2023 Integrated Resource Plan

Silicon Valley Power (SVP)

DRAFT 2023

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com Respectfully Submitted,
Nathan Lee
Energy and Environmental Economics, Inc. (E3)
44 Montgomery Street, Suite 1500
San Francisco, CA 94104

© DRAFT 2023 Energy & Environmental Economics, Inc.

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com Table of Contents
Table of Figures  _______________________________________________________________  i Acronym Definitions  __________________________________________________________   v

1.  Executive Summary  ______________________________________________________   1

2.  Introduction ____________________________________________________________   7

2.1.  Silicon Valley Power ___________________________________________________________  7

2.2.  State Laws, Policy, and Regulations _______________________________________________  7

2.3.  Relevant State Legislation and Executive Orders ____________________________________  8

2.4.  Federal Legislation  ___________________________________________________________  10

2.5.  CEC IRP Guidelines  ___________________________________________________________  10

2.6.  Public Stakeholder Engagement_________________________________________________  14

2.7.  The Integrated Resource Planning Process ________________________________________  15

3.  Energy and Demand Forecast  _____________________________________________  17

3.1.  Historic Energy Use and Demand ________________________________________________  17

3.2.  Demand Forecast Methodology and Assumptions __________________________________  17

4.  Existing and Planned System and Resources  _________________________________  21

4.1.  Existing Resources and System Description  _______________________________________  21

4.2.  Existing and Planned Resources _________________________________________________  22

4.3.  Description of Santa Clara Owned and Contracted Resources _________________________  26

4.4.  Northern California Power Agency (NCPA) Resources _______________________________  29

4.5.  M‐S‐R Resources _____________________________________________________________  31

4.6.  Renewable Energy Strategy ____________________________________________________  31

4.7.  Transmission and Distribution System Assets and Adequacy  _________________________  32

4.8.  Natural Gas Commodity, Transportation and Storage _______________________________  34

4.9.  Wholesale Energy Trading  _____________________________________________________  35

5.  Customer Programs, Energy Efficiency and Demand Response Resources __________  36

5.1.  Energy Efficiency Program Background ___________________________________________  36

5.2.  Current Energy Efficiency and Building Electrification Initiatives  ______________________  37

5.3.  Storage _____________________________________________________________________  44

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com

5.4.  Transportation Electrification  __________________________________________________  48

6.  SVP System Modeling Approach ___________________________________________  60

6.1.  PLEXOS LT Overview __________________________________________________________  60

6.2.  Objective Function  ___________________________________________________________  60

6.3.  SVP System Representation ____________________________________________________  61

6.4.  Model Constraints ____________________________________________________________  63

6.5.  Capacity Expansion Model Configuration _________________________________________  71

6.6.  Scenarios and Sensitivities Considered ___________________________________________  72

6.7.  Model Inputs ________________________________________________________________  73

6.8.  Model Outputs  ______________________________________________________________  75

7.  Portfolio Expansion Resource Options  ______________________________________  76

7.1.  Candidate Resource Assumptions _______________________________________________  76

7.2.  Candidate Resource Costs  _____________________________________________________  82

7.3.  Reliability Requirement Assumptions ____________________________________________  86

7.4.  Fuel Prices __________________________________________________________________  86

7.5.  Transmission ________________________________________________________________  88

8.  Results and Discussion ___________________________________________________   90

8.1.  Scenario 1: Base SB 100  _______________________________________________________  90

8.2.  Scenario 2: Accelerated SB 100  _________________________________________________  96

8.3.  Scenario 3: Zero Emissions with Emerging Technology  _____________________________  101

8.4.  Scenario Comparison  ________________________________________________________  107

8.5.  Sensitivity: Geothermal Limitations and Hydrogen Challenges _______________________  111

8.6.  Challenges Ahead to Meet IRP Goals ____________________________________________  114

8.7.  Potential Impacts on Retail Rates  ______________________________________________  116

8.8.  Consideration of Localized Air Pollutants and Disadvantaged Communities ____________  117

9.  Conclusions ___________________________________________________________   120 Appendix A.  SVP Community Survey Summary  ________________________________  121 Appendix B.  Energy Demand _______________________________________________  129 A.1.  Energy Use and Demand ______________________________________________________  129 Appendix C.  Hydrogen Price Forecasts  _______________________________________  133 Appendix D.  Standardized Tables  ___________________________________________  135

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com  i Table of Figures
Figure ES‐1. Silicon Valley Power IRP Scenarios ............................................................................................ 1 Figure ES‐2. Base Scenario Cumulative New Build Capacity ......................................................................... 2 Figure ES‐3. Scenario Comparison – 2035 Total Capacity ............................................................................. 3 Figure ES‐4. Scenario Comparison – 2035 Annual Cost Relative to Base Scenario (2022 $MM) ................. 4 Figure 1. Summary of CEC IRP Filing Requirements .................................................................................... 12 Figure 2. Core Objectives of SVP’s IRP ........................................................................................................ 16 Figure 3. SVP Customer Mix by Retail Sales in 2022 ................................................................................... 17 Figure 4. SVP Baseline Energy Demand Forecast (GWh) ............................................................................ 18 Figure 5. Reference Scenario Annual Electricity Demand and Demand Modifier Impacts (GWh) ............. 18 Figure 6: Total Annual Electricity Demand ‐ Reference Scenario ............................................................... 19 Figure 7. Hourly Demand Profile Components ........................................................................................... 20 Figure 8. SVP Generation Portfolio Mix by Technology, 2022 .................................................................... 22 Figure 9. SVP Existing and Planned Resource Portfolio, 2024‐2035 ........................................................... 23 Figure 10. SVP’s Resource Portfolio in 2023 ............................................................................................... 23 Figure 11. SVP’s Current Power Resource Locations (Owned and Contracted) ......................................... 25 Figure 12. SVP’s Planned Resource Additions in Future Years ................................................................... 25 Figure 13. Planned Resource Retirements .................................................................................................. 26 Figure 14. Current approved SVP Transmission Projects ............................................................................ 34 Figure 15. Forecasted Energy Efficiency Potential ...................................................................................... 37 Figure 16. Lithium Price ($/lbs) 2019‐2023 ................................................................................................. 45 Figure 17. New Zero Emission Vehicle Sales by year: Santa Clara .............................................................. 51 Figure 18. CVRP Rebate Dollars in SVP Service Territory by year ............................................................... 52 Figure 19. Cumulative SVP ZEV Rebates by ZEV Type, 2011‐2018 ............................................................. 52 Figure 20. CEC Projected EV Adoption (cumulative) ................................................................................... 53 Figure 21. Forecasted Plug‐in Vehicles and Charging Requirements, Cumulative – Santa Clara ............... 54 Figure 22. Current Charger Port Installations by Type and Ownership ...................................................... 54

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com  ii Figure 23. Map of PEV known Chargers within Santa Clara ....................................................................... 55 Figure 24. EV Charger Distributions by Santa Clara Zip Codes ................................................................... 56 Figure 25. Utility Risks and Opportunities from PEV Adoption .................................................................. 57 Figure 26. Overview of the PLEXOS LT Model ............................................................................................. 60 Figure 27. Objective Function of Capacity Expansion Problem .................................................................. 61 Figure 28. Simplified Topology for Capacity Expansion Model ................................................................... 61 Figure 29. CAISO Market Average Annual Price Forecast, $/MWh ............................................................ 62 Figure 30. Schematic of the Marginal Reliability Planning Process ............................................................ 65 Figure 31. Marginal ELCCs by Resource Type from the CPUC 38MMT Scenario ........................................ 67 Figure 32. Existing and Planned Resource Marginal ELCC and SVP’s Reliability Need, 2026‐35 ................ 68 Figure 33. RPS (Green) and CES (Blue) Compliance Targets ....................................................................... 69 Figure 34. CAISO Average Annual Emissions Factor and Carbon Price ....................................................... 70 Figure 35. Modeling Parameters that Vary by Scenario or Sensitivity ....................................................... 72 Figure 36. Key Model Outputs .................................................................................................................... 75 Figure 37. SVP Candidate Renewable Resources Mapping to CPUC Aggregation ...................................... 76 Figure 38. Candidate Renewable Resource Options ................................................................................... 77 Figure 39. Candidate Solar Monthly Capacity Factor ................................................................................. 78 Figure 40. Candidate Wind Monthly Capacity Factor ................................................................................. 79 Figure 41. Candidate Storage Resource Options ........................................................................................ 80 Figure 42. Candidate Thermal Resource Options ....................................................................................... 80 Figure 43. Candidate Thermal Operating Parameters ................................................................................ 80 Figure 44. Emerging Technology Resource Options ................................................................................... 82 Figure 45. Emerging Technology Operating Parameters ............................................................................ 82 Figure 46. Candidate Thermal Resource Levelized Fixed Costs, 2022 $/kW‐yr .......................................... 84 Figure 47. Levelized Cost of Electricity by Candidate Renewable Technology, 2022 $/MWh.................... 84 Figure 48 Candidate Storage Resource Levelized Fixed Costs, 2022 $/kW‐yr ............................................ 85 Figure 49. Candidate Emerging Technology Levelized Fixed Cost, 2022 $/kW‐yr ...................................... 85 Figure 50. Fuels Included in the SVP IRP Model ......................................................................................... 86

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com  iii Figure 51. Natural Gas Price Forecast, 2022 $/MMBtu .............................................................................. 87 Figure 52. Hydrogen Price Forecast, 2022 $/MMBtu ................................................................................. 87 Figure 53. TAC Forecast, 2022 $/MWh ....................................................................................................... 88 Figure 54. Transmission Deliverability Costs, 2022 $/kW‐yr ...................................................................... 89 Figure 55. Base Scenario Cumulative New Build Capacity .......................................................................... 91 Figure 56. Base Scenario Total Capacity ..................................................................................................... 91 Figure 57. Base Scenario Annual Generation .............................................................................................. 92 Figure 58. Base Scenario Annual Energy Balance of Loads and Resources ................................................ 93 Figure 59. Base Scenario Marginal Reliability Need and Marginal Effective Capacity ............................... 94 Figure 60. Base Scenario Marginal Reliability Need and Resource Capacity Accreditation ....................... 95 Figure 61. Accelerated SB 100 Scenario Cumulative New Build Capacity .................................................. 96 Figure 62. Accelerated SB 100 Scenario Total Capacity .............................................................................. 97 Figure 63. Accelerated SB 100 Scenario Annual Generation ...................................................................... 97 Figure 64. Accelerated SB 100 Scenario Annual Energy Balance of Loads and Resources ......................... 98 Figure 65. Accelerated SB 100 Scenario Marginal Reliability Need and Marginal Effective Capacity ........ 99 Figure  66.  Accelerated  SB  100  Scenario  Marginal  Reliability  Need  and  Resource  Capacity  Accreditation .................................................................................................................................................................. 100 Figure 67. Zero Emissions Scenario Cumulative New Build Capacity ....................................................... 102 Figure 68. Zero Emissions Scenario Total Capacity ................................................................................... 102 Figure 69. Zero Emissions Scenario Annual Generation ........................................................................... 103 Figure 70. Zero Emissions Scenario Annual Energy Balance of Loads and Resources .............................. 104 Figure 71. Zero Emissions Scenario Marginal Reliability Need and Marginal Effective Capacity ............. 105 Figure 72. Zero Emissions Scenario Marginal Reliability Need and Resource Capacity Accreditation ..... 106 Figure 73. Scenario Comparison – 2030 Cumulative New Build Capacity ................................................ 107 Figure 74. Scenario Comparison – 2035 Cumulative New Build Capacity ................................................ 108 Figure 75. Scenario Comparison – 2035 Total Capacity ............................................................................ 109 Figure 76. Scenario Comparison – 2035 Annual Generation .................................................................... 109 Figure 77. Scenario Comparison – 2035 Annual CO2 Emission ................................................................. 110 Figure 78. Scenario Comparison – 2035 Annual Cost Relative to Base Scenario (2022 $MM) ................ 111

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com  iv Figure 79. Hydrogen Sensitivity Cumulative New Build Capacity ............................................................. 112 Figure 80. Hydrogen Sensitivity Total Capacity......................................................................................... 112 Figure 81. Hydrogen Sensitivity Annual Generation ................................................................................. 113 Figure 82. Hydrogen Sensitivity Marginal Reliability Need and Marginal Effective Capacity ................... 114 Figure 83. Estimated Retail Rates Impacts ................................................................................................ 117 Figure 84. Disadvantaged Communities within SVP’s Service Territory ................................................... 119 Figure 85. Total Annual Electricity Demand by Scenario (GWh) .............................................................. 129 Figure 86. Annual Energy Efficiency Impact on Electricity Demand by Scenario (GWh) .......................... 130 Figure 87. Annual Building Electrification Impact on Electricity Demand by Scenario (GWh) ................. 130 Figure 88. Annual Transportation Electrification Impact on Demand by Scenario (GWh) ....................... 131 Figure 89. Total Annual Electricity Demand by Scenario .......................................................................... 132 Figure 90. Hourly Demand Profile Components ....................................................................................... 132 Figure 91. Electrolyzer Costs for Producing Hydrogen and SNG ............................................................... 133 Figure 92. Hydrogen Price Forecast .......................................................................................................... 134

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com  v Acronym Definitions
Acronym  Definition
AAEE  additional achievable energy efficiency
AAFS  annual achievable fuel substitution
AB  assembly bill
ATB  (NREL) annual technology baseline
BESS  battery energy storage system
CAISO  California Independent System Operator
CARB  California Air Resources Board
CCGT  combined cycle gas turbine
CCS  carbon capture and storage
CCWD  Calaveras County Water District
CDWR  California Department of Water Resources
CEC  California Energy Commission
CES  clean energy standard
COTP  California‐Oregon Transmission Project
CPUC  California Public Utilities Commission
CRAT  capacity resource accounting table
CT  combustion turbine
CVP  Central Valley Project
CVRP  clean vehicle rebate project
DCFC  Direct Current Fast Charger
DER  distributed energy resource
DMV  Department Of Motor Vehicles
DVR  Don Von Raesfeld Power Plant
EBT  energy balance table
ELCC  effective load carrying capability
EV  electric vehicle
FERC  Federal Energy Regulatory Commission
FO&M  fixed operation and maintenance
GEAT  GHG emissions accounting table
GHG  greenhouse gas
HVAC  heating, ventilation, and air conditioning
I&A  (CPUC IRP) inputs & assumptions
IEPR  Integrated Energy Policy Report
IRA  Inflation Reduction Act
IRP  integrated resource plan
ITC  Investment Tax Credit
LCFS  low carbon fuel standard

415.391.5100 | 44 Montgomery Street, Suite 1500, San Francisco, CA 94104 | www.ethree.com  vi LCOE  levelized cost of energy
LEC  Lodi Energy Center
LFC  levelized fixed cost
LOLE  loss of load expectation
LSE  load serving entity
LT  (PLEXOS) long‐term model
M‐S‐R PPA  M‐S‐R Public Power Agency
NCPA  Northern California Power Agency
NREL  National Renewable Energy Laboratory
PBC  Public Benefits Charge
PCC  portfolio content categories
PEV  plug‐in electric vehicle
PG&E  Pacific Gas and Electric Company
POU  publicly‐owned utility
PPA  power purchase agreement
PRM  planning reserve margin
PTC  Production Tax Credit
PUC  public utilities code
PV  photovoltaic
RA  resource adequacy
REC  renewable energy credit
RNG  renewable natural gas
RPS  renewable portfolio standard
RPT  RPS procurement table
SB  senate bill
SMR  small modular reactor
SVP  Silicon Valley Power
TAC  transmission access charge
TANC  Transmission Agency of Northern California
VO&M  variable operations & maintenance
WAPA  Western Area Power Administration
ZEV  zero‐emission vehicle

2023 Integrated Resource Plan      1

1.  Executive Summary
The  2023  Integrated  Resource  Plan  (IRP)  serves  as  a  long‐term  comprehensive  roadmap  to  continue Silicon  Valley  Power’s  long‐standing  focus  on  providing  customers  with  affordable  and  reliable  service while meeting State and local goals for greenhouse gas emissions reduction. The IRP provides a framework showing how Silicon Valley Power continues its transition away from carbon‐emitting resources towards 100% clean energy resources such as wind, geothermal, hydrogen, hydro‐electric, and solar. This aligns with  Silicon  Valley  Power’s  greenhouse  gas  emission  reduction  targets  and  is  in  accordance  with  the State’s policy goals required by Senate Bill 350 and Senate Bill 100, including the requirement to update its IRP no less than once every five years. The IRP includes the results of data modeling of customer energy demands  balanced  against  reliability,  sustainability,  and  affordability  goals  to  develop  a  least‐cost portfolio of resources to meet the needs of Santa Clara ratepayers.

Silicon  Valley  Power’s  2023  IRP  process  commenced  in  2023  with  customer  outreach  efforts,  which indicated that over 75% of the respondents were satisfied with SVP service and that the top concerns are reliability and affordability. On affordability, the respondents would be willing to pay 10‐25% more on their monthly electric bill to achieve clean energy goals faster. These community outreach efforts and directives from the City of Santa Clara set the direction for the current planning process.

In this IRP, Silicon Valley Power presents three scenarios developed using least‐cost optimization, all of which  meet  or  exceed  the  State’s  emission  and  reliability  requirements.  The  base  portfolio  meets  the California Air Resources Board’s base targets for Silicon Valley Power and Senate Bill 100 target of 60% renewable energy in 2030, using mature renewable technologies (those commercially available today).

The second portfolio moves forward the Senate Bill 100 renewable energy and zero‐carbon generation targets for 2045 to 2035, requires a minimum of 70% carbon‐free energy (60% renewable) in 2030 and 100% carbon free by 2035, and is limited to mature technology options. The third portfolio achieves a zero‐carbon emissions portfolio across all hours of the year and explores the use of emerging technologies (such as biogas, hydrogen, and natural gas with carbon capture and storage) to achieve that goal. In each potential portfolio, the power supply mix will continue Silicon Valley Power’s transition away from carbon‐ based generation, which has already reduced by approximately 50% its carbon emissions per kWh of retail sales since 2017. Figure ES‐1 presents the three scenarios explored in this IRP.

Figure ES‐1. Silicon Valley Power IRP Scenarios
Scenario 1:  Scenario 2:  Scenario 3:

Base SB 100  Accelerated SB 100  Zero Emissions with
Emerging Technology
Figure  ES‐2  shows  the  cumulative  resource  additions  through  2035  in  Scenario  1:  Base  SB  100  (Base Scenario). In early years there is an addition of wind, solar and storage to meet load growth and reliability requirements. Starting in 2028, geothermal becomes available and is added to the system in addition to wind capacity as it can provide both clean energy and firm capacity. The baseload operating characteristics of geothermal also align with the relatively high 80% load factor of the SVP system. By 2035, the total Executive Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   2
cumulative resource additions include 290 MW geothermal, 590 MW wind, 150 MW solar, and 110 MW storage capacity to meet load growth and clean energy requirements.

Figure ES‐2. Base Scenario Cumulative New Build Capacity

Note: Capacity additions begin in 2026
Figure ES‐3 presents the total capacity of the three scenarios in 2035, and although similar there are some key differences in the portfolios.

While the three scenarios have similar resource additions in the near‐term, the scenarios diverge towards the  end  of  the  planning  horizon  as  more  aggressive  clean  energy  targets  are  applied  in  Scenario  2:

Accelerated  SB  100  (Accelerated  SB  100  Scenario)  and  Scenario  3:  Zero  Emissions  with  Emerging Technology (Zero Emissions Scenario). The Accelerated SB 100 Scenario, which must meet a higher clean energy  requirement  in  2035  than  the  Base  Scenario  results  in  additional  renewable  capacity  including geothermal  wind,  and  solar,  and  a  larger  total  installed  capacity.  The  2035  total  capacity  of  the  Zero Emissions Scenario is similar to the Base Scenario,  but less than the Accelerated SB 100 Scenario as it includes the zero‐emission fuel conversion of existing gas resources and other emerging technologies. The emerging technologies, such as building new hydrogen plants and converting existing gas plants to burn on hydrogen or biogas, modeled in this IRP offer both clean and “firm capacity” attributes and significantly reduces  the  potential  for  “overbuilding”  of  existing  mature  technologies  like  solar,  wind,  and  battery storage.

Executive Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   3
Figure ES‐3. Scenario Comparison – 2035 Total Capacity

Meeting reliability needs is also a critical component of utility integrated resource planning. All scenarios considered  in  this  IRP  achieve  and/or  exceed  SVP’s  reliability  requirements,  following  the  “marginal reliability need” long‐term planning approach adopted by the California Public Utility Commission for its load serving entities, using marginal ELCC accreditation for all resource types.1 Regarding the annual modeled cost compared to the Base Scenario, which reaches $250 million (2022 $; TAC costs and non‐modeled system costs are excluded) in 2035, the annual modeled cost increases by about $25 million (2022 $) in the Accelerated SB 100 Scenario and increases by $55 million (2022 $) in the Zero Emissions Scenario. (Figure ES‐4). These costs only represent the cost components modeled and do not represent SVP’s total revenue requirement.2 When other forecasted system costs (e.g., TAC and non‐ modeled  costs)  are  included  and  spread  out  over  retail  sales,  the  estimated  2035  retail  rate  in  the Accelerated  SB  100  Scenario  and  Zero  Emissions  Scenario  is  about  1%  and  3%  higher  than  the  Base Scenario. However, it is important to note that there are large uncertainties in the availability and cost of emerging  technologies  and  zero‐emission  fuels  by  2035.  As  discussed  above,  without  the  clean  firm emerging technologies modeled in this study, achieving zero emissions with only commercially available resources will likely require significant additional resources to maintain reliability, which could result in a higher  system  cost.  Furthermore,  the  cost  of  converting  some  of  the  existing  gas  resources  to  zero‐ emission fuels is potentially optimistic here due to uncertainties in conversion technologies and limited

1 SVP is not a jurisdictional load serving entity subject the California Public Utility Commission. However, as the approach for long‐term resource adequacy requirements and the availability of future input data for SVP (PRM, resource accreditation, etc.) remain uncertain with shifts to new approaches, SVP opted to follow the long‐term planning method for system reliability needs consistent with the Public Utility Commission’s approach for its jurisdictional load serving entities. See Section 6.4 for further details on this approach.
2 Resulting costs are impacted by the inputs and assumptions to the model (such as resource cost forecasts, fuel prices, and load forecasts, among others). The inputs and assumptions were the best available data at the time of the modeling for this IRP.

Executive Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   4
data availability at the time of this IRP study. Resource cost and availability uncertainties can have large impacts on the resulting portfolio and system costs, and they should be monitored by SVP in future IRPs.

Figure ES‐4. Scenario Comparison – 2035 Annual Cost Relative to Base Scenario (2022 $MM)

Note: Annual modeled cost includes the operational cost of existing/planned capacity, the capital cost, and operational cost of new build capacity. Capital and fixed costs (including PPA cost) of existing/planned capacity, and transmission and distribution costs are not included.

Challenges Ahead to Meet SVP’s IRP Goals
Through studying Scenario 1: Base SB 100 (Base Scenario), which meets the current state policies, and two additional scenarios with more aggressive clean energy requirements in this IRP, multiple challenges are identified as SVP continues to provide affordable, clean, and reliable power to its growing customer load.
 SVP’s  load,  primarily  data  center  load,  is  expected  to  grow  substantially  throughout  the planning horizon. The forecasted annual load in 2035 almost doubles the current system load, and  significant  resource  additions  are  needed  to  meet  this  growing  load.  Also,  unlike  other utilities, SVP’s current and forecasted load is dominated by industrial (datacenter) load, which has a high load factor (or average load divided by peak load) of 80%, meaning that the system demand is relatively constant and there is less ability to shape loads to take advantage of certain resource production, such as low‐cost solar. Therefore, SVP’s future portfolio requires both clean resources and firm resources that can ensure there is enough energy to meet system load in all hours.  SVP  will  need  clean  firm  resources,  such  as  geothermal,  to  meet  future  needs  in  a  deep decarbonized system. SVP faces a common challenge of deeply decarbonized systems, which is the ability to provide power reliably without firm dispatchable (emitting) thermal plants. Clean

Executive Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   5
firm  resources  not  only  provide  clean  energy,  but  also  firm  capacity  to  help  ensure  system reliability.  The  clean,  firm,  and  baseload  characteristics  of  geothermal  align  well  with  SVP’s forecasted load growth and load shape and could provide a key clean firm option.  Competition for limited resources in California can add difficulties for SVP to procure some of cost‐effective resources for its system. For example, only a limited amount, about 3,400 MW, of geothermal  may  be  available  to  California.  Furthermore,  the  CPUC  Mid‐Term  Reliability  order requires CPUC‐jurisdictional LSEs to procure approximately 1,000 MW long lead‐time clean firm resources by 2028, and geothermal is one of the best available candidates to meet that order. An assumption of this IRP is that SVP may not be able to procure that 1,000 MW tranche. SVP would then be limited to a maximum of about 350 MW, which is approximately 15% of the remaining potential. The three scenarios in this IRP build to, or slightly below that limit. However, with the recent IRA including additional incentives for geothermal resources, and with all LSEs in California transitioning to a cleaner portfolio, there is a growing need for clean and firm resources, further driving  competition  for  limited  resources,  such  as  geothermal,  and  adding  challenges  (and potentially costs) to cost‐effective resource procurement.  SVP faces uncertainties in project delivery timelines. To keep pace with near‐term load growth to  2030  and  longer‐term  load  growth  and  policy  objectives,  SVP  will  need  to  bring  significant quantities of new resources online over the next several years. As development for new resources in California increases to unprecedented rates, SVP may face challenges including, but not limited to supply chain delays, labor shortage, as well as permitting and lengthy interconnection queue processes.  To  build  and  begin  utilizing  new  resources,  the  cost  and  schedule  uncertainty  of  a complex, multi‐step, multi‐year interconnection process can significantly complicate other parts of the development process, including financing and project costs.  There  are  uncertainties  in  long‐term  resource  cost  forecasts.  This  IRP  uses  the  long‐term resource cost forecast from the industry standard public data source, the NREL Annual Technology Baseline (ATB). However, recent market trends have shown that international trade policies and supply  chain  issues  can  significantly  impact  resource  costs  during  procurement.  Furthermore, market  competition  and  developer  profit  markup  are  difficult  to  forecast  and  model  but  do influence resource costs. While many cost uncertainties are not explicitly studied in this IRP, they can  impact  the  resulting  portfolio  choices  and  system  costs.  SVP  should  continue  to  monitor resource costs in future IRPs and resource procurement activities.  Achieving  zero  emission  in  every  hour  will  likely  require  a  combination  of  commercially available resources and new emerging technologies to be cost‐effective and affordable. To meet the  hourly  zero‐emission  target,  all  generation  needs  come  from  renewable,  carbon‐free resources,  and/or  market  purchases  (also  when  market  emissions  are  zero)  in  every  hour.  If Executive Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   6
emerging technologies and emerging zero‐emission fuels are not available, SVP would need to add much higher amounts of existing commercially available technologies, such as solar, wind, and battery storage resources. The total nameplate capacity of those resources is likely higher than  the  system  load  and  the  three  scenarios  presented  here.  Because  they  have  low  and marginally decreasing reliability value, more capacity is needed to cover the most critical hours, even though there might be high curtailment occurring in other normal and/or low load hours.

The  emerging  technologies,  such  as  building  new  hydrogen  plants  and  converting  existing  gas plants to burn on hydrogen or biogas, modeled in this IRP offer both clean and “firm capacity” attributes, and reduces the potential for “overbuilding” existing mature technologies.  There  are  large  uncertainties  and  risks  in  emerging  technologies.  The  emerging  technologies modeled in this IRP are developed based on various assumptions and limited data. Many of the emerging technologies are still in their research and development and/or piloting phases, and it is  difficult  to  predict  when  they  will  be  commercially  available  at  scale.  Additionally,  some emerging technologies, such as green hydrogen, require significant infrastructure development, such  as  electrolyzers,  renewables  for  electrolyzers,  pipelines,  and  storage.  The  costs  and infrastructure  required  to  support  emerging  technologies  are  uncertain  and  can  impact  the resulting  portfolio  feasibility  and  cost.  The  development  of  emerging  technologies  should continue to be monitored and studied by SVP in future IRPs and resource procurement.  SVP’s transmission capabilities with CAISO can have an impact on how much emission reduction SVP can achieve. DVR and Gianera are the only two resources, both natural gas plants, located within SVP’s local zone. When trying to meet more aggressive clean energy goals and reduce gas generation,  the  local  resources’  roles  and  SVP’s  transmission  capabilities  with  CAISO  become important. If the local resources cannot be dispatched to meet SVP’s load, all system load must be met with energy delivered via the transmission line from CAISO. However, the existing and planned transmission capacity may not always be sufficient to cover SVP’s forecasted peak load.

In this IRP, it is assumed that local resources would be able to run on emerging zero‐emission fuel and can be dispatched in Scenario 3: Zero Emissions with Emerging Technology, but SVP should continue to study system transmission capabilities and the clean transition of local resources in future IRPs.
2023 Integrated Resource Plan      7

2. Introduction

2.1. Silicon Valley Power
The City of Santa Clara (Santa Clara) is a charter California city located at the southern end of the San Francisco Bay. Since 1896 Santa Clara, currently under the name Silicon Valley Power (SVP), has provided all electric service within an area coterminous with the city’s boundaries.

SVP  is  a  fully  vertically  integrated  municipal  owned  (or  publicly  owned)  utility  (POU)  that  provides  all aspects  of  electric  services  including  generation,  transmission,  and  distribution  facilities.  SVP  also purchases  power  and  transmission  services  from  other  providers  and  participates  in  the  California Independent System Operator (CAISO) market. SVP, as a department of Santa Clara, is under the direction of the Chief Electric Utility Officer, who is appointed by and reports to the Santa Clara City Manager. The Santa Clara City Council fulfills the role of a rate making and policy decision board.

SVP  has  procured  renewable  energy  for  multiple  decades  in  the  form  of  wind,  hydro‐electric  and geothermal generation prior to the establishment of any Renewable Portfolio Standard (RPS) mandates.

SVP continues to make demonstrable progress towards meeting the Senate Bill (SB) 350 long‐term RPS procurement  mandates,  meeting  California’s  Resource  Adequacy  (RA)  mandates  and  providing  energy efficiency and electrification rebates within Santa Clara’s boundaries. SVP has installed over 147 public and  fleet  electric  vehicle  (EV)  charging  stations  within  Santa  Clara.  In  addition,  the  city  has  adopted building  codes  that  surpass  the  requirements  of  California  Title  24  to  facilitate  more  building electrification and EV charging infrastructure at the time of new construction.

Since 2018, SVP reduced its annual greenhouse gas (GHG) emissions by approximately 50%, primarily by divesting from all coal generation and certain natural gas generation.

SVP also maintains affordable electric rates relative to other California load serving entities (LSEs) and a robust  discount  program  for  income‐limited  residents.  Lower  rates  have  been  an  economic  driver  for development within Santa Clara, creating a unique customer base with a significant share of large‐ high‐ technology manufacturing and data management facilities. These facilities and other industrial customers accounted for over 90% of SVP’s customer mix, by retail sales, in 2021.

SVP  maintains  investment  grade  credit  ratings  from  Fitch  and  S&P,  which  has  made  SVP  a  desirable counterparty for generation companies.

2.2. State Laws, Policy, and Regulations
This section details the various California laws and regulations passed in recent years that apply to POU’s such as SVP. Although SVP adheres to the guidelines of the California Energy Commission (CEC) as well as the requirements of SB 350 and Public Utilities Code (PUC) 9621, additional laws, policies and regulations also impact long‐term planning conducted by SVP.

Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   8
SB 350, the Clean Energy and Pollution Reduction Act, signed in 2015, required POUs with a three‐year (2013‐2016) average annual energy requirement of greater than 700 GWh to file an initial IRP consistent with PUC 9621 with the CEC in 2019, to then be updated at least once every five years. This IRP, SVP’s first update to the 2019 IRP must be approved by the POU (the Santa Clara City Council) by January 1, 2024, and filed with the CEC by April 30, 2024.

PUC 9621 established several targets that impact future resource additions. These include:
 Meet  the  GHG  emissions  reduction  targets  established  by  the  California  Air  Resources  Board (CARB), in coordination with the CEC, for the electricity sector and each public utility that reflect the  sector’s  share  in  achieving  the  economy  wide  GHG  emissions  reduction  of  40%  GHG  from 1990 levels by 2030.
 Achieve  procurement  of  a  minimum  50%  eligible  renewable  energy  resources  by  2030  and compliance with the California RPS Program interim goals, which include 40% by 2024 and 45% by 2027.
 These targets are to be met while also complying with PUC 454.52 related to serving customers at  just  and  reasonable  rates  and  minimizing  ratepayer  impacts,  ensuring  system  reliability, strengthening the transmission and distribution systems, enhancing demand‐side management, and minimizing local air pollutants and other GHG emissions with early priority on disadvantaged communities.

SB 100, the 100 Percent Clean Energy Act, signed in 2018, accelerated the RPS requirements from 50% by 2030 to 60% by 2030 with interim targets of 44% by 2024 and 52% by 2027. SB 100 also requires all of California’s retail electricity supply be met with RPS‐eligible and zero‐carbon resources by December 31, 2045—achieving  100% clean energy.

SB  338,  effective  in  January  2018,  requires  electric  utilities  in  California  to  utilize  energy  efficiency, demand  management,  energy  storage,  and  other  strategies  to  meet  peak  demand  requirements, ultimately reducing the need for new generation and distribution resources in achieving the state’s energy goals at the least cost to ratepayers.

SB  1020,  the  Clean  Energy,  Jobs,  and  Affordability  Act,  signed  in  2022,  established  additional  interim targets to ensure that California meets SB 100’s 2045 goal of 100% RPS‐eligible and zero‐carbon resources.

These require clean energy generation to reach 90% of retail sales by 2035 and 95% by 2040.

2.3. Relevant State Legislation and Executive Orders
The following sections summarize additional key bills and orders for GHG emissions, energy efficiency, and renewable energy that affect the electric utility industry and have led up to SB 350 and PUC 9621.

Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   9
GHG Emissions Reductions
Assembly Bill (AB) 32, or the Global Warming Solutions Act of 2006, extended in 2016, sent an absolute limit on GHG emissions for the state requiring economy wide emissions reductions to 40% below 1990 levels by 2030. AB 32 required utilities to report GHG emissions to the CARB and permitted the CARB to set regulations for GHG emissions reductions—leading  to the implementation of a cap‐and‐trade program and GHG Planning Target Ranges for POUs. SVP’s IRP must ultimately align with the requirements of AB

32. SB 1368, or the Emissions Performance Standard, enacted in 2007, restricts new investments in baseload fossil fuel generation resources that exceed the rate of GHG emissions for existing combined‐cycle natural gas baseload generation. SB 1368 also allows the CEC to establish a regulatory framework to enforce this standard for POUs. CEC regulations prohibit investment in generation that exceeds 0.55 tons CO2/MWh of electricity produced, with limited exceptions.

Relatedly,  SB32,  implemented  in  2017,  requires  CARB  to  ensure  the  above  stated  GHG  emissions reductions  targets  are  met  by  2030,  and  AB  197,  also  implemented  in  2017,  increased  the  legislative oversight  of  the  CARB.  AB  197  also  requires  that  the  CARB,  in  any  consideration  of  limits  beyond  the existing statewide GHG emissions targets, protect the state’s most impacted disadvantaged communities consider  the  social  costs  of  emissions,  and  prioritize  emissions  reduction  rules  and  regulations  that achieve specified results.

