Juliette Substation Expansion Project 2025 Form CONTRACT 2462 Page 1
1. Award
of Contract. Contractor has submitted a Proposal to perform the Work to construct the Project. On _____________, 20___, City authorized award of this Contract to Contractor for the amount set forth in Section 4, below.
2. Con
tract Documents. The Contract Documents incorporated into this Contract include and are comprised of all of the documents listed below. The definitions provided in Article 1 of the General Conditions apply to all of the Contract Documents, including this Contract.
2.1 Addenda,
if any;
2.2 Proposal and attachments thereto;
2.3 Contract;
2.4 Payment and Performance Bonds;
2.5 General Conditions;
2.6 General Requirements;
2.7 Special Conditions;
2.8 Project Plans and Specifications;
2.9 Change Orders, if any;
2.10 Notice of Award;
2.11 Notice to Proceed; and
2.12 City’s Standard Details, as applicable
3. Con
tractor’s Obligations. Contractor shall perform all of the Work required for the Project, as specified in the Contract Documents. Contractor must provide, furnish, and supply all things necessary and incidental for the timely performance and completion of the Work, including all necessary labor, materials, supplies, tools, equipment, transportation, services, onsite facilities, and utilities, unless otherwise specified in the Contract Documents. Contractor must use its best efforts to diligently prosecute and complete the Work in a professional and expeditious manner and to meet or exceed the performance standards required by the Contract Documents.
4. Paymen
t. As full and complete compensation for Contractor’s timely performance and completion of the Work in strict accordance with the terms and conditions of the Contract Documents, City will pay Contractor $___________________ (“Contract Price”) for all of Contractor’s direct and indirect costs to perform the Work, including all labor, materials, supplies, equipment, taxes, insurance, bonds and all overhead costs, in accordance with the payment provisions in the General Conditions.
5. Time
for Completion. Contractor shall fully complete the Work for the Project, meeting all requirements for Final Completion within 304 Working Days from the start date set forth in the Notice to Proceed (“Contract Time”). By signing below, Contractor expressly waives any claim for delayed early completion.
6. Li
quidated Damages. As further specified in Section 5.4 of the General Conditions, if Contractor fails to complete the Work within the Contract Time, City will assess liquidated damages in the amount of $2,800 per day for each day of unexcused delay in achieving Attachment 1
Note: This Attachment 1 does not include the technical specifications and drawings due to their length. All technical specifications, drawings, and related requirements are included in the bid documents issued by the City.
Contract
This public works contract (“Contract”) is entered into by and between City of Santa Clara (“City”) and _______________________________________ (“Contractor”), for work on the Juliette Substation Expansion Project (“Project”).
The parties agree as follows:
Juliette Substation Expansion Project 2025 Form CONTRACT 2462 Page 2
Final Completion, and such liquidated damages may be deducted from City’s payments due or to become due to Contractor under this Contract.
7. La
bor Code Compliance.
7. 1 General. This Contract is subject to all applicable requirements of Chapter 1 of Part 7 of Division 2 of the Labor Code, including requirements pertaining to wages, working hours and workers’ compensation insurance, as further specified in Article 9 of the General Conditions.
7. 2 Prevailing Wages. This Project is subject to the prevailing wage requirements applicable to the locality in which the Work is to be performed for each craft, classification or type of worker needed to perform the Work, including employer payments for health and welfare, pension, vacation, apprenticeship and similar purposes. Copies of these prevailing rates are available online at http://www.dir.ca.gov/DLSR.
7.3 DIR Registration. City may not enter into the Contract with a Contractor without proof that the bidder and its Subcontractors are registered with the DIR to perform public work pursuant to Labor Code § 1725.5, subject to limited legal exceptions.
8. W
orkers’ Compensation Certification. Pursuant to Labor Code § 1861, by signing this Contract, Contractor certifies as follows: “I am aware of the provisions of Labor Code § 3700 which require every employer to be insured against liability for workers’ compensat ion
or
to undertake self-insurance in accordance with the provisions of that code, and I will c
omply with such provisions before commencing the performance of the Work on this Contract.”
9. Co
nflicts of Interest. Contractor, its employees, Subcontractors, and agents may not have, maintain, or acquire a conflict of interest in relation to this Contract in violation of any City ordinance or requirement, or in violation of any California law, including Government Code § 1090 et seq., or the Political Reform Act, as set forth in Government Code § 81000 et
seq. and its accompanying regulations. Any violation of this Section constitutes a material breach of the Contract.
