CITY OF SANTA ANA FY
25/26
CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
The project features the installation of a subsurface stormwater infiltration system, catch basin inlets, pre-treatment devices, and Bioretention Basins at the new park at
10 th St & Flower St.
PROJECT NEED:
Stormwater infiltration provides multiple benefits, including improving water quality, enhancing local water supplies, and reducing flooding.
PROJECT TITLE:
10 th and Flower Park Stormwater
Capture
PROJECT CATEGORY:
Utility/Drainage/Lighting
Improvements
Storm Drain/Water Quality
LOCATION MAP
AGENCY:
DIVISION:
CONTACT:
DATE:
Public Works
Construction Engineering
Craig Foster, NPDES Manager
20-Mar-2026
PROJECT COSTS
FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
FY 31/32
Construction
900,000
-
-
-
-
-
-
TOTAL
900,000
-
-
-
-
-
-
SOURCE OF FUNDS
FY 25/26
FY 26/27
FY 27/28
FY 28/29
FY 29/30
FY 30/31
FY 31/32
FED CLEAN WATER
300,000
-
-
-
-
-
-
MEASURE M2 COMPETITIVE
600,000
-
-
-
-
-
-
TOTAL
900,000
-
-
-
-
-
-