AB 1279, signed in 2022, establishes a binding goal for California to achieve caron neutrality no later than 2045 and establishes an 85% emissions reduction of emissions target (below 1990 levels) as part of the goal.

Energy Efficiency
SB 1037, signed in 2005, requires POUs to consider energy efficiency prior to investment in any other resources to meet growing energy demand, pursuant to the statewide commitment to cost‐effective and feasible energy efficiency. One year later in 2006, AB 2021 was signed into law requiring POUs to establish annual efficiency targets and report on a on a triennial basis over a 10‐year horizon. Subsequent decisions changed the time interval for establishing the annual targets to every four years.

Renewable Energy
The California Renewable Energy Resources Act (SB X1‐2), signed in 2011 codified the RPS target for POUs, but  also  established  specific  Portfolio  Content  Categories  (PCCs),  which  further  divided  the  eligible renewable  energy  resources  to  be  procured  and  established  limits.  The  four  PCC  categories  classify renewable resources by interconnection location and additional factors:
 PCC1: Products must be bunded and the POU cannot resell the energy; the resource’s first point of interconnection must be to a distribution system serving end‐users within a California balancing authority area; renewable energy products having a first point of interconnection outside a state Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   10
balancing authority area must be scheduled hourly into the area without substituting electricity from another source.
 PCC2: Products must be bundled and interconnected to Western Electricity Coordinating Council network; the electricity bust be scheduled into a California balancing authority area; the products must have a first point of interconnection outside of a state balancing authority area, and the electricity  must  not  be  in  the  portfolio  of  the  POU  prior  to  the  date  of  contract  or  ownership agreement; the electricity must be scheduled into the state balancing authority area within the same calendar year that the electricity is generated, and the energy may not be sold back by the POU.
 PCC3: unbundled renewable energy credits (RECs) and products not meetings the requirements of PCC1 or PCC2
 PCC0: renewable energy under contract prior to June 1, 2010 provided that the resource meets the  RPS  eligibility  requirements  in  effect  when  the  procurement  agreement  was  executed; subsequent  amendments  do  not  increase  the  capacity  or  production  or  substitute  a  different resource (any such change would be classified into PCC1, 2 or 3 and follow the portfolio balance requirements); and the duration of the contract may be extended if the original contract was for 15 years or more.

2.4. Federal Legislation
Future  federal‐level  laws  or  regulations  could  possibly  mandate  new  renewable  and  GHG  emissions standards implemented by the Environmental Protection Agency (EPA) that would impact POU operations.

However, regulation of GHG emissions at the federal level has been uncertain at times, and it is difficult to  foresee  how  future  federal  policy  on  GHG  emissions  may  impact  on  SVP  operations.  This  IRP  was prepared  assuming  that  California  GHG  emission  reduction  requirements  are  the  most  stringent applicable for planning.

2.5. CEC IRP Guidelines
Beginning on January 1, 2019 SVP, as a POU, was obligated by SB 350 to develop and submit it to the CEC to review at least every five years. SVP filed its first IRP with the CEC in accordance with SB 350 in 2019. “Climate change is a real threat to all our lives.

Baby steps aren’t going to be enough.” ‐Santa Clara
resident survey response
Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   11
This IRP process, will fulfill CEC requirements for SVP to receive POU (the Santa Clara City Council) approval of its second IRP by January 1, 2024, and file with the CEC by April 30, 2024.

The CEC developed the Publicly Owned Utility Integrated Resource Plan Submission and Review Guidelines document in July 2017 which established several requirements to be included in the IRP filing process.3 CEC is proposing amendments to the IRP Guidelines; however, as of the writing of this IRP, the proposed changes  are  not  yet  formally  adopted.  Therefore,  SVP  followed  the  current  approved  CEC  Guidelines, except for the planning horizon, which is detailed in Figure 1. These requirements include the following:
 POUs must submit the following four standardized tables to the CEC as part of the IRP Filing:
o Capacity Resource Accounting Table (CRAT): Annual peak capacity demand in each year and the contribution of each energy resource (capacity) in the POU’s portfolio to meet that demand.
o Energy Balance Table (EBT): Annual total energy demand and annual estimates for energy supply from various resources.
o GHG Emissions Accounting Table (GEAT): Annual  GHG emissions associated  with each resource  in  the  POU’s  portfolio  to  demonstrate  compliance  with  the  GHG  emissions reduction targets established by CARB.
o RPS Procurement Table (RPT): A detailed summary of a POU resource plan to meet the RPS requirements.
 The minimum planning period begins January 1 of the year that the POU’s governing board adopts the  IRP  and  must  go  through  December  31,  2030.  POU’s  are  encouraged  to  address  longer planning periods in post‐2030.
 POUs  are  encouraged  to  evaluate  alternative  resource  options  through  various  scenarios  and sensitivity analyses.
 The IRP Filing must include supporting information used to develop the Standardized Tables and other studies, data, analyses used or relied upon in developing the IRP.  POUs are required to report the forecasted peak demand in the CRAT and forecasted retail sales, other loads, and net energy for load in the EBT. The IRP must explain the demand forecasting methodology and assumptions used. The CEC encourages alternative demand forecast scenarios to be part of the IRP.

3 CEC, “Publicly Owned Utility Integrated Resource Plan Submission and Review Guidelines ‐ Adopted” (Sacramento, CA:

California Energy Commission (CEC), 2017), https://www.energy.ca.gov/rules‐and‐regulations/energy‐suppliers‐ reporting/clean‐energy‐and‐pollution‐reduction‐act‐sb‐350‐0.

Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   12
 The IRP must report the mix of resources in the required tables; this includes RPS procurement information  in  the  RPT.  The  mix  of  resources  refers  to  short‐term  and  long‐term  electricity, electricity‐related, and demand response products. RPS information provided must demonstrate the  achievement  of  the  RPS  target  by  listing  the  RPS  procurement  targets,  the  projection  of renewables  as  contained  in  a  RPS  procurement  plan.  The  reporting  of  resource  mix  must  also include  the  impacts  of  energy  efficiency  and  demand  response  resources.  Energy  storage  and transportation electrification should also be addressed in the IRP and included in the required tables, as appropriate.
 The  IRP  should  address  system  reliability.  This  includes  explaining  how  the  planning  reserve margin (PRM) was established and a discussion of any local transmission constrained areas.  GHG emission intensities must be reported in metric tons of carbon dioxide equivalent (CO2e) per MWh for each supply resource reported in the EBT.
 The IRP should be consistent with the goal of achieving just and reasonable rates and must include as  supporting  information,  a  report  on  rate  impacts  under  the  IRP  plan  if  that  report  was considered in the IRP planning.
 The IRP should report on the contribution of the IRP to increasing the diversity, sustainability, and resilience of the transmission and distribution system.  The IRP should be consistent with minimizing localized air pollutants and other GHG emissions with early priority on disadvantaged communities.

Figure 1 summarizes the IRP filing requirements as listed in the CEC guidelines document. The location where this information can be found in SVP’s IRP is outlined below.

Figure 1. Summary of CEC IRP Filing Requirements
Item  CEC Guidelines  IRP Location
A. Planning Horizon
and Objective of
Expansion Plan
“requires each POU to adopt an IRP that ensures the utility achieves specific goals and targets by 2030, including meeting the electricity sector and utility specific GHG emissions reduction targets established by the CARB that reflect the electricity sector’s percentage in achieving economy‐wide GHG emissions reductions of 40% below 1990 levels, and ensuring procurement of at least 50%of eligible renewable resources…The  minimum planning horizon that achieves this objective begins no later than January 1 of the year that the POU’s governing board adopts the plan and ends no earlier than December 31, 2030”.*
*Proposed revisions through 20454
Section 2

4 CEC, “Publicly Owned Utility Integrated Resource Plan Submission and Review Guidelines ‐ Draft Proposed” (Sacramento, CA:

California Energy Commission (CEC), 2022), https://www.energy.ca.gov/publications/2022/publicly‐owned‐utility‐integrated‐ resource‐plan‐submission‐and‐review‐guidelines.

Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   13
B. Scenarios and
Sensitivity Analysis
“POUs are encouraged to also evaluate other scenarios and sensitivity analyses to consider the feasibility and cost‐effectiveness (and rate impacts) of alternative resource options.”
Sections 6 and
8 C. Standardized Tables
“POUs must submit the following four standardized tables to the Energy Commission as part of the IRP Filing.”
Capacity Resource Accounting Table (CRAT)
Energy Balance Table (EBT)
RPS Procurement Table (RPT)
GHG Emissions Accounting Table (GEAT)
Appendix D
D. Supporting
Information
“(1) analyses, studies, data, and work papers, or other material that the POU used or relied upon (including inputs and assumptions) in creating the IRP…(2)  additional information required by these guidelines. Supporting Information supplements the data submitted in the standardized tables and must be submitted to the Energy Commission as part of the IRP Filing”
Sections 3, 4, 5,
6, 7 and
Appendix A
Appendix C
E. Demand Forecast

1. Reporting Requirements:
“report annual forecasted peak demand (megawatt [MW]) in the CRAT and annual forecasted retail sales, other loads, and net energy for load in the EBT”

2. Demand Forecast Methodology and Assumptions:
“describe the demand forecasting methodology and assumptions used.”

3. Demand Forecast – Other Regions
“If the POU uses system modeling as part of the IRP development, the IRP Filing must include the demand forecast assumptions for regions outside the POU jurisdiction.”
Section 3,
Appendix B
F. Resource
Procurement Plan
“The IRP Filing must report the mix of resources used by the POU in the IRP. This information must be reported on the CRAT, EBT, and GEAT, and RPS procurement must be reported on the RPT.” The IRP Filing must address the following:

Diversified Procurement Portfolio
RPS Planning Requirements
Energy Efficiency and Demand Response Resources
Energy Storage
Transportation Electrification
Section 8,
Appendix D
G. System and Local
Reliability
“requires Filing POUs to adopt an IRP to ensure that each POU meets the goal of ensuring system and local reliability.”

1. Reliability Criteria
“must include projections of annual peak capacity needs and the contribution of both demand and supply‐side resources…  must report the PRM and how it was determined.”

2. Local Reliability Area
“must identify any local transmission constrained areas in the POU service territory”

3. Addressing Net Demand in Peak Hours
“must include a narrative describing how existing renewable resources, grid operational efficiencies, multi‐hour energy storage, and distributed energy resources (DERs), including energy efficiency, were considered for meeting energy and reliability needs during the net‐peak hours.”
Sections 6, 7, 8,
and Appendix D
H. Greenhouse Gas
Emissions
“requires POUs to adopt an IRP to ensure the utility meets, by 2030, the GHG emissions reduction target established by CARB…must Sections 6, 8,
Appendix D
Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   14
report in the GEAT estimated emissions intensities (in metric tons of CO2e per/megawatt hour [mt CO2e/MWh] and total metric tons of carbon dioxide [mt CO2e] emissions for each supply resource reported in the EBT.”
I. Retail Rates
“requires POUs to adopt an IRP to ensure the POU achieves the goals of fulfilling its obligation to serve its customers at just and reasonable rates and minimizing impacts on ratepayer bills…  must include, as Supporting Information, a report or study on rate impacts under the IRP scenario”
Section 8
J. Transmission &
Distribution Systems
“ensure that the POU achieves the goal of strengthening the diversity, sustainability, and resilience of the bulk transmission and distribution systems, and local communities.”
Section 4 and 7
K. Localized Air
Pollutants and
Disadvantaged
Communities
“ensure the POU achieves the goal of minimizing localized air pollutants and other GHG emissions, with early priority on disadvantaged communities”
Section 8

2.6. Public Stakeholder Engagement
The public stakeholder engagement process for the IRP involved seeking groups who have an interest in future energy resource plans (i.e., stakeholders), gathering their feedback and addressing their goals and concerns.  Through  this  process,  participants  were  engaged  and  involved  early  in  IRP  development.

Stakeholders included large customers, local businesses, and the community at large.

The community engagement activities that shaped the IRP were conducted in two phases. The first phase was the creation of the Santa Clara Climate Action Plan, organized by Santa Clara and a consultant team in  2020  and  2021.  The  community  feedback  collected  during  this  process  was  used  to  help  shape  the Climate Action Plan, which would then be used as a guiding document for the IRP. The Climate Action Plan community engagement included:
 Online surveys,
 Virtual community workshops,
 Focus group interviews, and
 Public comment on the draft CAP.

Additional community engagement specifically for the IRP included:
 A community survey, open from September – November 2023 (results are in Appendix A)  A community workshop was presented in‐person and virtually, attended by both residential and commercial customers.
 Publication through newsletters.
 Social media posts on various online platforms from September to November 2023 Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   15
 Informational outreach and survey promotion at the Santa Clara Art & Wine Festival and the State of the City Events
There are plans to hold another community workshop after the IRP is presented to the City Council in December 2023 to discuss the results and the path forward.

2.7. The Integrated Resource Planning Process
Integrated Resource Planning identifies a long‐term resource portfolio plan that provides for future peak load  and  energy  demand,  while  maintaining  system  reliability,  and  achieves  a  reasonable  balance between fiscal responsibility and environmental stewardship. The IRP is a formal planning document to be submitted for approval by the Santa Clara City Council prior filing with the CEC.

The IRP process can be summarized in the following steps:

1. Identify  Objectives:  Establish  a  clear  vision  with  a  set  of  goals  for  the  IRP  that  will  drive  the planning process and ground it in the priorities and concerns of local stakeholders (Figure 2).

2. Design Scenarios: Build realistic potential futures that capture the key external forces and internal planning decisions to be explored in the IRP.

3. Determine  Future  Capacity  Needs:  Utilizing  the  latest  load  forecast  that  incorporates  load modifiers for energy efficiency and transportation and building electrification and comparing that to current information for existing supply‐side resources, expected retirement dates, and planned resource additions, identify a baseline for future capacity needs.

4. Identify Resource Options: Identify potential candidate resources that can be reliably utilized to serve load if a need is determined. This requires consideration of technology advancements, cost, resource location and potential, and performance characteristics.

5. Analyze Resource Options: Conduct analyses to identify resource options that ensure reliability and regulatory compliance at least cost.

6. Evaluate Resource Portfolios: Compare least‐cost resource portfolios, their costs, achievement of policy goals (i.e.,  GHG, clean energy, and reliability), and potential rate impacts to understand trade‐offs, and achievement of planning objectives.
“Consider cost and reliability above other
considerations.” ‐Santa Clara resident
survey response
“I have no trouble paying extra for electricity to
accelerate  sustainability.” ‐ Santa  Clara  resident
survey
Introduction2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   16

7. Finalize Plan: SVP will work with the Santa Clara City Council to a identify preferred, cost‐effective portfolio  resource  expansion  plan  to  file  with  the  CEC,  and  update,  as  appropriate,  as  part  of ongoing utility due diligence. The current document presents a set of scenarios to aid decision making; however, a preferred scenario is not identified.

The goal of SVP’s 2024 IRP is to “identify a plan that meets or exceed the State’s clean energy mandates while balancing affordability and reliability,” with the core objectives shown in Figure 2 that support SVP’s vision for the 2024 to 2035 planning horizon.

Figure 2. Core Objectives of SVP’s IRP

The sections that follow detail the additional steps of the SVP’s planning process.

Energy and Demand Forecast2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   17

3. Energy and Demand Forecast

3.1. Historic Energy Use and Demand
As of 2022, Santa Clara’s population was estimated at just over 128,000, and SVP served approximately 60,000 customer meters with 4,400 GWh of sales and a peak demand of 693 MW. The makeup of SVP’s customer base is unique for the state. While 85% of the total number of customers are residential, over 93% of the utility retail sales are to commercial and industrial customers, consisting of high‐technology manufacturing and data management facilities, shown in Figure 3. This results in a relatively flat demand profile and a high load factor. SVP’s demand has consistently increased in recent years, mostly due to growth of the industrial customer sector.

Figure 3. SVP Customer Mix by Retail Sales in 2022

3.2. Demand Forecast Methodology and Assumptions
A range of sources were leveraged to develop an SVP Reference scenario for the planning horizon 2024‐ 2035 of annual peak load and an hourly energy demand forecast.5 The Reference Scenario is a business‐ as‐usual forecast of energy demand in SVP territory using the utility’s baseline forecast of energy demand with additional energy efficiency and electrification  projections from the Planning  Forecast of the CEC 2022 Integrated Energy Policy Report (IEPR).6

5 Sensitivities were also explored to build High electrification and a IEPR local reliability load forecast, discussed in Appendix B. 6 CEC, “CEC 2022 Integrated Energy Policy Report (IEPR)” (Sacramento, CA: California Energy Commission (CEC), 2022), https://www.energy.ca.gov/data‐reports/reports/integrated‐energy‐policy‐report/2022‐integrated‐energy‐policy‐report‐ update.

Commercial

2.1%
Industrial

91.6%
Municipal

0.4%
Residential

5.9%
Energy and Demand Forecast2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   18
Annual Energy Demand Forecast
Baseline Energy Demand
SVP  baseline  energy  demand  is  developed  from  hourly  energy  forecasts  for  2023‐2035  originally submitted as part of the 2022 IEPR process and the Pacific Gas and Electric (PG&E) extended IRP process.7 SVP also utilized annual energy forecasts for 2023‐2035 by customer class for the Residential, Commercial, Industrial, and Municipal customer sectors. As shown in Figure 4, baseline energy demand grows quickly from 2023 to 2035 mainly due to increases in the Industrial sector (e.g., datacenter loads).

Figure 4. SVP Baseline Energy Demand Forecast (GWh)
Customer Class  2023  2024  2025  2026  2027  2028  2029  2030  2031  2032  2033  2034  2035 Residential  271  290  321  366  430  469  481  485  485  487  485  502  502 Commercial  98  132  161  195  241  288  325  355  355  356  355  368  368 Industrial  4,184  4,555  5,078  5,521  5,882  6,396  6,810  7,249  7,729  8,234  8,498  8,642  8,810 Municipal  17  17  17  17  17  17  17  17  17  17  17  18  18 Baseline Total  4,570  4,993  5,577  6,099  6,570  7,170  7,633  8,106  8,586  9,094  9,356  9,530  9,698 Energy Demand Modifiers
After  establishing  the  baseline  energy  demand  forecast,  load  modifiers  for  energy  efficiency,  building electrification, and transportation electrification were developed and layered onto the baseline forecast to establish the total annual demand for the Reference Scenario. Figure 5 shows these energy demand modifiers  and  SVP  resulting  total  annual  demand,  and  the  assumptions  behind  these  modifiers  are explained in the following paragraphs. The Reference Scenario also includes a 2.9% line‐loss factor for losses between the CAISO point of interconnection and SVP's retail load when reporting final electricity demand.8
Figure 5. Reference Scenario Annual Electricity Demand and Demand Modifier Impacts (GWh) Scenario  2023  2024  2025  2026  2027  2028  2029  2030  2031  2032  2033  2034  2035 Baseline Total  4,570  4,993  5,577  6,099  6,570  7,170  7,633  8,106  8,586  9,094  9,356  9,530  9,698 Energy
Efficiency  ‐62  ‐97  ‐136  ‐171  ‐204  ‐226  ‐248  ‐271  ‐294  ‐313  ‐333  ‐350  ‐365 Building
Electrification  13  21  29  36  43  51  59  67  74  81  88  94  99 Transportation
Electrification  8  15  24  32  40  49  59  69  81  94  107  120  135 Total Annual  4,529  4,933  5,494  5,995  6,449  7,044  7,503  7,971  8,448  8,955  9,218  9,394  9,567 For energy efficiency the Reference Scenario reflects the “Scenario 3 (Mid)” additional achievable energy efficiency  (AAEE)  modeled  by  CEC  from  the  2022  IEPR  for  Residential  and  Commercial  sector  energy efficiency, aligning with the assumptions used in the 2022 IEPR Planning Forecast.9 These assumptions lead to 130 GWh and 169 GWh of annual savings by 2035 for the residential and commercial sectors,

7 SVP, “SVP Hourly Energy Forecasts: 2023‐2035,” 2023, Data Provided by Silicon Valley Power. 8 Line‐loss factor from SVP
9 CEC, “2022 IEPR AAEE‐AAFS Annual Impacts,” 2022, https://efiling.energy.ca.gov/Lists/DocketLog.aspx?docketnumber=22‐ IEPR‐03.

Energy and Demand Forecast2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   19
respectively, from measures targeting lighting, heating, ventilation, and air conditioning (HVAC), water heating,  and  other  end  uses.  Finally,  the  Reference  scenario  includes  the  cumulative  total  energy efficiency  potential  of  66  GWh  by  2031,  with  most  of  these  savings  occurring  for  non‐residential customers.

For building electrification assumptions, the Reference Scenario follows the assumptions of “Scenario 3 (Mid)” Annual Achievable Fuel Substitution (AAFS) modeled by CEC for the 2022 IEPR, aligning with the assumptions used in the 2022 IEPR Planning Forecast.

Finally, the Reference Scenario reflects the base level of transportation electrification from the 2022 IEPR assumptions from CEC. The total annual electricity demand for the Reference Scenario is shown in Figure

6. Figure 6: Total Annual Electricity Demand ‐ Reference Scenario

Hourly Energy Demand Forecast
To facilitate capacity expansion modeling for the integrated planning process an hourly demand forecast was developed from this annual forecast. A separate hourly load profile was assigned to the annual baseline energy demand, energy efficiency and electrification load modifiers to develop a complete hourly energy demand forecast for the Reference Scenario forecast. Figure 7 lists the sources used to develop these hourly demand profiles.

As IEPR does not provide an hourly load profile for SVP, PG&E‐wide hourly load shapes for energy efficiency and building and transportation electrification were downscaled from the 2022 IEPR PG&E Planning Scenario.

Energy and Demand Forecast2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   20
Figure 7. Hourly Demand Profile Components
Energy Demand Component  Source for Hourly Demand Profile Baseline Energy Demand  SVP Hourly Energy Demand Forecast 2023‐2035 Energy Efficiency  2022 IEPR Hourly Forecast – PG&E Planning Scenario10 Building Electrification from 2022 IEPR
Transportation Electrification

10 CEC, “CED 2022 Hourly Forecast ‐ PGE ‐ Planning Scenario,” 2022, https://efiling.energy.ca.gov/Lists/DocketLog.aspx?docketnumber=22‐IEPR‐03.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   21

4. Existing and Planned System and Resources

4.1. Existing Resources and System Description
This section provides a description of all the resources currently procured to meet customer load. SVP’s portfolio includes Santa Clara‐owned resources, jointly owned resources, and resources procured through Power Purchase Agreements (PPAs). Santa Clara is a member of two joint powers agencies: the Northern California Power Agency (NCPA) and the M‐S‐R Public Power Agency (M‐S‐R PPA).11 Each of these agencies has shared interests in several facilities, as described later in this section.

This  IRP  accounts  for  Santa  Clara’s  Metered  Subsystem  Aggregation  Agreement  (MSSA)  between  the NCPA  and  California  Independent  System  Operator  (CAISO).  The  NCPA  serves  as  SVP’s  schedule coordinator and is not obligated to offer its generation into the CAISO market. SVP pays a Transmission Access Charge (TAC) to CAISO for energy delivered into its service area (see Sections 4.7 and 7.5).

SVP’s energy resource planning strategies, methods and processes are consistent with applicable Western Electricity  Coordinating  Council  and  North  American  Electric  Reliability  Corporation  (NERC)  standards, SVP’s Strategic Plan, the  MSSA and other relevant  contracts into which Santa Clara has entered,  good utility practice, and sound economic and business principles. SVP will continue to maintain an integrated and balanced portfolio of resources that is sufficient to meet its obligations.

When  procuring  resources  to  serve  customer  load,  risk  management  processes  and  procedures  are followed  using  Santa  Clara’s  official  Risk  Management  Policy.  Risk  management  practices  apply  to decisions concerning the mix of resources and their loading order, including the decision to use supply or demand‐side  resources,  whether  to  operate  inside  Santa  Clara  versus  remote  resources,  what  type  of generation to procure and other questions. In general, SVP’s approach is to maintain a diverse portfolio of generating resources and  market energy resources to reduce risk and minimize exposure to loss of generating capacity. Due to SVP’s dependence on transmission services provided by the CAISO and others to import power, SVP is exposed to costs increases and to potential power delivery interruptions failures.

SVP  continually  seeks  strategies  to  reduce  the  impacts  of  transmission  cost  increases  and  maintains contingency plans for such occurrences. SVP also procures fuel for its natural gas‐fired generating facilities with supply contracts that are laddered with staggered start times and durations to limit its exposure to fuel price fluctuations.

A summary of SVP’s calendar year 2022 generation portfolio mix by resource type is presented in Figure

8. This does not include SVP’s excess renewable resources sold to third parties. Due to SVP’s long position in renewables, SVP will either sell excess renewable generation to other entities, or bank surplus RECs for

11 M‐S‐R Public Power Agency (M‐S‐R PPA) was created through a Joint Exercise of Powers Agreement among Modesto Irrigation District, the City of Santa Clara (as Silicon Valley Power), and the City of Redding for the purposes of acquiring, constructing, operating, and maintaining, any project for the purpose of providing electrical energy or other project benefits for public or private uses.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   22
utilization in future years. This allows SVP to evaluate additional eligible renewable resources projects that will optimize the value for the customers.

Figure 8. SVP Generation Portfolio Mix by Technology, 2022

Note: Unspecified Power is electricity that has been purchased through open market transactions and is not traceable to a specific generation source.

4.2. Existing and Planned Resources
SVP’s portfolio of existing (owned, jointly owned and/or contracted) generators and planned resource additions through the modeling horizon to 2035 is shown in Figure 9. This portfolio includes resources that are currently in SVP’s portfolio, those that are planned for future delivery, and those that retire within the planning horizon.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   23
Figure 9. SVP Existing and Planned Resource Portfolio, 2024‐2035

More  information  on  the  individual  resources  under  contract  to  deliver  electricity  in  2023  to  SVP  is provided in Figure 10.

Figure 10. SVP’s Resource Portfolio in 2023
Portfolio Resource Type RPS
Eligible
PCC
Type
System
RA Capacity, MW
City-Owned /
Contracted
Tri-Dam Donnells Hydro No Yes 72.0
WAPA Base Resource Hydro No Yes 126.0
Ameresco Forward Landfill Gas Yes PCC1 Yes 4.2 Ameresco VASCO Landfill Gas Yes PCC1 Yes 4.3 G2 Landfill Landfill Gas Yes PCC0 Yes 1.6 Donald Von Raesfeld (DVR) Natural Gas No Yes 147.8 Gianera Generating Station Natural Gas No Yes 49.5 Black Butte Small Hydro Yes PCC0 Yes 6.2 Camp Far West Hydro (Index+) Small Hydro Yes PCC1 Yes 6.8 Friant 1 Small Hydro Yes PCC1 Yes 25.0
Friant 2 (Quinten) Small Hydro Yes PCC1 No 7.3 Grizzly Hydro Small Hydro Yes PCC0 Yes 17.7 Rio Bravo (Index+) Small Hydro Yes PCC1 Yes 14.0 Stony Gorge Small Hydro Yes PCC0 Yes 4.9 Tri Dam Southern/Sandbar Small Hydro Yes PCC1 Yes 16.2 Tri-Dam Beardsley Small Hydro Yes PCC1 Yes 11.5 Tri-Dam Tulloch Small Hydro Yes PCC1 Yes 25.9

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   24
Aquamarine Westside (Index+) Solar Yes PCC1 Yes 75.0 Central 40 Solar Yes PCC1 Yes 40.0
Rosamond Solar Solar Yes PCC1 Yes 20.0
Manzana Wind Wind Yes PCC1 Yes 50.0
Total, City-Owned and Contracted 725.9
NCPA
Geo Plant 1-4 4 Geothermal Yes PCC0 Yes 58.4 Collierville Hydro No Yes 91.4
South Feather - Woodleaf Hydro No Yes 38.5 South Feather – Forbstown Hydro No Yes 24.0 Alameda 1 & 2 Natural Gas No Yes 19.6 Lodi CT Natural Gas No Yes 9.9
Lodi Energy Center (LEC) Natural Gas No Yes 77.9 New Spicer Small Hydro Yes PCC0 Yes 2.2 South Feather – Kelly Ridge Small Hydro Yes PCC1 Yes 7.0 South Feather – Sly Creek Small Hydro Yes PCC1 Yes 8.3 Total, NCPA-Owned and Contracted 337.2
MSR Big Horn 1 Wind Yes PCC0 Yes 105.0
Big Horn 2 Wind Yes PCC0 Yes 17.5
Total, MSR Resources 122.5

Total, Renewable 529.0
Total, Zero Carbon Resources 880.9
TOTAL 1,185.6

SVP’s diverse portfolio of resources is located throughout California and Washington State and soon in the Country of Mexico, as mapped in Figure 11.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   25

Figure 11. SVP’s Current Power Resource Locations (Owned and Contracted)

Additional  resources  that  are  under  contract  and  scheduled  to  come  online  in  future  years  are summarized in Figure 12.

Figure 12. SVP’s Planned Resource Additions in Future Years Portfolio Resource Type RPS
Eligible
System
RA
Delivery
Year
Capacity,
MW
City-Owned /
Contracted
BESS 200 MWh Li-ion Battery No Yes 2025 50.0 Calpine Geothermal 1 Geothermal Yes Yes 2025 35.0 Calpine Geothermal 2 Geothermal Yes Yes 2027 35.0 Rooney Ranch Wind Yes Yes 2026 19.0
Sand Hill A Wind Yes Yes 2026 13.0
Sand Hill B Wind Yes Yes 2026 17.5
Cimmaron Wind Wind Yes No 2026 300.0
Total, City-Owned and Contracted 469.5

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   26

Several resources in SVP’s portfolio are expected to be retired due to aging units or expiration of the PPA contracts. The schedule of planned contract expirations and resource retirements is provided in Figure 13.

Among the resources leaving SVP’s portfolio are 8.5 MW of biogas generators and 172.5 MW of aging wind assets.

Figure 13. Planned Resource Retirements
Year  Capacity Retired
(MW)
2026  105.0
2032  50.0
2034  8.5
2035  17.5

4.3. Description of Santa Clara Owned and Contracted Resources Aquamarine Westside Solar
In  2021,  Santa  Clara  entered  into  a  PPA  with  Aquamarine  Westside  LLC.,  a  solar  PV  generator  project located in Kings County, CA. Under this agreement SVP owns a share of the system and receives up to 75 MW of the total project.

Ameresco Landfill Gas
In 2010, Santa Clara signed PPAs with Ameresco for the Ameresco Forward and Ameresco Vasco projects.

Ameresco  Forward  is  a  landfill  gas  generator  located  in  Manteca,  CA.  Ameresco  Vasco  is  a  landfill  gas generator located near Livermore, CA. SVP is contracted to receive up to 4.6 MW (and potentially up to

9.2 MW) from Ameresco Forward and up to 5 MW from Ameresco Vasco.

Stony Creek Hydroelectric System
SVP owns and operates the Stony Creek Hydroelectric System, which consists of three small hydroelectric plants. The 4.9‐MW Stony Gorge generator is located at the Stony Gorge Dam near Willows, CA. The 6.2‐ MW Black Butte generator is located at the Black Butte Dam near Orland, CA. A third, 0.53‐MW generator located near the Black Butte dam, is not modeled.

Central 40 Solar
In 2017, Santa Clara signed a PPA with Samsung to develop the Central 40 project. Central 40 is a solar PV generator located in Stanislaus County, CA. SVP is contracted to receive 40 MW from the project.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   27
Donald Von Raesfeld (DVR)
In 2005, Santa Clara commissioned the Donald R. Von Raesfeld (DVR) natural gas combined cycle power plant located within the City of Santa Clara. DVR is a 122 MW nominal / 147 MW peaking generator. SVP economically bids DVR into the CAISO market and is operated based on CAISO dispatch instructions.

Friant 1 & 2 Hydro Facilities
In 2016, Santa Clara signed a PPA with the Friant Power Authority for Facility 1. Facility 1 consists of three run‐of‐river hydroelectric facilities in Madera County, CA, totaling 25 MW: the River Outlet (2 MW), the Friant‐Kern (15 MW), and the Madera (8 MW). SVP is contracted to purchase up to 68,000 MWh per year from Facility 1.

In  2012,  Santa  Clara  entered  a  PPA  with  the  Friant  Power  Authority  for  Facility  2,  a  run‐of‐river hydroelectric generator in Madera County, CA. Facility 2 consists of the Quinten Luallen Power Plant, rated at 7.3 MW.

G2 Landfill Gas
In 2009, Santa Clara signed a PPA for the G2 landfill gas project in Wheatland, CA. G2 has a nameplate rating of 1.6 MW.

Gianera Generating Station
In 1987, Santa Clara completed the construction of the Gianera Generating Station, located within the City of Santa Clara. Gianera consists of two dual‐fuel (natural gas and fuel oil) combustion turbines, each with a nominal rating of 25 MW. Gianera 1 & 2 combine to provide 49.5 MW of capacity for SVP. Due to the plant’s air permit, Gianera can only be operated up to 877 hours annually.

Grizzly Hydro Project
In a 1990 settlement agreement with PG&E, Santa Clara purchased the Grizzly Creek hydroelectric facility in  Plumas  County,  CA.  Grizzly  Creek  is  nominally  a  20‐MW  facility,  and  SVP  contracted  to  receive  all electricity produced by the system, less transmission losses, which amounts to an effective contracted capacity of 17.7 MW.

Manzana Wind
In 2012, Santa Clara signed a PPA with Avangrid for the Manzana Wind Power Project. Manzana is a 50‐ MW wind project located in Kern County, CA.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   28
Rosamond Solar
In 2011, SVP entered PPA with Recurrent Energy for the entire output from the RE Rosamond One LLC project, a 20‐MW solar PV project in Kern County, CA.

Rio Bravo
In 2019, Santa Clara signed a PPA with the Olcese Water District for the Rio Bravo project. Rio Bravo is a 14‐MW hydroelectric power plant located in Kern County, CA.

Jenny Strand Solar Park
Santa Clara originally entered into an agreement with MiaSole on December 6, 2011, for the purpose of having MiaSole donate one thousand (1,000) solar PV modules to Santa Clara at no cost to Santa Clara to further the city’s ability to provide renewable power.12 Tioga Solar
On February 2, 2012, Santa Clara entered a 20‐year PPA with Tioga Solar Santa Clara, LLC. The project is located on the City of Santa Clara’s multi‐level parking structure on Tasman Drive in the City of Santa Clara.

Nameplate capacity is 389.76 kW. 13
Tri‐Dam Large and Small Hydroelectric Project
In 2013, Santa Clara signed a PPA with the Tri‐Dam Power Authority to purchase the output from four hydroelectric power plants located on the Middle Fork of the Stanislaus River in Tuolumne County. The Donnell’s Powerhouse is a large hydroelectric generator rated at 72 MW. The other three power plants are small hydroelectric generators: Tulloch (25.9 MW), Beardsley (11.5 MW), and Southern (16.2 MW).

Western Area Power Administration
In 2005, Santa Clara signed a PPA with the Western Area Power Administration (WAPA) for the purchase of hydroelectricity from the Central Valley Project (CVP). In 2021, Santa Clara City Council approved an amendment  to  the  PPA  extending  the  purchase  of  output  through  calendar  year  2054.  The  CVP  is  a collection of federal hydroelectric facilities operating in Northern California. SVP is contracted to receive approximately  9.6%  of  the  electricity  from  WAPA,  which  translates  to  a  nameplate  capacity  of approximately 126 MW.