10. In
dependent Contractor. Contractor is an independent contractor under this Contract and wi
ll have control of the Work and the means and methods by which it is performed. Contractor and its Subcontractors are not employees of City and are not entitled to participate in any health, retirement, or any other employee benefits from City.
11 . Notice. Any notice required by or pursuant to the Contract Documents must be made in wr
iting, signed, dated, and sent to the other party by personal delivery, U.S. Mail, a reliable ov
ernight delivery service, or by email as a PDF file. Notice is deemed effective upon deliv
ery, except that service by U.S. Mail is deemed effective on the second working day after deposit for delivery. Notice for each party must be given as follows:
Ci
ty:
881 M
artin Ave.
Santa Clara, CA 9505
Attn: Joseph Bruzzone
J
[email protected]
Copy
to: [email protected]
Juliette Substation Expansion Project 2025 Form CONTRACT 2462 Page 3
Contractor:
Nam
e:_____________________________________
Address:___________________________________
City/State/Zip:_______________________________
Phone:_____________________________________
Attn:_______________________________________
Email:______________________________________
Copy to:____________________________________
12. Ge
neral Provisions.
12.1 Assi
gnment and Successors. Contractor may not assign its rights or obligations under this Contract, in part or in whole, without City’s written consent. This Contract is binding on Contractor’s and City’s lawful heirs, successors and permitted assigns.
12.2 T
hird Party Beneficiaries. There are no intended third party beneficiaries to this Contract.
12.3 G
overning Law and Venue. This Contract will be governed by California law and venue will be in the Santa Clara County Superior Court, and no other place.
Contractor waives any right it may have pursuant to Code of Civil Procedure § 394, to file a motion to transfer any action arising from or relating to this Contract to a venue outside of Santa Clara County, California.
12.4 Amen
dment. No amendment or modification of this Contract will be binding unless it is in a writing duly authorized and signed by the parties to this Contract.
12.5 Int
egration. This Contract and the Contract Documents incorporated herein, including authorized amendments or Change Orders thereto, constitute the final, complete, and exclusive terms of the agreement between City and Contractor.
12. 6 Severability. If any provision of the Contract Documents is determined to be illegal, invalid, or unenforceable, in whole or in part, the remaining provisions of the Contract Documents will remain in full force and effect.
12. 7 Iran Contracting Act. If the Contract Price exceeds $1,000,000, Contractor certifies, by signing below, that it is not identified on a list created under the Iran Contracting Act, Public Contract Code § 2200 et seq. (the “Act”), as a person engaging in investment activities in Iran, as defined in the Act, or is otherwise expressly exempt under the Act.
12.8 A
uthorization. Each individual signing below warrants that he or she is authorized to do so by the party that he or she represents, and that this Contract is legally binding on that party. If Contractor is a corporation, signatures from two officers of the corporation are required pursuant to California Corporations Code § 313.
T
he parties agree to this Contract as witnessed by the signatures below:
C
ITY: Approved as to form:
s
/_______________________________ s/__________________________________ ________
________________________ ___________________________________ Juliette Substation Expansion Project 2025 Form CONTRACT 2462 Page 4
Name, Title Name, Title
Dat
e: ___________________________ Date: ______________________________ At
test:
s
/_______________________________
________
_________________________
Name, Title
Dat
e: ___________________________
CO
NTRACTOR: ___________________________________________________ Business Name
s
/_______________________________ Seal:
________
_________________________
Name, Title
Dat
e: ____________________________
S
econd Signature (See Section 12.8):
s
/_______________________________
________
_________________________
Name, Title
Dat
e: ____________________________
________
___________________________________________
Contractor’s California License Number(s) and Expiration Date(s) Juliette Substation Expansion Project 2025 Form PAYMENT BOND 2462 Page 5
Payment Bond
Cit
y of Santa Clara (“City”) and ________________________ (“Contractor”) have entered into a contract for work on the Juliett Substation Expansion Project (“Project”). The Contract is incorporated by reference into this Payment Bond (“Bond”).
