Attachment No. 2
Bid Summary
CE 20-21-09 (P3 & P4) PUBLIC RIGHT-OF-WAY ADA
IMPROVEMENTS - PACKAGE 3 & 4 PROJECT
BID SUMMARY*
Bid Opening Date: November 17, 2022
ENGINEER’S ESTIMATE:
$ 4,892,000.00
Contractor
Total Bid ($)
Percentage above/below
Engineer’s Estimate
FBD Vanguard Construction, Inc.
$ 3,847,733.50
21.3% below
Sposeto Engineering, Inc.
$ 3,933,593.85
19.6% below
J.J.R. Construction, Inc.
$ 4,380,568.43
10.4% below