CONDITIONS OF TENTATIVE PARCEL MAP APPROVAL
2302 Calle Del Mundo (PLN21-15122)
In addition to complying with all applicable codes, regulations, ordinances and resolutions, the following conditions of approval are recommended:

CONDITIONS OF APPROVAL
In addition to complying with all applicable codes, regulations, ordinances and resolutions, the following conditions of approval are recommended:

GENERAL
If relocation of an existing public facility becomes necessary due to a conflict with the developer's new improvements, then the cost of said relocation shall be borne by the developer.

Comply with all applicable codes, regulations, ordinances and resolutions.

ATTORNEY’S OFFICE
The Developer agrees to defend and indemnify and hold City, its officers, agents, employees, officials and representatives free and harmless from and against any and all claims, losses, damages, attorneys' fees, injuries, costs, and liabilities arising from any suit for damages or for equitable or injunctive relief which is filed by a third party against the City by reason of its approval of developer's project.

COMMUNITY DEVELOPMENT
The project shall comply with all conditions of approval for the approved project under the Planning records, PLN2021-14878 and PLN2019-00987.

Developer shall submit to the City Covenants, Conditions and Restrictions (CC&Rs) or equivalent prior to building permit final. Said document shall be recorded along with the Title for each property with the Santa Clara County Recorder’s Office.

ENGINEERING
Obtain site clearance through Public Works Department prior to issuance of Building Permit. Site clearance will require payment of applicable development fees. Other requirements may be identified for compliance during the site clearance process. Contact Public Works Department at (408) 615-3000 for further information.

All work within the public right-of-way and/or public easement, which is to be performed by the Developer/Owner, the general contractor, and all subcontractors shall be included within a Single Encroachment Permit issued by the City Public Works Department. Issuance of the Encroachment Permit and payment of all appropriate fees shall be completed prior to commencement of work, and all work under the permit shall be completed prior to issuance of occupancy permit.

Submit public improvement plans prepared in accordance with City Public Works Department procedures which provide for the installation of public improvements. Plans shall be prepared by a Registered Civil Engineer and approved by the City Engineer prior to approval and recordation of parcel map and/or issuance of building permits.

Existing non-standard or non-ADA compliant frontage improvements shall be replaced with current City standard frontage improvements as directed by the City Engineer or his designee.

Dedicate, as required, on-site easements for new and existing utilities and paseo by Subdivision Map or approved instrument at time of development. Developer shall pay applicable easement preparation/processing fee.

Dedicate a sidewalk easement for the sidewalk and driveway portions within private property and pay the easement preparation fee. Sidewalk easement shall be 1’ behind proposed back-of-walk if there is landscaping behind sidewalk and/or at the proposed back-of-walk with a cold joint if there is hardscape concrete behind sidewalk.

Obtain Council approval of a resolution ordering vacation of existing public easement(s) proposed to be abandoned, if any, through Public Works Department, and pay all appropriate fees, prior to start of construction After City Council approval of the Tentative Map, submit 10 copies of the Subdivision Map, prepared by a Licensed Land Surveyor or a Registered Civil Engineer with Land Surveyor privileges to the Engineering Department. The submittal shall include a title report, closure calculations, and all appropriate fees. 2302 Calle Del Mundo – Vesting Tentative Parcel Map Conditions of Approval PAGE \* MERGEFORMAT 3 of 2