1. G
eneral. Under this Bond, Contractor as principal and ____________________________, its surety (“Surety”), are bound to City as obligee in an amount not less than $_______
__________, under California Civil Code § 9550 et seq., to ensure payment to authorized claimants. This Bond is binding on the respective successors, assigns, owners, heirs, or executors of Surety and Contractor.
2. S
urety’s Obligation. If Contractor or any of its Subcontractors fails to pay a person aut
horized in California Civil Code § 9100 to assert a claim against a payment bond, any amounts due under the Unemployment Insurance Code with respect to work or labor performed under the Contract, or any amounts required to be deducted, withheld, and paid ov
er to the Employment Development Department from the wages of employees of Contractor and its Subcontractors under California Unemployment Insurance Code § 13020 wit
h respect to the work and labor, then Surety will pay the obligation.
3. Ben
eficiaries. This Bond inures to the benefit of any of the persons named in California Civ
il Code § 9100, so as to give a right of action to those persons or their assigns in any suit brought upon this Bond. Contractor must promptly provide a copy of this Bond upon r
equest by any person with legal rights under this Bond.
4. Du
ration. If Contractor promptly makes payment of all sums for all labor, materials, and equipm
ent furnished for use in the performance of the Work required by the Contract, in c
onformance with the time requirements set forth in the Contract and as required by California law, Surety’s obligations under this Bond will be null and void. Otherwise, Surety’s obligations will remain in full force and effect.
5. W
aivers. Surety waives any requirement to be notified of alterations to the Contract or extensions of time for performance of the Work under the Contract. Surety waives the pr
ovisions of Civil Code §§ 2819 and 2845. City waives the requirement of a new bond for any supplemental contract under Civil Code § 9550. Any notice to Surety may be given in t
he manner specified in the Contract and sent to Surety as follows:
A
ttn: _____________________________________________________ Address: __________________________________________________ City/State/Zip: ______________________________________________ Phone: ___________________________________________________ Email: ____________________________________________________
6. La
w and Venue. This Bond will be governed by California law, and venue for any dispute pur
suant to this Bond will be in the Santa Clara County Superior Court, and no other place.
Surety will be responsible for City’s attorneys’ fees and costs in any action to enforce the pr
ovisions of this Bond.
[
Signatures are on the following page.]
Juliette Substation Expansion Project 2025 Form PAYMENT BOND 2462 Page 6
7. E
ffective Date; Execution. This Bond is entered into and is effective on __________, 20__.
SU
RETY:
________
___________________________
Business Name
s
/__________________________________ ______________________________ Date
___________________________________
Name, Title
(
Attach Acknowledgment with Notary Seal and Power of Attorney) CO
NTRACTOR:
________
___________________________
Business Name
s
/__________________________________ ______________________________ Date
___________________________________
Name, Title
A
PPROVED AS TO FORM:
s
/ __________________________________ ______________________________ Date
____________________________________
Name, Title
E
ND OF PAYMENT BOND
Juliette Substation Expansion Project 2024 Form PERFORMANCE BOND 2462 Page 7
Performance Bond
Cit
y of Santa Clara (“City”) and __________________________ (“Contractor”) have entered into a contract for work on the Juliette Substation Expansion Project (“Project”). The Contract is incorporated by reference into this Performance Bond (“Bond”).
1. G
eneral. Under this Bond, Contractor as principal and ___________________________, it
s surety (“Surety”), are bound to City as obligee for an amount not less than $_______
___________ to ensure Contractor’s faithful performance of its obligations under the Contract. This Bond is binding on the respective successors, assigns, owners, heirs, or executors of Surety and Contractor.
2. S
urety’s Obligations. Surety’s obligations are co-extensive with Contractor’s obligations under the Contract. If Contractor fully performs its obligations under the Contract, including it
s warranty obligations under the Contract, Surety’s obligations under this Bond will bec
ome null and void. Otherwise, Surety’s obligations will remain in full force and effect.
3. W
aiver. Surety waives any requirement to be notified of and further consents to any alterations to the Contract made under the applicable provisions of the Contract Documents, including changes to the scope of Work or extensions of time for performance of
Work under the Contract. Surety waives the provisions of Civil Code §§ 2819 and 2845.