12 Because of the size of this resource relative to the City’s load, it was not included in the model for this IRP. 13 Like the Jenny Strand Solar Park, due to the size of this resource relative to the City’s load, it was not included in the model.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   29
Altamont Wind Repower
In 2016, Santa Clara commenced a re‐power project with S‐Power at its existing Altamont Wind Project site. S‐Power will own and operate 19 MW capacity of wind generation. Two additional PPAs were entered with S‐Power under the Rooney Ranch, LLC, including Sand Hill A (13 MW) and Sand Hill B (17.5 MW). In total, the re‐power project will be upgraded to deliver 49.5 MW of capacity to SVP and is scheduled to be completed by 2026.

Kifer Receiving Station Battery Energy Storage System Project SVP is currently contracting with a third party to build and operate a 50‐MW, 4‐hour (200 MWh) utility‐ scale lithium‐ion BESS within the City of Santa Clara at the City’s Kifer Receiving Station. The BESS project is expected to be completed in late 2025.

Cimmaron Wind
SVP entered a PPA for the long‐term supply of renewable energy from Cimmaron, a cross‐border wind generation facility under development in Baja California, Mexico. Cimarron is expected to be a 300 MW wind generation facility that utilizes existing cross‐border high voltage transmission line to interconnect and deliver clean energy to the East County Substation in San Diego County. The project has a commercial operation date of December 31, 2025.

4.4. Northern California Power Agency (NCPA) Resources
Santa  Clara,  together  with  the  Cities  of  Alameda,  Biggs,  Gridley,  Healdsburg,  Lodi,  Lompoc,  Palo  Alto, Redding,  Roseville  and  Ukiah,  the  Plumas‐Sierra  Rural  Electric  Cooperative,  the  Truckee‐Donner  Public Utility District, the Bay Area Rapid Transit District and the Port of Oakland, is a member of the California joint powers agency known as Northern California Power Agency (NCPA). The resources that Santa Clara jointly shares with other NCPA members are presented here.

NCPA Hydroelectric Project
In 1982,  the  NCPA jointly  developed the NCPA Hydroelectric Project with the  Calaveras County Water District (CCWD). CCWD is the licensee and NCPA is the project operator. The NCPA Hydroelectric Project includes the 246.86 MW Collierville Powerhouse and 6.0 MW Spicer Powerhouse. Santa Clara has a 37% share in NCPA’s Hydroelectric Project, amounting to 91.4 MW of the Collierville project and 2.2 MW of Spicer.

NCPA Geothermal Project
The NCPA owns and operates geothermal projects in Sonoma and Lake Counties, CA. NCPA’s leasehold agreement with the federal government was renewed in 2013. The Geothermal Project consists of two electric  generating  stations  (Geothermal  Plant  1  and  Geothermal  Plant  2),  each  with  two  55‐MW Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   30
nameplate turbines. Santa Clara is contracted for 54.65% and 34.13% entitlement shares, respectively, in both plants.

NCPA Combustion Turbine Project No. 1 – Alameda 1 & 2 and Lodi CT NCPA owns and operates the Combustion Turbine Project Number One (CT 1) (the Combustion Turbine Project), originally consisting of five CT units, each nominally rated 25 MW. Two of the units are in the City of Roseville, two are in the City of Alameda and one is in the City of Lodi. Santa Clara purchased a 25% entitlement share in NCPA’s Combustion Turbine Project pursuant to a power sales contract with NCPA, which has recently been amended to reflect that Santa Clara’s 25% share comes specifically from the two Alameda plants (Alameda CT 1 & 2) and the one Lodi plant (Lodi CT).

NCPA Lodi Energy Center Project
NCPA owns and operates the Lodi Energy Center (LEC), a 302 MW natural gas‐fired, combined‐cycle power generation plant located in Lodi, CA, which was placed into commercial operation in 2012. Pursuant to the LEC Power Sales Agreement, Santa Clara has purchased from NCPA a 25.75% generation entitlement share of the capacity and energy from LEC.

NCPA Lodi Energy Center Project – Hydrogen Transition
NCPA is planning a transition of natural gas units to hydrogen beginning with LEC’s conversion to a 45% hydrogen blend in 2027. By 2032, NCPA expects to have LEC running on 100% hydrogen.

For the 45% hydrogen blend in 2027, NCPA plans to install an electrolyzer with 60 MW of capacity at the LEC  providing  the  capability  of  producing  24  tons  of  hydrogen  per  day.  The  cost  of  the  electrolyzer  is expected to be $145 million with an additional $80 million needed for the installation. By 2032, NCPA estimates an additional 360 MW of electrolyzer capacity will be needed to operate LEC at 100% hydrogen, at a rough cost of an additional $2 billion. The renewable generation that  powers the electrolysis (for hydrogen generation) would be eligible for the standard IRA tax incentives.

South Feather River Hydroelectric
In  2021,  Santa  Clara  entered  a  PPA,  via  third  party  agreement  with  NCPA,  to  purchase  64.2%  of  the electricity output from the South Feather Power Project. The project consists of four hydroelectric power plants: the 37.5 MW Forbestown Powerhouse, the 11 MW Kelly Ridge Powerhouse, the 13 MW Sly Creek Powerhouse  and  the  60  MW  Woodleaf  Powerhouse.  The  four  plants  that  make  up  the  South  Feather Power Project are located across Butte, Plumas and Yuba counties on the South Fork of the Feather River and  Slate  Creek.  Santa  Clara’s  project  participation  share  of  the  generation  output  is  expected  to  be approximately 245 GWh annually.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   31
Camp Far West Hydroelectric
In 2022 Santa Clara entered into a PPA, via third phase agreement with the NCPA, with the South Sutter Water District for the generation output of the Camp Far West Hydroelectric Facility. Camp Far West is a run‐of‐river hydroelectric facility with a capacity of 6.8 MW and will produce approximately 23,700 MWh of electricity per year. SVP is the sole off‐taker of this project’s output.

Calpine Geothermal
SVP entered into a long‐term PPA for renewable geothermal energy that will begin delivery energy to SVP in 2025.  The  PPA will allow the City of Santa Clara  to receive  clean, renewable energy produced from multiple Calpine geothermal power plants located in Sonoma and Lake Counties. It will deliver up to 50 MW  of  renewable  energy  during  the  period  of  2025  to  2026  and,  in  2027,  the  amount  delivered  will increase to 100 MW through 2036.

4.5. M‐S‐R Resources
Santa Clara, along with the Modesto Irrigation District and the City of Redding, is a member of the M‐S‐R PPA. The resources that are jointly owned, or procured through PPAs are described below:

M‐S‐R PPA Purchased Power – Big Horn Project I and II
In 2005, the M‐S‐R PPA entered a series of PPAs with Avangrid Renewables for the purchase of energy from the Big Horn I Project. Big Horn I is a 199.5‐MW wind project located near the town of Bickleton, WA.

Santa Clara receives 52.5% of the power purchased by the M‐S‐R PPA from Big Horn I, which equates to approximately  105  MW.  Santa  Clara  uses  a  portion  of  its  transfer  capability  of  the  California‐Oregon Transmission Project (COTP) to provide for the transmission of the output from the Big Horn I Project to the California‐Oregon border.

In 2010, the M‐S‐R PPA subsequently negotiated with Avangrid for the purchase of the output from a 50‐ MW expansion of Big Horn I, called the Big Horn II Project. Santa Clara receives 35% of the output from this project, or approximately 17.5 MW of project capacity.

4.6. Renewable Energy Strategy
A significant portion of the energy received by Santa Clara customers is generated from renewable energy resources. Santa Clara’s power mix in Calendar Year 2022 consisted of 34% eligible renewable resources.

When large hydroelectric resources are included, Santa Clara’s power mix consisted of 74% renewable and large hydroelectric power. On December 6, 2016, the Santa Clara City Council adopted revisions to Santa Clara’s Environmental Stewardship and RPS Policy Statement (Santa Clara Resolution 16‐8392), and adopted a new RPS Enforcement Program, to conform to the standards and timetable set forth in SBX1‐ 2, signed by the Governor on October 6, 2016.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   32
 Santa Clara satisfied the RPS target for Compliance Period 1 (from 2011 through 2013), with an average  of  approximately  20%of  Santa  Clara’s  energy  portfolio  supplied  from  renewable resources over such period.
 Santa Clara satisfied the RPS target for Compliance Period 2 (from 2014 through 2016), meeting the compliance requirement of 20% of retail sales in 2014 and 2015, and 25%of retail sales in 2016.
 Santa Clara satisfied the RPS target for Compliance Period 3 (from 2017 through 2020), meeting the compliance requirement of 27%of retail sales in 2017, 29%of retail sales in 2018, 31%of retail sales in 2019, and 33%of retail sales in 2020.

Compliance Periods 1‐3 have been verified and approved by the State of California. In the first and second year of Compliance Period 4 (from 2021 through 2024), Santa Clara satisfied the RPS target, meeting the requirement of 35.75% of retails sales in 2021 and 38.5% of retail sales in 2022. Santa Clara expects to fulfill  the  Compliance  Period  4  RPS  requirement  by  procuring  eligible  renewable  energy  resources (excluding “large hydro”)  amounting  to 44% of total retail sales by 2024. SB  100 requires  60% eligible renewable  energy  compliance  by  December  31,  2030.  Santa  Clara  is  well  positioned  to  meet  the  new renewable energy compliance requirements of SB 100.

Due to SVP’s long position in renewables, SVP will either sell excess renewable generation to other entities or accumulate RECs that exceed RPS requirements as excess procurement to be utilized in future years in case of unplanned curtailment, plant interruptions, and unexpected load growth, future project delays or as  needed  to  ensure  compliance  with  the  RPS.  Excess  procurement  allows  SVP  to  evaluate  additional eligible renewable resources projects, other generation and potential battery storage projects that will optimize the value for the customers. SVP starts new procurement processes for a forecasted need at a minimum 3‐5 years before the resource is needed. SVP is fully compliant with the State requirement that 65% of eligible renewables are under long term contracts.

4.7. Transmission and Distribution System Assets and Adequacy Santa Clara’s service area is surrounded by PG&E’s service area and the two systems are interconnected at two Santa Clara‐owned 115 kV receiving stations – Northern Receiving Station (NRS) and Kifer Receiving Station, each located within Santa Clara’s city limits. In addition, Santa Clara has a 230‐kV interconnection with  PG&E  at  PG&E’s  Los  Esteros  Substation  (LES)  in  the  City  of  San  Jose.  Power  received  at  LES  is transmitted by Santa Clara approximately six miles to NRS. Santa Clara owns facilities for the distribution of electric power within its city limits (approximately 18.4 square miles), which includes approximately 27 miles of 60 kV power lines, approximately 500 miles of 12 kV distribution lines (approximately 64% of which are underground), and 27 stations. Santa Clara’s electric system experiences approximately 0.5 to

1.5 hours of outage time per customer per year. This compares favorably with other utilities in California with reliability factors ranging from 1.0 to 2.5 hours outage per customer per year. To the extent Santa Clara requires additional transmission beyond its current transmission system limit, the city will need to advocate  at  the  CAISO  for  additional  transmission  capability  through  the  CAISO  annual  Transmission Planning Process (TPP) (See SVP Transmission Projects Below).

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   33
NCPA Geysers Transmission Project
To meet certain obligations required of NCPA to secure transmission and other support services for the NCPA Geothermal Project, NCPA undertook the geysers transmission project (the Geysers Transmission Project). The Geysers Transmission Project includes (i) a co‐tenancy interest in PG&E’s 230 kV line from Castle Rock Junction in Sonoma County to the Lakeville Substation (the Castle Rock to Lakeville Line), (ii) additional firm transmission rights in the Castle Rock to Lakeville Line and (iii) the Central Dispatch Facility.

Santa Clara has a 55 MW share in the Geysers Transmission Project, which provides a link from the Geysers to PG&E’s bulk transmission system.

TANC California–Oregon Transmission Project (COTP)
The Transmission Agency of Northern California (TANC) is a joint power agency established by a group of California publicly‐owned utilities in 1984. Its purpose was to plan, design and construct the California Oregon  Transmission  Project  (COTP),  a  240‐mile  long,  500‐kilavolt  (kV)  alternating  current  (AC) transmission line between the California‐Oregon border and Central California. The COTP was completed and energized in 1993. Santa Clara is a member of the TANC and has an approximate 10% of TANC’s share of COTP transfer capability. Santa Clara is using a portion of its share of the project transfer capability of the COTP to provide transmission of energy generated from the Big Horn Projects.

TANC Tesla–Midway Transmission Service
TANC and certain TANC Members have arranged for PG&E to provide TANC and such TANC Members with 300 MW of firm, bi‐directional transmission capacity on its transmission system between PG&E’s Midway Substation and the electric systems of the TANC Members or the COTP (the Tesla‐Midway Service) under a  long‐term  agreement  known  as  the  South  of  Tesla  Principles  (SOTP).  Santa  Clara’s  share  of  Tesla– Midway  Transmission  Service  is  81  MW.  Santa  Clara  utilizes  its  share  of  the  TANC  Tesla–Midway Transmission Service to provide access to power supplies located in the southwest.

SVP Transmission Projects
On September 6, 2022 SVP set a system peak load of 702 MW. With recent load growth of 5 to 7% and increasing industrial sector demand, SVP is looking to increase the capacity of its existing transmission system. Figure 14 presents the projects have been approved to increase the capacity or enhance reliability of the transmission system. Even with these additional transmission projects, the City of Santa Clara will face challenges to fully decarbonize by 2035 while also meeting its growing load requirements.

During the CAISO 2021‐2022 TPP, CAISO approved the development of two new 500 MW high voltage direct  current  (HVDC)  lines  in  the  South  Bay  area.  One  of  those  lines  will  connect  from  the  Newark substation to Los Esteros substation and into SVP’s Northern Receiving Station while the other 500 MW line will connect from Metcalf substation to San Jose B substation. In March 2023, LS Power Grid California, LLC, was selected to finance, construct, own, operate and maintain these two new lines. The Newark‐ Northern Receiving Station line is anticipated to be in service in 2028.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   34
Figure 14. Current approved SVP Transmission Projects
Transmission and Distribution Upgrades/Replacements Identified and in Budget  Cost (Million $)
60KV Breaker Upgrades   $3.10
Duane‐Scott 115kV   $1.62
Esperanca Substation   $26.92
Fiber Development, Design, and Expansion   $3.44
Homestead Substation Rebuild   $1.45
KRS Rebuild and Replacement   $86.46
Northwest Loop Capacity Upgrade   $4.75
NRS Transformer and Breaker Upgrades   $87.55
NRS‐KRS 115kV Line   $31.35
Operations and Planning Technology   $1.61
Serra Substation Re‐Build   $0.22
South Loop Reconductor   $18.61
SRS Rebuild and Replacement   $90.55
Storm Water Compliance   $0.72
Substation Capital Maintenance and Betterments   $1.03
Substation Control and Communication System Replacement   $0.14 Substation Physical Security Improvement   $0.23
System Capacity Expansion   $3.35
Transmission and Distribution Capital Maintenance and Betterments   $9.44 Transmission Loop 1   $4.69
Transmission Loop 2   $2.00
Transmission System Reinforcements   $0.40
Walsh‐Uranium 60kV Reconductor   $2.41
Total   $382.02

4.8. Natural Gas Commodity, Transportation and Storage
SVP owns several gas‐fired power plants in its portfolio. Through the gas pre‐pay agreement described below, SVP aims to hedge the impact of gas supply and price volatility on its customers.

Natural gas is the primary fuel and the primary variable operating cost of Santa Clara’s Gianera Generating Station, DVR Power Plant and the LEC. These plants can require delivery of up to 49,000 MMBtu per day fuel,  with  current  average  daily  requirements  of  24,400  MMBtu  per  day.  Santa  Clara  has  developed  a comprehensive  natural  gas  program  to  both  manage  supply  and  price  volatility.  This  includes  the procurement  of  a  supply  of  natural  gas  at  a  discount  from  the  monthly  index  price  pursuant  to  a  gas prepayment arrangement and several fixed price contracts for 10,000 MMBtu from 2020 to 2025.

Existing and Planned System and Resources2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   35
M‐S‐R Energy Authority – Gas Prepay
In 2009, Santa Clara participated in the M‐S‐R EA Gas Prepay Project. The Gas Prepay Project provides, through a Gas Supply Agreement between M‐S‐R EA and Santa Clara, for a secure and long‐term supply of natural gas of 7,500 MMBtu daily (or 2,730,500 MMBtu annually) through December 31, 2012, and 12,500 MMBtu daily (or 4,562,500 MMBtu annually) thereafter until September 30, 2039. The Gas Supply Agreement provides this supply at a discounted price below the monthly market index price (the PG&E Citygate index) over the 30‐year term.

4.9. Wholesale Energy Trading
For several years, Santa Clara has  used its energy and transmission resources together with its  power scheduling  capabilities  to  buy  and  sell  energy  in  the  western  North  American  market.  As  deregulation unfolded,  a  greater  need  to  manage  resources  on  a  day‐to‐day  basis  evolved,  resulting  in  a  more comprehensive approach to trading operations at Santa Clara. The principal reason for wholesale power trading  is  to  optimize  the  value  of  the  utility’s  assets  and  cost‐effectively  serve  its  retail  load.  Since  a substantial portion of Santa Clara’s energy needs are being met through contracts, SVP uses its energy, RA and transmission resources to buy and sell actively in five established wholesale power trading market zones: Mid‐Columbia (MID‐C), California‐Oregon Border (COB), North of Path 15 (NP15), South of Path 15 (SP15) and Palo Verde Hub. Trades may be directly with counterparties or through clearinghouses, such as the InterContinental Exchange (ICE).

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   36

5. Customer Programs, Energy Efficiency and Demand
Response Resources

5.1. Energy Efficiency Program Background
Targets  for  energy  efficiency  programs  (and  established  under  PUC  section  9505)  are  based  on  the estimated net market potential.14 The net market potential provides a forecast of market potential for specific  utility  energy  efficiency  programs.  The  net  market  potential  is  a  subset  of  the  total  economic potential and technical potential and recognizes that not all impacts that are technically or economically achievable will be realized.

Santa  Clara’s  energy  efficiency  programs  are  separated  into  residential  and  non‐residential  programs.

Total  Public  Benefits  Charge  (PBC)  funds  are  about  $16  million  in  fiscal  year  ending  2023.  Residential programs include rate assistance for income‐qualified customers, energy efficiency rebates (heat pump water  heaters,  room  air  cleaners,  pre‐owned  EV  rebates  for  income‐qualified  customers  and  variable speed pool pumps), energy audits, an income‐qualified solar grant program and programs for schools and libraries. Non‐residential programs include energy audits, installation management assistance for small companies, rebates for a wide variety of equipment (lighting, air conditioning systems, chillers, motors, new construction, food service equipment and customized installations, etc.), energy efficiency grants for nonprofit  organizations  and  Homeowners  Associations,  building  electrification  rebates  and  design  and construction assistance.

The goals and objectives of the programs are as follows:
 Implement cost‐effective energy efficiency programs to lower energy use. The cost to implement energy efficiency programs should be lower than the capital cost to build new generation and benefits of the total programs should exceed costs under the Total Resource Cost test under the methodology reviewed and approved by the NCPA Demand Management Working Group, of which SVP is a member.
 Provide the public benefit programs in a manner that creates value to the community and meets all applicable legal requirements.
 Assist Divisions and City Departments in achieving optimal energy efficiency at City facilities and assist in implementing new energy related technologies for the benefit of Santa Clara and community.

14 CMUA, “2020 Energy Efficiency Potential Forecast” (Sacramento, CA: California Municipal Utilities Association, 2020), https://www.cmua.org/sb1037‐reports.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   37
 Implement programs to support renewable power generation that increase resource diversity and minimize adverse environmental impacts from electric generation and operation of the electric system.
 Support emerging technologies to speed up market acceptance therefore, allowing energy efficiency services and products to compete in the open market.  Assist income‐qualified residents in lowering their electric bills and in installing energy efficient appliances and other measures.
 Determine the best energy programs to offer Santa Clara customers by collecting input from community organizations, businesses, and other city departments.

SVP  participated  in  the  California  Municipal  Utilities  Association  (CMUA)  Energy  Efficiency  Potential Forecasting Study. The most recent study was adopted by the Santa Clara City Council in 2021. Figure 15 presents the results of energy efficiency potential forecasting study.15 Figure 15. Forecasted Energy Efficiency Potential
Year  Utility Specified
Feasible Goal (MWh)
2021  11,584
2022  11,536
2023  11,013
2024  10,604
2025  8,913
2026  7,305
2027  6,651
2028  5,808
2029  5,817
2030  5,372

5.2. Current Energy Efficiency and Building Electrification Initiatives SVP  maintains  a  robust  suite  of  energy  efficiency  programs  that  will  contribute  to  the  state’s  goal  of doubling  statewide  energy  efficiency  savings  as  codified  in  SB  350.  Energy  efficiency  programs  are intended to  offer maximum  benefit  to  the community while meeting all regulatory requirements. The regulatory requirements include the following:
 PUC 385 requires that the utilities collect and spend a percentage of their base retail electric revenues on qualified Public Benefits Programs. The customary amount collected by public utilities in California is a minimum 2.85%of annual base retail electric revenues. The funds must

15 CMUA.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   38
be spent on programs in four categories including energy efficiency, research and development, renewable energy resource development and income‐qualified assistance.  PUC 386 requires each local POU to ensure that income‐qualified families have access to affordable electricity, and the level of assistance reflects the level of need. Furthermore, utilities shall ensure that income‐qualified families have access to low‐cost, no‐cost measures that reduce energy consumption.
 PUC 454.5 and PUC 9615 both require utilities to address unmet resource needs through energy efficiency and demand response prior to procuring new sources of power.  PUC 9505 requires each local POU to annually report investments and achievements in energy efficiency and demand reduction programs. Furthermore, utilities must identify all potentially achievable cost‐effective electricity efficiency saving and report savings targets to the CEC.  Public Resources Code 25305.2 requires the CEC to report to the Legislature a comparison of the annual energy savings targets versus the actual energy efficiency savings and demand reduction for each local POU.
 Public Resources Code 25310 I(1) requires the CEC to set goals that will double statewide energy efficiency savings in California by 2030 and will require specific targets for SVP.

A comprehensive list of energy efficiency projects and programs under consideration is presented here.

New Programs for Fiscal Year 2023/2024 to 2028/2029
 Commercial Solar and/or Solar Plus Battery Storage Performance Incentive Program – This program will provide performance‐based incentives to commercial customers who install large solar plus battery storage systems to assist in reducing the coincident peak demand and/or assist in areas where electric transmission and distribution resources are constrained. A performance‐based incentive for installation of large solar systems may also be offered if there are significant grid benefits to SVP for installations without battery storage systems.  Nonprofit Solar Grant Program – As part of the commercial solar rebate initiative, funds have been designated to provide grants to nonprofit facilities in Santa Clara interested in installing a PV system at their facility. The grant allows a portion of the funding to be spent on roof repairs or replacement to make the facility ready for a PV system.  Municipal Energy Efficiency Project On‐Bill Financing Program – This program will provide on‐ bill financing for projects implemented at Santa Clara facilities where the city is the utility account holder and that meet all other requirements of SVP’s energy efficiency programs.

Projects must have a payback period not more than 5 years after rebates. Payments will be spread across utility bills based on the payback period, not to exceed 5 years. The intent of this Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   39
program is to help Santa Clara city departments fund energy efficiency projects through utility bill savings.
 Scholarship Program for Income‐qualified Residents – This program will provide scholarships to customers who meet specified income requirements. Eligibility will be working age adults who enroll in a technical school or training program for a career that will support the energy industry.

Examples include but are not limited to HVAC technicians, solar system installers, utility line workers, etc. The intent of the program is to assist those with the lowest incomes to obtain the skills and certifications necessary to obtain higher paying jobs and to support workforce development in the energy industry or industries that support energy efficiency and building electrification programs.
 Income‐Qualified Used EV Rebate – This program will provide an incentive for income‐qualified customers to purchase a used EV or plug‐in hybrid EV. Incentives will be tiered to provide a higher incentive for an EV over a plug‐in hybrid and will include an equity component with a bonus incentive for those who qualify for the Low‐Income Home Energy Assistance Program. An additional bonus incentive may be included for vehicles meeting the specified minimum charging efficiency (kWh per 100 miles driven). Funding for past Income‐Qualified EV Rebates came from Low Carbon Fuel Standard Credit funding, and this program will be funded under the income‐qualified category of the Public Benefit Charge.

Ongoing Programs
 Residential Pool Pump Rebate – This program provides a rebate to residential customers installing a new variable speed pool pump with a qualifying controller.  Residential Heat Pump Electric Water Heater Rebate – SVP offers a rebate for the purchase of a qualified electric heat pump water heater with bonus incentives to income‐qualified customers.  Residential In‐Home Energy Audits, Education, and Hot Line: The program encourages residents to become more energy efficient and reduce their energy bills through home audits, online and in person classes, school programs and community outreach at events. Energy audits include free items to improve home weatherization where needed. This program also includes “Santa Clara could perhaps focus more on investing in
distributed  solar  in  the  near  term.” ‐ KJ,  Santa  Clara resident
Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   40
support of the Santa Clara libraries and schools through donation of materials on the topics of energy efficiency and renewable energy for libraries and classrooms.  Tier II Advanced Power Strip Giveaway Program: SVP provides free Tier II Advanced Power Strips (APS) to income‐qualified customers and residents of multifamily apartment complexes. A Tier II APS is also included in the energy saving items provided during a home energy audit.  Tool Lending Library: This program provides tools and equipment to the Santa Clara libraries so they may be checked out to library patrons to assist in measuring energy consumption and installing energy efficient measures in their homes.
 Silicon Valley Power Marketplace: The Marketplace is an online marketplace where residential customers can purchase energy saving equipment and electric yard care equipment. Instant rebates are available on some types of equipment, with higher rebate levels available to income‐qualified customers. Shipping is free on all purchases over $50 and is a flat rate of $5 per order for all other orders.
 Residential Blower Door and Duct Testing Pilot Program: To help customers improve the efficiency and comfort of their homes through the reduction of leaks, this pilot program will be available to residential customers in single family homes who have central air conditioning. A free SVP audit will be required to determine if the home is a good candidate for the blower door test. Duct testing is a much more involved process and will be offered to those customers who are a good candidate for reducing the leaks in their air conditioning duct system, who demonstrate an interest in taking action to improve the duct work, and who are not already doing an air conditioning system upgrade where a duct test is required by building code. The service will be free to eligible customers under the pilot program. At the time of this report, this pilot program is still in the design phase and has not yet been launched.  Customer Directed Rebate – This program provides incentives based on actual energy saved for energy efficiency measures that do not fall into SVP’s standard business rebate programs. The program also includes a performance incentive option for projects where persistence savings is questionable.
 Data Center Efficiency Program – This program targets data centers with IT server load greater than 350 kW or cooling load greater than 100 tons. The incentive is paid as a performance incentive over multiple years.
 Commercial New Construction Rebate:  This program provides a rebate to customers who exceed Title 24 by 10 percent for the measure being incentivized, in line with other prescriptive rebates for retrofit projects. A Design Team Incentive matching the Investor‐Owned Utilities program is provided.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   41
 Business Energy Audits: Provides free energy efficiency audits to business customers. Energy and Resource Solutions administers this and other business PBC programs.  Business Rebates: Encourages businesses to install energy efficient lighting, HVAC equipment, enhanced ventilation controls, food service equipment, etc. The programs are occasionally changed to match statewide programs.
 Small Business Efficiency Services Program – This program is targeted at small business customers, and aids in identifying energy efficiency projects, selecting and managing contractors, and help with filling out rebate application paperwork. The program also provides a 35%incentive for lighting and HVAC rebates, if customers to install the lighting measures within 6 months of program enrollment and HVAC measures within 12 months of enrollment in order to receive the additional incentive.
 Energy Efficiency Grant for Nonprofit Organizations: This program provides grants to non‐profit organizations to improve the energy efficiency of their facilities.  Building Operator Certification Training Scholarships: This program provides scholarships to building operators responsible for facilities in Santa Clara who meet the Building Operator Certification Training Program’s prerequisites. The coursework helps customers identify energy efficiency opportunities within their facilities, which can lead to energy efficiency project implementation.
 Energy Efficiency Grant for Homeowners Associations: This program provides a grant for Homeowners Associations to upgrade to more energy efficient equipment in the common areas of their communities.
 Community Outreach Grants for Energy Efficiency and Building Electrification Education: This program provides an opportunity for nonprofits and community‐based organizations to receive a grant up to $10,000 to promote energy efficiency and building electrification benefits within our community. A focus on traditionally underserved communities or diversity, equity and inclusion is required.
 Student Grants for Energy Efficiency and Renewable Energy Projects or Awareness Campaigns:

SVP offers grants up to $5,000 for high school students to create projects or awareness campaigns that will educate the Santa Clara community about energy efficiency and/or renewable energy. Examples include but are not limited to educational videos, public art displays, online resources, outreach materials, demonstration projects, webinars, or workshops.  Controls Program: This program is available for projects where at least 80% of the savings come from the control strategies. Incentives are paid on a performance basis over 5 years.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   42
 Building Optimization Rebate: For buildings with HVAC systems controlled by building automation systems, a rebate is provided for reprogramming the control system to optimize HVAC performance. Typically, this involves conducting an energy assessment that provides an implementation plan for testing and making control system improvements that optimize HVAC operation.
 Public Facilities’ Energy Efficiency Program:  SVP provides technical assistance and financial incentives for the expansion, remodel, and new construction of Santa Clara buildings. Included in this program are higher levels of rebates for qualifying equipment and energy management assistance.

Third Party Programs for Business Customers
As one of the ways to enhance energy savings through the PBC programs and meet kilowatt hour and kilowatt demand reduction goals, SVP periodically embarks on an Request for Proposal process to add third party energy efficiency programs to its Public Benefit Program offering. Of the responses received each cycle, a review team selects responses that are both cost‐effective and the most likely to help customers without overlapping with programs already being provided. The last Request for Proposal was issued in April 2018 and all selected programs have ended. An Request for Proposal is currently in process.

Complementary Programs
 Income‐Qualified Programs:
o Financial Rate Assistance Program: SVP’s income‐qualified programs include a Rate Assistance Program, where income‐qualified customers receive a 25% discount on their electric bill.
o Income‐Qualified EV Charging Station Grant for Multi‐family Properties: Under its income‐qualified programs, SVP offers a grant of up to $1,000 per charging station for multi‐family properties where a specified percentage of customers residing at the property qualify for SVP’s income‐qualified programs. This is in addition to the rebate program the utility offers to all multifamily complexes in Santa Clara.  Medical Assistance Programs
o Medical Rate Assistance Program: Customers receive a 25% discount on their electric bill if they qualify due to high electric use for medical reasons. The programs are managed in‐house.
 Research, Development, and Demonstration:

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   43
o Emerging Technologies Grant: This program encourages businesses to demonstrate new products and product applications not yet commercially viable in today’s marketplace, install energy efficient technologies not generally known or widely accepted, yet show potential for successful market growth, successfully apply energy efficiency solutions in new ways, or introduce energy efficiency into industries or businesses that are resistant to adopting new technologies or practices.
o APPA DEED Program: SVP is a paying member of the American Public Power Association (APPA) Demonstration of Energy & Efficiency Developments (DEED). This program funds grants, internships and student scholarships to further R&D in the electric utility industry and support innovative applications of energy efficient or renewable technologies. Over the years, SVP has applied for and received several DEED grants.

Most recently, SVP has received grants for additional research of ductless mini split HVAC units and for commercial food preparation appliance energy savings. o California Lighting Technology Center (CLTC): SVP provides financial support to the CLTC to further research and testing of emerging lighting technologies.  Building Electrification Programs:
o Heat Pump Water Heater Electrification Program: SVP provides funding for a regional midstream heat pump water heater electrification program through BayREN where enrolled contractors receive a $1000 incentive for installing an electric heat pump water heater in place of a natural gas water heater. SVP pays an additional incentive to income‐qualified customers.
o Multifamily Boiler Electrification Pilot Program:  This program provides up to $100,000 in funding for the conversion of a natural gas boiler to an electric boiler at multifamily complexes with at least 25 dwelling units. The program covers up to 100% of the incremental cost of replacing the gas boiler with an efficient boiler. o Smart Electric Panel Upgrade Rebates: SVP provides a rebate to residential customers who upgrade their electric panel to a smart panel and install circuits for both an EV charger and an appliance converted from natural gas to electricity. A bonus incentive is available to income‐qualified customers.
o Commercial Electrification Incentives: SVP provides bonus incentives for the electrification of efficient food service equipment. Incentives are also available for heat pump water heaters, heat recovery chillers, heat pump pool heaters and heat pump air conditioners. The utility also offers a Customer Directed Electrification Rebate that pays Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   44
an incentive based on measured and verified energy savings for any building electrification project that does not fall within its standard electrification rebates. o Induction Cooking Demonstration Project: SVP retrofitted the Santa Clara Unified School District’s Adult Education cooking classroom with induction cooktops and new cookware. The utility sponsors classes once or twice per month for residents to learn to cook new cuisine while trying out an induction cooktop. Adult Education cooking instructors were provided with training on the benefits of induction cooktops and lessons they can teach to demonstrate the benefits. Handouts are also provided to all program participants.

Ending Programs
 Residential Electric Dryer Rebate – This program provided a rebate for ENERGY STAR‐qualified electric clothes dryers that meet the minimum Combined Energy Factor rating. Due to low energy savings that can be claimed, this program ended June 30, 2023.  Variable Frequency Drive Air Compressor Rebate – This measure is for Variable Frequency Drives on rotary screw air compressors of 5hp – less than 25hp, as the energy code requires Variable Frequency Drives on compressors of 25hp or greater. Following customer outreach for this program, we found very little potential within Santa Clara, so this program was retired on June 30, 2023. If a customer has a qualifying air compressor and would like to install a Variable Frequency Drive, an incentive can be provided under the Customer Directed Rebate program.

5.3. Storage
In 2013, AB2514 codified Public Utilities Code Section 2836(B) that requires the governing board of each local publicly owned electric utility (POU) to determine appropriate targets for the utility to procure viable and cost‐effective energy storage systems to be achieved by December 31, 2016, and December 31, 2020, on or before October 1, 2014, as part of their supply plan. There are no requirements for POUs to set future  targets  for  energy  storage.  The  statute  also  requires  each  governing  board  to  re‐evaluate  the determinations made pursuant to this subdivision not less than once every three years, where the first three‐year period ended in 2017, and the second evaluation period ended December 31, 2020. All future updates are now included in the IRP process.

In 2017, SVP determined that energy storage was not cost‐effective, therefore, did not pursue energy storage targets. At the time, SVP analyzed three potential Research and Development pilot projects at the transmission,  distribution  point‐of‐interconnections,  and  behind‐the‐customer  meter  and  provided updates in the 2020 AB2514 submittal to the CEC, Docket Number 20‐MISC‐01 TN# 235878). In 2020, SVP had four on‐going pilot projects that were to be commercially operational from 2021 through 2023. What was  unanticipated  was  the  supply  chain  issues  that  arose  during  the  COVID  pandemic  and  the  price Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   45
escalation  of  Lithium  that  changed  the  economics  of  battery  storage  projects  (Figure  16).  Updates  on these projects are included in this plan.

