BID SUMMARY
ENGINEER’S ESTIMATE:
Contractor Total Bid ($) Percentage
above/below
Engineer’s Estimate
Henkels & McCoy West $398,859.31 1.7%
Hotline Construction Inc. $917,086.00 134.0%
Rising Edge Group $933,431.28 138.1%
$ 392,000.00
Page 1 of 1 ends
City of Santa Clara
Attachment No. 1
Bid Summary
23-119
REPORT TO COUNCIL
SUBJECT
Action on Award of Contract for the Freedom Circle Junction Cut-In Transmission Line Extension Project Contract No. 2451 to Henkels & McKoy West Bid Opening Date: August 24, 2023