4. Ap
plication of Contract Balance. Upon making a demand on this Bond for completion of the Work prior to acceptance of the Project, City will make the Contract Balance available to S
urety for completion of the Work under the Contract. For purposes of this provision, the Cont
ract Balance is defined as the total amount payable by City to Contractor as the Cont
ract Price minus amounts already paid to Contractor, and minus any liquidated dam
ages, credits, or backcharges to which City is entitled under the terms of the Contract.
5. Co
ntractor Default. Upon written notification from City of Contractor’s termination for default under Article 13 of the Contract General Conditions, time being of the essence, Surety must act within the time specified in Article 13 to remedy the default through one of the following courses of action:
5.1 A
rrange for completion of the Work under the Contract by Contractor, with City’s c
onsent, but only if Contractor is in default solely due to its financial inability to c
omplete the Work;
5.2 A
rrange for completion of the Work under the Contract by a qualified contractor acceptable to City, and secured by performance and payment bonds issued by an admitted surety as required by the Contract Documents, at Surety’s expense; or
5.3 W
aive its right to complete the Work under the Contract and reimburse City the amount of City’s costs to have the remaining Work completed.
6. S
urety Default. If Surety defaults on its obligations under the Bond, City will be entitled to r
ecover all costs it incurs due to Surety’s default, including legal, design professional, or delay costs.
7. No
tice. Any notice to Surety may be given in the manner specified in the Contract and s
ent to Surety as follows:
A
ttn: _____________________________________________________ Address: __________________________________________________ Juliette Substation Expansion Project 2024 Form PERFORMANCE BOND 2462 Page 8
City/State/Zip: ______________________________________________ Phone: ___________________________________________________ Fax: ______________________________________________________ Email: ____________________________________________________
8. La
w and Venue. This Bond will be governed by California law, and venue for any dispute pur
suant to this Bond will be in the Santa Clara County Superior Court, and no other place.
Surety will be responsible for City’s attorneys’ fees and costs in any action to enforce the pr
ovisions of this Bond.
9. E
ffective Date; Execution. This Bond is entered into and effective on ________
____________, 20___.
SU
RETY:
________
___________________________
Business Name
s
/__________________________________ ______________________________ Date
___________________________________
Name, Title
(
Attach Acknowledgment with Notary Seal and Power of Attorney) CO
NTRACTOR:
________
___________________________
Business Name
s
/__________________________________ ______________________________ Date
___________________________________
Name, Title
A
PPROVED AS TO FORM:
s
/ __________________________________ ______________________________ Date
____________________________________
Name, Title
E
ND OF PERFORMANCE BOND
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 9
General Conditions
Art
icle 1 - Definitions
Definitions. The following definitions apply to all of the Contract Documents unless otherwise indicated, e.g., additional definitions that apply solely to the Specifications or other technical documents. Defined terms and titles of documents are capitalized in the Contract Documents, with the exception of the following (in any tense or form): “day,” “furnish,” “including,” “install,” “work day,” or “working day.”
A
llowance means a specific amount that must be included in the Proposal form, for a specified purpose.
Art
icle, as used in these General Conditions, means a numbered Article of the General Conditions, unless otherwise indicated by the context.
C
hange Order means a written document duly approved and executed by City, which changes the scope of Work, the Contract Price, or the Contract Time.
Ch
ief Electric Utility Officer means the director of the Electric Utility Department, also known as Silicon Valley Power, and his or her authorized delegee(s).
Ci
ty means the City of Santa Clara, acting through its City Council, officers, employees, City Engineer, and any other authorized representatives.
C
ity Council means the City Council of the City of Santa Clara, and its authorized delegee(s).
Ci
ty Engineer means the City Engineer for City and his or her authorized delegee(s).
Cl
aim means a separate demand by Contractor for a change in the Contract Time or Contract Price, that has previously been submitted to City in accordance with the requirements of the Contract Documents, and which has been rejected by City, in whole or in part; a written demand by Contractor disputing a unilateral Change Order or a portion thereof; or a written demand by Contractor objecting to the amount of Final Payment.
Co
ntract means the signed agreement between City and Contractor for performing the Work required for the Project, and all documents expressly incorporated therein.
Co
ntract Documents means, collectively, all of the documents listed as such in Section 2 of the Contract, including the Proposal and attachments thereto; the Contract; Notice to Proceed; the payment and performance bonds; the General Conditions; the General Requirements; the Special Conditions; the Project Plans and Specifications; any Change Orders; and any other documents which are clearly and unambiguously made part of the Contract Documents. The Contract Documents do not include documents provided “For Reference Only,” or documents that are intended solely to provide information regarding existing conditions.