Figure 16. Lithium Price ($/lbs) 2019‐202316

Current Utility‐Scale Energy Storage Projects
SVP is currently contracting with a third party to build and operate up to a 50 MW 4‐hour (200 MWh) utility‐scale  lithium‐ion  BESS  within  SVP’s  service  territory.  This  contract  will  allow  SVP  to  be  the beneficiary of the BESS for a twenty‐year term with an option to extend it for an additional five years. The BESS  will  participate  in  the  CAISO  market  and  will  have  the  capability  of  performing  intraday  energy arbitrage by charging the BESS when market prices are low (buying the energy from the CAISO market) and discharging the BESS  when  market prices are high (selling the energy into the CAISO  market) and capturing  the  difference  between  these  prices.  Typically,  the  BESS  will  charge  when  there  is  surplus renewable electricity on the CAISO grid. The BESS will also be able to help control voltage and frequency.

Using the BESS may help integrate renewables, reduce dependence on gas‐fired generation, and reduce GHG and criteria air pollutant emissions in Santa Clara. The BESS will also qualify as a resource adequacy resource and can be used to meet SVP’s RA requirements along with the other resources in SVP’s portfolio.

The BESS project is expected to be in commercial operation in late‐2025.

Current Microgrid Projects
SVP was developing two Renewable Energy Microgrids to support two City of Santa Clara Fire Stations for up to four hours of run‐time providing back‐up power during grid outages. SVP studied the feasibility of meeting  and  exceeding  6‐8  hours  long‐duration  run‐times  for  the  energy  storage  systems.  SVP  is

16  Daily Metal Price: Lithium Price. https://www.dailymetalprice.com/metalpricecharts.php?c=li&u=lb&d=1200

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   46
partnering with the Fire Department to prioritize Fire Station #1 , and Fire Station #2 with the potential to co‐locate the microgrid at Fire Station #2with co‐located public sites to enable a community microgrid concept. Due to increased costs, the microgrid project at Fire Station #1 is no longer feasible. Only Fire Station  #2  is  moving  forward  but  has  been  combined  to  include  more  structures  like  the  Emergency Operations Center for the City of Santa Clara. The project will demonstrate the installation of solar and storage and potentially EVs, integrated with smart microgrid components. The microgrids will support the research, design, deployment, and operations of a microgrid through the implementation of advanced energy management controller/software, load control, for standby power, energy and capacity and test feasibility to serve grid ancillary services. This project will also pilot an SVP specific engineered switch to enable future microgrids  to interconnect with the  SVP grid in  the future. The design was a result of a previous data center pilot that SVP had to cancel.

SVP is piloting microgrid concept to create more redundancy in its grid, enable the detection of outages and  faults  on  the  grid,  to  prevent  outages,  and  power  quality  events.  The  microgrid  automatically responds to a grid outage by islanding. The microgrid remains in island mode supporting the Fire Station and auxiliary load until a resynchronization command is issued. This allows the microgrid to autonomously support  the islanded loads during grid  outages and  then automatically resynchronize and resume grid connection  upon  restoration  of  normal  grid  voltage  and  frequency.  Additionally,  built‐in  software  will perform an analysis of the microgrid components to detect equipment and process inefficiencies.

SVP  will  be  receiving  $500,000  in  Federal  funding  to  help  bring  the  project  on‐line.  SVP  will  also  be exploring funding through the California Electricity Backup Assets Program when it launched later in 2023 or early 2024. The project is targeted to be commercially online in 2025.

Customer‐Sited Battery Storage and Solar Power Purchase Agreement SVP partnered with one of its commercial customers on a 2 MW/4MWh behind‐the‐meter battery energy storage system, charged for the most part from on‐site PV solar generation. The battery will be cycled daily  to  increase  renewable  energy  consumption  from  the  on‐site  solar  PV  system,  while  also  being discharged, to reduce run‐times for natural gas generation dispatch during the evening peak. Commercial operation of the solar PV and battery storage system was originally planned for October 2021 but due to cost increases and supply chain delays the new target is 2024.

Data Center Battery Storage Project
In 2018, SVP  was awarded a grant of $300,000 from the Bay Area Air Quality Management District  to implement a behind‐the‐meter lithium‐ion battery storage pilot project. SVP has partnered with a battery equipment manufacturer and a data center to pilot a demonstration project. The project was cancelled in 2022 due to the doubling of the project costs, from $2.5M to $5M. What was salvaged out of the four‐ year  project  was  the  engineering  design  of  a  specific  switch  that  allows  for  easy  “plug‐in”  of  future microgrids. This switch is projected to be utilized in the Fire Station Microgrid project (previously detailed).

The project was to demonstrate the use‐case for lithium‐ion batteries as longer‐duration uninterruptible power supply for data centers that are instantaneous and reliable, delaying or avoiding the use of diesel generators as backup power. Additionally, the pilot will demonstrate the economic viability and flexibility Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   47
of a 2 MW/4 MWh battery energy storage system (BESS) that can be simultaneously dispatched at 2 MW capacity to support critical loads during a power quality event or outage. The main target was to reduce GHG and particulate matter, with a focus on vulnerable communities.

Residential Distributed Energy Resources Resilience and Equity Program In  2019,  SVP  joined  three  community‐choice  aggregators  (CCAs),  East  Bay  Community  Energy,  Silicon Valley Clean Energy, and Peninsula Clean Energy in the release of a joint request for proposal for Resource Adequacy  and  load  modification  capacity  to  reduce  SVP’s  system  and  CAISO  coincident  peak.  SVP requested a total of 0.7 MW for the residential sector, and 2 MW for the commercial and industrial sectors.

SVP’s  Residential  Distributed  Energy  Resources  (DER)  Resilience  and  Equity  program  was  meant  to operationalize a fleet of residential PV‐paired battery systems as a peak shaving instrument and also to increase renewables and reduce GHG emissions in the most vulnerable communities through a virtual power  plant  concept.  The  program  would  prioritize  customer  segments  including  income‐qualified, medical baseline, and the disadvantaged communities. Additionally, the program intended to mitigate localized grid congestion and provide back‐up power during grid outages or PG&E’s Public Safety Power Shutoff  events.  The  program  would  also  evaluate  installations  at  single‐family  homes  and  multi‐unit dwellings.

In 2021, the selected vendor decided that SVP was not a big enough market and noted that our residential pricing structure is not high enough to make the venture work out economically SVP will re‐evaluate a new residential program in the future.

Green Lots – Tasman Drive Parking Structure
SVP completed a pilot energy storage project at the Tasman Drive Parking Structure with the intent to reduce customer‐side peak demand charges due to high energy consumption from EV level 2 and Direct Current  (DC)  fast  charging.  Green  Charge  Networks,  a  Santa  Clara  based  energy  storage  company, approached SVP to install a 30 kW “GreenStation” battery energy storage system along with an EV DC fast charger  station  at  this  location.  The  cost  of  the  energy  storage  system,  the  DC  fast  charger  and  the installation was covered by a CEC grant program, resulting in no costs to the City of Santa Clara or SVP.

The pilot ended in 2018, and through the monitoring of the EV Charging Station patterns, the pilot resulted in an increased usage of the EV charging stations from 2015 through 2018. It was concluded that given the large station count (49 in total), power demand is still peaking at a small fraction of the system capacity (under 17% for the 30‐day period from February 19, 2018 to March 21, 2018). The GreenStation is installed behind‐the‐meter and dampens the demand spikes that occur when the DC fast charging station is used, therefore reducing the operating costs for the City’s Streets Department due to the management of spikes to avoid an increase in demand charges. The battery was decommissioned and removed in 2023.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   48
Looking Forward
In the next five to ten years, SVP plans to focus its research on the deployment of energy storage projects and  to  develop  localized  system  integration  studies  to  determine  locational  nodes  in  SVP’s  service territory to alleviate congestion and to manage energy and capacity needs as well as maintaining balance of its grid. Other variables will also impact scalability and the use‐case for storage, including, SVP’s load growth,  increased  behind‐the‐meter  customer  distributed  energy  resources,  electric  vehicles,  and building  electrification.  The  deployment  of  storage  will  help  SVP  meet  on‐going  State  and  City‐wide renewable energy and sustainability goals and targets.

SVP plans to research the potential to participate in the CAISO wholesale market, including participating in  the  non‐generator  resource,  regulation  energy  market,  and  proxy  demand  response  participation models, which include not only bidding energy resources, but also ancillary services (frequency regulation, spin, non‐spin).

To manage, operate, and monitor performance, SVP intends to research an architecture that integrates each of its pilot programs into a distributed energy resources management platform, tied to additional microgrid  sites.  The  purpose  is  to  enhance  coordination  amongst  DERs,  dispatch,  and  communication across DER assets connected to the grid to optimize reliability, safety and efficiency when operating the distribution grid.

SVP believes that commercially available long‐duration technologies tied to clean fuel sources that can be stored on‐site will be required to transform adoption at the utility‐scale level. SVP and its customers must have confidence that there is no interruption to the electric or gas supply if on‐site fuel cannot be achieved, otherwise  storage  fuel  must  be  dense  enough  to  store  on‐site.  Further,  SVP  anticipates  that  more demonstration projects from utilities and utility‐customer partnerships will be required to test end‐use applications, monitor stacked benefits, and to help scale the technology. Grant funding along with the decrease in energy storage costs will be needed to assist in bringing down the total installed costs of the systems. Additional federal, state, and local incentives and grants can encourage investment to scale the technology and test various end‐use applications.

Lastly, SVP will continue to benchmark new storage technologies, assess scalability and cost‐effectiveness, and  pilot  new  programs/projects  that  foster  a  diverse  set  of  clean,  hybrid  and  long‐duration  energy storage technologies. Because the City of Santa Clara is approximately 18.4 square miles, new storage technologies sited within the city’s boundaries must be energy dense to accommodate space constraints.

5.4. Transportation Electrification
Transportation electrification and zero‐emission vehicle (ZEV) policies have been gaining momentum in recent years, both at the state and federal levels. California has been a leader in this movement, with its Zero‐Emission Vehicle Program that requires automakers to produce a certain number of EVs each year.

The state has also set a goal to have 5 million ZEVs on the road by 2030.

At the federal level, the Biden administration has set a goal of reaching net‐zero emissions by 2050 and has proposed investing $174 billion in EV infrastructure, including  charging stations and incentives for consumers to buy Evs. The most significant legislation to accelerate transportation electrification in U.S.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   49
history was the Inflation Reduction Act (IRA) of 2022, which was signed into law on August 16. The IRA introduced several significant changes to the tax credit for new Evs and the reforms to the $7,500 tax credit for Evs will evolve considerably over the coming months and years. The IRA also established tax credits for pre‐owned clean vehicles and for commercial clean vehicles.

California calls for a 40% reduction in GHG emissions from 1990 levels by 2030 and an 80% reduction by 2050 per Executive Order S‐3‐05 (2005). Air quality goals include a 90% reduction in emissions of Nox from 2010 levels by 2032. In January 2018, Governor’s Executive Order B‐48‐18 set a goal of 5 million ZEVs on California  roads  by  2030  and  directs  state  agencies  to  accelerate  deployment  of  250,000  chargers (including 10,000 direct current fast chargers (DCFCs) by 2025). SB 350 requires state agencies to identify recommendations  on  how  to  increase  access  to  zero‐emission  and  near‐zero‐emission  transportation options to income‐qualified customers. In December 2018, CARB passed the “Innovative Clean Transit” policy stating that by 2023, one quarter of purchased transit buses need to be zero emission, and by 2029, 100% of new buses purchased need to be zero emission. Governor’s Executive Order B‐55‐18 directs state agencies  to  work  together  to  support  the  deployment  of  ZEVs  in  California,  including  through  the development of infrastructure and incentives. Most recently in 2020, Governor’s Executive Order N‐79‐ 20 set a goal of transitioning all new passenger cars and trucks sold in California to ZEVs with the share of VEZ and plug‐in hybrid electric vehicles (PHEV) to reach 100% of new vehicle sales by 2035. CARB codified the Governor’s EO N‐79‐20 for light‐duty passenger vehicles with the adoption of the Advanced Clean Cars II rule that established a year‐by‐year roadmap for the share of VEZ to reach 100% of new vehicle sales by 2035.

One  of  California’s  most  important  policies  is  the  Zero‐Emission  Vehicle  Program,  which  requires automakers to produce a certain number of ZEVs each year. The program was first implemented in 1990 and  has  since  been  updated  several  times.  In  2020,  the  state  adopted  new  regulations  that  require automakers to sell an increasing percentage of ZEVs each year. By 2025, automakers must sell enough ZEVs  to  account  for  8%  of  their  total  sales  in  the  state.  In  addition,  the  Advanced  Clean  Trucks  (ACT) Regulation requires manufacturers of medium‐ and heavy‐duty vehicles to sell a certain percentage of zero‐emission trucks in California, starting in 2024. SVP aims to prepare Santa Clara for success as new clean fleet requirements are set by the state. In April 2023, the CARB adopted the Advanced Clean Fleets regulation that requires beginning January 1, 2024, 50% of State and Local Government Agency Fleets annual  vehicle  purchases  per  calendar  year  to  be  zero‐emissions,  and  beginning  January  1,  2027,  that 100%of vehicle purchases to be zero‐emissions.

California has also implemented several financial incentives to encourage consumers to buy ZEVs. The state offers rebates of up to $7,000 for the purchase or lease of a new EV, and there are also federal tax credits  available.  Additionally,  California  allows  ZEVs  to  use  carpool  lanes  regardless  of  how  many passengers  are  in  the  vehicle,  providing  an  added  incentive  for  drivers.  In  2020,  SVP  along  with  other California electric utilities teamed up with CARB to offer the California Clean Fuel Reward, a point‐of‐sale price reduction of up to $1,500 for the purchase or lease of any eligible new Battery Electric or Plug‐in Hybrid vehicle. As of 2023, the reward amount has temporarily been reduced to zero and SVP is engaging with program stakeholders on the future strategy of the program.

To support the increased adoption of ZEVs, California has also invested heavily in charging infrastructure.

The AB 2127 Electric Vehicle Charging Infrastructure Assessment found that for passenger vehicle charging Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   50
in 2030, over 700,000 public and shared private chargers are needed to support 5 million ZEVs, and nearly

1.2  million  chargers  to  support  about  8  million  ZEVs  anticipated  under  Executive  Order  N‐79‐20.  An additional 157,000 chargers are needed to support 180,000 medium‐ and heavy‐duty vehicles anticipated for 2030.

Local Government Regulatory Landscape
SVP encourages the use of Evs as a part of our commitment to reduce carbon emissions. With convenient and publicly accessible EV charging stations, residents and business can help accelerate the efforts. Since 2019,  Santa  Clara  has  initiated  a  suite  of  Council  actions,  policies,  and  strategies  to  be  an  EV  ready community by 2030.
 May 2019 – Adopted a Green Fleet Policy
 June 2019 – Adopted the EV Ready Community Blueprint
 April 2020‐ City Council approves a Public and Fleet Infrastructure Access Project  January 2021‐ City of Santa Clara Fleet Electrification Plan  September 2022‐ City Adopted All‐Electric Reach Codes SVP designed and built a robust and accessible EV charging infrastructure that maximizes the number of residents and visitors served. SVP has added over 100 EV charging connectors throughout Santa Clara’s 18  square  miles  in  parks,  community  centers  and  other  public  access  areas  near  multifamily  housing; providing an amenity that increased park utilization and access to EV charging to residents who may not have access to charging at home.

SVP has also helped Santa Clara reduce its fleet operational costs and environmental impact by replacing Santa  Clara‐owned  old  combustion  vehicles  with  all‐electric  vehicles.  SVP  purchased  46  all‐electric vehicles and an electric forklift to support Police, Fire, Public Works and other City department fleets in fiscal  year  2022.  Santa  Clara  will  receive  the  benefits  of  lower  operating  and  maintenance  costs  EVs provide as well as a reduction in smog and GHG emissions from operating their vehicle fleet.

In parallel with purchasing cleaner vehicles for Santa Clara, SVP also installed EV charging stations at City facilities to support the new clean fleet. SVP took a holistic approach using design thinking by partnering early  with  other  City  departments  to  select  optimal  locations  and  helped  streamline  the  permitting process for future EV charging projects. SVP also explored enhancing projects with faster charging times and additional resiliency by adding renewable solar PVs plus storage. By Q3 2023, SVP energized nearly 50 additional charging ports at 8 locations supporting public and fleet charging and plans the next phase of EV charger installations to prepare for the City’s incoming medium and heavy‐duty fleet.

Using CARB’s Clean Vehicle Rebate Project (CVRP), which began tracking rebates for purchased ZEVs in 2011 through 2022, 2,764 battery‐electric, 910 plug‐in hybrids, 99 fuel cell, and 5 categorized as other vehicle rebates have been distributed for a total of 3,778 clean vehicle rebates registered within Santa Clara. Note that not all plug‐in hybrid, all‐battery, and fuel cell EVs sold/leased in the state are captured in  this  database.  Not  every  eligible  vehicle  owner  applies  to  the  CVRP,  and  not  every  clean  vehicle  is Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   51
eligible for the rebate. Over the first five years of the program, owners of about 75% of eligible vehicles participated in the rebate project. Department of Motor Vehicle (DMV) registration data is a preferred source for a more accurate estimate of current Plug‐in Electric Vehicle (PEV) adoption within a city; that data can also provide information on vehicle class for commercial vehicles. However, neither of these sources  forecast  vehicle  ownership  trends  or  inflow  of  traffic  from  surrounding  areas.  SVP  requested registration data from the DMV on a bi‐annual basis beginning 2023 to support SVP’s energy procurement, transmission,  and  distribution  planning  for  transportation  electrification.  In  partnership  with  other northern California municipal utilities, SVP is actively coordinating with the DMV to establish a registration data sharing protocol that would enable data collection on a more frequent cadence. As Californians adopt more  hybrid  electric  and  alternative  fuel  vehicles,  we  are  working  on  a  transportation  electrification strategy to prepare their electrical distribution grid for the future demands. SVP is also exploring managed charging programs using vehicle telematics to coordinate the customer side of the meter with the utility’s side,  optimizing  critical  assets  throughout  the  distribution  network.  In  addition  to  shifting  charging  to times of day when there is more renewable energy supply on the grid, managed charging programs can also defer costly upgrades to distribution grid assets. SVP is also exploring fleet advisory program offerings such as online fleet planning tools and technical assistance for fleet customers in our service territory.

SVP also utilizes CEC new ZEV sales data which is updated on a quarterly basis by examining the DMV Vehicle Registration database to track vehicle adoption in Santa Clara. By the end of June 2023, the CEC reported a cumulative total of 8,824 all‐electric vehicles, 2,596 plug‐in hybrid EVs, and 140 hydrogen fuel cell vehicles in Santa Clara as shown in Figure 17.

Figure 17. New Zero Emission Vehicle Sales by year: Santa Clara

Figure 18 shows the cumulative growth of ZEV rebates dollars distributed though the CVRP program within SVP’s service territory, by vehicle type, from 2011‐2023. The slight decline in annual rebates in 2019 was

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   52
due to popular rebate‐eligible vehicles. Reaching 200,000 sold in the U.S. and thus no longer qualifying for  the  federal  PEV  rebates.  The  IRA  of  2022  changed  the  rules  for  the  federal  tax  credit  for  vehicles purchased  from  2023  to  2032  which  made  certain  vehicles  eligible  again.  The  decline  was  further exacerbated  by  the  Covid‐19  pandemic  which  unfolded  in  early  2020  and  imposed  global  lockdowns leading to an unprecedented drop in car sales. Despite gradual recovery over the following year, the ZEV market also suffered from a rippling effect of global supply chain issues limiting vehicle availability.

Figure 18. CVRP Rebate Dollars in SVP Service Territory by year

Figure 19. Cumulative SVP ZEV Rebates by ZEV Type, 2011‐2018 Rebates and Rebate Funding Issued or Approved to Date
Battery Electric Vehicle  2,869  $7,304,362
Plug‐in Hybrid Electric Vehicle  912  $1388,284
Fuel‐cell Electric Vehicle  105  $522,500
Other  5  $4,200
Total  3891  $9,219,346

For the SVP service area, EV forecast involves a significant increase in the number of vehicles through 2026.  Figure  20  shows  the  cumulative  number  of  EVs,  including  EVs  and  PEVs  that  are  projected  to increase from approximately 2,200 in 2018 to more than 24,000 by 2030 based on the CEC EV model.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   53
Figure 20. CEC Projected EV Adoption (cumulative)

SVP EV Readiness by 2030
In  December  2017,  the  CEC  released  a  Grant  Funding  Opportunity  (GFO‐17‐604)  for  EV  Ready Communities Challenge Phase I – Blueprint Plan Development.

On May 9, 2018, at the CEC Business Meeting, SVP was officially awarded a grant to develop an EV Ready Communities  Blueprint.  SVP,  along  with  various  Santa  Clara  city  departments  and  stakeholders,  has completed and developed the Electric Vehicle Ready Communities Blueprint (EV Blueprint) for Santa Clara per the grant requirements. The EV Blueprint identifies the actions and milestones needed to proceed toward implementation of an EV ready community through 2030. When the CEC solicited Phase II of the grant funding in 2020, SVP used the EV Blueprint as a submission for the application but unfortunately was  not  awarded  Phase  II  funding.  The  EV  Blueprint  for  Santa  Clara  defined  goals  and  requirements, analyzed  target  areas,  provided  technical  recommendations,  and  economic  recommendations  for charging infrastructure; and evaluated city programs to be implemented. The EV Blueprint also forecasted the  number  of  PEV  adoptions  which  included  both  person  and  commercial  vehicles.  Recognizing  the inherent  uncertainty  in  any  forecast,  and  especially  in  nascent  technology,  the  EV  Blueprint  Team developed three forecast cases: low, base, and high. The base case was based on SVP’s 2018 IRP using the “2017 SB 350 Common Assumptions Guidelines for Transportation Electrification Analysis.” To place that forecast in context, the EV Blueprint Team set a low case assuming no further PEV adoption and a high case based on Siemens proprietary PEV adoption forecasting tool, which resulted in adoption rates closely aligned with California’s statewide five million ZEV goal by 2030. Figure 21 shows the number of PEVs and required charge connectors forecasted for each of the adoption scenarios.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   54
Figure 21. Forecasted Plug‐in Vehicles and Charging Requirements, Cumulative – Santa Clara

Source: SVP 2019 EV Readiness Blueprint
Current Electric Vehicle Charge Connectors
By  2022,  Santa  Clara  and  its  businesses  had  installed  753  Level  2  charging  connectors  and  39  DCFC charging connectors. Note that a typical charging station contains multiple charging connectors to plug into multiple vehicles. In Santa Clara, the average charging station has six charging connectors. Using the Alternative  Fuels  Data  Center  (AFDC),  Santa  Clara  tracks  installation  of  public  and  private  charge connectors.17  This information, as well as ownership type, is detailed in Figure 22.

Figure 22. Current Charger Port Installations by Type and Ownership18 EV Ownership Type  EV Level 2 EVSE  EV DC Fast
Private  47  0
Public  726  39
Total  773  39
The 812 public and private charge ports currently within Santa Clara are found in 340 different locations, for an average of 2.4 charge ports per location. However, specifically for DCFC, there are only one or two charge ports per location. Figure 23 maps where PEV chargers are located within Santa Clara, based on city permitting data. Most of the charging infrastructure is in the northern part of Santa Clara, zip code 95054, with 83% of all charge ports. Figure 24 details the distribution of EV chargers in Santa Clara by ownership,  charger  level,  and  location  relative  to  the  CalEPA  SB  535  designated  disadvantaged communities (DAC) area and the Justice 40 Initiative criteria area. Santa Clara currently has a total of 113

17 U.S. DOE, “Electric Vehicle Charging Station Locations,” U.S. Department of Energy, Alternative Fuels Data Center, 2023, https://afdc.energy.gov/fuels/electricity_locations.html#/find/nearest?fuel=ELEC. 18 U.S. DOE.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   55
city‐installed Level 2 public charging ports located at Libraries, Community Recreation Centers, Santa Clara Convention Center, Tasman Garage, City Hall, and Parks. Two DCFC ports at the Central Park Library and the  Santa  Clara  Convention  Center  have  been  identified  for  replacement.  Figure  23  maps  where  PEV chargers are located within Santa Clara, based on city permitting data.

Figure 23. Map of PEV known Chargers within Santa Clara 19

19 Source: SVP Geographic Information Systems Team

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   56
Figure 24. EV Charger Distributions by Santa Clara Zip Codes

Grid Impacts of EV Adoption
SVP’s primary responsibility is to  provide safe, reliable  power, while limiting future cost increases and complying  with  city  core  values.  PEV  adoption  poses  both  risks  and  opportunities  to  utilities  as summarized in Figure 25. Since SVP’s electricity sales are primarily commercial/industrial, its energy use and  peak  demand  profile  is  relatively  flat  monthly.  However,  SVP  has  historically  experienced  sudden increases in electricity demand at times, as customers move into new facilities. Data center loading can cause SVP’s load growth profile to be “lumpy”, due to new connections of substantial blocks of power‐ consuming facilities or equipment by industrial customers. This profile is reflective of the high intensity of industrial  energy  use  in  SVP’s  service  area,  which  is  heavily  weighted  toward  high‐technology manufacturing and data management facilities. To accurately plan impacts of PEV adoption on the grid, the SVP  EV Blueprint Team first gathered data on The City forecasted energy demand for electricity then identified the utility risks and opportunities from PEV adoption.

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   57
Figure 25. Utility Risks and Opportunities from PEV Adoption20

Unlike  many  cities,  which  experienced  lower  than  expected  load  growth  due  to  energy  efficiency programs,  and  DER,  Santa  Clara  is  experiencing  consistent  growth  in  energy  and  peak  demand.  Both energy and peak demand have been consistently increasing over the years and this trend is forecasted to continue going forward. The current forecast for PEV energy demand by 2030 is an additional 52 GWh to 143 GWh based on preliminary modeling. Overall, anywhere from a 0.70% to 2.61% of SVP’s total load demand.

SVP conducts Forward System Planning on an annual basis through a System Impact Study process, where load  estimation  from  various  SVP  departments  is  incorporated  into  a  set  of  unified  planning  input assumptions and studied under a variety of Planning Scenarios. The outcomes of the System Impact Study process  are  the  determination  of  system  constraints  along  with  an  assessment  of  mitigation  options (Operationally, or Capital Improvement Project – CIP based) and associated costs. The Public Facing case is submitted annually to the CEC IEPR and CAISO Transmission Planning Process (TPP). For CY2023 TPP 24/25 SVP System EV Load Impacts will be studied as part of our annual System Impact Study process for the first time internally under a sensitivity scenario.

SVP also plans to conduct a 20‐Year Forecast beginning Q3‐Q4 2023 that will include a Spatial Analysis of Light, Medium and Heavy EVs and identify where the load will materialize on SVP’s system via Santa Clara city  geographic  information  system  (GIS)  parcel  map  (each  parcel  assigned  to  a  feeder).  SVP  will  also identify  requirements  to  manage  EV  growth  (including  sensitivities  for  both  known  &  unknown  load growth).  In  addition,  SVP  plans  to  update  its  2019  EV  Readiness  Community  Blueprint  and  develop  a comprehensive Equity Focused Transportation and Building Electrification Plan. The primary purpose of the  EV Blueprint was  to develop a program of initiatives the City of Santa Clara could lead to support increased EV adoption and the many benefits which derive from that adoption. The plan update should

20 Source: SVP EV Ready Communities Blueprint 2019

Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   58
expand  on  that  initiative  to  include  the  equitable  transition  to  electrify  both  transportation  and  built environment. The Equity Focused Transportation and Building Electrification Plan development process should establish a firm planning foundation that involves engaging internal and external stakeholders, analyzing the current state of transportation and building electrification, forecast long‐term impacts of Plug‐in Electric Vehicle (PEV) and building electrification adoption, and prioritize key requirements to help Santa  Clara  meet  greenhouse  gas  emissions  reduction  targets  as  identified  in  the  City’s  2022  Climate Action  Plan.  The  plan  shall  develop  supporting  analysis  for  multiple  electrification  scenarios  in  its forecasting  and  provide  recommendations  that  provide  Santa  Clara  with  a  clear  understanding  of  the technical and economical requirements to support EV and building electrification adoption specific to the City’s  ecosystem  and  its  clean  energy  goals.  The  study  aims  to  determine  SVP’s  incremental  resource needs by comparing SVP’s load and resource forecast against key Integrated Resource Plan constraints (including  resource  adequacy  requirements,  Clean  Energy  and  Climate  Act  targets);  identify  gaps  for meeting  the  constraints;  identify  cost‐saving  opportunities  under  existing  arrangements;  and  propose resource  solutions.  The  plan  should  develop  a  strategy  to  connect  resource  planning  and  beneficial electrification to form a cohesive decarbonization strategy.

Low Carbon Fuel Standard
In October of 2016, SVP entered a voluntary CARB program called the Low Carbon Fuel Standard (LCFS) Program. The LCFS Program was created through AB 32, California Global Warming Solutions Act of 2006 and  Governor’s  Executive  Order  S‐01‐07.  The  LCFS  Program  is  a  key  part  of  a  comprehensive  set  of programs in California to cut GHG emissions and other smog‐forming and toxic air pollutants by improving vehicle technology, reducing fuel consumption, and increasing transportation mobility options. The LCFS Program is designed to decrease the carbon intensity of California’s transportation fuel pool and provide an increasing range of low‐carbon and renewable‐powered alternatives. The goal of this program is to reduce by at least 20% the carbon intensity of California’s transportation fuels by 2030.

Through  compliance  with  the  LCFS  Program,  SVP  receives  LCFS  credits.  These  credits  are  sold  in  an exchange and these funds are to be used to comply with Title 17 of the California Code of Regulations Section  95483I  (1)  (A‐D),  LCFS  program  proceeds  may  only  be  used  in  accordance  with  the  following requirements.

Regulated Parties for Electricity
For electricity used as a transportation fuel, the party who is eligible to generate credits is determined as specified below:

For on‐road transportation fuel supplied through EV charging in a single‐ or multi‐family residence, the Electrical Distribution Utility is eligible to generate credits in its service territory. To receive such credits, the Electrical Distribution Utility SVP must:
 Use all credit proceeds to benefit current or future EV customers;  Educate  the  public on the benefits of EV transportation (including environmental benefits and costs of EV charging, or total cost of ownership, as compared to gasoline); Customer Programs, Energy Efficiency and Demand Response Resources2023 Integrated Resource Plan2023 Integrated Resource Plan
2023 Integrated Resource Plan   59
 Provide  rate  options  that  encourage  off‐peak  charging  and  minimize  adverse  impacts  to  the electrical grid; and
 Include  in  annual  compliance  reporting  the  following  supplemental  information:  an  itemized summary  of  efforts  to  meet  requirements  (A)  through  (C)  above  and  costs  associated  with meeting the requirements.

The LCFS combined with other programs, enables SVP to create an EV program that includes the following initiating activities in fiscal year 2021/22. SVP used LCFS proceeds to fund a residential electric bicycle rebate program where customers could receive a 10% rebate on the purchase price of a new e‐bike, up to $300. Income‐qualified customers were eligible to receive an additional rebate up to $200. SVP also funded an EV charging station rebate program to residents (up to $550), multi‐family properties (up to $3,000), schools and non‐profits (up to $5,000). We also offered an additional grant of up to $1,000 for the purchase and installation of qualified Level 2 EV Charging Stations to income‐qualified multi‐family properties.  Beginning  January  1,  2023,  SVP  increased  the  rebate  amounts  for  the  multifamily  and commercial EV charging station rebate program that provided increased per port incentives (up to $8,000) for projects that installed 8+ charging connections. SVP’s rebate program offers up to $150,000 per site for Multifamily Residential Properties and Commercial Properties to help lower the upfront costs of Level 1 and Level 2 EV charging station projects. Increased incentives are available for projects that meet equity eligibility criteria.

In addition to offering rebates on the EV chargers, SVP also funded a income‐qualified EV rebate up to $1,500 to qualifying customers who purchased a new or used EV or plug‐in hybrid vehicle. In July 2023, this program transitioned to an income‐qualified rebate up to $3,500 for the purchase of a pre‐owned EV or  plug‐in  hybrid  vehicle.  Income  qualified  customers  can  receive  $1,500  for  a  fully  electric  vehicle  or $1,000  for  a  plug‐in  hybrid  vehicle.  Customers  who  meet  the  Low‐Income  Home  Energy  Assistance Program eligibility requirements may be eligible for a bonus rebate of $1,000. Vehicles with a miles per gallon gasoline equivalent of 117 or greater may be eligible for a bonus rebate of $1,000.

LCFS  proceeds  were  also  used  to  fund  the  Electric  Vehicle  Charging  Access  Project  that  furnished  and installed Santa Clara‐owned Level 2 EV chargers at 16 public locations, libraries, parks, and community centers, near multi‐family properties and 6 city locations to jumpstart the implementation of the city’s Fleet Electrification Plan. LCFS funds were also spent to fund the California Clean Fuel Reward and the Peninsula‐Silicon Valley California Electric Vehicle Infrastructure Project 1.0 program. In 2021 and 2022, as a medium‐sized POUs, SVP was required to transfer funds to the CFR Program equal to 20% of proceeds generated from base credits from the LCFS program. Beginning 2023, the CFR requirement increased to 25%. The Peninsula‐Silicon Valley Incentive Project is no longer accepting applications as of June 2023.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   60

6. SVP System Modeling Approach

6.1. PLEXOS LT Overview
E3 performed resource portfolio optimization in this study using PLEXOS LT, an electricity system capacity expansion model that identifies the least‐cost long‐term combination of generation investments subject to reliability, policy, and operational constraints.21 PLEXOS LT considers investment costs, fixed costs, and production costs to simultaneously optimize long‐term capacity expansion and dispatch decisions. This allows  the  model  to  directly  capture  dynamic  trade‐offs  between  investments  and  dispatch,  such  as energy storage investments versus renewable curtailment and/or overbuild. PLEXOS LT also captures the reliability contributions of all resources to the system towards satisfying its reliability constraint.

Figure  26  provides  an  overview  of  the  PLEXOS  LT  model  including  the  objective  function,  key  model decisions, and key constraints.

Figure 26. Overview of the PLEXOS LT Model

6.2. Objective Function
The objective function minimizes the net present value (NPV) of electricity system forward looking costs over the planning horizon subject to constraints. Forward‐looking costs include investment costs, fixed costs, and  production costs. Investment costs include the  capital  costs of new generation and storage resources.  Fixed  costs  include  fixed  operations  and  maintenance  (FO&M)  costs  of  existing  and  new resources. Finally, production costs include variable operation and maintenance (VO&M) costs of existing

21 PLEXOS is a widely‐used commercially available software package from Energy Exemplar for electricity system modeling.

PLEXOS LT is the Long‐term plan phase of PLEXOS used for capacity expansion modeling.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   61
and new resources, fuel costs, and the costs of imported power (offset by any exported power revenues).

Figure 27 depicts an example optimal portfolio for a capacity expansion problem’s objective function.

Figure 27. Objective Function of Capacity Expansion Problem

The  objective  function  is  also  subject  to  investment  and  operational  constraints  (see  next  section).

Investment  constraints  include  maximum  resource  potential  for  addition/retirement  candidates (max/min units built/retired), and other potential policy‐related constraints, such as minimum RPS and SB 100  procurement  requirements,  emissions  reductions  requirements,  and  minimum  reliability requirements.  Operationally,  the  model  is  constrained  by  the  hourly  energy  balance  in  each  modeled period, resource limits set by energy, fuel, emissions, and other limits of generation and storage.

