City of Santa Clara
Attachment No. 2
Bid Summary
25-1162
REPORT TO COUNCIL
SUBJECT
Action on Award of Contract for the Pruneridge Avenue Signal Timing Project to Tennyson Electric, LLC.
BID SUMMARY
Bid Opening Date: March 20, 2025
ENGINEER’S ESTIMATE:
$ 554,329
Contractor
Total Bid ($)
Percentage above/below
Engineer’s Estimate
Tennyson Electric
$489,280
(12%)
Bear Electric Solutions
$544,280
(2%)
St. Francis Electric
$562,700
2%