City of Santa Clara
Attachment 1
Bid Summary
22-1463
REPORT TO COUNCIL
SUBJECT
Action on Award of Contract for the Citywide Emergency Generator Replacement Phase 2 Project (CE 20-21-10)
BID SUMMARY Bid Opening Date: December 22, 2022
ENGINEER’S ESTIMATE: $ 3,582,000
Contractor Total Bid ($) Percentage above/below
Engineer’s Estimate
Redwood Engineering Construction $2,739,000.00 -24%
ADC Construction Management $3,839,001.00 7%
Rosendin $5,439,642.00 52%