Co
ntract Price means the total compensation to be paid to Contractor for performance of the Work, as set forth in the Contract and as may be amended by Change Order or adjusted for an Allowance. The Contract Price is not subject to adjustment due to inflation or due to the increased cost of labor, material, supplies, or equipment following submission of the Proposal.
Co
ntract Time means the time specified for complete performance of the Work, as set forth in the Contract and as may be amended by Change Order.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 10
Contractor means the individual, partnership, corporation, or joint-venture that has signed the Contract with City to perform the Work.
Day m
eans a calendar day unless otherwise specified.
Desi
gn Professional means the licensed individual(s) or firm(s) retained by City to provide architectural, engineering, or other design professional services for the Project. If no Design Professional has been retained for this Project, any reference to Design Professional is deemed to refer to the Engineer.
DI
R means the California Department of Industrial Relations.
Di
rector means the director of the Department of Public Works and his or her authorized delegee(s).
Draw
ings has the same meaning as Plans.
E
ngineer means, for a Project administered by the City’s Department of Public Works, the City Engineer and his or her authorized delegees; for a Project administered by the City’s Water & Sewer Utilities, the Director of Water and Sewer Utilities and his or her authorized delegees; and for a Project administered by Silicon Valley Power, the Chief Electric Utility Officer and his or her authorized delegees.
E
xcusable Delay is defined in Section 5.3(B), Excusable Delay.
E
xtra Work means new or unforeseen work added to the Project, as determined by the Engineer in his or her sole discretion, including Work that was not part of or incidental to the scope of the Work when the Contractor’s Proposal was submitted; Work that is substantially different from the Work as described in the Contract Documents at the time of proposal submission; or Work that results from a substantially differing and unforeseeable condition.
Fi
nal Completion means Contractor has fully completed all of the Work required by the Contract Documents to the City’s satisfaction, including all punch list items and any required commissioning or training, and has provided the City with all required submittals including the instructions and manuals, product warranties, and as-built drawings.
F
inal Payment means payment to Contractor of the unpaid Contract Price, including release of undisputed retention, less amounts withheld or deducted pursuant to the Contract Documents.
Fur
nish means to purchase and deliver for the Project.
G
overnment Code Claim means a claim submitted pursuant to California Government Code § 900 et seq.
Haz
ardous Materials means any substance or material identified as hazardous under any Laws, or any other substance or material that may be considered hazardous or otherwise subject to Laws governing handling, disposal, or cleanup.
Inc
luding, whether or not capitalized, means “including, but not limited to,” unless the context clearly requires otherwise.
Ins
pector means the individual(s) or firm(s) retained or employed by City to test and/or inspect the workmanship, materials, and manner of construction of the Project and its components to ensure compliance with the Contract Documents and all Laws.
I
nstall means to fix in place for materials, and to fix in place and connect for equipment.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 11
Laws means all applicable local, state, and federal laws, regulations, rules, codes, ordinances, permits, orders, and the like enacted or imposed by or under the auspices of any governmental entity with jurisdiction over any of the Work or any performance of the Work, including health and safety requirements.
Non-Excusable Delay is defined in Section 5.3(D), Non-Excusable Delay.
Plans means the City-provided plans, drawings, details, or graphical depictions of the Project requirements, but does not include Shop Drawings.
Project means the public works project referenced in the Contract, as modified by any Project alternates elected by City, if any.
Project Manager means the individual designated by City to oversee and manage the Project on City’s behalf and may include his or her authorized delegee(s) when the Project Manager is unavailable. If no Project Manager has been designated for this Project, any reference to Project Manager is deemed to refer to the Engineer.
Recoverable Costs is defined in Section 5.3(F), Recoverable Costs.
Request for Information or RFI means Contractor’s written request for information about the Contract Documents, the Work or the Project, submitted to City in the manner and format specified by City.
Section, when capitalized in these General Conditions, means a numbered section or subsection of the General Conditions, unless the context clearly indicates otherwise.
Shop Drawings means drawings, plan details or other graphical depictions prepared by or on behalf of Contractor, and subject to City acceptance, which are intended to provide details for fabrication, installation, and the like, of items required by or shown in the Plans or Specifications.