6.3. SVP System Representation
In E3’s modeling approach, SVP’s system is represented with a simplified zonal topology consisting of two nodes (“SVP” and “External”) and a single transmission connection. The SVP node contains SVP’s load and local existing and planned resources (DVR, Cogen, Gianera, and the planned BESS project). The External node contains SVP’s other existing and planned resources, candidate expansion resources, and the CAISO market, with which SVP can buy and sell electricity. Figure 28 illustrates SVP’s simplified topology used in the capacity expansion model.

Figure 28. Simplified Topology for Capacity Expansion Model

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   62
In addition to their contracted resources, SVP can execute market transactions with other CAISO entities for energy, RECs, and RA attributes. For the IRP, only the energy market interactions are modeled. In every hour of the modeling horizon, SVP has the option to either purchase electricity from the market to serve load or to sell generation from its owned/contracted portfolio to the market. These interactions include both  the  cost/value  of  imports/exports  as  well  as  the  associated  carbon  emissions.  In  the  SVP  system topology (Figure 28), the CAISO Market is in the External Node, and any purchases must flow over the transmission line to serve SVP’s load.

The hourly market price forecast used to Inform SVP’s market decisions is derived from E3’s CAISO Market Price Forecast dataset.22 Annual averages of the hourly price forecast are provided in Figure 29. Average market  prices  over  the  2025‐2035  horizon  are  primarily  influenced  by  near‐term  solar  build‐out  and transmission flow constraints between Northern and Southern California. The hourly market prices are correlated  to  the  market  emissions  rate,  discussed  in  Section  6.4.  E3’s  price  forecasts  represent  a fundamentals‐based view of the CAISO market, including long‐run portfolio changes to meet the energy, reliability, and policy requirements of the region.

Figure 29. CAISO Market Average Annual Price Forecast, $/MWh

Price forecasts used in capacity expansion modeling are typically an hourly‐varying input price stream that does  not  change  with  system  dynamics.  While  these  price  streams  are  useful  to  approximate  the complicated dynamics that occur outside the area of interest, they can, in many instances, overstate the arbitrage  opportunities  that  may  exist  between  external  resources  and  resources  within  the  area  of interest  (i.e.,  SVP’s  territory).  To  the  extent  that  unrealistic  arbitrage  opportunities  exist  for  these transactions, the result may be a portfolio that is too reliant on external transactions relative to what will be realized in practice. It is therefore prudent for modeling and planning to restrict market transactions

22 Purchase required. https://shop.ethree.com/product/caiso‐price‐forecast‐2022‐edition‐core‐case/.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   63
in  capacity  expansion  simulations  to  minimize  the  impact  that  these  transactions  may  have  on  the resource portfolio.

To limit speculation on external market revenues from biasing SVP’s portfolio economics, for IRP modeling in PLEXOS, sales to the CAISO Market are capped at 20% of SVP’s load in each hour, and 5% of SVP’s annual load  in  each  year.  These  values  were  determined  based  on  SVP’s  historical  market  activity  and  risk tolerance to market exposure. These constraints prevent the over‐procurement of resources for energy trading and limit any model behavior associated with a potential disequilibrium between the market price forecast and the SVP IRP inputs. These constraints only impact market interactions and do not limit the availability  of  SVP‐contracted  resources  in  the  External  node  (Section  4,  Section  7)  to  utilize  SVP’s dedicated transmission lines.

In  Scenario  3:  Zero  Emissions  with  Emerging  Technology  (Zero  Emissions  Scenario),  market  activity  is restricted to obey the zero hourly emissions rule, whereby emissions are only allowed during hours with 0 MT CO2/MWh emissions factors (i.e., when excess renewable energy in the CAISO would have otherwise been curtailed). This is discussed in detail in Section 6.4.

6.4. Model Constraints
Resource Adequacy Modeling Approach
Traditionally, for near term local resource adequacy the CEC published a monthly Coincident Peak for all CAISO load serving entities (LSEs), including SVP, based on their respective load forecasts for the following year. Per CAISO Tarif Section 40 From the coincident peak number the CEC and CAISO required LSEs to provide sufficient capacity to meet each LSE’s needs (115% of the coincident peak), through Local and System requirements for the upcoming year. The Local Requirement is the amount of capacity required to be satisfied by local resources classified as being able to meet that LSE’s local Requirement, and the remaining amount can be satisfied by system resources not tied to a specific location.23 However, the long‐term RA requirements and future input data for SVP (PRM, resource accreditation, etc.) are  uncertain  as  the  California  Public  Utilities  Commission  (CPUC)  moves  towards  the  “slice‐of‐day” approach  for  resource  adequacy.24 Once  slice‐of‐day  is  implemented,  CPUC  jurisdictional  LSE  resource accreditation  will  be  done  within  a  spreadsheet  model  using  LSE  specific  loads;  no  resource  level accreditation metrics (like the average ELCCs published for solar and wind historically) will be available for POUs to utilize. Even if the historical approach were to be maintained, there are no public CAISO system level  forecasts  of  average  ELCCs  for  solar,  wind,  and  storage,  which  form  the  bulk  of  forecasted  SVP capacity additions. For these reasons, SVP has opted to follow the long‐term planning method for system reliability needs consistent with the CPUC‘s approach for its jurisdictional LSEs utilized in the current 2022‐

23 SVP Local Area Requirements can be satisfied by resources within the local areas of Humbolt, North Coast/North Bay, Stockton, Greater Bay, Greater Fresno, Kern, Bid Creek/Ventura, LA Basin, San Diego/Imperial Valley 24 CPUC, “Resource Adequacy Homepage,” California Public Utilities Commission, 2023, https://www.cpuc.ca.gov/industries‐ and‐topics/electrical‐energy/electric‐power‐procurement/resource‐adequacy‐homepage.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   64
2023  CPUC  IRP  cycle.  This  approach,  as  described  in  the  following  section,  plans  for  the  “marginal reliability need” using marginal effective load carrying capability (ELCC) accreditation for all resource types.

Local reliability needs are not explicitly optimized in SVP’s IRP, as SVP’s procurement approach for their slice of the PG&E transmission territory local resource needs is to primarily rely on short‐term market purchases and sales to balance their local reliability position. SVP’s plan also relies on significant growth of  remote  solar,  wind,  storage,  and  geothermal  resources;  some  of  these  could  be  sited  in  locally constrained areas. SVP will rely on resource adequacy market purchases to fill any residual local reliability needs.

System Reliability Constraints
Meeting reliability needs is a critical component of utility integrated resource planning. Amongst utilities, SVP – and other CAISO LSEs – face a unique reliability planning situation, whereby 1) system reliability needs are measured at the CAISO level, 2) LSEs have their own bilateral RA obligations, and 3) the long‐ term system reliability value of LSE resources is dependent upon the resource decisions of all LSEs. Using inputs developed by the CPUC for use in CPUC jurisdictional LSE IRPs, the reliability constraints in PLEXOS are set up to reflect this unique situation.

For their 2022 IRPs, the CPUC directed LSEs to plan for their share of the “marginal reliability need” using marginal  ELCC  accreditation  for  all  resource  types.  This  represents  a  departure  from  the  historical paradigm  in  the  CPUC  RA  process  to  rely  on  “average”  ELCCs,  but  provides  a  more  accurate  –  and therefore  economically  efficient  –  long‐term  forecast  of  the  marginal  system  reliability  value  of incremental resource changes on top of the larger CAISO fleet. It therefore represents a robust set of reliability planning inputs for SVP’s IRP process, consistent with the latest long‐term planning guidance available from a California state agency.

Figure 30 illustrates the key steps for a marginal reliability planning process: 1) determining the periods of  future  loss  of  load  risk  under  a  forecasted  system‐level  portfolio,  2)  calculating  and  allocating  the marginal reliability need during those same periods, and 3) measuring the resource contributions during those risk periods using marginal ELCC.25

25 Note: The marginal reliability need can be calculated in two ways to arrive at the same value: 1) as shown in this diagram, it can be calculated as the gross load plus operating reserves minus allowed loss of load under the adopted reliability standard, or 2) as the sum of the marginal ELCCs of the resource portfolio that is tuned to the adopted reliability standard.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   65
Figure 30. Schematic of the Marginal Reliability Planning Process

The following process was used by the CPUC to develop their marginal reliability planning inputs, used for the IRPs of the CPUC jurisdictional LSEs as well as for SVP’s IRP:

1. Data Development: A loss of load probability model and dataset were developed. The CPUC uses Astrapé’s SERVM model for this purpose, considering weather, load, and renewable variability over 23 historical years of weather conditions (1998‐2020) as well as stochastic draws for forced outages and economic load uncertainty.

2. System‐level Need Determination: Using the loss of load probability model, the Total Reliability Need  was  be  calculated  by  measuring  the  total  effective  capacity  (i.e.,  ELCC  MW  or  perfect capacity  (PCAP)  equivalent  MW)  needed  to  reach  the  CPUC’s  1‐day‐in‐10‐years  loss  of  load expectation (LOLE) standard (also described as reaching 0.1 days/year LOLE).

3. CAISO level resource portfolio forecast: a forecasted resource portfolio for the entire CAISO was developed based on the CPUC’s 2021 Preferred System Plan, tuning that resource portfolio to the

0.1 days/year LOLE standard each year.

4. Marginal ELCC forecast: the marginal ELCC for each resource type in the forecasted portfolio was calculated for key years (with between years using interpolation) to produce an annual forecast of marginal ELCCs by resource type. Marginal ELCCs are calculated as removing a small increment (e.g.,  100  MW)  of  each  resource  type  from  the  portfolio  and  calculating  the  perfect  capacity equivalent, measuring the marginal value of each resource type to reduce loss of load risk.

5. Translation  of  the  total  need  into  the  marginal  reliability  need  for  use  in  LSE  IRPs:  when accrediting against the total ELCC required to reach 0.1 LOLE in all hours, “average ELCCs” are used. For a system at the reliability criteria, the sum of average ELCCs for all resources equals the Total  Reliability  Need  MW  to  reach  the  reliability  criteria.  However,  when  accrediting  using

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   66
marginal  ELCCs,  which  produce  a  more  economically  efficient  signal  of  the  marginal  reliability value of each resource, the sum of the marginal ELCCs produces a lower MW value than the Total Reliability Need. This lower MW value is the marginal reliability need. For a system at the reliability criteria, the sum of marginal ELCCs for all resources equals the marginal reliability need MW to reach the reliability criteria. The CAISO’s marginal reliability need was calculated by the CPUC for each  year  based  on  the  sum  of  the  marginal  ELCCs  for  the  resource  portfolio  tuned  to  the reliability criteria.

6. Allocation  of  the  marginal  reliability  need  to  each  LSE:  the  CPUC  allocates  the  system  level marginal reliability need to each LSE based on their share of the IEPR’s coincident managed peak.

While this does not fully capture LSE contributions during the multiple hours where loss of load risk may occur, it used existing available data and – due to the large behind the meter PV peak shift captured in the managed peak – is a reasonable initial proxy for LSE contributions during the net peak.26
The resulting marginal ELCCs by resource and the marginal reliability need published by the CPUC for use by  their  jurisdictional  LSEs  are  shown  in  Figure  31.  These  values  come  from  the  “38  MMT  by  2030” modeling scenario from the 2021 Preferred System Plan.27

26 Gross peak = the consumption peak prior to behind the meter (PV, storage, etc.) resource output. Managed peak = the metered peak after behind the meter resource output. Net peak = the resulting system load after the output from supply side renewable resources. The net peak can also be defined as the remaining system load after all variable and use limited resources are dispatched (including storage, hydro, DR, etc. and not just solar and wind), which would align it more critically with the hours of loss of load risk for a system with increasing battery storage penetrations. 27 Slide 42, “Reliability Filing Requirements for Load Serving Entities’ 2022 Integrated Resource Plans – Results of PRM and ELCC Studies.” https://www.cpuc.ca.gov/‐/media/cpuc‐website/divisions/energy‐division/documents/integrated‐resource‐plan‐ and‐long‐term‐procurement‐plan‐irp‐ltpp/2022‐irp‐cycle‐events‐and‐materials/20220729‐updated‐fr‐and‐reliability‐mag‐ slides.pdf.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   67
Figure 31. Marginal ELCCs by Resource Type from the CPUC 38MMT Scenario

The inputs used for the CPUC IRP process were also utilized as the key inputs for the reliability constraint in  the  SVP  IRP.  SVP’s  marginal  reliability  need  was  calculated  using  its  forecasted  share  of  the  CAISO coincident  managed  peak  in  the  2022  IEPR.  The  SVP  managed  peak  MW  was  divided  by  the  CAISO managed peak MW; this ratio was then multiplied by the CPUC’s marginal reliability need to obtain the SVP‐level need. This marginal reliability need represents SVP’s share of the system need during hours with loss of load risk as measured in ELCC MW. All existing and new candidate resource options in PLEXOS’s optimization that provide system RA attributes are also counted in ELCC MW, using the marginal ELCC percentages reported above. This approach puts all resources on a level playing field by measuring their reliability contributions consistently using marginal ELCC, which accounts for the operational limitations of all resource types, including variable renewables, use‐limited hydro, use‐limited energy storage, and thermal units subject to forced outages.

Figure 32 shows the contributions of SVP’s existing and planned resources towards its forecasted marginal reliability need. The shortfall between the existing portfolio ELCC MW and SVP’s marginal reliability need must be satisfied via candidate resource builds. Due to constraints on candidate resource availability (see Section 7.1), the reliability constraint will not be enforced until 2026.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   68
Figure 32. Existing and Planned Resource Marginal ELCC and SVP’s Reliability Need, 2026‐3528

Clean Energy and Emissions Reduction Requirements
SVP must satisfy three key policy criteria in its IRP. SB 100 and SB1020 set targets for the RPS and Clean Energy Standard (CES) annually through 2045, and the CARB has also stipulated a GHG reduction target for 2030.
 RPS targets stipulated in legislation are 44% of retail electricity sales by 2024, 52% by 2027, and 60% by 2030.29 Only eligible renewable energy resources qualify for the RPS, including solar, wind, geothermal, and small hydroelectric units.
 CES policy goals are 90% by 2035, 95% by 2040, and 100% by 2045. Resource qualification for the CES is expanded to include all zero‐carbon resources, including nuclear, large hydro, and emerging

28 The marginal reliability constraint is only enforced in the model beginning in 2026, which is the first year when SVP expects to be able to sign new long‐term contracts as discussed in Section 7. In the intervening years, it is assumed that SVP will sign short‐term capacity contracts to meet their reliability need if there is any capacity shortage. 29 The RPS constraint is only enforced in the model beginning in 2026, which is the first year when SVP expects to be able to sign new long‐term contracts as discussed in Section 7. In the intervening years, it is assumed that SVP will buy RECs if there is any REC shortage.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   69
technologies such as hydrogen and Carbon Capture and Storage (CCS). In the intervening years between the expiration of the RPS (2030) and the enforcement of the CES (2035), a ramp‐up is modeled to smooth policy compliance in the model (Figure 33).  GHG  reductions  target  the  electric  sector’s  share  of  a  40%  economy‐wide  reduction  of  GHG emissions from 1990 levels by 2030. For SVP, this amounts to 485,000 MMT CO2e, as published in the SB 350 Final Report.30  This value represents the high end of the GHG target range published by  CARB  and  hence  the  minimum  requirement  for  SVP.  Scenarios  of  more  aggressive  carbon reduction were modeled focused on the year 2035, as described below.

The  schematic  outlined  in  Figure  33  shows  the  compliance  targets  for  the  RPS  and  CES,  expressed  as percentages of retail sales.

Figure 33. RPS (Green) and CES (Blue) Compliance Targets

All of SVP’s existing and planned renewable resources, including solar, wind, geothermal, biogas, and small hydro generators, are assumed to be REC‐producing and qualify towards RPS compliance. Additionally, all candidate wind, solar, and geothermal resources selected in the capacity expansion model are assumed to provide RECs to SVP.

In addition to renewable resources, SVP’s portfolio of large hydro generators is assumed to qualify for the CES  and  provide  credits  to  SVP.  Candidate  renewables  and  zero‐emission  emerging  technologies  are assumed to qualify for the CES as well.

The GHG constraint is enforced starting in 2030. Gas‐fired thermal generators are assumed to generate carbon emissions at a rate of 117 pounds CO2 per MMBtu of fuel consumption. When LEC undergoes its planned conversion to 45% hydrogen fuel blending in 2027, its emissions factor reduces to 92.2 pounds per  MMBtu  of  blended  fuel  (see  Emerging  Technology  in  Section  7.1).  The  Allam  Cycle  CCS  resource modeled in Scenario 3: Zero Emissions with Emerging Technology (Zero Emissions Scenario) has a 100%

30 CARB, “Senate Bill 350 ‐ Integrated Resource Planning Electricity Sector Greenhouse Gas Planning Targets: 2020 Update” (Sacramento, CA: California Air Resource Board (CARB), 2020), https://ww2.arb.ca.gov/sites/default/files/2021‐04/sb350‐ final‐report‐2020.pdf.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   70
carbon capture efficiency, and consequently is not modeled as producing emissions. When Gianera 1 and 2 convert to renewable natural gas (RNG) in the Zero Emissions Scenario, the lifecycle carbon emissions of RNG are assumed to be zero. For more information on the emerging technologies under consideration, refer to Section 7.1.

Market  interactions  also  contribute  to  the  carbon  emissions  constraint.  The  hourly  market  emissions factors used for purchases and sales are equal to the average hourly emission factors from the CAISO‐ wide thermal generator fleet that dispatches in each hour, as calculated from the E3 CAISO Market Price forecast dataset.31 Purchases in each hour from the market incur a carbon penalty at the hourly market emissions factor, while market sales offset SVP’s carbon emissions at that same rate. This representation is consistent with the emissions accounting approach used in the CPUC IRP and reflects SVP’s continuous participation in the CAISO market.

A volumetric cost is modeled for every ton of carbon produced by SVP. These costs are also taken from the E3 CAISO Market Price Forecast. Market prices, emission factors, and carbon prices are all correlated in this dataset.

The CAISO average annual emission factors and annual carbon price forecasts are shown in Figure 34.

Figure 34. CAISO Average Annual Emissions Factor and Carbon Price

In the Zero Emissions Scenario, the GHG constraint is modified such that no emissions are permitted in all hours of the year, beginning in 2035. Under this scenario, market sales do not offset SVP emissions, and

31 E3, “California ISO Market Price Forecast E3 Core Case 2022,” Energy + Environmental Economics (E3), 2022, https://shop.ethree.com/wp‐content/uploads/2022/11/Market‐Summary_CAISO_2022‐edition_SAMPLE.pdf.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   71
market purchases are only allowed in hours where the average market emissions factor is zero. For more information, refer to Section 6.6.

6.5. Capacity Expansion Model Configuration
To identify a least‐cost capacity expansion and system operations portfolio, PLEXOS LT optimizes across the entire planning horizon from 2024 to 2035 (11 years) in a single step, resulting in a computationally intensive optimization problem. To ensure the capacity expansion problem is computationally tractable while  still  providing  accurate  and  actionable  results,  PLEXOS  performs  several  modifications  to  the system’s  representation  to  make  the  model  more  tractable.  These  modifications  are  described  in  the following sections.

Day Sampling
Regarding the chronology or level of detail in representing the planning horizon, day sampling ensures that  the  model  captures  intra‐month  and  monthly  variations  in  load  and  resources  annually  while reducing the size of the simulation. Instead of modeling every day of the modeling horizon, a sample set of three days per month are studied. A statistical sampling algorithm within PLEXOS LT extracts similar periods (such as days, weeks, months) with a focus on highly variable data (such as load, solar and wind profiles),  leaving  a  sample  set  of  days  that,  together,  have  characteristics  that  are  representative  of conditions on the electricity system over the course of multiple years. After sampling, PLEXOS LT rescales the results to ensure that the total energy equals the original input values.

Expansion Decisions
The capacity expansion algorithm in PLEXOS LT can be programmed to select new generator builds using integer decision variables or linearized variables. In the integer representation, each generator must be built at its full nameplate capacity, or not at all. In the linear representation, partial builds are allowed. In general, integer/discrete problems are much harder for PLEXOS to solve than linear problems. In this study, the model is permitted to make linear expansion decisions, which significantly reduces the computational time  required  to  solve  the  problem  while  still  providing  sufficient  information  on  the  magnitude  and diversity of new builds to support decision making.

Operation Decisions
Operations unit commitment optimality determines how unit commitment decision variables are treated in the optimization problem. Operations in PLEXOS LT are simulated through economic dispatch of existing and new resources to meet load in each hour. The dispatch logic depends on the type of resource. Solar and wind resources have fixed generation profiles (input as hourly capacity factors) based on the resource location and can be curtailed when total generation exceeds load. Thermal resources (such as natural gas turbines) are operated flexibly while meeting operating constraints such as maximum capacity rating and minimum generation level. Must‐run resources are operated at their rated capacity in all hours except for planned  outages.  Market  purchases  and  demand  response  resources  are  configured  similarly  to SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   72
generation  and  can  be  operated  flexibly  while  also  meeting  operating  constraints.  Energy  storage resources (such as batteries and pumped hydropower) increase load when charging and can serve load when discharging.

6.6. Scenarios and Sensitivities Considered
Three modeling scenarios and one modeling sensitivity were considered for the SVP IRP. Scenario 1: Base SB 100 (Base Scenario) consists of the default inputs and assumptions regarding load growth, resource availability, policy targets, and market activity. Under Scenario 2: Accelerated SB 100 (Accelerated SB 100 Scenario), the compliance targets are accelerated from 60% RPS to 70% carbon‐free energy (60 % still needs to come from renewable resources) by 2030, and from 90% carbon‐free energy to 100% by 2035.

Finally, Scenario 3: Zero Emissions with Emerging Technology (Zero Emissions Scenario) restricts SVP from producing any carbon emissions in all hours starting in 2035, enables the selection of certain zero‐emitting emerging technologies beginning in 2035, and includes conversion of LEC, DVR, and Gianera 1 and 2 to zero‐carbon fuels by 2035. The emissions restrictions in this Scenario extend to market activity, where purchases are only allowed during hours where the market average emissions rate is zero, and sales are not permitted to provide negative emissions “credits” during hours when market average emissions rates are non‐zero.

The  Geothermal  Limitations  and  Hydrogen  Challenges  Sensitivity  (Hydrogen  Sensitivity)  represents  a variation  of  the  Zero  Emissions  Scenario  where  the  geothermal  resource  potential  available  to  SVP  is capped to 50 MW and the costs of  hydrogen retrofits, new hydrogen turbines, and hydrogen fuel are increased due to uncertainty over a future hydrogen economy.

A summary of the key changes by Scenario are shown in Figure 35 below.

Figure 35. Modeling Parameters that Vary by Scenario or Sensitivity Scenario 1:  Scenario 2:  Scenario 3:  Sensitivity:

Parameter  Base SB 100  Accelerated SB
100
Zero Emissions
with Emerging
Technology
Geothermal
Limitations and
Hydrogen
Challenges
SB 100 CES
Targets
90% by 2035
100% by 2045
70% by 2030
100% by 2035
70% by 2030
100% by 2035
70% by 2030
100% by 2035
Carbon Emission
Reduction Targets
485,000 MT by
2030
485,000 MT by
2030
485,000 MT by
2030
Zero hourly
emissions
beginning in 2035
485,000 MT by
2030
Zero hourly
emissions
beginning in 2035
SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   73
Zero‐carbon
Emerging
Technologies
Not included  Not included  Included  Included
Gas Plant
Conversions*
LEC 45%
(volumetric)
Hydrogen in 2027
LEC 45%
(volumetric)
Hydrogen in 2027
All gas plants are
converted to
100% zero‐carbon
fuels by 2035
All gas plants are
converted to
100% zero‐carbon
fuels by 2035
Market Purchases  Allowed  Allowed
Allowed before
2035
Restricted in 2035
to hours where
market emission
factor is zero
Allowed before
2035
Restricted in 2035
to hours where
market emission
factor is zero
Carbon Credits
via Market Sales  Allowed  Allowed
Allowed before
2035
Not allowed in
2035
Allowed before
2035
Not allowed in
2035
Geothermal
Resource
Potential
Default  Default  Default  Reduced to 50
MW in 2028
Hydrogen
Retrofit, New
Build, and Fuel
Costs
Default  Default  Default  High
*Gas plant conversions are discussed in Section 7.1.

6.7. Model Inputs
The inputs to the PLEXOS model, discussed in Sections 3, 4, 6, and 7, are organized into the following topics:
 Load Forecast – The load forecast was developed using a combination of a baseline load forecast provided by SVP and load modifiers to form a Reference Scenario forecast. This load forecast was used in all scenarios. See Section 3.
 Existing and Planned Resources – Inputs were provided by SVP and are discussed in Section 4:

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   74
o Online and retirement dates – As a PLEXOS modeling assumption, all of SVP’s small and large hydro generators are retained over the planning horizon, irrespective of contract status.
o Nameplate capacity
o Variable O&M
o Thermal operating parameters
o Generation  profiles  &  capacity  factors  –  Geothermal  and  hydro  energy  budgets  were provided by SVP. Renewable solar and wind profiles were collected from the CPUC IRP 2023 Inputs and Assumptions (I&A) supporting information.  Candidate Resources – Inputs were developed by E3 and are discussed in Section 7:
o Resource costs – Resource costs for candidate resources were derived from the National Renewable Energy Laboratory (NREL) 2023 Annual Technology Baseline (ATB).32 Emerging technology cost assumptions were collected via E3 literature review. o Resource  Potential  &  Availability  –  The  availability  and  build  limits  for  candidate resources were collected from the CPUC IRP 2023 I&A document, with modifications to reflect SVP’s market share and procurement risk.33
o Generation Profiles & Capacity Factors – Profiles were collected from the CPUC IRP 2023 I&A supporting information.
o Thermal Operating Parameters – Data was taken from the CPUC IRP 2023 Resource Cost and Build workbook.
 Reliability Need – Inputs were developed by E3 and are discussed in Section 6.4:
o Reliability Need – Developed using the CPUC data and SVP’s coincident peak demand to derive the SVP marginal reliability need.
o Resource  Capacity  Contributions  –  The  marginal  ELCCs  for  candidate  renewable resources were adopted from CPUC data, using a marginal reliability need framework.  Fuel Prices – These trajectories were derived from several data sources. More information can be found in Section 7.4, including:

32 https://atb.nrel.gov/electricity/2023/index
33 Resource potential and availability limits were reduced from the CAISO‐wide potentials to represent what would be available to SVP for procurement. Further discussion can be found in Section 7.1.

SVP System Modeling Approach2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   75
o Natural Gas – The gas forecast was derived from the Energy Information Administration 2022 Annual Energy Outlook, with the trajectory regionalized to the settlement node of SVP’s contracted gas supply.
o Hydrogen – Green hydrogen price forecasts were developed by E3. The forecast assumes electrolysis of hydrogen using an alkaline electrolyzer that is powered by solar energy.

Hydrogen electrolyzer costs are derived from the CEC publication on hydrogen production costs.34 Hydrogen storage costs are derived from Department of Energy (DOE) project ST‐ 001  costs.35 Hydrogen  transport  costs  are  derived  using  Argonne’s  Hydrogen  Delivery Scenario Analysis Model (HDSAM).36 A $3/kg Production Tax Credit (PTC) from the IRA is applied to units brought online by 2035.37
o Renewable Natural Gas – Fuel cost provided by SVP.
o Uranium – Fuel cost taken from the CPUC IRP 2023 Resource Cost and Build Workbook.

6.8. Model Outputs
The following outputs are produced by PLEXOS and are the subject of discussion and interpretation in this report. All fields are reported annually for each generator, except for the Constraint outputs which are single‐defined  values  for  each  year  of  the  modeling  horizon.  The  key  model  outputs  for  this  IRP  are reported in Figure 36.

Figure 36. Key Model Outputs
PLEXOS Output  Description  Output Units
Installed Capacity  Installed capacity of Generation and Battery Storage.  MW Generation  Total annual generation of Generation and Battery Storage.  GWh Annualized Build Cost  Total fixed costs of candidate resources, including levelized capital costs and FO&M costs.

Nominal $’000
VO&M Cost  Total VO&M cost.  Nominal $’000
Fuel Cost  Total annual fuel bill.  Nominal $’000
Market Net Purchases  Energy purchases from the market, net of sales to market.  GWh Market Cost  Cost of market purchases.  Nominal $’000
Market Revenue  Revenue (negative cost) collected from market sales.  Nominal $’000 Emission Production  Total production of carbon emissions, including from generation and market activity.

Short tons
Emission Cost  Total cost of emissions, equal to the emission price times production.

Nominal $’000

34 https://www.energy.ca.gov/sites/default/files/2021‐06/CEC‐500‐2019‐055‐F.pdf. 35 https://www.hydrogen.energy.gov/pdfs/review22/st001_ahluwalia_2022_p.pdf. 36 https://hdsam.es.anl.gov/index.php?content=hdsam.
37 Qualification of hydrogen generators for the Hydrogen PTC under the IRA assumes a three‐year safe harboring following the expiration of the IRA tax credits in 2032. The PTC applies to the first ten years of plant operations. This credit is levelized over the useful life of the hydrogen generator and is bundled into the fuel price forecast.

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   76

7. Portfolio Expansion Resource Options

7.1. Candidate Resource Assumptions
When planning for capacity expansion, SVP can select from a range of candidate resource options to meet growing load, reliability requirements, GHG policy targets, and additional policy goals. These resources are grouped into the following categories:
 Candidate Renewable Resources
 Candidate Storage Resources
 Candidate Thermal Resources
 Candidate Emerging Technology Resources
For resource cost assumptions, see to Section 7.2.

Candidate Renewable Resources
Candidate  renewable  resources  include  the  renewable  energy  resources  available  to  SVP  under  all modeling scenarios. These are established and commercially viable technologies, including solar PV, in‐ state wind, out‐of‐state wind, offshore wind, and geothermal.

The candidate renewable resources available to SVP are aggregations of the resources reported in the CPUC  IRP  I&A  document.38 For  solar  and  in‐state  wind,  the  resource  potentials  were  aggregated  into Northern,  Central,  and  Southern  regions  according  to  the  region  boundaries  used  by  the  CPUC.

Geothermal is represented as a single resource encompassing all in‐state geothermal resource potential in the CPUC model. Details of the aggregation are summarized in Figure 37.

Figure 37. SVP Candidate Renewable Resources Mapping to CPUC Aggregation SVP Resource Name  CPUC Aggregation
Northern California Solar  Northern California
Central California Solar  Southern PGAE, Greater Kramer, Tehachapi, Southern NV Eldorado Southern California Solar  Greater LA, Riverside, Greater Imperial, Arizona Northern California Wind  Northern California, Solano
Central California Wind  Central Valley North Los Banos, Tehachapi, Southern NV Eldorado Baja California Wind  Baja California
Geothermal  All in‐state geothermal resources
The resource potentials available to SVP are indexed to the corresponding potentials from the CPUC IRP I&A document. Specifically, the solar resource potential is assumed to be sufficiently large to capture all of SVP’s potential needs, and no resource potential limit is modeled. For in‐state wind, out‐of‐state wind,

38 CPUC 2022‐23 IRP Cycle Events and Materials. https://www.cpuc.ca.gov/industries‐and‐topics/electrical‐energy/electric‐ power‐procurement/long‐term‐procurement‐planning/2022‐irp‐cycle‐events‐and‐materials.

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   77
and offshore wind, the portion of the CPUC resource potentials available to SVP is assumed to be 5% of the  reported  totals,  reflecting  SVP’s  market  share  and  ability  to  procure  wind  generation.  For  Baja California Wind, the available potential reported by the CPUC is also reduced to account for Cimarron Wind, for which SVP is already under contract. For geothermal, it is understood that, of the 3.3 GW of resource potential modeled in the CPUC IRP, 1 GW of this resource must be earmarked for the CPUC Mid‐ Term Reliability Clean Firm order. As such, SVP’s portion of the CPUC resource potential for geothermal is represented as 15% of the net remaining statewide potential of 2.3 GW.

Each candidate renewable resource’s first available year reflects feasible timelines for bringing resources online based on the CAISO interconnection queue and typical development lead times. Additionally, no resources  are  made  available  for  selection  in  the  capacity  expansion  model  until  2026  at  the  earliest, reflecting SVP’s near‐term procurement decisions.

For candidate solar and wind resources, the renewable profiles and capacity factors were adopted from the profiles used in the CPUC IRP model.39 A single weather year (2020) was sampled to create the profiles.

Weather stations were selected for candidate renewable resources that align with the geographic extent of the resource potential.

Key metrics for the candidate renewable resources available to  SVP are summarized in Figure 38.  The resource  potential  totals  represent  the  total  amounts  available  to  the  model  by  2035;  for  wind  and geothermal resources, the available potential is staggered between 2026‐2030 to reflect construction lead time, projects in the CAISO interconnection queue, and commercial interest.

Figure 38. Candidate Renewable Resource Options
Technology  Resource Name  First Year
Available
Resource
Potential
Lifetime
(years)
Capacity
Factor
Solar  Northern California Solar  2026  Uncapped  30  29.9% Solar  Central California Solar  2026  Uncapped  30  32.5% Solar  Southern California Solar  2026  Uncapped  30  33.7% Solar  Distributed Solar  2026  36.6 GW  30  25.9%
In‐State Wind  Northern California Wind  2026  142 MW  30  21.2% In‐State Wind  Central California Wind  2026  478 MW  30  33.2% In‐State Wind*  Baja California Wind  2026  109 MW  30  30.4% Out‐of‐State Wind  New Mexico Wind  2026  275 MW  30  48.1% Out‐of‐State Wind  Wyoming Wind  2027  200 MW  30  51.2% Offshore Wind  Humboldt Bay Offshore Wind  2034  134 MW  25  57.1% Offshore Wind  Morro Bay Offshore Wind  2034  244 MW  25  47.6% Geothermal  Geothermal  2028  347 MW  25  ‐
* Baja California Wind interconnects directly to the CAISO system and is considered in‐state

39 CPUC System Reliability Modeling Datasets 2023. https://www.cpuc.ca.gov/industries‐and‐topics/electrical‐energy/electric‐ power‐procurement/long‐term‐procurement‐planning/2022‐irp‐cycle‐events‐and‐materials/system‐reliability‐modeling‐ datasets‐2023.

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   78
Further breakdowns of the average solar and wind capacity factors by month, as calculated from the CPUC weather profiles, are provided in Figure 39 and Figure 40.

