CITY OF SANTA ANA FY 26/27CIP
CAPITAL IMPROVEMENT PROJECT WORKSHEET
PROJECT DESCRIPTION:
Construction of bikeway, ADA compliant sidewalks, curb ramps, bulb-outs (curb extensions), raised medians/crosswalks, traffic signal modification and channelization on Memory Lane and Flower Street.
PROJECT NEED:
The City of Santa Ana and City of Orange designed to increase bicyclist and pedestrian safety and mobility.
PROJECT TITLE:
Memory Lane and Flower Street
Bikeway
PROJECT CATEGORY:
Traffic Improvements
Street/Bridge Improvements &
Widening
LOCATION MAP
AGENCY: DIVISION: CONTACT: DATE:
Public Works CIP Engineering Gilbert Castillo, Senior Engineer 11-Aug-2026 PROJECT COSTS FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32 FY 32/33 Construction 4,806,808 - - - - - -
Contingency 480,681 - - - - - -
Engineering 721,021 - - - - - -
TOTAL 6,008,510 - - - - - -
SOURCE OF FUNDS FY 26/27 FY 27/28 FY 28/29 FY 29/30 FY 30/31 FY 31/32 FY 32/33 ATP 4,550,000 - - - - - -
GENERAL FUND 775,473 - - - - - -
RMRA SB1 683,037 - - - - - -
TOTAL 6,008,510 - - - - - -
Exhibit 5