Specialty Work means Work that must be performed by a specialized Subcontractor with the specified license or other special certification, and that the Contractor is not qualified to self- perform.
Specifications means the technical, text specifications describing the Project requirements, which are prepared for and incorporated into the Contract by or on behalf of City, and does not include the Contract, General Conditions or Special Conditions.
Standard Details means the latest version of the City’s standard details and technical standards, including the City of Santa Clara Standard Details, available at https://www.santaclaraca.gov/our-
city/departments-g-z/public-works/engineering/technical-documents, and the Silicon Valley Power Technical Standards, which may be available at https://www.siliconvalleypower.com/svp-and- community/rules-and-regulations and/ or provided by City upon request.
Standard Plans means the latest version of the State of California Department of Transportation Standard Plans.
Subcontractor means an individual, partnership, corporation, or joint-venture retained by Contractor directly or indirectly through a subcontract to perform a specific portion of the Work.
The term Subcontractor applies to subcontractors of all tiers, unless otherwise indicated by the context. A third party such as a utility performing related work on the Project is not a Subcontractor, even if Contractor must coordinate its Work with the third party.
SVP means Silicon Valley Power, the City’s municipal electric utility.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 12
T
echnical Specifications has the same meaning as Specifications.
W
ork means all of the construction and services necessary for or incidental to completing the Project in conformance with the requirements of the Contract Documents.
W
ork Day or Working Day, whether or not capitalized, means a weekday when the City is open for business, and does not include the following holidays observed by the City. If a holiday falls on a Saturday, the preceding Friday will be the holiday. If a holiday falls on a Sunday, the following Monday will be the holiday.
(A) New Y
ear’s Day, January 1;
(B) Martin Luther King Jr.’s Birthday, third Monday in January; (C) Presidents’ Day, third Monday in February;
(D) Spring Holiday, the Friday before Easter Sunday;
(E) Memorial Day, last Monday in May;
(F) Independence Day, July 4;
(G) Labor Day, first Monday in September;
(H) Admission Day, September 9;
(I) Indigenous Peoples’ Day, second Monday in October;
(J) Veterans’ Day, November 11;
(K) Thanksgiving Day;
(L) The Day following Thanksgiving Day;
(M) Christmas Day and City Closure, December 25-31; and (N) Each day appointed by the Governor of California and formally recognized by the Cit
y Council as a day of mourning, thanksgiving, or special observance.
W
orksite means the place or places where the Work is performed, which includes, but may extend beyond the Project site, including separate locations for staging, storage, or fabrication.
Art
icle 2 - Roles and Responsibilities
2.1 City.
(A) C
ity Council. The City Council has final authority in all matters affecting the P
roject, except to the extent it has delegated authority to the Engineer. (
B) Engineer. The Engineer, acting within the authority conferred by the City Council, is responsible for administration of the Project on behalf of City, including aut
hority to provide directions to the Design Professional and to Contractor to ensure pr
oper and timely completion of the Project. The Engineer’s decisions are final and c
onclusive within the scope of his or her authority, including interpretation of the Contract Documents.
(
C) Project Manager. The Project Manager assigned to the Project will be the pr
imary point of contact for the Contractor and will serve as City’s representative for daily administration of the Project on behalf of City. Unless otherwise specified, all of Contractor’s communications to City (in any form) will go to or through the Project Manager. City reserves the right to reassign the Project Manager role at any time or t o
delegat
e duties to additional City representatives, without prior notice to or consent of Contractor.
(
D) Design Professional. The Design Professional is responsible for the overall des
ign of the Project and, to the extent authorized by City, may act on City’s behalf to ens
ure performance of the Work in compliance with the Plans and Specifications, Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 13
including any design changes authorized by Change Order. The Design Professional’s duties may include review of Contractor’s submittals, visits to any Worksite, inspecting the Work, evaluating test and inspection results, and participation in Project-related meetings, including any pre-construction conference, weekly meetings, and coordination meetings. The Design Professional’s interpretation of the Plans or Specifications is final and conclusive.
2. 2 Contractor.
