas Construction 353,290 Design phase funding only; Design 90% complete. Design Phase 3-6 months
Parks Logan/Chepas Park Master Design 166,987 Design phase funding only; Design 100% complete. Design Complete 9-12 months
Parks Memorial Park & Aquatics Facility 17,996,947 In construction 10/15/2024 9/4/2026 Parks Newhope Library Improvements 3,462,010 In construction 9/17/2024 3/24/2026 Parks Park Rehabs 300,000 Expected to advertise July 2026 Design Phase 3-6 months Parks Park Shade Structures 15,000 In construction In-house 6/30/2026 Parks Portola Splash Pads 3,132,646 In construction 1/20/2026 3/31/2027 Parks Santa Ana Zoo Educational Hub 4,567,598 In construction 9/16/2025 12/26/2026 Parks Santa Anita Community Center Renovations 411,445 In construction 7/19/2022 5/31/2026 Parks Santa Anita Phase II 6,805 In construction 7/19/2022 5/31/2026 Parks Santa Anita Pool Renovations 500,000 In construction 1/6/2026 4/30/2026 Parks Santiago Nature Center Renovations 98,356 In construction 6/6/2023 6/30/2026 Parks Santiago Park Trail & Habitat 121,488 Design phase funding only; Design 95% complete. Design Complete 6-9 months
Parks Thornton Lake Renovation 81,738 Expected to advertise July 2026 Design Phase 3-6 months EXHIBIT 3
FY2025-26 CIP
Project Status Update
Project Type Project Name Project Balance
(As of 01/12/26) Status
Construction
Contract Award
Date
Estimated
Completion or
Construction
Duration
Parks Warner-Delhi Linear Park 14,532 Design phase funding only; Design 95% complete. Design Phase 3-6 months
Parks Zoo Ticket Booth Roof 232,105 In construction 9/22/2025 4/13/2026 Parks Zoo Wall 1,220,958 Expected to advertise July 2026. Design Phase 2-3 months Pedestrian Jackson Elem/Diamond Elem SRTS 7,934,689 Expected to advertise December 2028 Design Phase 6-9 months Pedestrian Macarthur Int & Taft Elem SRTS 4,596,146 Expected to advertise June 2027 Design Phase 6-9 months Pedestrian Madison/Roosevelt/Century SRTS 9,726,074 Expected to advertise June 2027 Design Phase 6-9 months Pedestrian Mendez/Ala/Santiago/Siera SRTS 9,752,994 Expected to advertise December 2028 Design Phase 6-9 months Pedestrian Peebler (S. Main) 759,129 In construction 7/19/2022 12/1/2026 Pedestrian Santa Ana HS & Heninger Elementary SRTS 7,873,638 Expected to advertise December 2028 Design Phase 6-9 months Pedestrian Santiago Creek Pedestrian Bridge 677,590 Design phase funding only; Design 5% complete. Design Phase 6-9 months
Roadways Neighborhood Streetlights 1,268,870 Expected to advertise April 2026 Design Phase 6-9 months Roadways Orange Ave Complete Streets 844,958 Expected to advertise June 2027 Design Phase 6-9 months Roadways Walnut Street Urban Greening 1,964,058 Expected to advertise July 2026 Design Phase 6-9 months Streets 10Th And Flower Street 364,539 In construction 10/15/2024 2/27/2026 Streets 17th St Rehab Cabrillo Pk to City Limits 398,532 Design phase funding only. Design 10% complete. In Design 3-6 months
Streets 17Th St Rehab Grand- Cabrillo 809,581 Design phase funding only. Design 15% complete. In Design 3-6 months
Streets Alley Improvement Program 1,500,000 In construction 1/20/2026 6/30/2026 Streets Alley Improvements Program FY 24/25 60,031 In construction 1/26/2026 3/31/2026 Streets Bristol St & Memory Ln Intersection Widening 2,170,068 In construction 2/17/2026 8/30/2026 Streets Bristol St Rehab: Santa Clara-Memory 1,477,012 In construction 6/3/2025 2/26/2026 Streets Bristol Widening: Civic Center- Washington
Phase IIIA 3,134,545 In construction 9/17/2024 5/11/2026 Streets Bristol Widening-Warner/St Andrew Phase IV 22,452,118 In construction 3/4/2025 11/30/2026 Streets Bristol-Tolliver Street 176,300 In construction 2/26/2026 3/30/2026 Streets Broadway Rehab: Bishop To First St 133,364 Design phase funding only. Design 5% complete. Design Phase 3-6 months
Streets Broadway St Rehab 17th- Main Place 302,859 Design phase funding only. Design 5% complete. Design Phase 3-6 months
