PROJECT DESCRIPTION:
The project features the construction of a new park and includes site preparation, grading, and construction of park improvements such as walking paths, landscaped areas, irrigation systems, lighting, and related amenities.
PROJECT NEED:
The project addresses the need for additional neighborhood park space by improving access to recreational amenities, enhancing neighborhood livability, and activating an underutilized site.
PROJECT TITLE:
10 th and Flower Park
PROJECT CATEGORY:
City & Park Facility Improvements
Park Facility
LOCATION MAP
AGENCY:
DIVISION:
CONTACT:
DATE:
Public Works
Parks, Fleet & Facilities
Mike Ortiz, Deputy PW Director / Parks, Fleet, and
Facilities
20-Mar-2026
PROJECT COSTS
FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
FY 31/32
Construction
3,749,580
-
-
-
-
-
-
Contingency
464,958
-
-
-
-
-
-
Engineering
697,437
-
-
-
-
-
-
TOTAL
4,911,975
-
-
-
-
-
-
SOURCE OF FUNDS
FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
FY 31/32
A & D District 2
2,661,975
-
-
-
-
-
-
LAND & WATER
CONSERVATION GRNT
2,250,000
-
-
-
-
-
-
TOTAL