Text extracted from the city's file for reading and search. Open the original on santa-ana.primegov.com. That file is the official record.

Public Works Agency
www.santa-ana.org/pw
Item # 14
City of Santa Ana
20 Civic Center Plaza, Santa Ana, CA 92701
Staff Report
July 21, 2026
TOPIC: Construction Materials Testing and Special Inspection Services

AGENDA TITLE
Agreements with AESCO, Inc., Kleinfelder Inc., Koury Engineering & Testing, Inc., and Twining, Inc. for Construction Materials Testing and Special Inspection Services (General Fund & Non-General Fund)

RECOMMENDED ACTION

1. Authorize the City Manager to execute federally procured agreements with AESCO, Inc., Kleinfelder Inc., Koury Engineering & Testing, Inc., and Twining, Inc. to provide on-call materials testing and special inspections services for a shared annual amount of $800,000, for a term beginning July 21, 2026 and expiring July 20, 2027, with provisions for four, one-year extensions in a total aggregate amount not to exceed $4,000,000. (Agreement Nos. A-2026-XXX)

2. Authorize the City Manager to execute agreements with AESCO, Inc., Kleinfelder Inc., Koury Engineering & Testing, Inc., and Twining, Inc. to provide on-call materials testing and special inspections services for shared annual amount of $800,000, for a term beginning July 21, 2026 and expiring July 20, 2027, with provisions for four, one-year extensions in a total aggregate amount not to exceed $4,000,000. (Agreement Nos. A-2026-XXX)
GOVERNMENT CODE §84308 APPLIES: Yes

DISCUSSION
The Public Works Agency (PWA) is responsible for the administration and oversight of all Capital Improvement Projects in the City. PWA manages various types of construction projects, including street pavement rehabilitation, traffic signal installations, underground utilities, building improvements, bridges, and park facilities. These projects require independent materials testing and special inspections to verify compliance with approved plans, specifications, and applicable building and engineering standards.

Special inspections are required for certain types of construction activities such as welding and fire proofing.

Construction Materials Testing and Special Inspection Services July 21, 2026

Page 2 ends

5 8
9 8
The volume and technical specialization of these services exceed available in-house resources and, in many cases, require certified third-party testing and inspection.

Having specialized firms available on an as-needed basis to support the City’s construction management team is necessary to keep projects on schedule. The current agreements in place for these services expired on July 5, 2026 with an average annual expenditure of $800,000.

Staff recommends retaining testing and inspection firms to provide on-call quality assurance services during the construction of CIP projects. The selected firms will provide on-call testing and inspections that include code-required inspection of structural steel, concrete placement, masonry, welding, reinforcing steel, soils, asphalt, and other construction activities to verify compliance with applicable engineering and building standards.

Staff recommends procuring two separate sets of agreements, Federal and Non- Federal, to provide flexibility in administering projects funded through different sources.

Federally funded projects require consultants to comply with specific federal regulations and procurement requirements that typically result in higher costs. Maintaining both sets of agreements allows the City to assign work based on project funding requirements, ensure regulatory compliance, obtain best pricing, and streamline project delivery while minimizing procurement timelines and administrative costs.

Request for Proposals (RFP) No. 26-059A was issued on May 1, 2026 on the City’s online bid management and publication system.

A summary of vendor participation and results is as follows:

1,041
1 52
11 0
Vendors notified
Santa Ana vendor notified
Vendors downloaded the RFP packet
Responsive proposals received
Responsive proposals received from Santa Ana vendors
Proposals were solicited, opened on May 21, 2026, and evaluated. Eleven proposals were submitted by the RFP deadline and were determined to be responsive to the specifications and met the City’s requirements. An evaluation committee reviewed and rated the proposals according to the criteria listed in the RFP. Based on the evaluation criteria established in the RFP, the following firms received the highest overall scores:

RANK BIDDER’S NAME LOCATION
1 Kleinfelder, Inc. Ontario, CA
2 Koury Engineering & Testing, Inc. Chino, CA
3 Twining, Inc. Long Beach, CA
4 AESCO Huntington Beach, CA
Construction Materials Testing and Special Inspection Services July 21, 2026

Page 3 ends

5 8
9 8
Staff recommends awarding agreements to AESCO, Kleinfelder Inc., Koury Engineering & Testing, Inc., and Twining, Inc. (Exhibits 1 - 8), as the four firms achieved the highest overall scores and were determined to be the most qualified firms. The selected firms demonstrated extensive experience with public works construction projects, strong technical capabilities, qualified personnel, familiarity with Federal and Caltrans requirements, and the capacity to respond to multiple concurrent assignments.

Materials testing and inspection requests occur simultaneously on multiple projects and often require rapid response. Staff recommends multiple on-call firms to ensure adequate capacity, maintain project schedules, and allow work to be assigned based on consultant availability, expertise, and workload. Awarding agreements to four qualified firms will provide the City with sufficient capacity to support multiple concurrent construction projects, maintain project schedules, ensure compliance with applicable construction standards, and deliver quality assurance services in a timely and cost- effective manner.

ENVIRONMENTAL IMPACT
There is no environmental impact associated with this action.

FISCAL IMPACT
There is no fiscal impact at this time. These on-call agreements establish contractual authority only. Funding for individual task orders is approved by City Council through the annual operating and capital budgets, or other Council-approved budget actions when approving agreements, as applicable. Prior to utilizing any of these on-call services, Public Works Agency staff must obtain approval from the Finance and Management Services Agency (FMSA) by submitting a Notice to Proceed Request. This request must specify the funding source and the required dollar amount. FMSA will verify that the necessary funds are encumbered and available within the authorization and aggregate limits of these agreements. Once approved, PWA will issue a Notice to Proceed to the vendor detailing the specific scope of work and the maximum expenditure for the task.

EXHIBIT(S)

1. Agreement with AESCO – Caltrans Version

2. Agreement with Kleinfedler Inc. – Caltrans Version

3. Agreement with Koury Engineering & Testing, Inc. – Caltrans Version

4. Agreement with Twining, Inc. – Caltrans Version

5. Agreement with AESCO

6. Agreement with Kleinfedler Inc.

7. Agreement with Koury Engineering & Testing, Inc.

8. Agreement with Twining, Inc.

Submitted By: Rodolfo Rosas, P.E., Acting Executive Director, Public Works Agency Approved By: Alvaro Nuñez, City Manager