Figure 39. Candidate Solar Monthly Capacity Factor
Month  Central
California Solar
Northern
California Solar
Southern
California Solar
Distributed
Solar
January  20%  14%  24%  19%
February  29%  29%  29%  24%
March  28%  25%  31%  23%
April  36%  35%  40%  28%
May  44%  35%  43%  33%
June  44%  43%  44%  33%
July  45%  46%  40%  33%
August  38%  36%  38%  29%
September  33%  29%  35%  26%
October  27%  29%  31%  24%
November  24%  21%  26%  20%
December  21%  16%  23%  17%
Annual  32%  30%  34%  26%

“I think we should continue to explore the viability of other  energy  options,  such  as  hydrogen  or  even
nuclear.” ‐Santa Clara resident survey response
Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   79
Figure 40. Candidate Wind Monthly Capacity Factor
Month  Baja CA
Wind
Central CA
Wind
New
Mexico
Wind
Northern
CA Wind
Wyoming
Wind
Humboldt
Bay
Offshore
Wind
Morro Bay
Offshore
Wind
January  18%  37%  59%  22%  72%  56%  51%
February  19%  39%  56%  27%  63%  69%  48%
March  32%  31%  62%  27%  54%  44%  29%
April  38%  28%  60%  17%  47%  45%  61%
May  43%  39%  51%  24%  42%  60%  56%
June  47%  34%  46%  16%  40%  65%  51%
July  44%  29%  27%  14%  37%  83%  48%
August  34%  21%  23%  12%  33%  70%  49%
September  22%  24%  35%  21%  46%  37%  42%
October  29%  28%  47%  25%  54%  68%  34%
November  21%  39%  55%  23%  60%  43%  50%
December  19%  48%  56%  26%  68%  47%  52%
Annual  30%  33%  48%  21%  51%  57%  48%
Candidate Storage Resources
To  complement  candidate  renewables,  candidate  energy  storage  resources  are  represented  in  SVP’s capacity expansion model.  Energy storage resources can shift the generation from variable renewable resources to serve load during critical system hours when renewables might otherwise not be producing electricity. Four energy storage resources are modeled, including both conventional technologies (Li‐ion batteries, Pumped Hydro Storage) and a generic emerging energy storage technology. The four energy storage resources each have a different storage duration, allowing the model to select the optimal mix of storage capacity and duration.

Li‐ion batteries are modeled in two durations (4‐ and 8‐hr) and are available for selection immediately in 2026. Pumped Storage is modeled with a 12‐hr duration and is the only energy storage resource modeled with limits on the available resource potential. The resource potential for Pumped Storage is taken from the  CPUC  IRP  I&A  document.40 This  resource  is  an  aggregation  of  several  project  sites  that  have  been identified as suitable for development, the first of which could be developed as early as 2027. Finally, the Generic  Energy  Storage  (100‐hr)  resource  is  only  available  for  selection  in  scenarios  where  emerging technologies are allowed, starting in 2036.

Key metrics for the candidate storage resources available to SVP are summarized in Figure 41.

40 CPUC 2022‐23 IRP Cycle Events and Materials. https://www.cpuc.ca.gov/industries‐and‐topics/electrical‐energy/electric‐ power‐procurement/long‐term‐procurement‐planning/2022‐irp‐cycle‐events‐and‐materials.

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   80
Figure 41. Candidate Storage Resource Options
Resource Name  Duration
(hr)
First Available
Year
Cumulative
Build Limit
Lifetime
(years)
Round‐Trip
Efficiency
Li Battery 4hr  4  2026  Uncapped  20  85%
Li Battery 8hr  8  2026  Uncapped  20  85%
Pumped Storage 12hr  12  2027  3.2 GW  50  70%
Generic Energy Storage 100hr  100  2036  Uncapped  20  45% Candidate Thermal Resources
Candidate thermal resources are also made available to SVP in scenarios where new emitting resources are  allowed  to  be  procured.  These  include  new  combined  cycle  gas  turbines  (CCGTs),  CTs,  and reciprocating engine units. The first available year for all new thermal units is 2027. New thermal units are assumed to be procured from outside the SVP system.

Key metrics for the candidate thermal resources available to SVP are summarized in Figure 42 and Figure

43. Figure 42. Candidate Thermal Resource Options
Resource Name  First Available
Year
Cumulative Build
Limit2
Lifetime
(years)
Advanced CCGT  2027  Uncapped  25
Aero CT  2027  Uncapped  25
Reciprocating Engine  2027  Uncapped  25
Figure 43. Candidate Thermal Operating Parameters
Resource Name
Heat Rate Curve  VO&M
($/MWh)  Fuel Type Intercept
(MMBtu)
Slope
(MMBtu/MWh)
Advanced CCGT  500  6.0  2.12  Spot Gas
Aero CT  346  6.0  6.96  Spot Gas
Reciprocating Engine  4.9  9.2  6.96  Spot Gas
Emerging Technology Resources
Emerging  technology  resources  include  zero‐carbon  technologies  that  have  not  yet  reached  full commercialization. These resources are not included in core portfolios that are considered for adoption in  SVP’s  IRP;  they  are  only  considered  in  Scenario  3:  Zero  Emissions  with  Emerging  Technology  (Zero Emissions  Scenario)  and  the  Geothermal  Limitations  and  Hydrogen  Challenges  Sensitivity  (Hydrogen Sensitivity).  Emerging  technologies  under  consideration  include  both  candidate  emerging  technology resources,  which  are  subject  to  optimization  decisions  in  the  PLEXOS  capacity  expansion  model;  and planned emerging technology conversions, which include retrofits and fuel conversions of specific thermal generators  for  the  combustion  of  zero‐carbon  fuels.  While  emerging  technologies  are  generally  more expensive to build and operate than conventional renewable resources, their chief advantage is that they are firm, non‐emitting resources capable of serving peak load.

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   81
Candidate emerging technology resources under consideration in the IRP are Allam Cycle CCS with 100% carbon capture efficiency, Nuclear small module reactor (SMR), and Hydrogen CT. The candidate hydrogen resource  modeled  in  the  IRP  represents  the  procurement  of  new  hydrogen  CTs.  Other  components required for the hydrogen economy, including pipelines, storage reservoirs, electrolyzers, and dedicated renewable electricity to run the electrolyzers, are bundled into the hydrogen fuel cost, discussion in the Fuel Prices section.

SVP’s portfolio of existing thermal units is assumed to undergo retrofits or conversions to zero‐emission fuels in the emerging technology scenarios:
 Lodi  Energy  Center  (LEC)  –  LEC  is  assumed  to  undergo  a  two‐phase  retrofit  to  transition  from natural gas to hydrogen by 2035. The first phase occurs in 2027 where a 45% hydrogen fuel blend is assumed. This first phase occurs in all model scenarios, not just the Zero Emissions Scenario. In the second phase, the system is assumed to switch to 100% hydrogen combustion beginning in 2032. Since this is a planned conversion, no costs are modeled for this retrofit.  Alameda CT 1 and 2 – These units are assumed to retrofit to 100% hydrogen starting in 2030. The conversion is a forced‐in decision, and the costs of the retrofit are included in the total system cost.
 Lodi CT – Lodi CT is assumed to retrofit to 100% hydrogen in 2032. The conversion is a forced‐in decision, and the costs of the retrofit are included in the total system cost.  DVR Hydrogen – DVR is assumed to undergo a retrofit for hydrogen fuel combustion in 2035. The conversion is represented as a forced‐in decision, and the costs of the retrofit are included in the total system cost.
 Gianera 1 and 2 – These units are assumed to switch fuels from natural gas to RNG, beginning in 2035. Apart from an increased fuel price and the ending of carbon emissions, no other costs or impacts of the fuel switch are modeled.

Key  metrics  for  the  emerging  technology  resources  available  to  SVP  are  summarized  in  Figure  44  and Figure 45.

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   82
Figure 44. Emerging Technology Resource Options
Resource Name  First Available Year  Cumulative Build
Limit  Lifetime (years)
Allam Cycle 100% CCS  2036  Uncapped  25
Nuclear SMR  2036  Uncapped  25
Hydrogen CT  2035  Uncapped  25
Lodi Energy Center (LEC)
2027 – 45% Fuel Blend (modeled in all
scenarios)
2032 – 100% Hydrogen (Zero
Emissions Scenario and Hydrogen
Sensitivity only)
‐‐  ‐‐
Alameda CT 1 Hydrogen  2030 – Retrofit  ‐‐  25
Alameda CT 2 Hydrogen  2030 – Retrofit  ‐‐  25
Lodi CT Hydrogen  2032 – Retrofit  ‐‐  25
DVR Hydrogen  2035 – Retrofit  ‐‐  25
Gianera 1 RNG  2035 – Fuel Switch ‐ ‐   ‐‐
Gianera 2 RNG  2035 – Fuel Switch  ‐‐  ‐‐
Figure 45. Emerging Technology Operating Parameters
Resource Name
Heat Rate Curve  VO&M
($/MWh)  Fuel Type  Pmin Intercept
(MMBtu)
Slope
(MMBtu/MWh)
Allam Cycle 100% CCS  1,624  6.3  5.09  Spot Gas  50%
Nuclear SMR  0  10.0  3.38  Uranium  40%
Hydrogen CT  346  6.1  6.96  Hydrogen  ‐‐
Lodi Energy Center (LEC)
Load points
provided by
SVP
Load points
provided by
SVP  3.66
Spot Gas (2024‐26)
Hydrogen 45% Blend
(2027‐2031)
Hydrogen (2032+)
‐‐
Alameda CT 1 Hydrogen
Load points
provided by
SVP
Load points
provided by
SVP

1.52  Spot Gas (2024‐2029)
Hydrogen (2030+)  ‐‐
Alameda CT 2 Hydrogen
Load points
provided by
SVP
Load points
provided by
SVP

1.52  Spot Gas (2024‐2029)
Hydrogen (2030+)  ‐‐
Lodi CT Hydrogen
Load points
provided by
SVP
Load points
provided by
SVP

1.52  Spot Gas (2024‐2031)
Hydrogen (2032+)  ‐‐
DVR Hydrogen
Load points
provided by
SVP
Load points
provided by
SVP

3.00  Spot Gas (2024‐2034)
Hydrogen (2035+)  ‐‐
Gianera 1
Load points
provided by
SVP
Load points
provided by
SVP

3.00  Spot Gas (2024‐2034)
RNG (2035+)  ‐‐
Gianera 2
Load points
provided by
SVP
Load points
provided by
SVP

3.00  Spot Gas (2024‐2034)
RNG (2035+)  ‐‐

7.2. Candidate Resource Costs
Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   83
The  total  fixed  costs  of  candidate  resources,  including  capital  cost,  FO&M  costs,  interconnection, investment tax credits (ITCs), property taxes, and warranty and augmentation costs, if any, were derived from  the  2023  NREL  ATB  Electricity  report.41 These  costs  on  a  $/kW  basis  were  then  levelized  using  a nominal  developer  weighted  average  cost  of  capital  (WACC)  over  the  resource’s  economic  life.

Additionally, transmission cost adders for out‐of‐state resources, discussed in the Transmission section, are added to this value to determine the Levelized Fixed Cost (LFC). In PLEXOS, the Build Cost parameter represents the levelized cost inputs from NREL ATB plus any transmission deliverability cost adders. The sum of these values yields LFC for each candidate resource.

The IRA is expected to impact the costs of candidate clean energy resources. These impacts are largely due to existing tax credits extending beyond 2024 and new technology‐neutral tax credits that will begin in 2025. Due to the IRA, solar PV can elect to receive a PTC instead of the ITC. Early analysis suggests that the PTC will outperform the ITC for utility‐scale solar projects. Therefore, new candidate solar resources are assumed to elect the PTC. In addition, standalone storage projects are now eligible for the ITC under the IRA. Projects are eligible for the full “Bonus” tax credit amounts (30% of qualifying capital expenditure for the ITC or $26/MWh of electricity generation for the PTC) if specific prevailing wage and apprenticeship requirements are met. If these requirements are not met, the project is eligible for one‐fifth of the full tax credit amount. The full “Bonus” IRA tax credits will be used to calculate resource costs.

Emerging clean energy technologies such as hydrogen and CCS are eligible for new tax credits under the IRA for systems that produce green electrofuels and thermal generators equipped with CCS technologies.

Systems  are  eligible  for  these  PTCs  until  2032,  which  can  be  extended  to  2035  using  a  three‐year assumption for Continuity Safe Harbor. The PTC for hydrogen CTs and retrofits built in 2035 is factored into the hydrogen fuel price, discussed in a later section. For Allam Cycle 100% CCS, since the resource is not available until 2036, no PTC is modeled.

Inflationary pressures and supply chain issues have caused price increases for certain metals and other raw materials which may drive up the costs for some technologies. Studies have shown that since 2020, renewable technologies such as wind, solar, and lithium‐ion batteries have seen increases in Levelized Cost  of  Energy  (LCOE)  and  overnight  capital  expenditure  (CAPEX).  Modifications  to  the  NREL  ATB  cost trajectory for utility‐scale solar, onshore wind, offshore wind, and Li‐ion batteries were made to reflect current market conditions and substantial impacts to the supply chain.

Although  new  emitting  thermal  generation  is  not  allowed  in  the  scenarios  considered,  the  LFCs  for candidate thermal resources are summarized in Figure 46 for reference.

41 https://atb.nrel.gov/electricity/2023/index
Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   84
Figure 46. Candidate Thermal Resource Levelized Fixed Costs, 2022 $/kW‐yr Resource Name  2026  2028  2030  2032  2035
Advanced CCGT  $187.37  $184.31  $181.24  $178.16  $173.43 Aero CT  $187.14  $184.64  $182.00  $179.36  $175.60
Reciprocating Engine  $187.14  $184.64  $182.00  $179.36  $175.60 For candidate renewable resources, the LCOE is derived from the LFC using the annual capacity factor, plus  any  VO&M  cost,  fuel  cost,  and  PTCs,  if  applicable.  The  LCOE  represents  the  volumetric  cost  of electricity  required  for  the  candidate  resource  to  recover  its  variable  and  fixed  costs.  The  LCOEs  of candidate renewable resources are summarized in Figure 47.

Figure 47. Levelized Cost of Electricity by Candidate Renewable Technology, 2022 $/MWh

LFCs for candidate energy storage and emerging technologies are derived from NREL ATB and the CPUC IRP  I&A  documentation.  LFCs  are  provided  in  Figure  48  and  Figure  49  for  storage  and  emerging technologies, respectively. Note that in the Geothermal Limitations and Hydrogen Challenges Sensitivity, the cost of hydrogen retrofits are doubled relative to what is presented in Figure 49.

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   85
Figure 48 Candidate Storage Resource Levelized Fixed Costs, 2022 $/kW‐yr

Figure 49. Candidate Emerging Technology Levelized Fixed Cost, 2022 $/kW‐yr

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   86

7.3. Reliability Requirement Assumptions
The reliability contribution from candidate resources was determined using a marginal ELCC accounting framework as discussed in Section 6.4. The marginal ELCCs by technology and year are provided in Figure 31 of Section 6.4.

7.4. Fuel Prices
Several fuels are modeled for the thermal resources in SVP’s existing and planned resource portfolio, as well  as  for  candidate  and  planned  emerging  technology  resources  in  Scenario  3:  Zero  Emissions  with Emerging Technology (Zero Emissions Scenario) and the Geothermal Limitations and Hydrogen Challenges Sensitivity (Hydrogen Sensitivity). These fuels include natural gas, RNG, hydrogen, and uranium, shown in Figure 50. See Appendix C for hydrogen fuel price assumptions.

Figure 50. Fuels Included in the SVP IRP Model
Fuel  Generators  Data Source
Natural Gas  Existing thermal fleet
Candidate thermal resources  E3 Gas Price Forecast
Hydrogen Blend  Lodi Energy Center (from 2027)  45%/55% Blend of Natural Gas and Hydrogen fuel prices
Hydrogen*
Candidate Hydrogen CT
Alameda CT 1 and 2 (from 2030)
Lodi CT (from 2032)
Lodi Energy Center (from 2032)
DVR (from 2035)
E3 Electrofuels Calculator
Renewable Natural Gas*  Gianera 1 and 2 (from 2035)  SVP price estimate Uranium*  Candidate Nuclear SMR  CPUC IRP Inputs & Assumptions * Only modeled in the Zero Emissions Scenario and Hydrogen Sensitivity SVP’s existing portfolio of thermal‐fired units are assumed to use natural gas settled at the PG&E City Gate spot gas price. The price forecast was developed by E3 using a combination of forward prices in the near‐ term42 and Energy Information Administration Annual Energy Outlook fundamentals‐based forecasts for the longer term.43 The price forecasts were localized to the PG&E Gate using projections of monthly basis differentials from the near‐term forward prices. The resulting spot gas price forecast is shown in Figure

51. 42 Henry Hub forwards from S&P Global Market Intelligence, https://www.spglobal.com/marketintelligence/en/. 43 https://www.eia.gov/outlooks/aeo/.

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   87
Figure 51. Natural Gas Price Forecast, 2022 $/MMBtu

The  hydrogen  fuel  price  forecast,  shown  in  Figure  52,  was  calculated  using  E3’s  Hydrogen  Calculator.

Hydrogen fuel prices are levelized and vintaged by generator construction year due to the hydrogen PTC.

In the Geothermal Limitations and Hydrogen Challenges Sensitivity, hydrogen fuel prices are increased to reflect  an  upper  bound  of  uncertainty  over  future  fuel  prices.  For  details  on  hydrogen  forecast assumptions, see Appendix C.

Figure 52. Hydrogen Price Forecast, 2022 $/MMBtu

A RNG price assumption of $30/MMBtu in 2035 was provided by SVP for Gianera 1 and 2.

A uranium fuel price of $0.71/MMBtu in real 2022 dollars was adopted from the CPUC IRP Inputs and Assumptions document.44

44 https://www.cpuc.ca.gov/industries‐and‐topics/electrical‐energy/electric‐power‐procurement/long‐term‐procurement‐ planning/2022‐irp‐cycle‐events‐and‐materials

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   88

7.5. Transmission
As discussed in Section 6, the two regions in the SVP IRP model represent the SVP metered subsystem (MSS) and the rest of CAISO. These two nodes are connected by a transmission line that represents SVP’s tie‐ins to the bulk CAISO system. Per SVP’s MSS agreement, SVP must pay a TAC on net imports over this line. In PLEXOS, this consideration is instead implemented by applying a discount, equal to the TAC, on DVR and Gianera 1 and 2, such that these resources are incentivized to dispatch as resources that reduce SVP’s net load. The TAC is then added back in as a post‐processing step to calculate total system costs.

Here, the TAC is applied to SVP’s total load.

The forecast  of high‐voltage and low‐voltage  TAC was provided  by a consultant supporting SVP and is provided in Figure 53.

Figure 53. TAC Forecast, 2022 $/MWh

Two out‐of‐state resources, Wyoming  Wind and New Mexico Wind, are located external  to the CAISO system.  Instead  of  modeling  these  remote  candidate  resources  in  separate  zones  within  PLEXOS  to simulate the full transmission network, the transmission considerations have been modeled implicitly:
 The availability of remote candidate resources is  delayed reflecting  the expected timelines for additional capability to be made available on specific transmission lines, aligned with the latest assumptions from the CPUC IRP Inputs and Assumptions document.45  Cost  adders  have  been  assigned  to  specific  candidate  resources  based  on  the  need  for  line upgrades to accommodate additional transmission capability. These are included in the resource “Build Cost” in the PLEXOS model.

45 https://www.cpuc.ca.gov/industries‐and‐topics/electrical‐energy/electric‐power‐procurement/long‐term‐procurement‐ planning/2022‐irp‐cycle‐events‐and‐materials

Portfolio Expansion Resource Options2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   89
Out‐of‐state resources are assumed to require new transmission connections to the CAISO system. These connections incur out‐of‐state transmission deliverability costs which include transmission upgrade costs and wheeling charges. Transmission cost data for these remote wind generators are summarized in Figure

54. Figure 54. Transmission Deliverability Costs, 2022 $/kW‐yr Resource Name  Upgrade Cost  Wheeling Charge  Notes
New Mexico Wind  $71.20  $30.78  SunZia46 + SRP Wheeling47 Wyoming Wind  $118.80  N/A  TransWest48

46 https://nmfwri.org/wp‐content/uploads/2022/02/Mountainair‐Collaborative_SunZia‐Update‐1‐27‐2022.pdf. 47 http://www.oasis.oati.com/woa/docs/SRP/SRPdocs/SRP_OATT_08‐01‐2022_Final.pdf. 48 https://www.energy.ca.gov/reti/.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   90

8. Results and Discussion
This  section  presents  the  SVP  system  resource  portfolios  in  three  scenarios  with  varying  clean  energy requirements from 2026, the first year when new resource additions are allowed, to 2035, the end of the planning  horizon.  The  three  scenarios  are  listed  in  order  of  least  to  most  stringent  clean  energy requirements:
 Scenario 1: Base SB 100
 Scenario 2: Accelerated SB 100
 Scenario 3: Zero Emissions with Emerging Technology
Scenario 1: Base SB 100 (Base Scenario) identifies the optimal least‐cost portfolio that meets the current state policies. Scenario 2: Accelerated SB 100 (Accelerated SB 100 Scenario) advances the statewide SB 100 targets from the Base Scenario to reach 100% of retail sales clean by 2035. Scenario 3: Zero Emissions with  Emerging  Technology  (Zero  Emissions  Scenario)  achieves  zero  hourly  emissions  in  2035  with emerging technologies. For detailed scenario assumptions, please refer to Section 6.6.

The following Sections 8.1, 8.2, and 8.3 summarize results in each of the scenarios. Section 8.4 compares the three scenarios to identify the impacts of more aggressive clean energy policies.

The  accompanying  CEC  Standardized  Tables  (CRAT,  EBT,  RPT,  and  GEAT)  for  the  three  scenarios  are included in Appendix D.

8.1. Scenario 1: Base SB 100
Figure  55  shows  the  cumulative  resource  additions  through  2035  in  Scenario  1:  Base  SB  100  (Base Scenario). In the period 2026‐2027, SVP is modeled to add 180 MW wind, 150 MW solar, and 110 MW battery storage capacity to meet load growth and reliability requirements. Starting in 2028, geothermal becomes available and is added to the system (as well as wind capacity) as geothermal, though higher cost per MWh than wind, provides both clean energy generation and firm capacity that carries a higher reliability contribution. The baseload operating characteristics of geothermal also align with the relatively high 80% load factor (or average load divided by peak load) of the SVP system. A high load factor means that the system demand is relatively constant. Due to the large share of industrial load on SVP’s system and forecasted data center load growth, there is less ability to shape loads to take advantage of certain resource  production,  such  as  low‐cost  solar.  By  2035,  the  total  resource  additions  include  290  MW geothermal, 590 MW wind, 150 MW solar, and 110 MW storage capacity to meet load growth and the increasing clean energy requirement.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   91
Figure 55. Base Scenario Cumulative New Build Capacity

Figure 56 shows the total capacity through 2035 in the Base Scenario. In addition to resource additions in the new build capacity, this figure includes SVP’s existing and planned resources. Renewable and zero‐ carbon resources make up an increasing share of the total system capacity as no new emitting fossil fuel resources can be added to the system. One of the existing gas resources, LEC (78 MW), also transitions from 100% natural gas to 45% (volumetric) hydrogen blending. For detailed assumptions on existing and planned resources, please refer to Section 4 Existing and Planned System and Resources.

Figure 56. Base Scenario Total Capacity

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   92
Figure 57 shows the annual generation by resource type through 2035 in the Base Scenario. With existing, planned, and new build renewable resources, RPS (as a % of retail sales) reaches slightly over 60% in 2026, four years ahead of the 60% by 2030 SB 100 target and increases to around 80% by 2035.

Zero‐carbon resource generation (as a percentage of retail sales) reaches an estimated 77% in 2026 and increases to 90% in 2035, meeting SB 100 interim targets. Despite significant load growth forecasted over the planning period, gas‐based generation gradually reduces and stays relatively consistent in later years, as clean energy generation is selected to meet new loads.

Figure 57. Base Scenario Annual Generation

Note: RPS and Zero Carbon percentages are based on retail sales and on the accounting framework of annual targets in SB 100
Figure 58 details the annual energy balance of loads and resources.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   93
Figure 58. Base Scenario Annual Energy Balance of Loads and Resources

Figure 59 shows the system reliability modeling results through 2035 in the Base Scenario, using SVP’s marginal reliability need and marginal ELCC MW values. While the marginal ELCC per nameplate capacity of some resources such as gas and geothermal remains high, that of other resources such as wind, solar, and battery storage is lower and declines over the planning horizon as large volumes of these resources are added by other CAISO LSEs. Therefore, even with a relatively large share of the total nameplate Technology 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 5,983 6,436 7,037 7,492 7,964 8,428 8,953 9,210 9,387 9,559 DVR Gas - CC 1,103 1,195 1,214 1,163 1,036 1,012 1,005 1,034 1,041 946 Gianera 1 Gas - CT 10 10 10 7 3 7 5 - 0 1 Gianera 2 Gas - CT 10 10 10 5 4 4 5 - - 0 Alameda CT 1 Gas - CT - - - - - - - - - - Alameda CT 2 Gas - CT - - - - - - - - - - Lodi CT Gas - CT - - - - - - - - - - LEC Gas - CC 284 - - - - - - - - - LEC Hydrogen 45 Blend Hydrogen Blend - 254 257 214 76 108 67 16 78 93 Collierville Large Hydro 158 158 158 158 158 158 158 158 158 158 BESS 50MW 200MWh Li-ion Battery (4-hr) (7) (6) (7) (7) (10) (11) (13) (13) (11) (13) Black Butte Small Hydro 8 8 8 8 8 8 8 8 8 8 Stony Gorge Small Hydro 6 7 7 7 7 7 7 7 7 7 Grizzly Hydro Small Hydro 43 43 43 43 43 43 43 43 43 43 Big Horn 1 Wind 209 - - - - - - - - - Big Horn 2 Wind 41 40 42 37 37 42 36 35 37 28 Geo Plant 1 Unit 1 Geothermal 105 105 105 105 105 105 105 105 105 105 Geo Plant 1 Unit 2 Geothermal 105 105 105 105 105 105 105 105 105 105 Geo Plant 2 Unit 4 Geothermal 140 140 141 140 140 140 141 140 140 140 Spicer Small Hydro 5 5 5 5 5 5 5 5 5 5 2,221 2,074 2,098 1,990 1,716 1,733 1,678 1,644 1,717 1,626 Tri-Dam Donnells Large Hydro 243 243 243 243 243 243 243 243 243 243 WAPA Base Resource Large Hydro 250 250 250 250 250 250 250 250 250 250 South Feather - Forbstown Large Hydro 59 60 59 57 58 60 58 59 60 57 South Feather - Woodleaf Large Hydro 99 100 99 98 95 99 100 98 95 95 Ameresco Forward Biogas 37 37 37 37 36 37 36 36 6 - Ameresco Vasco Biogas 38 38 38 38 37 37 37 37 6 - G2 Landfill Biogas - - - - - - - - - - Tri-Dam Beardsley Small Hydro 43 44 45 45 44 45 44 44 43 43 Tri-Dam Sand Bar Small Hydro 71 74 73 75 73 75 74 73 70 70 Tri-Dam Tulloch Small Hydro 111 109 108 108 108 110 110 108 106 106 Friant 1 Small Hydro 66 67 66 66 65 66 66 66 65 65 Friant 2 (Quinten) Small Hydro 39 39 39 39 39 40 39 39 38 38 Rio Bravo (Index+) Small Hydro 15 15 14 14 14 15 14 13 15 14 Camp Far West Hydro (Index+) Small Hydro 26 26 24 26 25 25 25 26 25 26 South Feather - Kelly Ridge Small Hydro 27 27 27 28 27 27 27 27 27 27 South Feather - Sly Creek Small Hydro 14 14 14 14 14 14 14 14 14 14 Central 40 Solar Solar 113 113 110 111 112 113 107 109 111 110 Rosamond Solar Solar 63 63 61 62 62 62 60 61 63 60 Aquamarine Westside (Index+) Solar - - - - - - - - - - Manzana Wind Wind 132 125 116 119 128 126 125 - - - Cimmaron Wind Wind 930 786 742 783 886 820 855 786 797 761 Calpine Geo Geothermal 307 613 615 613 613 613 615 613 613 613 Sand Hill A Wind 30 28 29 28 28 29 30 26 27 30 Sand Hill B Wind 41 38 39 38 37 39 40 36 37 40 Rooney Ranch Wind 44 41 43 41 41 42 43 39 40 43 2,795 2,949 2,891 2,931 3,034 2,986 3,012 2,804 2,751 2,705 New Resources (Non -
RPS Eligible) Li_Battery_4hr Li-ion Battery (4-hr) (10) (10) (12) (13) (17) (19) (23) (20) (21) (22) Central_California_Wind Wind - - - 256 471 471 560 561 569 948 Geothermal Geothermal - - 466 465 1,026 1,397 2,012 2,482 2,508 2,541 New_Mexico_Wind Out-of-state Wind 432 415 437 514 525 505 484 486 562 500 Southern_California_Solar Solar 438 442 426 438 442 450 426 440 443 424 Wyoming_Wind Out-of-state Wind - 328 354 615 683 674 640 662 695 703 860 1,176 1,672 2,275 3,130 3,479 4,098 4,610 4,756 5,096 407 560 728 671 483 653 612 613 633 609 (300) (322) (352) (375) (399) (422) (448) (461) (470) (478) 107 237 376 296 84 231 164 152 163 131 5,983 6,436 7,037 7,492 7,964 8,428 8,953 9,210 9,387 9,559 Annual Energy Balance of Loads and Resources
Silicon Valley Powe r
Description
System Annual Energy Demand (GWh)
SVP Owned Units - Generation (GWh)
Long-term Contracts
(RPS Eligible)
Total Long-term Contracts (GWh)
New Resource Additions - Generation (GWh)
SVP Owned Units
(Non-RPS Eligible)
SVP Owned Units
(RPS Eligible)
Total SVP Owned Units (GWh)
Long-Term Contracts - Generation (GWh)
Long-term Contracts
(Non-RPS Eligible)
Net System Energy (G Wh)
New Resources
(RPS Eligible)
Total New Resource Additions (GWh)
Market Purchases and Sales (G Wh)
Market Purchases (GWh)
Market Sales (GWh)
Net Market Purchases (G Wh)
Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   94
capacity, solar, wind, and battery storage only contribute to a small share of the total effective capacity need. Geothermal, existing gas and hydro remain important for system reliability throughout the planning horizon.

The marginal reliability need shown in Figure 59 is not as high as peak load plus a margin as in the traditional PRM approach and it does not necessarily increase. However, it should not be directly interpreted as meaning there are lower capacity needs for the system, because the corresponding marginal ELCCs used for resource accreditation are also lower than the average ELCCs used in the traditional PRM approach. Hence, relative to the traditional PRM planning approach, the need declines but the resource contributions also decline accordingly. Although not directly used in modeling, the estimated total reliability need, using the traditional framework, and the difference in resource capacity accreditation (“CAISO Portfolio Effects”) is included in the reliability figure for illustrative purposes.49 For more details on the marginal reliability framework, please refer to Section 6.4 Model Constraints.

Figure 59. Base Scenario Marginal Reliability Need and Marginal Effective Capacity

Figure 60 details the annual marginal reliability need and resource capacity.

49 The total reliability need is estimated based on SVP’s coincident load with CAISO’s gross peak in the 2022 IEPR forecast and a perfect capacity (PCAP)‐based PRM of 14%. Gross peak is CAISO’s managed net peak with all BTM PV’s load‐reducing impacts added back. The 14% PCAP PRM translates to about 22% ICAP PRM and is a more stringent target than previous CAISO studies to ensure a 1‐day‐in‐10‐years LOLE target.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   95
Figure 60. Base Scenario Marginal Reliability Need and Resource Capacity Accreditation

Technology 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 845 906 987 1,056 1,124 1,186 1,251 1,287 1,315 1,341 System Coincident Peak(Coincident with 2022 IEPR CAISO Gross Peak) 790 843 858 952 1,010 1,085 1,164 1,163 1,144 1,210 PCAP PRM (%) 14% 14% 14% 14% 14% 14% 14% 14% 14% 14%
System Total Reliability Need (MW) 900 961 979 1,085 1,152 1,237 1,326 1,326 1,304 1,380 CAISO Portfolio Effects (MW) 76 107 116 203 243 300 333 370 334 432 825 853 863 882 909 937 993 956 970 947 DVR Gas - CC 130 129 129 127 126 128 129 131 133 135 Gianera 1 Gas - CT 21 20 20 20 20 20 20 20 21 21 Gianera 2 Gas - CT 21 20 20 20 20 20 20 20 21 21 Alameda CT 1 Gas - CT 8 8 8 8 8 8 8 8 8 8 Alameda CT 2 Gas - CT 8 8 8 8 8 8 8 8 8 8 Lodi CT Gas - CT 8 8 8 8 8 8 8 8 8 8 LEC Gas - CC 68 - - - - - - - - - LEC Hydrogen 45 Blend Hydrogen Blend - 68 68 67 66 67 68 69 70 71 Collierville Large Hydro 51 49 46 45 44 43 42 41 40 39 BESS 50MW 200MWh Li-ion Battery (4-hr) 46 42 39 38 37 34 30 27 23 20 Black Butte Small Hydro 2 2 2 2 2 2 2 2 2 2 Stony Gorge Small Hydro 2 2 2 2 2 2 2 2 2 2 Grizzly Hydro Small Hydro 7 7 6 6 6 6 6 6 6 5 Big Horn 1 Wind 23 - - - - - - - - - B i g H o r n 2W i n d4 4 4 3 3 3 3 3 3 3 Geo Plant 1 Unit 1 Geothermal 11 11 11 11 11 11 11 11 11 11 Geo Plant 1 Unit 2 Geothermal 11 11 11 11 11 11 11 11 11 11 Geo Plant 2 Unit 4 Geothermal 14 15 15 15 15 15 15 15 15 15 Spicer Small Hydro 1 1 1 1 1 1 1 1 1 1 436 406 399 392 386 385 384 384 383 382 Tri-Dam Donnells Large Hydro 40 38 36 35 35 34 33 32 32 31 WAPA Base Resource Large Hydro 71 67 63 62 61 59 58 57 55 54 South Feather - Forbstown Large Hydro 13 13 12 12 12 11 11 11 11 10 South Feather - Woodleaf Large Hydro 22 20 19 19 19 18 18 17 17 17 Ameresco Forward Biogas 3 3 3 3 3 3 3 3 - - Ameresco Vasco Biogas 3 3 3 3 3 3 3 4 - - G2 Landfill Biogas - - - - - - - - - - Tri-Dam Beardsley Small Hydro 5 4 4 4 4 4 4 4 4 4 Tri-Dam Sand Bar Small Hydro 7 6 6 6 6 5 5 5 5 5 Tri-Dam Tulloch Small Hydro 10 10 9 9 9 9 9 8 8 8 Friant 1 Small Hydro 10 10 9 9 9 8 8 8 8 8 Friant 2 (Quinten) Small Hydro - - - - - - - - - - Rio Bravo (Index+) Small Hydro 6 5 5 5 5 5 5 5 4 4 Camp Far West Hydro (Index+) Small Hydro 3 3 2 2 2 2 2 2 2 2 South Feather - Kelly Ridge Small Hydro 3 3 3 2 2 2 2 2 2 2 South Feather - Sly Creek Small Hydro 3 3 3 3 3 3 3 3 3 3 Central 40 Solar Solar 4 4 4 3 2 2 2 2 3 3 Rosamond Solar Solar 2 2 2 2 1 1 1 1 1 1 Aquamarine Westside (Index+) Solar - - - - - - - - - - Manzana Wind Wind 8 6 4 4 4 4 3 - - - Cimmaron Wind Wind - - - - - - - - - - Calpine Geo Geothermal 31 64 65 65 64 65 65 66 66 67 Sand Hill A Wind 4 3 2 2 2 2 2 2 1 1 Sand Hill B Wind 5 4 3 3 3 3 2 2 2 2 Rooney Ranch Wind 6 5 3 3 3 3 3 2 2 2 260 277 262 257 252 248 244 237 226 222 New Resources (Non -
RPS Eligible) Li_Battery_4hr Li-ion Battery (4-hr) 79 92 84 83 81 74 66 59 51 44 Central_California_Wind Wind - - - 8 12 11 12 11 9 14 Geothermal Geothermal - - 49 49 108 148 215 268 272 279 New_Mexico_Wind Out-of-state Wind 34 36 37 34 26 27 29 30 32 33 Southern_California_Solar Solar 16 15 14 12 9 9 9 9 9 10 Wyoming_Wind Out-of-state Wind - 28 29 47 35 37 39 41 43 45 129 171 214 233 271 307 370 418 417 425 825 853 875 882 909 940 999 1,039 1,026 1,030 New Resources
(RPS Eligible)
Total New Resource Additions (MW)
Total System Marginal ELCC Capacity (MW)
Long-term Contracts
(Non-RPS Eligible)
Long-term Contracts
(RPS Eligible)
Total Long-term Contracts (MW)
New Resource Additions - Marginal Effective Load Carrying Capability, ELCC (MW) SVP Owned Units - Marginal Effective Load Carrying Capability, ELCC (MW) SVP Owned Units
(Non-RPS Eligible)
SVP Owned Units
(RPS Eligible)
Total SVP Owned Units (MW)
Long-Term Contracts - Marginal Effective Load Carrying Capability, ELCC (MW) Marginal Reliability Need and Resource Capacity Accreditation Silicon Valley Powe r
Description
System Non-Coincident Peak Demand (MW)
System Marginal Reliability Need (MW)
Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   96

8.2. Scenario 2: Accelerated SB 100
The Accelerated SB 100 Scenario builds on top of Scenario 1: Base SB 100 (Base Scenario) to accelerate the SB 100 targets from 60% RPS to 70% carbon‐free energy (60% still needs to come from renewable resources) by 2030, and from 90% carbon‐free energy to 100% by 2035.