Streets Business Area Road Improvement 1,500,000 Expected to advertise January 2026 Design Complete 2-3 months Streets Cedar Street Improvements 415,655 Expected to advertise June 2026 Design Phase 2-3 months Streets Croddy Way Street Improvements 897,000 Expected to advertise March 2026 Design Phase 3-6 months Streets Dyer Rd Rehab: Main To Grand 595,100 Expected to advertise March 2027 Design Phase 3-6 months Streets Dyer Street Improvement 2,971,122 Expected to advertise March 2028 Design Phase 6-9 months Streets Euclid Rehab: City Limit-McFadden 11,233 Expected to advertise February 2027 Design Phase 6-9 months Streets Euclid Rehab: McFadden To First St - Expected to advertise February 2027 Design Phase 6-9 months Streets Euclid St Rehab: 1St To Hazard 3,515 Expected to advertise February 2027 Design Phase 6-9 months Streets Fairview Ave Rehab: City Limits-Alton 6,155,333 Expected to award March 2026 Design Complete 7/30/2026 Streets Fairview Bridge & Street Improvements 4,828,952 Design phase funding only; Design 95% complete. Design Phase 12-18 months
Streets Fairview St Improvements: 17th To Trask 6,921,100 Expected to advertise August 2027 Right-of-Way Phase 9-12 months
Streets Fifth Rehab Fairview To Raitt 150,000 Expected to advertise August 2027 Design Phase 3-6 months FY2025-26 CIP
Project Status Update
Project Type Project Name Project Balance
(As of 01/12/26) Status
Construction
Contract Award
Date
Estimated
Completion or
Construction
Duration
Streets First St Rehab Grand To Tustin 2,779,186 Expected to advertise February 2027 Design Phase 3-6 months Streets First St Rehab: Grand To Tustin 822,004 Expected to advertise February 2027 Design Phase 3-6 months Streets First St Traffic Safety Corridor - Expected to advertise October 2026 Design Phase 3-6 months Streets Grand Av Rehab: Edinger-McFadden 2,274,838 Expected to award March 2026 Design Complete 7/31/2026 Streets Grand Ave Rehab First St-Santa Ana 2,972,300 Expected to advertise June 2026 Design Phase 3-6 months Streets Industrial St Repair FY23/24 2,197,906 Expected to advertise February 2026 Design Complete 3-6 months Streets Industrial St Repair Pro 24/25 2,479,361 Expected to advertise February 2026 Design Complete 3-6 months Streets Industrial St Repair Program 2,857,801 Expected to advertise February 2026 Design Complete 3-6 months Streets Local St Preventative Maintenance 277,687 Expected to advertise April 2026 Design Phase 6-9 months Streets Macarthur Rehab Harbor-Fairview - Expected to advertise August 2027 Design Phase 3-6 months Streets MacArthur Rehab: Fairview-Raitt 818,135 Expected to advertise August 2026 Design Phase 12/31/2027 Streets Main Rehab Edgewood-Memory Ln 269,586 Design phase funding only; Design 20% complete. Design Phase 3-6 months
Streets McFadden Rehab Fairview - Raitt 847,005 In construction 9/17/2024 6/31/26 Streets McFadden Rehab Harbor-Fairview 756,716 In construction 9/17/2024 6/31/26 Streets McFadden Rehab Raitt To Grand 835,201 In construction 9/17/2024 6/31/26 Streets Memory Ln & Mainplace Dr 690,000 Expected to advertise August 2027 Design Phase 3-6 months Streets Raitt St Rehab Cc-Washington 2,609,580 Expected to advertise February 2026 Design Phase 6-9 months Streets Raitt St Rehab: McFadden-First 4,388,228 Expected to advertise February 2026 Design Phase 6-9 months Streets Santa Ana Grade Separation 75,000 Expected to advertise March 2028 Design Phase 18-24 months Streets Standard Avenue Widening 969,043 Design phase funding only; Design 5% complete. Design Phase 9-12 months
