Cities Index.
Proposed Amendment No. 1 to Deposit Agreement with Mission College

City Council and Authorities Concurrent
March 21, 2023

Document
Proposed Amendment No. 1 to Deposit Agreement with Mission College
Meeting
March 21, 2023
Body
City Council and Authorities Concurrent
Original file
261 KB
Text extracted from the city's file for reading and search. Open the original on santaclara.legistar1.com. That file is the official record.

Amendment No. 1 to Agreement/West Valley – Mission Community College District Page 1 Rev. 10/25/19

AMENDMENT NO. 1

TO THE DEPOSIT AGREEMENT

BETWEEN THE

CITY OF SANTA CLARA, CALIFORNIA,
AND
WEST VALLEY – MISSION COMMUNITY COLLEGE DISTRICT

PREAMBLE
This agreement (“Amendment No. 1”) is entered into between the City of Santa Clara, California, a chartered California municipal corporation (City) and West Valley - Mission Community College District, a California Public Community College, (Customer). City and Customer may be referred to individually as a “Party” or collectively as the “Parties” or the “Parties to this Agreement.”

RECITALS
A. The Parties previously entered into an agreement entitled “Deposit Agreement Between the City of Santa Clara, California and West Valley – Mission Community College District”, dated March 28, 2022 (Agreement); B. The Parties entered into the Agreement for the purpose of having Customer pay a deposit related to the Services (as defined in the Agreement) for the project described in Exhibit A of the Agreement, as amended herein; and C. The Parties now wish to amend the Agreement to update the costs due to increase in costs of equipment provided by manufacturer.

NOW, THEREFORE, the Parties agree as follows:

AMENDMENT TERMS AND CONDITIONS

1. The first sentence of Section II of the Agreement is amended to read as follows:
“Customer agrees to deposit $504,000 (Deposit) with the City.”

2. Exhibit A of the Agreement, entitled “Scope of Work and Cost Estimate” is amended and replaced with Exhibit A – Scope of Work and Cost Estimate – Amended December 1, 2022:

3. Except as set forth herein, all other terms and conditions of the Agreement shall remain in full force and effect. In case of a conflict in the terms of the Agreement and this Amendment No. 1, the provisions of this Amendment No. 1 shall control.

DocuSign Envelope ID: D1982E18-C39E-4E0E-8216-F49C7FD0DFF4 Amendment No. 1 to Agreement/ West Valley - Mission Community College District Page 2 Rev. 10/25/2019
T
he Parties acknowledge and accept the terms and conditions of this Amendment No. 1 as evidenced by the following signatures of their duly authorized representatives.

CITY OF SANTA CLARA, CALIFORNIA
a chartered California municipal corporation
Approved as to Form: Dated:

Office of the City Attorney
City of Santa Clara
Office of the City Manager
City of Santa Clara
1500 Warburton Avenue
Santa Clara, CA 95050
Telephone: (408) 615-2210
Fax: (408) 241-6771
“CITY”
WEST VALLEY – MISSION COMMUNITY COLLEGE DISTRICT
a California Public Community College
Dated:

By (Signature):

Name: Brad Davis
Title: Chancellor
Principal Place of
Business Address:
1400 Fruitvale Ave.

Saratoga, CA 95070
Telephone: (408) 741-2421
“CUSTOMER”
DocuSign Envelope ID: D1982E18-C39E-4E0E-8216-F49C7FD0DFF4 2/7/2023

Amendment No. 1 to Agreement/ West Valley - Mission Community College District Page 3 Rev. 10/25/2019

DEPOSIT AGREEMENT BETWEEN

THE CITY OF SANTA CLARA, CALIFORNIA AND

WEST VALLEY - MISSION COMMUNITY COLLEGE DISTRICT
EXHIBIT A - SCOPE OF WORK AND COST ESTIMATE –
AMENDED DECEMBER 1, 2022
Project Description

SVP must complete system upgrades in order to accommodate Customer’s Distributed Energy Resource (DER) system. Mission College has an existing 1.12 MW Photovoltaic (PV) capacity. In addition to the existing PV Capacity, Customer will interconnect and operate a new 2.5 MW PV with 2MW/4MWH battery energy storage in parallel operation with SVP’s distribution system.

Scope
The scope of work to be performed by SVP includes the purchase and installation by SVP personnel of equipment identified as system upgrades necessary to interconnect the Customer’s system to Silicon Valley Power’s distribution system. This scope does not require SVP to acquire any easements or permits on the behalf of the customer.

Cost Estimate

The Preliminary estimation of costs below includes interconnection and/or system upgrades required to interconnect the Customer’s system to Silicon Valley Power’s distribution system, but does not include any generation facilities constructed, owned and operated by the Customer. The below costs are estimates using average cost without actual field verification.

Interconnection
Requirements
Customer
Cost
Notes
Fiber Installation $29,000 Includes staff labor. Engineering by Fiber group, construction by SVP Fiber Group
T&D Installation $8,000 Includes staff labor. Engineering by SVP, SVP system support, SVP Transmission and
Distribution crew to construct
Vacuum Disconnect
Switch
$270,000 Equipment procurement from Innovative
Switchgear
Programming $37,000 Performed by Eaton/innovative Switchgear Acceptance Testing
and Commissioning
$17,000 Acceptance and commissioning cost performed
by Eaton/Innovative Switchgear
Metering Upgrades $3,000 Cost of new metering
Testing and
Commissioning
$20,000 SVP Engineering
DocuSign Envelope ID: D1982E18-C39E-4E0E-8216-F49C7FD0DFF4 Amendment No. 1 to Agreement/ West Valley - Mission Community College District Page 4 Rev. 10/25/2019
Interconnection
Requirements
Customer
Cost
Notes
Sub total $384,000
25% Contingency $96,000
5% Contribution in lieu $24,000
Total Cost $504,000

DocuSign Envelope ID: D1982E18-C39E-4E0E-8216-F49C7FD0DFF4