Figure  61  shows  the  cumulative  resource  additions  through  2035  in  the  Accelerated  SB  100  Scenario.

Near‐term additions are similar to those in the Base Scenario prior to the accelerated clean energy targets driving decisions later in the horizon. By 2035, the total resource additions include 330 MW geothermal, 740 MW wind, 180 MW solar, and 100 MW battery storage. 40 MW more geothermal, 150 MW more wind, and 30 MW more solar are selected compared to the Base Scenario to meet the higher clean energy requirement. Figure 62 shows the total capacity, including existing and planned resources, through 2035.

Figure 61. Accelerated SB 100 Scenario Cumulative New Build Capacity

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   97
Figure 62. Accelerated SB 100 Scenario Total Capacity

Figure 63 shows the annual generation by resource type through 2035 in the Accelerated SB 100 Scenario.

With  existing,  planned,  and  new  build  resources,  carbon‐free  resource  generation  (as  a  percentage  of retail sales) surpasses the 70% target in 2030, as clean energy generation is selected to meet SVP’s large increase in retail sales, and increases to 100%, meeting the accelerated 2035 target. Gas‐based generation is lower than that in the Base Scenario, but still present as the clean energy requirement is based on the accounting framework of SB 100, which requires 100% clean energy generation of retail sales, not total generation.

Figure 63. Accelerated SB 100 Scenario Annual Generation

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   98
Note: RPS and Zero Carbon percentages are based on retail sales and based on the accounting framework of annual targets in SB 100
Figure 64 details the annual energy balance of loads and resources.

Figure 64. Accelerated SB 100 Scenario Annual Energy Balance of Loads and Resources

Technology 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 5,983 6,436 7,037 7,492 7,964 8,428 8,953 9,210 9,387 9,559 DVR Gas - CC 1,056 1,152 1,193 1,139 1,026 1,007 1,005 1,020 876 508 Gianera 1 Gas - CT 10 10 10 6 1 5 5 - - - Gianera 2 Gas - CT 10 10 10 4 3 5 5 - - - Alameda CT 1 Gas - CT - - - - - - - - - - Alameda CT 2 Gas - CT - - - - - - - - - - Lodi CT Gas - CT - - - - - - - - - - LEC Gas - CC 274 - - - - - - - - - LEC Hydrogen 45 Blend Hydrogen Blend - 237 236 188 57 111 65 15 22 38 Collierville Large Hydro 158 158 158 158 158 158 158 158 158 158 BESS 50MW 200MWh Li-ion Battery (4-hr) (8) (6) (7) (8) (11) (12) (13) (12) (13) (38) Black Butte Small Hydro 8 8 8 8 8 8 8 8 8 8 Stony Gorge Small Hydro 6 7 7 7 7 7 7 7 7 7 Grizzly Hydro Small Hydro 43 43 43 43 43 43 43 43 43 43 Big Horn 1 Wind 208 - - - - - - - - - Big Horn 2 Wind 41 40 42 37 37 42 36 35 37 27 Geo Plant 1 Unit 1 Geothermal 105 105 105 105 105 105 105 105 105 105 Geo Plant 1 Unit 2 Geothermal 105 105 105 105 105 105 105 105 105 105 Geo Plant 2 Unit 4 Geothermal 140 140 141 140 140 140 141 140 140 140 Spicer Small Hydro 5 5 5 5 5 5 5 5 5 5 2,163 2,014 2,056 1,938 1,686 1,729 1,676 1,630 1,493 1,107 Tri-Dam Donnells Large Hydro 243 243 243 243 243 243 243 243 243 243 WAPA Base Resource Large Hydro 250 250 250 250 250 250 250 250 250 250 South Feather - Forbstown Large Hydro 59 60 59 57 59 60 58 59 60 57 South Feather - Woodleaf Large Hydro 99 100 99 98 97 99 101 98 95 94 Ameresco Forward Biogas 37 37 37 37 37 37 36 36 6 - Ameresco Vasco Biogas 38 38 38 38 37 37 37 37 6 - G2 Landfill Biogas - - - - - - - - - - Tri-Dam Beardsley Small Hydro 43 44 45 45 44 45 44 44 43 43 Tri-Dam Sand Bar Small Hydro 71 74 73 75 73 75 74 73 70 70 Tri-Dam Tulloch Small Hydro 111 109 108 108 108 110 110 108 106 106 Friant 1 Small Hydro 66 67 66 66 65 66 66 66 65 65 Friant 2 (Quinten) Small Hydro 39 39 39 39 39 40 39 39 38 38 Rio Bravo (Index+) Small Hydro 15 15 14 14 14 15 14 13 15 14 Camp Far West Hydro (Index+) Small Hydro 26 26 24 26 25 25 25 26 25 26 South Feather - Kelly Ridge Small Hydro 26 27 27 28 27 27 27 27 27 26 South Feather - Sly Creek Small Hydro 14 14 14 14 14 14 14 14 14 13 Central 40 Solar Solar 113 113 110 111 112 113 107 107 110 103 Rosamond Solar Solar 62 63 61 62 62 62 59 61 62 55 Aquamarine Westside (Index+) Solar - - - - - - - - - - Manzana Wind Wind 131 125 116 119 128 127 123 - - - Cimmaron Wind Wind 930 786 742 783 886 822 851 777 794 732 Calpine Geo Geothermal 307 613 615 613 613 613 615 613 613 613 Sand Hill A Wind 30 28 29 28 28 29 29 26 27 28 Sand Hill B Wind 41 38 39 38 38 39 40 36 37 37 Rooney Ranch Wind 44 41 43 41 41 42 43 39 40 41 2,792 2,949 2,891 2,931 3,039 2,988 3,005 2,792 2,747 2,654 New Resources (Non -
RPS Eligible) Li_Battery_4hr Li-ion Battery (4-hr) (11) (10) (12) (13) (17) (20) (21) (20) (21) (33) Central_California_Wind Wind - - - 256 389 390 526 527 534 1,242 Geothermal Geothermal - - 466 465 1,045 1,389 1,961 2,447 2,869 2,821 New_Mexico_Wind Out-of-state Wind 445 427 450 534 545 524 502 505 584 520 Southern_California_Solar Solar 525 529 511 524 530 539 510 528 531 508 Wyoming_Wind Out-of-state Wind - 328 354 615 683 674 640 662 695 938 959 1,275 1,769 2,382 3,176 3,497 4,118 4,649 5,193 5,995 369 520 674 616 463 637 601 601 425 281 (300) (322) (352) (375) (399) (422) (448) (461) (470) (478) 69 198 322 241 64 214 153 140 (45) (198) 5,983 6,436 7,037 7,492 7,964 8,428 8,953 9,210 9,387 9,559 Net System Energy (G Wh) New Resources
(RPS Eligible)
Total New Resource Additions (GWh)
Market Purchases and Sales (G Wh)
Market Purchases (GWh)
Market Sales (GWh)
Net Market Purchases (G Wh)
Long-term Contracts
(RPS Eligible)
Total Long-term Contracts (GWh)
New Resource Additions - Generation (GWh)
SVP Owned Units
(Non-RPS Eligible)
SVP Owned Units
(RPS Eligible)
Total SVP Owned Units (GWh)
Long-Term Contracts - Generation (GWh)
Long-term Contracts
(Non-RPS Eligible)
Annual Energy Balance of Loads and Resources
Silicon Valley Powe r
Description
System Annual Energy Demand (GWh)
SVP Owned Units - Generation (GWh)
Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   99
Figure 65 shows the system reliability modeling results through 2035 in the Accelerated SB 100 Scenario.

As more capacity is added to meet the clean energy target in this scenario, the total system marginal ELCC MW is higher than that in the Base Scenario and is above the marginal reliability need towards the end of the planning horizon, which illustrates that the clean energy target is the more stringent requirement to meet.

Figure 65. Accelerated SB 100 Scenario Marginal Reliability Need and Marginal Effective Capacity

Figure 66 details the annual marginal reliability need and resource capacity.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   100
Figure 66. Accelerated SB 100 Scenario Marginal Reliability Need and Resource Capacity Accreditation

Technology 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 845 906 987 1,056 1,124 1,186 1,251 1,287 1,315 1,341 System Coincident Peak (Coincident with 2022 IEPR CAISO Gross Peak) 790 843 858 952 1,010 1,085 1,164 1,163 1,144 1,210 PCAP PRM (%) 14% 14% 14% 14% 14% 14% 14% 14% 14% 14%
System Total Reliability Need (MW) 900 961 979 1,085 1,152 1,237 1,326 1,326 1,304 1,380 CAISO Portfolio Effects (MW) 76 107 116 203 243 300 333 370 334 432 825 853 863 882 909 937 993 956 970 947 DVR Gas - CC 130 129 129 127 126 128 129 131 133 135 Gianera 1 Gas - CT 21 20 20 20 20 20 20 20 21 21 Gianera 2 Gas - CT 21 20 20 20 20 20 20 20 21 21 Alameda CT 1 Gas - CT 8 8 8 8 8 8 8 8 8 8 Alameda CT 2 Gas - CT 8 8 8 8 8 8 8 8 8 8 Lodi CT Gas - CT 8 8 8 8 8 8 8 8 8 8 LEC Gas - CC 68 - - - - - - - - - LEC Hydrogen 45 Blend Hydrogen Blend - 68 68 67 66 67 68 69 70 71 Collierville Large Hydro 51 49 46 45 44 43 42 41 40 39 BESS 50MW 200MWh Li-ion Battery (4-hr) 46 42 39 38 37 34 30 27 23 20 Black Butte Small Hydro 2 2 2 2 2 2 2 2 2 2 Stony Gorge Small Hydro 2 2 2 2 2 2 2 2 2 2 Grizzly Hydro Small Hydro 7 7 6 6 6 6 6 6 6 5 Big Horn 1 Wind 23 - - - - - - - - - B i g H o r n 2W i n d4 4 4 3 3 3 3 3 3 3 Geo Plant 1 Unit 1 Geothermal 11 11 11 11 11 11 11 11 11 11 Geo Plant 1 Unit 2 Geothermal 11 11 11 11 11 11 11 11 11 11 Geo Plant 2 Unit 4 Geothermal 14 15 15 15 15 15 15 15 15 15 Spicer Small Hydro 1 1 1 1 1 1 1 1 1 1 436 406 399 392 386 385 384 384 383 382 Tri-Dam Donnells Large Hydro 40 38 36 35 35 34 33 32 32 31 WAPA Base Resource Large Hydro 71 67 63 62 61 59 58 57 55 54 South Feather - Forbstown Large Hydro 13 13 12 12 12 11 11 11 11 10 South Feather - Woodleaf Large Hydro 22 20 19 19 19 18 18 17 17 17 Ameresco Forward Biogas 3 3 3 3 3 3 3 3 - - Ameresco Vasco Biogas 3 3 3 3 3 3 3 4 - - G2 Landfill Biogas - - - - - - - - - - Tri-Dam Beardsley Small Hydro 5 4 4 4 4 4 4 4 4 4 Tri-Dam Sand Bar Small Hydro 7 6 6 6 6 5 5 5 5 5 Tri-Dam Tulloch Small Hydro 10 10 9 9 9 9 9 8 8 8 Friant 1 Small Hydro 10 10 9 9 9 8 8 8 8 8 Friant 2 (Quinten) Small Hydro - - - - - - - - - - Rio Bravo (Index+) Small Hydro 6 5 5 5 5 5 5 5 4 4 Camp Far West Hydro (Index+) Small Hydro 3 3 2 2 2 2 2 2 2 2 South Feather - Kelly Ridge Small Hydro 3 3 3 2 2 2 2 2 2 2 South Feather - Sly Creek Small Hydro 3 3 3 3 3 3 3 3 3 3 Central 40 Solar Solar 4 4 4 3 2 2 2 2 3 3 Rosamond Solar Solar 2 2 2 2 1 1 1 1 1 1 Aquamarine Westside (Index+) Solar - - - - - - - - - - Manzana Wind Wind 8 6 4 4 4 4 3 - - - Cimmaron Wind Wind - - - - - - - - - - Calpine Geo Geothermal 31 64 65 65 64 65 65 66 66 67 Sand Hill A Wind 4 3 2 2 2 2 2 2 1 1 Sand Hill B Wind 5 4 3 3 3 3 2 2 2 2 Rooney Ranch Wind 6 5 3 3 3 3 3 2 2 2 260 277 262 257 252 248 244 237 226 222 New Resources (Non -
RPS Eligible) Li_Battery_4hr Li-ion Battery (4-hr) 74 88 81 79 78 70 63 56 49 42 Central_California_Wind Wind - - - 8 10 9 11 10 9 18 Geothermal Geothermal - - 49 49 110 148 210 264 312 317 New_Mexico_Wind Out-of-state Wind 35 37 38 36 27 28 30 31 33 34 Southern_California_Solar Solar 19 18 17 14 11 11 11 11 11 11 Wyoming_Wind Out-of-state Wind - 28 29 47 35 37 39 41 43 60 129 171 214 233 271 304 365 414 457 484 825 853 875 882 909 937 993 1,035 1,066 1,088 New Resources
(RPS Eligible)
Total New Resource Additions (MW)
Total System Marginal ELCC Capacity (MW)
Long-term Contracts
(Non-RPS Eligible)
Long-term Contracts
(RPS Eligible)
Total Long-term Contracts (MW)
New Resource Additions - Marginal Effective Load Carrying Capability, ELCC (MW) SVP Owned Units - Marginal Effective Load Carrying Capability, ELCC (MW) SVP Owned Units
(Non-RPS Eligible)
SVP Owned Units
(RPS Eligible)
Total SVP Owned Units (MW)
Long-Term Contracts - Marginal Effective Load Carrying Capability, ELCC (MW) Marginal Reliability Need and Resource Capacity Accreditation Silicon Valley Powe r
Description
System Non-Coincident Peak Demand (MW)
System Marginal Reliability Need (MW)
Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   101

8.3. Scenario 3: Zero Emissions with Emerging Technology This  scenario  represents  the  most  stringent  clean  energy  target  modeled  in  this  IRP.  Scenario  3:  Zero Emissions with Emerging Technology (Zero Emissions Scenario) builds on top of Scenario 2: Accelerated SB 100 and limits emission to zero in every hour in 2035.

As gas plants cannot  be dispatched to  serve load or meet reliability requirements without resulting  in carbon  emissions  in  this  scenario,  they  must  either  retire  or  convert  to  zero‐carbon  fuels  by  2035.

Additionally,  market  purchases  are  only  allowed  in  hours  when  the  market  emission  factors  are  zero.

However,  emerging  technologies  are  assumed  to  be  available  to  help  achieve  zero  emissions  in  this scenario. As many studies have shown, “clean firm” resources that can provide zero‐carbon generation on demand to fill in gaps in variable resource output are a critical component of reaching a zero‐emissions power  system.  The  “clean  firm”  technologies  considered  include  building  new  green  hydrogen  power plants, CCS (Allam cycle with 100% capture and storage) plants, and long‐duration storage. In addition to the ability to build new clean firm resources, retrofits of SVP’s existing thermal portfolio to zero‐emission fuels are assumed:
 LEC  transitions  from  45%  (volumetric)  hydrogen  blending  (2027)  to  100%  hydrogen  starting  in 2032 50
 Alameda CT 1 and 2 run on 100% hydrogen starting in 2030  Lodi CT runs on 100% hydrogen starting in 2032
 DVR runs on 100% hydrogen starting in 2035
 Gianera 1 and 2 run on 100% biogas starting in 2035
DVR and Gianera are two significant local SVP resources, and the transition of these resources to zero‐ emission fuels in 2035 in this scenario is partly driven by transmission limitations between SVP and CAISO.

If  local  resources  aren’t  available,  SVP  may  be  completely  dependent  on  electricity  delivered  via transmission from CAISO to meet load. However, the existing and planned transmission capacity would have insufficient capacity and is about 90 MW below SVP’s forecasted peak load in 2035. Therefore, it is not  feasible  under  current  and  planned  transmission  additions  to  reach  zero‐emissions  without retrofitting local gas generating resources to run on zero‐emission fuel and allow them to be dispatched to meet SVP’s load.

Figure  67  shows  the  cumulative  resource  additions  through  2035  in  the  Zero  Emissions  Scenario.  The figure  includes  the  above  existing  resources’  assumed  transitions  to  zero‐emission  fuels.  Near‐term additions  are  similar  to  the  Accelerated  SB  100  Scenario’s  additions  as  the  zero‐emission  limit  is  not applied until 2035. By 2035, the total resource additions include 280 MW hydrogen (250 MW comes from assumed transitions of DVR and LEC and 30 MW comes from building new hydrogen plants), 350 MW geothermal, 50 MW biogas (assumed transition of Gianera), 530 MW wind, 150 MW solar, and 100 MW

50 The 2032 start year is assumed based on information provided to SVP in communications with NCPA.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   102
battery storage. Other emerging technologies, such as CCS and long‐duration storage are not selected due to economics. See Figure 68 for the total system capacity, including other existing resources, through 2035.

Figure 67. Zero Emissions Scenario Cumulative New Build Capacity

Figure 68. Zero Emissions Scenario Total Capacity

See Figure 69 for the annual generation by resource type through 2035 in the Zero Emissions Scenario.

Generation mix follows similar trends as seen in the Accelerated SB 100 Scenario in the near term. In 2035 when  the  zero‐emission  limit  is  applied,  no  gas  generation  is  allowed  and  all  generation  comes  from renewable and carbon‐free resources, and zero‐emission market purchases. The reason that the  zero‐

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   103
carbon percentage exceeds 100% in 2035 is because it is calculated based on the accounting framework of SB 100, which is different from total system generation.

Figure 69. Zero Emissions Scenario Annual Generation

Note: RPS and Zero Carbon percentages are based on retail sales and based on the accounting framework of annual targets in SB 100
Figure 70 details the annual energy balance of loads and resources.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   104
Figure 70. Zero Emissions Scenario Annual Energy Balance of Loads and Resources

Technology 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 5,983 6,436 7,037 7,492 7,964 8,428 8,953 9,210 9,387 9,559 DVR Gas - CC 1,067 1,160 1,196 1,141 1,027 1,007 1,006 1,027 891 - Gianera 1 Gas - CT 10 10 10 6 2 5 5 - - - Gianera 2 Gas - CT 10 10 10 4 3 5 5 - - - Alameda CT 1 Gas - CT - - - - - - - - - - Alameda CT 2 Gas - CT - - - - - - - - - - Lodi CT Gas - CT - - - - - - - - - - LEC Gas - CC 273 - - - - - - - - - LEC Hydrogen 45 Blend Hydrogen Blend - 242 240 198 67 113 - - - - Collierville Large Hydro 158 158 158 158 158 158 158 158 158 158 BESS 50MW 200MWh Li-ion Battery (4-hr) (7) (6) (7) (7) (11) (11) (14) (13) (13) (15) Black Butte Small Hydro 8 8 8 8 8 8 8 8 8 8 Stony Gorge Small Hydro 6 7 7 7 7 7 7 7 7 7 Grizzly Hydro Small Hydro 43 43 43 43 43 43 43 43 43 43 Big Horn 1 Wind 209 - - - - - - - - - Big Horn 2 Wind 41 40 42 37 37 42 36 35 37 28 Geo Plant 1 Unit 1 Geothermal 105 105 105 105 105 105 105 105 105 105 Geo Plant 1 Unit 2 Geothermal 105 105 105 105 105 105 105 105 105 105 Geo Plant 2 Unit 4 Geothermal 140 140 141 140 140 140 141 140 140 140 Spicer Small Hydro 5 5 5 5 5 5 5 5 5 5 2,174 2,028 2,063 1,951 1,696 1,732 1,612 1,621 1,486 584 Tri-Dam Donnells Large Hydro 243 243 243 243 243 243 243 243 243 243 WAPA Base Resource Large Hydro 250 250 250 250 250 250 250 250 250 250 South Feather - Forbstown Large Hydro 59 60 59 57 59 60 58 59 59 57 South Feather - Woodleaf Large Hydro 99 100 99 98 97 99 100 98 95 94 Ameresco Forward Biogas 37 37 37 37 37 37 36 36 6 - Ameresco Vasco Biogas 38 38 38 38 37 37 37 37 6 - G2 Landfill Biogas - - - - - - - - - - Tri-Dam Beardsley Small Hydro 43 44 45 45 44 45 44 44 43 43 Tri-Dam Sand Bar Small Hydro 71 74 73 75 73 75 74 73 70 70 Tri-Dam Tulloch Small Hydro 111 109 108 108 108 110 110 108 106 106 Friant 1 Small Hydro 66 67 66 66 65 66 66 66 65 65 Friant 2 (Quinten) Small Hydro 39 39 39 39 39 40 39 39 38 38 Rio Bravo (Index+) Small Hydro 15 15 14 14 14 15 14 13 15 14 Camp Far West Hydro (Index+) Small Hydro 26 26 24 26 25 25 25 26 25 26 South Feather - Kelly Ridge Small Hydro 26 27 27 28 27 27 27 27 27 27 South Feather - Sly Creek Small Hydro 14 14 14 14 14 14 14 14 14 13 Central 40 Solar Solar 113 113 110 111 113 113 106 108 110 108 Rosamond Solar Solar 62 63 61 62 63 62 59 60 62 59 Aquamarine Westside (Index+) Solar - - - - - - - - - - Manzana Wind Wind 132 125 116 119 128 126 123 - - - Cimmaron Wind Wind 930 786 742 783 887 821 854 783 794 752 Calpine Geo Geothermal 307 613 615 613 613 613 615 613 613 613 Sand Hill A Wind 30 28 29 28 28 29 30 27 27 29 Sand Hill B Wind 41 38 39 38 38 39 40 36 37 40 Rooney Ranch Wind 44 41 43 41 41 42 43 39 40 43 2,794 2,949 2,891 2,931 3,042 2,987 3,006 2,799 2,745 2,691 Hydrogen_Aero_CT_2035 Hydrogen - - - - - - - - - 25 Li_Battery_4hr Li-ion Battery (4-hr) (9) (9) (11) (12) (17) (17) (20) (19) (18) (15) DVR Hydrogen Hydrogen - - - - - - - - - 856 Alameda CT 1 Hydrogen Hydrogen - - - - - - - - - - Alameda CT 2 Hydrogen Hydrogen - - - - - - - - - 5 Lodi CT Hydrogen Hydrogen - - - - - - - - - 5 LEC Hydrogen 100 Blend Hydrogen - - - - - - 38 14 75 158 Central_California_Wind Wind - - - 256 378 378 541 542 550 563 Geothermal Geothermal - - 466 465 1,055 1,413 1,977 2,432 2,802 3,000 New_Mexico_Wind Out-of-state Wind 509 489 515 599 612 588 564 566 655 583 Southern_California_Solar Solar 437 441 425 437 441 449 425 439 442 423 Wyoming_Wind Out-of-state Wind - 328 354 615 683 674 640 662 695 938 Gianera 1 RNG Biogas - - - - - - - - - 10 Gianera 2 RNG Biogas - - - - - - - - - 8 937 1,250 1,750 2,360 3,152 3,485 4,165 4,637 5,201 6,558 379 532 685 625 472 646 617 614 424 204 (300) (322) (352) (375) (399) (422) (448) (461) (470) (478) 79 209 333 250 73 224 169 153 (46) (274) 5,983 6,436 7,037 7,492 7,964 8,428 8,953 9,210 9,387 9,559 Net System Energy (G Wh) New Resources (Non -
RPS Eligible)
New Resources
(RPS Eligible)
Total New Resource Additions (GWh)
Market Purchases and Sales (G Wh)
Market Purchases (GWh)
Market Sales (GWh)
Net Market Purchases (G Wh)
Long-term Contracts
(RPS Eligible)
Total Long-term Contracts (GWh)
New Resource Additions - Generation (GWh)
SVP Owned Units
(Non-RPS Eligible)
SVP Owned Units
(RPS Eligible)
Total SVP Owned Units (GWh)
Long-Term Contracts - Generation (GWh)
Long-term Contracts
(Non-RPS Eligible)
Annual Energy Balance of Loads and Resources
Silicon Valley Powe r
Description
System Annual Energy Demand (GWh)
SVP Owned Units - Generation (GWh)
Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   105
Figure 71 shows the system reliability modeling results through 2035 in the Zero Emissions Scenario.

Resource capacity contribution is similar to the Accelerated SB 100 Scenario before 2035. In 2035, more clean resources are added to the system due to the stringent emission target and surpass the marginal reliability need, meaning the marginal reliability requirement is not the primary driver of resource builds by 2035.

Figure 71. Zero Emissions Scenario Marginal Reliability Need and Marginal Effective Capacity

Figure 72 details the annual marginal reliability need and resource capacity.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   106
Figure 72. Zero Emissions Scenario Marginal Reliability Need and Resource Capacity Accreditation

Technology 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 845 906 987 1,056 1,124 1,186 1,251 1,287 1,315 1,341 System Coincident Peak (Coincident with 2022 IEPR CAISO Gross Peak) 790 843 858 952 1,010 1,085 1,164 1,163 1,144 1,210 PCAP PRM (%) 14% 14% 14% 14% 14% 14% 14% 14% 14% 14%
System Total Reliability Need (MW) 900 961 979 1,085 1,152 1,237 1,326 1,326 1,304 1,380 CAISO Portfolio Effects (MW) 76 107 116 203 243 300 333 370 334 432 825 853 863 882 909 937 993 956 970 947 DVR Gas - CC 130 129 129 127 126 128 129 131 133 - Gianera 1 Gas - CT 21 20 20 20 20 20 20 20 21 - Gianera 2 Gas - CT 21 20 20 20 20 20 20 20 21 - Alameda CT 1 Gas - CT 8 8 8 8 - - - - - - Alameda CT 2 Gas - CT 8 8 8 8 - - - - - - Lodi CT Gas - CT 8 8 8 8 8 8 - - - - LEC Gas - CC 68 - - - - - - - - - LEC Hydrogen 45 Blend Hydrogen Blend - 68 68 67 66 67 - - - - Collierville Large Hydro 51 49 46 45 44 43 42 41 40 39 BESS 50MW 200MWh Li-ion Battery (4-hr) 46 42 39 38 37 34 30 27 23 20 Black Butte Small Hydro 2 2 2 2 2 2 2 2 2 2 Stony Gorge Small Hydro 2 2 2 2 2 2 2 2 2 2 Grizzly Hydro Small Hydro 7 7 6 6 6 6 6 6 6 5 Big Horn 1 Wind 23 - - - - - - - - - B i g H o r n 2W i n d4 4 4 3 3 3 3 3 3 3 Geo Plant 1 Unit 1 Geothermal 11 11 11 11 11 11 11 11 11 11 Geo Plant 1 Unit 2 Geothermal 11 11 11 11 11 11 11 11 11 11 Geo Plant 2 Unit 4 Geothermal 14 15 15 15 15 15 15 15 15 15 Spicer Small Hydro 1 1 1 1 1 1 1 1 1 1 436 406 399 392 370 369 292 290 289 110 Tri-Dam Donnells Large Hydro 40 38 36 35 35 34 33 32 32 31 WAPA Base Resource Large Hydro 71 67 63 62 61 59 58 57 55 54 South Feather - Forbstown Large Hydro 13 13 12 12 12 11 11 11 11 10 South Feather - Woodleaf Large Hydro 22 20 19 19 19 18 18 17 17 17 Ameresco Forward Biogas 3 3 3 3 3 3 3 3 - - Ameresco Vasco Biogas 3 3 3 3 3 3 3 4 - - G2 Landfill Biogas - - - - - - - - - - Tri-Dam Beardsley Small Hydro 5 4 4 4 4 4 4 4 4 4 Tri-Dam Sand Bar Small Hydro 7 6 6 6 6 5 5 5 5 5 Tri-Dam Tulloch Small Hydro 10 10 9 9 9 9 9 8 8 8 Friant 1 Small Hydro 10 10 9 9 9 8 8 8 8 8 Friant 2 (Quinten) Small Hydro - - - - - - - - - - Rio Bravo (Index+) Small Hydro 6 5 5 5 5 5 5 5 4 4 Camp Far West Hydro (Index+) Small Hydro 3 3 2 2 2 2 2 2 2 2 South Feather - Kelly Ridge Small Hydro 3 3 3 2 2 2 2 2 2 2 South Feather - Sly Creek Small Hydro 3 3 3 3 3 3 3 3 3 3 Central 40 Solar Solar 4 4 4 3 2 2 2 2 3 3 Rosamond Solar Solar 2 2 2 2 1 1 1 1 1 1 Aquamarine Westside (Index+) Solar - - - - - - - - - - Manzana Wind Wind 8 6 4 4 4 4 3 - - - Cimmaron Wind Wind - - - - - - - - - - Calpine Geo Geothermal 31 64 65 65 64 65 65 66 66 67 Sand Hill A Wind 4 3 2 2 2 2 2 2 1 1 Sand Hill B Wind 5 4 3 3 3 3 2 2 2 2 Rooney Ranch Wind 6 5 3 3 3 3 3 2 2 2 260 277 262 257 252 248 244 237 226 222 Hydrogen_Aero_CT_2035 Hydrogen - - - - - - - - - 24 Li_Battery_4hr Li-ion Battery (4-hr) 73 86 79 77 76 69 62 55 48 41 DVR Hydrogen Hydrogen - - - - - - - - - 135 Alameda CT 1 Hydrogen Hydrogen - - - - 8 8 8 8 8 8 Alameda CT 2 Hydrogen Hydrogen - - - - 8 8 8 8 8 8 Lodi CT Hydrogen Hydrogen - - - - - - 8 8 8 8 LEC Hydrogen 100 Blend Hydrogen - - - - - - 68 69 70 71 Central_California_Wind Wind - - - 8 10 9 12 10 9 8 Geothermal Geothermal - - 49 49 111 150 211 263 304 331 New_Mexico_Wind Out-of-state Wind 40 42 44 40 30 32 34 35 37 39 Southern_California_Solar Solar 16 15 14 12 9 9 9 9 9 10 Wyoming_Wind Out-of-state Wind - 28 29 47 35 37 39 41 43 60 Gianera 1 RNG Biogas - - - - - - - - - 21 Gianera 2 RNG Biogas - - - - - - - - - 21 129 171 215 233 287 321 459 507 545 784 825 853 876 882 909 939 995 1,035 1,059 1,117 New Resources (Non -
RPS Eligible)
New Resources
(RPS Eligible)
Total New Resource Additions (MW)
Total System Marginal ELCC Capacity (MW)
Long-term Contracts
(Non-RPS Eligible)
Long-term Contracts
(RPS Eligible)
Total Long-term Contracts (MW)
New Resource Additions - Marginal Effective Load Carrying Capability, ELCC (MW) SVP Owned Units - Marginal Effective Load Carrying Capability, ELCC (MW) SVP Owned Units
(Non-RPS Eligible)
SVP Owned Units
(RPS Eligible)
Total SVP Owned Units (MW)
Long-Term Contracts - Marginal Effective Load Carrying Capability, ELCC (MW) Marginal Reliability Need and Resource Capacity Accreditation Silicon Valley Powe r
Description
System Non-Coincident Peak Demand (MW)
System Marginal Reliability Need (MW)
Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   107

8.4. Scenario Comparison
In 2030, the three scenarios have similar resource additions. At least 120 MW geothermal, 400 MW wind, 150 MW solar, and 100 MW battery are selected across the scenarios, indicating that these resources are fairly robust and likely low‐regret decisions for SVP in the near term, given the assumptions in this study.

Figure 73. Scenario Comparison – 2030 Cumulative New Build Capacity

While the three scenarios have similar resource additions in the near‐term, they begin to diverge towards the  end  of  the  planning  horizon  as  more  aggressive  clean  energy  targets  are  applied  in  Scenario  2:

Accelerated  SB  100  (Accelerated  SB  100  Scenario)  and  Scenario  3:  Zero  Emissions  with  Emerging Technology (Zero Emissions Scenario). Figure 74 compares the cumulative resource additions between the scenarios by 2035. The resource capacities in the Zero Emissions Scenario include the assumed retrofit of some existing SVP natural gas resources (DVR, Gianera, and LEC) to zero‐emission fuels.

Compared to Scenario 1: Base SB 100 (Base Scenario), the Accelerated SB 100 Scenario adds about 40 MW more geothermal, 150 MW more wind, and 30 MW more solar capacities to achieve the accelerated 100% carbon free of retail sales by 2035 based on SB 100’s annual accounting framework.

Compared to the Base Scenario, the Zero Emissions Scenario assumes 300 MW of existing gas resources are converted to zero‐emission fuel by 2035 and adds about 30 MW more hydrogen and 50 MW more geothermal  resources  to  the  portfolio.  While  solar  and  battery  storage  capacities  are  similar,  wind capacity  is  60  MW  less  than  the  Base  Scenario  due  to  the  availability  of  emerging  technologies  and additional  geothermal  capacity  selected.  Clean  firm  resources,  such  as  hydrogen  and  geothermal considered  in  this  IRP,  are  favored  in  this  scenario  as  it  is  difficult  to  meet  SVP’s  load  profile  with  no emissions in every hour without firm and dispatchable resource options. The critical role of “clean firm”

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   108
resources  in  deep‐decarbonized  and  zero‐emission  systems  has  been  highlighted  and  discussed  in  the industry.51
Figure 74. Scenario Comparison – 2035 Cumulative New Build Capacity

Figure 75 shows a comparison of total capacity between the three scenarios in 2035. The total capacity of the Zero Emissions Scenario is similar to the Base Scenario and lower than the Accelerated SB 100 Scenario because it  includes the zero‐emission fuel  conversion of some of the existing  gas resources and other emerging technologies. However, there are uncertainties in these assumptions. If emerging technologies and zero‐emission fuels are not available to SVP by 2035, SVP would need to procure higher amounts of existing mature technologies, such as solar, wind, and battery storage resources to achieve zero emission in every hour. The total nameplate capacity of those resources is likely higher than the system load and the  three  scenarios  explored  here.  Because  they  have  low  and  marginally  decreasing  reliability  value, more  capacity  would  be  needed  to  cover  the  most  critical  hours,  even  though  there  might  be  high curtailment in other normal and/or low load hours. Emerging technology options, such as new hydrogen plants  and  retrofit  of  existing  gas  plants  to  hydrogen  or  biogas,  offer  the  “clean  firm”  attributes  and significantly reduces the potential for “overbuilding” existing mature technologies. Thus, reaching a zero‐ emissions SVP system at reasonable costs by 2035 requires reliance on “clean firm” emerging technologies that are not available commercially at scale today.