Streets Warner Ave Improvements Phase 2-Oak-Grand 20,690,659 Expected to advertise February 2026 Design Complete 12-18 months Streets Warner Ave Widening: Main-Oak Phase I 4,875,238 In construction 3/16/2021 6/30/2026 Traffic Safety Bristol Corridor Regional Traffic 3,574,926 Expected to advertise February 2026 Design Complete 3-6 months Traffic Safety Bristol St Bike Lanes: First to Civic Center 1,265,718 Expected to advertise November 2026 Design Phase 3-6 months Traffic Safety Flower & Macarthur Left Turn Signal 250,000 Expected to advertise February 2026 Design Complete 1-3 months Traffic Safety Grand Ave Traffic Signal Synchronization 5,710,514 Construction to begin June 2026 9/16/2025 6-9 months Traffic Safety High Visibility Marked Crosswalk Improvements - Expected to advertise May 2026 Design Phase 6-9 months Traffic Safety McFadden Ave Transit Signal 2,179,222 In construction 7/1/2025 2/6/2026 Traffic Safety McFadden Protected Bike Lane Harbor-Grand 6,507,633 In construction 9/17/2024 6/26/2026 Traffic Safety Raitt St Protected & Buff Bikeway 85,403 Expected to advertise February 2026 Design Phase 6-9 months Traffic Safety Seger/Raitt Traffic Signal 1,279,311 In construction 11/4/2025 6/9/2026 Traffic Safety Segerstrom/Spruce Traffic Signal 613,464 In construction 10/1/2024 2/20/2026 Traffic Safety Signal Installation Segerstrom & Rosewood 1,114,409 In construction 1/21/2025 4/17/2026 Traffic Safety Standard Ave Prot Bk Ln: 3-War 539,901 In construction 9/17/2024 6/26/2026 Traffic Safety Traffic Calming FY 23/24 288,181 In construction 9/23/2024 2/28/2027 Traffic Safety Traffic Calming: Memory & Flower 896,438 Expected to advertise March 2026 Design Phase 6-9 months Traffic Safety Warner Protected Bike Lane: Oak-Grand 1,129,991 Expected to advertise February 2026 Design Complete 12-18 months Utility Bristol Water Main Improvements-Phase 4 3,146,154 In construction 2/24/2025 12/31/2026 Utility 10Th & Flower Stormwater Capture 600,000 In award phase. Anticipated award in March 2026. Design Complete 6-9 months
Utility Bristol Phase 3A Water 1,300,143 In construction 2/24/2025 6/30/2026 Utility Bristol-Tolliver St Urban Greening 1,290,861 In construction 3/18/2025 4/1/2026 Utility Citywide Facilities PFAS Improvements 6,000,000 In construction 11/4/2025 12/30/2033 FY2025-26 CIP
Project Status Update
Project Type Project Name Project Balance
(As of 01/12/26) Status
Construction
Contract Award
Date
Estimated
Completion or
Construction
Duration
Utility Fairhaven Neighborhood Sewer Improvements 299,831 Design phase funding only; Design 15% complete. Design Phase 2-4 months
Utility Fire Hydrant Improvements 600,000 In construction 11/4/2025 9/30/2027 Utility Hazard Ave Sewer Improvements 300,000 Expected to advertise June 2026 Design Complete 2-4 months Utility Lacy Neighborhood Water Improvements 273,507 Design phase funding only; Design 70% complete. Design Phase 2-4 months
Utility Large Water Services Vault & Meter 2,400,000 In construction 11/4/2025 12 monhts Utility Maxine Sewer Lift Station Improvements 500,000 Design phase funding only; Design 15% complete. Design Phase 9-12 months
Utility Memorial Neighborhood Sewer Main
Improvements 335,175 Design phase funding only; Design 15% complete. Design Phase 3-6 months
Utility Rene Dr Sewer Improvements 665,809 Design phase funding only; Design 50% complete. Design Phase 2-4 months
Utility Rousselle St Flood Protection 494,340 In construction 1/21/2025 4/26/2026 Utility SA-1 Hydrogenerator Upgrade 299,000 In construction Design Complete 12/30/2028 Utility Warner Ave Flood Protection 1,020,886 Expected to advertise February 2026 Design Phase 6-9 months Utility Washington Square Sewer Main Improvements 1,403,609 Design phase funding only; Design 90% complete. Design Phase 3-6 months
Utility Washington Well Site Improvements 3,070,440 In construction 7/18/2023 2/28/2027 Utility Well 29 Improvements 376,564 In construction 9/20/2022 3/30/2026 Utility Wright St Sewer Main Improvements 3,775,477 Expected to advertise July 2026 Design Complete 3-6 months Utility Zoo Stormwater Capture & Diversion 4,679,049 In construction 12/2/2025 3/31/2027