51 Burdick et al, 2022. “Lighting a Reliable Path to 100% Clean Electricity. Evolving Resource Adequacy Practices for a Decarbonizing Grid.” IEEE Power & Energy Magazine. July/August 2022 NREL. “LA100 Report.” 2021. https://maps.nrel.gov/la100/la100‐study/report E3 and EFI. “Net‐Zero New England: Ensuring Electric Reliability in a Low‐Carbon Future.” 2020. https://www.ethree.com/wp‐ content/uploads/2020/11/E3‐EFI_Report‐New‐England‐Reliability‐Under‐Deep‐Decarbonization_Full‐ Report_November_2020.pdf
E3. “Resource Adequacy in the Pacific Northwest.” 2019. https://www.ethree.com/wp‐ content/uploads/2019/03/E3_Resource_Adequacy_in_the_Pacific‐Northwest_March_2019.pdf

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   109
Figure 75. Scenario Comparison – 2035 Total Capacity

Figure  76  shows  the  comparison  of  annual  generation  between  the  three  scenarios  in  2035.  Gas generation reduces from Base to Accelerated SB 100 Scenario as the clean energy target increases and becomes zero in the Zero Emissions Scenario. Market purchases also reduce, and the annual net market transaction becomes net sales to market in the latter two scenarios as more energy needs to come from specified renewable and carbon‐free resources, and market purchases can only occur in periods when the market is also “clean” (i.e., the emission factor is zero) in the most stringent scenario.

Figure 76. Scenario Comparison – 2035 Annual Generation

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   110
Figure  77  shows  the  comparison  of  annual  CO2  emissions  between  the  three  scenarios  in  2035.  This includes emissions from SVP’s resources and market purchases. It also includes emission offset credits from market sales when applicable in the Base and Accelerated SB 100 Scenarios (see Section 6.4 for the detailed  emission  accounting  methodology).  The  2035  annual  emissions  are  approximately  380,000 metric  tons,  85,000  metric  tons  in  the  Accelerated  SB  100  Scenario,  and  zero  in  the  Zero  Emissions Scenario. System emission reduces following the generation mix trends discussed above.

Figure 77. Scenario Comparison – 2035 Annual CO2 Emission

Note: Annual CO2 emission includes emission from SVP’s resources and market purchases. In the Base and Accelerated SB 100 Scenarios, it also includes emission offset credits from market sales when applicable.

See Figure 78 for the comparison of annual modeled cost between the three scenarios in 2035. This only represents  the  cost  components  modeled  and  does  not  represent  SVP’s  total  revenue  requirement.

Modeled  cost  includes  the  operational  cost  (e.g.,  variable  O&M,  fuel  costs)  of  existing  and  planned capacity, and the capital cost and operational cost of new build capacity. Capital and fixed costs (including PPA cost) of existing and planned capacity are not included. Transmission and distribution costs are also not included.

Compared to the annual modeled cost in the Base Scenario, which reaches $250 million (2022 $; TAC costs and non‐modeled system costs are excluded) in 2035, the annual modeled cost increases by about $25 million  (2022  $)  in  the  Accelerated  SB  100  Scenario  and  increases  by  $55  million  (2022  $)  in  the  Zero Emissions Scenario. However, it is important to note that there are large uncertainties in the availability and cost of emerging technologies and zero‐emission fuels by 2035. As discussed above, without the clean firm  emerging  technologies  modeled  in  this  study,  achieving  zero  emissions  with  only  commercially available resources will likely require significant “overbuilding” of those resources to maintain reliability and the system cost can be much higher. Furthermore, the cost of converting some of the existing gas resources  to  zero‐emission  fuels  is  potentially  underestimated  due  to  uncertainties  in  conversion

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   111
technologies and limited data at the time of this IRP study. Resource cost and availability uncertainties can  have  large  impacts  to  the  resulting  portfolio  and  system  cost,  and  they  should  continue  to  be monitored by SVP in future IRPs.

Figure 78. Scenario Comparison – 2035 Annual Cost Relative to Base Scenario (2022 $MM)

Note: Annual modeled cost includes the operational cost of existing/planned capacity and the capital cost and operational cost of new build capacity. Capital and fixed costs (incl. PPA cost) of existing/planned capacity are not included. Transmission and distribution costs are not included.

8.5. Sensitivity: Geothermal Limitations and Hydrogen Challenges The  Geothermal  Limitations  and  Hydrogen  Challenges  Sensitivity  (Hydrogen  Sensitivity)  represents  an additional modification to Scenario 3: Zero Emissions with Emerging Technology (Zero Emissions Scenario), designed  to  explore  uncertainty  over  future  hydrogen  prices  and  resource  availability.  Like  the  Zero Emissions Scenario, this sensitivity includes the most stringent clean energy target modeled in this IRP, limiting emission to zero in every hour in 2035.

The  cost  of  hydrogen  retrofits  and  hydrogen  fuel  prices  are  uncertain  in  a  future  scenario  with  deep decarbonization. In this sensitivity, hydrogen costs have been increased relative to the Zero Emissions Scenario to reflect an upper bound to this uncertainty. Hydrogen retrofits costs for SVP’s existing gas fleet have been doubled, and fuel prices have been increased by making more conservative assumptions for electrolyzer technology, process electricity costs, and pipeline capacity factor. See Figure 52 and Appendix C for details on hydrogen price forecast.

Finally, this sensitivity explores scarcity of conventional clean firm resources by limiting SVP’s geothermal resource potential to 50 MW, first available in 2028.

Figure 74 shows the cumulative resource additions through 2035 in the Hydrogen Sensitivity. The figure includes  the  above  existing  resources’  assumed  transitions  to  zero‐emission  fuels.  By  2035,  the  total

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   112
resource additions include 163 MW of CCS, 255 MW hydrogen (all coming from assumed transitions SVP’s existing thermal fleet), 50 MW geothermal, 50 MW biogas (assumed transition of Gianera), 1,262 MW wind, 62 MW offshore wind, 905 MW solar, and 276 MW battery storage. Other emerging technologies, such as nuclear and long‐duration storage, are not selected due to economics. See Figure 80 for the total system capacity, including other existing resources, through 2035.

Figure 79. Hydrogen Sensitivity Cumulative New Build Capacity

Figure 80. Hydrogen Sensitivity Total Capacity

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   113
See Figure 81 for the annual generation by resource type through 2035 in the Hydrogen Sensitivity. In 2035, when the zero‐emission limit is applied, no gas generation is allowed and all generation comes from renewable and carbon‐free resources, and zero‐emission market purchases. The reason that the  zero‐ carbon percentage exceeds 100% in 2035 is because it is calculated based on the accounting framework of SB 100, which is different from total system generation.

Figure 81. Hydrogen Sensitivity Annual Generation

Note: RPS and Zero Carbon percentages are based on retail sales and based on the accounting framework of annual targets in SB 100
Figure 82 shows the system reliability modeling results through 2035 in the Hydrogen Sensitivity. Unlike previous scenarios, the reliability constraint binds in 2033‐34 due to the reduced geothermal resource potential before emerging technologies are available for selection. In 2035, more clean resources are added to the system due to the stringent emission target and surpass the marginal reliability need, meaning the marginal reliability requirement is not the primary driver of resource builds in 2035.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   114
Figure 82. Hydrogen Sensitivity Marginal Reliability Need and Marginal Effective Capacity

8.6. Challenges Ahead to Meet IRP Goals
Through studying Scenario 1: Base SB 100 (Base Scenario) that meets the current state policies, and two additional scenarios with more aggressive clean energy requirements in this IRP, multiple challenges are identified as SVP continues to provide affordable, clean, and reliable power to its growing customer load.  SVP’s  load,  primarily  data  center  load,  is  expected  to  grow  substantially  throughout  the planning horizon. The forecasted annual load in 2035 almost doubles the current system load, and  significant  resource  additions  are  needed  to  meet  this  growing  load.  Also,  unlike  other utilities, SVP’s current and forecasted load is dominated by industrial (datacenter) load, which has a high load factor (or average load divided by peak load) of 80%, meaning that the system demand is relatively constant and there is less ability to shape loads to take advantage of certain resource production, such as low‐cost solar. Therefore, SVP’s future portfolio requires both clean resources and firm resources that can ensure there is enough energy to meet system load in all hours.  SVP  will  need  clean  firm  resources,  such  as  geothermal,  to  meet  future  needs  in  a  deep decarbonized system. SVP faces a common challenge of deeply decarbonized systems, which is the ability to provide power reliably without firm dispatchable (emitting) thermal plants. Clean firm  resources  not  only  provide  clean  energy,  but  also  firm  capacity  to  help  ensure  system reliability.  The  clean,  firm,  and  baseload  characteristics  of  geothermal  align  well  with  SVP’s forecasted load growth and load shape and could provide a key clean firm option.

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   115
 Competition for limited resources in California can add difficulties for SVP to procure some of cost‐effective resources for its system. For example, only a limited amount, about 3,400 MW, of geothermal  may  be  available  to  California.  Furthermore,  the  CPUC  Mid‐Term  Reliability  order requires CPUC‐jurisdictional LSEs to procure approximately 1,000 MW long lead‐time clean firm resources by 2028, and geothermal is one of the best available candidates to meet that order. An assumption of this IRP is that SVP may not be able to procure that 1,000 MW tranche. SVP would then be limited to a maximum of about 350 MW, which is approximately 15% of the remaining potential. The three scenarios in this IRP build to, or slightly below that limit. However, with the recent IRA including additional incentives for geothermal resources, and with all LSEs in California transitioning to a cleaner portfolio, there is a growing need for clean and firm resources, further driving  competition  for  limited  resources,  such  as  geothermal,  and  adding  challenges  (and potentially costs) to cost‐effective resource procurement.  SVP faces uncertainties in project delivery timelines. To keep pace with near‐term load growth to  2030  and  longer‐term  load  growth  and  policy  objectives,  SVP  will  need  to  bring  significant quantities of new resources online over the next several years. As development for new resources in California increases to unprecedented rates, SVP may face challenges including, but not limited to supply chain delays, labor shortage, as well as permitting and lengthy interconnection queue processes.  To  build  and  begin  utilizing  new  resources,  the  cost  and  schedule  uncertainty  of  a complex, multi‐step, multi‐year interconnection process can significantly complicate other parts of the development process, including financing and project costs.  There  are  uncertainties  in  long‐term  resource  cost  forecasts.  This  IRP  uses  the  long‐term resource cost forecast from the industry standard public data source, the NREL Annual Technology Baseline (ATB). However, recent market trends have shown that international trade policies and supply  chain  issues  can  significantly  impact  resource  costs  during  procurement.  Furthermore, market  competition  and  developer  profit  markup  are  difficult  to  forecast  and  model  but  do influence resource costs. While many cost uncertainties are not explicitly studied in this IRP, they can  impact  the  resulting  portfolio  choices  and  system  costs.  SVP  should  continue  to  monitor resource costs in future IRPs and resource procurement activities.  Achieving  zero  emission  in  every  hour  will  likely  require  a  combination  of  commercially available resources and new emerging technologies to be cost‐effective and affordable. To meet the  hourly  zero‐emission  target,  all  generation  needs  come  from  renewable,  carbon‐free resources,  and/or  market  purchases  (also  when  market  emissions  are  zero)  in  every  hour.  If emerging technologies and emerging zero‐emission fuels are not available, SVP would need to add much higher amounts of existing commercially available technologies, such as solar, wind, and battery storage resources. The total nameplate capacity of those resources is likely higher than  the  system  load  and  the  three  scenarios  presented  here.  Because  they  have  low  and Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   116
marginally decreasing reliability value, more capacity is needed to cover the most critical hours, even though there might be high curtailment occurring in other normal and/or low load hours.

The  emerging  technologies,  such  as  building  new  hydrogen  plants  and  converting  existing  gas plants to burn on hydrogen or biogas, modeled in this IRP offer both clean and “firm capacity” attributes, and reduces the potential for “overbuilding” existing mature technologies.  There  are  large  uncertainties  and  risks  in  emerging  technologies.  The  emerging  technologies modeled in this IRP are developed based on various assumptions and limited data. Many of the emerging technologies are still in their research and development and/or piloting phases, and it is  difficult  to  predict  when  they  will  be  commercially  available  at  scale.  Additionally,  some emerging technologies, such as green hydrogen, require significant infrastructure development, such  as  electrolyzers,  renewables  for  electrolyzers,  pipelines,  and  storage.  The  costs  and infrastructure  required  to  support  emerging  technologies  are  uncertain  and  can  impact  the resulting  portfolio  feasibility  and  cost.  The  development  of  emerging  technologies  should continue to be monitored and studied by SVP in future IRPs and resource procurement.  SVP’s transmission capabilities with CAISO can have an impact on how much emission reduction SVP can achieve. DVR and Gianera are the only two resources, both natural gas plants, located within SVP’s local zone. When trying to meet more aggressive clean energy goals and reduce gas generation,  the  local  resources’  roles  and  SVP’s  transmission  capabilities  with  CAISO  become important. If the local resources cannot be dispatched to meet SVP’s load, all system load must be met with energy delivered via the transmission line from CAISO. However, the existing and planned transmission capacity may not always be sufficient to cover SVP’s forecasted peak load.

In this IRP, it is assumed that local resources would be able to run on emerging zero‐emission fuel and can be dispatched in Scenario 3: Zero Emissions with Emerging Technology, but SVP should continue to study system transmission capabilities and the clean transition of local resources in future IRPs.

8.7. Potential Impacts on Retail Rates
SVP is obligated to serve its customers at just and reasonable rates and to minimize impacts to ratepayers.

Notably for SVP, lower rates have been an economic driver for robust development within Santa Clara, and continuing this long‐standing focus on providing affordable and reliable services to customers is a goal of this IRP. This section explores the potential impact that the three scenarios explored in this work may have on retail rates through the planning horizon.

Figure 83 shows the estimated retail rate impacts of the scenarios from 2024 to 2035. Rates are calculated as the annual cost and annual retail demand ($/kWh). These estimates are based on two components 1) non‐modeled costs, which are SVP baseline system rates, and 2) the incremental modeled scenario costs and TAC costs. The SVP baseline system rates are assumed to escalate at 3% real (5% nominal) per year, Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   117
which SVP characterizes as the baseline revenue requirements for the system. The incremental scenario costs shown represent the additional cost to implement each scenario in order of least to most stringent clean energy requirements. Of note here is the impact of the significant impact of TAC, a charge from CAISO for energy delivered into SVP service area, on the final rates, which is a charge that is not overseen by SVP.

Scenario 1: Base SB 100 (Base Scenario) rates reach approximately $0.16/kWh in 2030 and approximately $0.185/kWh  by  2035.  Additional  rate  impacts  from  Scenario  2:  Accelerated  SB  100  begin  later  in  the horizon, with an incremental cost of approximately $0.002/kWh by 2035 (or an estimated $0.187/kWh).

Finally,  Scenario  3:  Zero  Emissions  with  Emerging  Technology  (Zero  Emissions  Scenario)  results  in  an incremental  cost  to  the  Base  Scenario  of  approximately  $0.005/kWh  by  2035  reaching  approximately $0.19/kWh by 2035.

Although the cost impacts are less apparent when spread across the annual load here, the 2035 annual costs  of  these  scenarios  relative  to  Base  Scenario  are  2022  $25  million  and  2022  $55  million,  in  the Accelerated SB 100 and Zero Emissions Scenarios, respectively (see Figure 78).

Figure 83. Estimated Retail Rates Impacts

The  uncertainties  related  to  emerging  technology  availability  and  costs,  as  discussed  in  the  previous section, of course, carry through  to these estimated rate impacts. The relatively slight rate impacts of reaching the Zero Emissions Scenario ride on the assumptions that existing SVP resources can be retrofit to clean energy fuels at minimal to no capital costs by 2035 with low‐cost (PTC‐ eligible) hydrogen fuel availability. The sensitivity case that tested potential geothermal availability limitations and high hydrogen costs results in an incremental cost to the Base Scenario of approximately $0.012/kWh by 2035 reaching approximately $0.197/kWh by 2035.

8.8. Consideration of Localized Air Pollutants and Disadvantaged Communities Santa Clara’s defined Disadvantaged Community is comprised of Industrial and Commercial customers with few residential and even fewer income‐qualified FRAP (Federal Rate Assistance Program customers) residential customers residing within the borders as shown in Figure 84. SVP’s disadvantaged community

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   118
(DAC) borders Highway 101 and the San Jose Airport and is comprised of 24/7 manufacturing, SVP’s DVR power plant, data centers, high tech companies and small industrial customers. Santa Clara has zoned this area  of  the  city  for  heavy  industrial  and  commercial  and  has  kept  housing  at  a  minimum  with  few exceptions.

Santa Clara is only 18.4 square miles and land is at a premium, and in most cases, utilized to maximum densities. In working with the City of Santa Clara as it updates its General Plan, there is an opportunity for SVP  to  encourage  maximum  infill  building  potential  with  whole  building  electrification  and  maximize potential of DERs. There is no land available to build large‐scale PV projects (greater than 10 MW) within the city limits, but there is ample opportunity throughout California, keeping with SVP’s position of having a  diversified  portfolio  (both  geographically  and  resource  type).  Adding  renewable  generation  to  SVP’s portfolio is beneficial to the disadvantaged community as well as to SVP’s service area.

SVP offers multiple customer programs and rebates to income‐qualified customers, as outlined below.

Specifically  for  energy  efficiency,  one  of  the  many  goals  of  the  programs  is  to  assist  income‐qualified residents in paying their electric bills and installing energy efficient appliances to lower energy costs. The following  programs  are  offered  by  SVP  to  specifically  support  income‐qualified  and  disadvantaged communities:
 Financial Rate Assistance Program (FRAP)
 Multifamily Residential and Commercial EV Charging Station Incentive Program (Equity+ Funding Lane)
 Free EV Charging Technical Assistance for Multifamily Housing & Small Businesses  E‐Bike Rebate (Increased incentives for FRAP customers)  Heat Pump Water Heater Rebate (Increased incentives for FRAP and LIHEAP customers)  Income‐Qualified Pre‐Owned Electric Vehicle Rebate
 Income‐Qualified Solar Grant
 Smart Electric Panel (Increased incentives for FRAP and LIHEAP customers)  Battery Storage Systems Rebate (Increased incentives for FRAP and LIHEAP customers)  Medical Rate Assistance Program
 Trade School Scholarships for income‐qualified customers  Increased  rebates  on  electric  yard  care  equipment  and  room  air  cleaners  for  income‐qualified customers through the online SVP Marketplace

Results and Discussion2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   119
Figure 84. Disadvantaged Communities within SVP’s Service Territory

Conclusions2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   120

9. Conclusions
SVP’s 2023 IRP identified three least‐cost optimal resource portfolios, all of which meet or exceed SVP's clean energy, emissions reductions, and reliability requirements. In all portfolios, the power supply mix continues  SVP’s  transition  away  from  carbon‐based  generation  with  significant,  new  clean  energy resource additions to meet increasing state policy goals and SVP’s growing load. The portfolios studied represent increasingly progressive clean energy goals. Scenario 1: Base SB 100 (Base Scenario) meets the SB 100 target of 60% renewable energy in 2030 and 90% renewable and zero‐carbon energy by 2035, relying  only  on  mature  clean  energy  technologies.  Scenario  2:  Accelerated  SB  100  explores  additional procurement  required  to  meet  an  acceleration  of  the  long‐term  SB  100  targets  for  100%  carbon  free electricity from 2045 to 2035 and relies only on mature renewable technology options. Finally, Scenario 3: Zero Emissions with Emerging Technology (Zero Emissions Scenario) limits carbon emissions in all hours of the year, beginning in 2035, and explores the use of emerging clean energy technologies.

All the resulting portfolios represent diverse resource mixes of clean firm capacity, scalable clean energy, and balancing resources. Portfolio capacity additions include a mix of solar, in‐state and out‐of‐state wind, energy storage, and geothermal capacity. The added firm geothermal and balancing storage resources, in addition to SVP’s existing firm capacity, complement the intermittent nature of the high level of variable wind and solar resources added, ensuring SVP has sufficient capacity to meet its share of CAISO reliability needs. In the near term, through 2030, all resource portfolios present a common trend of at least 400 MW wind, 150 MW solar, 100 MW battery energy storage and 120 MW geothermal resource additions to meet increasing load as well as reliability and clean energy targets. This presents a robust, fairly low‐regrets near‐term planning pathway for the level of SVP clean energy resource additions.

The  scenarios  begin  to  diverge  after  2030  as  potential  clean  energy  and  emissions  requirements  and emerging  technologies  are  assumed  to  become  increasingly  available.  By  2035  the  Zero  Emissions Scenario diverges with the assumed availability of hydrogen and biofuel clean‐firm resources, enabling SVP to retrofit existing fossil‐fuel resources and add additional hydrogen combustion capacity.

Sensitivities on the availability of geothermal (clean firm) and hydrogen costs (retrofit capital costs and hydrogen  fuel  prices)  show  the  increased  costs  that  could  occur  due  to  competition  over  limited geothermal potential and a less optimistic view of hydrogen as an electricity generation fuel. Uncertainty for these “clean firm” resources needed to help SVP and the state achieve a zero‐emissions grid can be addressed by further study in SVP’s subsequent IRPs, when the California electricity market will have more clarity on the viability and cost parameters of new emerging technologies. However, with large near‐term forecasted load growth, this IRP provides SVP with a clear pathway for near‐term procurement to meet its needs over the next 5‐10 years.

It  is  noted  that  while  this  IRP  provides  an  outline  for  future  resource  additions,  SVP’s  actual  future resource additions will be determined by results of competitive solicitations for resources and these may differ based on changes in forecasted loads, economic conditions, technology advances, specific bid‐based generation resource prices, and evolving environmental and regulatory standards.

SVP Community Survey Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   121
Appendix A. SVP Community Survey Summary

SVP Community Survey Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   122

SVP Community Survey Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   123

SVP Community Survey Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   124

SVP Community Survey Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   125

SVP Community Survey Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   126

SVP Community Survey Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   127

SVP Community Survey Summary2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   128

Energy Demand2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   129
Appendix B. Energy Demand
A.1.  Energy Use and Demand
E3 leveraged a range of sources to develop a Reference Scenario and two sensitivities of annual peak load and hourly energy demand forecasts for SVP:
 Reference:  a  business‐as‐usual  forecast  of  energy  demand  in  SVP  territory  using  the  utility’s baseline  forecast  of  energy  demand  with  additional  energy  efficiency  and  electrification projections from the Planning Forecast of the CEC 2022 IEPR52  High  Electrification:  utilizes  the  same  baseline  forecast  of  energy  demand  as  the  Reference scenario,  but  layers  in  less  aggressive  energy  efficiency  assumptions  and  more  aggressive electrification assumptions from the 2022 IEPR
 IEPR  Local  Reliability:  utilizes  the  same  baseline  forecast  of  energy  demand  as  the  Reference scenario,  but  uses  energy  efficiency  and  electrification  projections  from  the  Local  Reliability Forecast of the 2022 IEPR
Figure 85. Total Annual Electricity Demand by Scenario (GWh) Scenario  2023  2024  2025  2026  2027  2028  2029  2030  2031  2032  2033  2034  2035 Reference  4,529  4,933  5,494  5,995  6,449  7,044  7,503  7,971  8,448  8,955  9,218  9,394  9,567 High Elec.  4,546  4,965  5,548  6,072  6,553  7,175  7,668  8,171  8,684  9,228  9,529  9,742  9,950 IEPR Local
Reliability  4,773  5,171  5,794  6,381  6,938  7,489  7,919  8,381  8,883  9,415  9,838  10,040  10,248 E3 used two sources for energy efficiency assumptions: the 10 Year Energy Goals provided by SVP and AAEE modeled by CEC for the 2022 IEPR.53 Different levels of AAEE were used for each:
 The Reference scenario used the “Scenario 3 (Mid)” AAEE assumptions from the 2022 IEPR for Residential and Commercial sector energy efficiency, aligning with the assumptions used in the 2022 IEPR Planning Forecast
 The High Electrification scenario used the “Scenario 1 (Very Low)” AAEE assumptions, the most conservative scenario for energy efficiency included in the 2022 IEPR  The IEPR Local Reliability scenario used the “Scenario 2 (Low)” AAEE assumptions, aligning with the assumptions used in the 2022 IEPR Local Reliability forecast

52 CEC, “CEC 2022 Integrated Energy Policy Report (IEPR).” 53 CEC, “2022 IEPR AAEE‐AAFS Annual Impacts.”
Energy Demand2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   130
Figure 86 shows the combined impact of energy efficiency measures on annual electricity demand in each scenario.

Figure 86. Annual Energy Efficiency Impact on Electricity Demand by Scenario (GWh) Scenario  2023  2024  2025  2026  2027  2028  2029  2030  2031  2032  2033  2034  2035 Reference ‐ 62 ‐ 97 ‐ 136 ‐ 171 ‐ 204 ‐ 226 ‐ 248 ‐ 271 ‐ 294 ‐ 313 ‐ 333 ‐ 350 ‐ 365 High Elec.  ‐45  ‐65  ‐83  ‐98  ‐110  ‐113  ‐116  ‐121  ‐126  ‐128  ‐132  ‐135  ‐138 IEPR Local
Reliability  ‐52 ‐ 79 ‐ 104 ‐ 126 ‐ 146 ‐ 156 ‐ 166 ‐ 178 ‐ 189 ‐ 199 ‐ 209 ‐ 217 ‐ 224 Additional  electricity  demand  modifiers  for  building  electrification  are  layered  into  the  baseline.  For buildings, the electrification assumptions are based on the AAFS modeled by CEC for the 2022 IEPR in all scenarios. For the High Electrification and IEPR Local Reliability scenarios, E3 also included electrification assumptions based on the 2022 Electric Infrastructure Impacts from Proposed Zero NOx Standards report, where E3 analyzed the electricity demand implications of a zero NOx standard for space and water heaters for the Bay Area Air Quality Management District.54
 The  Reference  scenario  used  the  “Scenario  3  (Mid)”  AAFS  assumptions,  aligning  with  the assumptions used in the 2022 IEPR Planning Forecast
 The High Electrification scenario also used the “Scenario 3 (Mid)” AAFS assumptions and layered in additional electrification of space and water heating based on a zero NOx standard beginning in 2027 for residential water heating and 2029 for residential space heating, commercial water heating, and commercial space heating
 The IEPR Local Reliability scenario used the “Scenario 4 (High)” AAFS assumptions and layered in the same additional electrification of space and water heating from a zero NOx standard as the High Electrification scenario
Figure 87 shows the combined impact of building electrification measures on annual electricity demand in each scenario.

Figure 87. Annual Building Electrification Impact on Electricity Demand by Scenario (GWh) Scenario  2023  2024  2025  2026  2027  2028  2029  2030  2031  2032  2033  2034  2035 Reference  13  21  29  36  43  51  59  67  74  81  88  94  99 High Elec.  13  21  29  36  47  57  73  89  105  121  136  151  165 IEPR Local
Reliability  14  22  31  39  50  61  78  95  111  128  144  159  173 For transportation electrification, the Reference scenario reflects the Base level of electrification from the 2022  IEPR,  while  the  High  Electrification  and  Local  Reliability  scenario  both  use  the  Additional  Annual Transportation Electrification (AATE) assumptions modeled in the 2022 IEPR Planning Forecast. While the

54 E3, “Bay Area Air Quality Management District” (San Francisco, CA: Energy + Environmental Economics (E3), 2022), https://www.baaqmd.gov/~/media/dotgov/files/rules/reg‐9‐rule‐4‐nitrogen‐oxides‐from‐fan‐type‐residential‐central‐ furnaces/2021‐amendments/documents/20221220_sr_appd_rg09040906‐pdf.pdf?la=en.

Energy Demand2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   131
AAEE  and  AAFS  assumptions  for  energy  efficiency  and  building  electrification  for  the  2022  IEPR  are provided at the SVP territory level, the Base and AATE assumptions are provided at the PG&E planning area level.55 E3 downscaled the transportation loads to SVP territory through a two‐step process. First, loads were scaled to Santa Clara County based on the county’s share of light duty vehicle and medium‐ and‐heavy  duty  vehicles  registrations  for  all  counties  in  PG&E  service  territory  using  California  DMV vehicle registration data.56 Next, transportation loads were scaled from Santa Clara County to SVP service territory using the City of Santa Clara’s share of total vehicle miles travelled for Santa Clara County as reported in the city and county’s respective GHG inventories.5758 Figure  88  shows  the  combined  impact  of  transportation  electrification  measures  on  annual  electricity demand in each scenario.

Figure 88. Annual Transportation Electrification Impact on Demand by Scenario (GWh) Scenario  2023  2024  2025  2026  2027  2028  2029  2030  2031  2032  2033  2034  2035 Reference  8  15  24  32  40  49  59  69  81  94  107  120  135 High Elec.  8  15  25  35  47  62  78  97  119  142  168  196  225 IEPR Local
Reliability  8  15  25  35  47  62  78  97  119  142  168  196  225 Finally, the IEPR Local Reliability included a demand modifier to align total annual electricity demands between  the  E3  bottom‐up  constructed  demand  scenario  with  the  published  Local  Reliability  forecast from the 2022 IEPR.

The total annual electricity demand for each scenario is shown in Figure 89.

55 CEC, “2022 IEPR AAEE‐AAFS Annual Impacts”; CEC, “CED 2022 Hourly Forecast ‐ PGE ‐ Planning Scenario.” 56 CA DMV, “VEHICLES REGISTERED BY COUNTY,” California Department of Motor Vehicles, 2023, https://www.dmv.ca.gov/portal/dmv‐research‐reports/research‐development‐data‐dashboards/vehicles‐registered‐by‐ county/.
57 Country of Santa Clara, “2017 Community Wide Greenhouse Gas Inventory and Forecast” (Santa Clara, CA: County of Santa Clara, 2021),
https://sustainability.sccgov.org/sites/g/files/exjcpb976/files/documents/SCC%20GHG%20Inventory%20and%20Forecast%2 0Report_6‐29‐21_0.pdf.
58 City of Santa Clara, “Climate Action Plan: 2018 Annual Report” (Santa Clara, CA: City of Santa Clara, 2018), https://www.santaclaraca.gov/home/showpublisheddocument/62433/636809212556470000.

Energy Demand2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   132
Figure 89. Total Annual Electricity Demand by Scenario

Hourly Energy Demand Forecast
To enable capacity expansion modeling for the integrated planning process an hourly demand forecast was developed from this annual forecast. A separate hourly load profile was assigned to the annual baseline energy demand, energy efficiency and electrification load modifiers, and the IEPR Local Reliability alignment energy demands to get a complete hourly energy demand forecast for all scenarios.

Figure 90 details the sources used for converting the energy demand components to hourly demand profiles.

Figure 90. Hourly Demand Profile Components
Energy Demand Component  Source for Hourly Demand Profile Baseline Energy Demand  SVP Hourly Energy Demand Forecast 2023‐2035 Energy Efficiency  2022 IEPR Hourly Forecast – PG&E Planning Scenario Building Electrification from 2022 IEPR  2022 IEPR Hourly Forecast – PG&E Planning Scenario Building Electrification from Zero NOx Standard  2022 Electric Infrastructure Impacts from Proposed Zero NOx Standards report
Transportation Electrification  2022 IEPR Hourly Forecast – PG&E Planning Scenario IEPR Alignment (Local Reliability Scenario Only)  SVP Hourly Energy Demand Forecast 2023‐2035

Hydrogen Price Forecasts2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   133
Appendix C. Hydrogen Price Forecasts
E3 developed an assessment of the  cost trajectory  of hydrogen  that can be  delivered to  SVP’s service territory.

The hydrogen assessment in this analysis stems from E3’s and the University of California (UC) Irvine's work on the CEC’s The Challenge of Retail Gas in California’s Low Carbon Future Report. A set of cost and efficiency assumptions for the production of hydrogen using electrolysis was developed. The assumptions consist of inputs indexed by fuel, electrolysis technology, year, and level of industry learning assumed to occur between 2020 and 2050. Inputs consist of the levelized capital cost and annual fixed O&M cost, variable O&M cost, and  overall energy efficiency,  considering only renewable electricity  as the energy input, including for heat input, if applicable.

Base Assumptions
E3 assumes alkaline electrolysis cell (AEC) as the primary means of producing green hydrogen59 due to its low cost and technologically mature attributes. 60  E3 developed two cost trajectories for AEC based on cumulative national installed capacity, as shown in Figure 91. 61 The Conservative cost trajectory is used in this study.

Figure 91. Electrolyzer Costs for Producing Hydrogen and SNG

(Derived from E3’s work for the California Energy Commission (CEC, The Challenge of Retail Gas in California’s Low‐ Carbon Future) in partnership with UC Irvine. The secondary y‐axis shows the potential electrolyzer market size.)

E3  assumed  new  off‐grid  solar  resources  from  Southern  California  to  power  electrolyzers  to  produce hydrogen. Hydrogen is assumed to be stored underground in lined rock caverns and piped to SVP’s service

59 Hydrogen produced by breaking water into hydrogen and oxygen using an electric current in which electricity is renewable. 60 As opposed to producing clean hydrogen through a proton‐exchange membrane (PEM) or steam methane reforming or coal gasification with CCS.
61 Cost trajectories were developed in partnership with UC Irvine in 2019. https://www.ethree.com/at‐cec‐e3‐highlights‐need‐for‐gas‐ transition‐strategy‐in‐california/.

Hydrogen Price Forecasts2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   134
territory. New pipelines are assumed to be 400 miles long and are fully utilized by hydrogen producers and consumers beyond those modeled in this study. This assumption thereby spreads the cost of pipeline transportation more evenly across hydrogen produced by facilities modeled in this study. Hydrogen costs assumed in this study are delivered hydrogen costs and include production costs, new lined rock cavern underground storage, and new dedicated hydrogen pipelines.

All hydrogen plants that being operation between 2025 and 2035 are assumed to receive the full $3/kg 45V tax credit. The 45V tax credit is applied to all hydrogen production in the first 10 years of plants’ lives, but it’s impact is levelized across the entire 25‐year lifetimes of all plants. As a result, hydrogen costs from E3’s electrofuel spreadsheet should be treated as a PPA‐like cost, rather than the instantaneous cost of hydrogen each year.

Geothermal Limitations and Hydrogen Challenges Sensitivity Assumptions Compared  to  base  assumptions,  the  sensitivity  case  studies  a  future  with  higher  hydrogen  costs.  The electrolyzer technology is assumed to be proton exchange membrane electrolysis cell (PEMEC) instead of AEC.  The  electricity  source  for  hydrogen  production  is  assumed  to  be  SoCal  wind  and  the  hydrogen pipelines are only half utilized.

See Figure 92 for the resulting hydrogen price forecast through 2035.

Figure 92. Hydrogen Price Forecast

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   135
Appendix D. Standardized Tables
Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   136

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   137

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   138

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   139

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   140

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   141

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   142

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   143

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   144

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   145

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   146

Standardized Tables2023 Integrated Resource Plan2023 Integrated Resource Plan 2023 Integrated Resource Plan   147

← All documents from this meeting