(A) G
eneral. Contractor must provide all labor, materials, supplies, equipment, services, and incidentals necessary to perform and timely complete the Work in strict accordance with the Contract Documents, and in an economical and efficient manner in t
he best interests of City, and with minimal inconvenience to the public. (B) R
esponsibility for the Work and Risk of Loss. Contractor is responsible for supervising and directing all aspects of the Work to facilitate the efficient and timely completion of the Work. Contractor is solely responsible for and required to exercise full c
ontrol over the Work, including the construction means, methods, techniques, sequences, procedures, safety precautions and programs, and coordination of all por
tions of the Work with that of all other contractors and Subcontractors, except to the ex
tent that the Contract Documents provide other specific instructions. Contractor’s responsibilities extend to any plan, method or sequence suggested but not required by City or specified in the Contract Documents. From the date of commencement of t he
W
ork until either the date on which City formally accepts the Project or the effective date of
termination of the Contract, whichever is later, Contractor bears all risks of injury or damage to the Work and the materials and equipment delivered to any Worksite, by any cause including fire, earthquake, wind, weather, vandalism or theft, subject to the lim
itations of Laws, including Public Contract Code § 7105. (
C) Project Administration. Contractor must provide sufficient and competent administration, staff, and skilled workforce necessary to perform and timely complete the W
ork in accordance with the Contract Documents. Before starting the Work, Contractor must designate in writing and provide complete contact information, including telephone num
bers, email address, and emergency contact information, for the officer or employee in Cont
ractor’s organization who is to serve as Contractor’s primary representative for the P
roject, and who has authority to act on Contractor’s behalf. A Subcontractor may not serve as Contractor’s primary representative.
(
D) On-Site Superintendent. Contractor must, at all times during performance of the Work, provide a qualified and competent full-time superintendent acceptable to City, and as
sistants as necessary, who must be physically present at the Project site while any aspect of the Work is being performed. The superintendent must have full authority to act and c
ommunicate on behalf of Contractor, and Contractor shall be bound by the s
uperintendent’s communications to City. City’s approval of the superintendent is required before the Work commences. Contractor must also provide emergency contact information for the superintendent. If City is not satisfied with the superintendent’s performance, City may request a qualified replacement of the superintendent. Failure t o
c
omply may result in temporary suspension of the Work, at Contractor’s sole expense and wit
h no extension of Contract Time, until an approved superintendent is physically present to supervise the Work. Contractor must provide written notice to City, as soon as practicable, and receive City’s approval, before replacing the superintendent. (
E) Standards. Contractor must, at all times, ensure that the Work is performed in a n efficient, skillful manner following best practices and in full compliance with the Contract Documents, Laws, all rules and regulations of public utilities, and applicable m
anufacturer’s recommendations. Contractor has a material and ongoing obligation to Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 14
provide true and complete information, to the best of its knowledge, with respect to all records, documents, or communications pertaining to the Project, including oral or written reports, statements, certifications, Change Order requests, or Claims. (F) M
eetings. Contractor, its project manager, superintendent and any primary S
ubcontractors requested by City, must conduct and/or attend, as applicable, the meetings specified in this subsection. For each meeting, Contractor must prepare m
eeting minutes and submit the meeting minutes to City following the meeting. (
1) Pre-Construction Conference. Contractor, its project manager, superintendent, authorized representative responsible for scheduling, and any primary Subcontractors and/or key personnel requested by City, must attend a pr
e-construction conference. City will designate a date and time for a pre- construction conference with Contractor following Contract execution. The parties will discuss coordination between City and Contractor and Project administration pr
ocedures, including, but not limited to, schedules, personnel and vehicle permit procedures, use of premises, location for temporary facilities at the Project site, security, submittal procedures, utility shutdown procedures, inspection and t
esting procedures, control and reference point survey procedures, and Cont
ractor’s safety program. Contractor must present City with the following inf
ormation or documents at the conference for City’s review and acceptance bef
ore the Work commences:
(
a) Name, 24-hour contact information, and qualifications of the pr
oposed on-site superintendent;
(b) Lis
t of all key Project personnel and their complete contact information, including email addresses and telephone numbers during r
egular hours and after hours;
(c) S
taging plans that identify the sequence of the Work, including any phases and alternative sequences or phases, with the goal of minimizing t
he impacts on residents, businesses and other operations in the Project vicinity;
(
d) Contractor’s traffic control and detour plan and any other traffic control plans associated with the staging plans, that are signed and s
tamped by a licensed engineer (if required);
(
e) Contractor’s initial schedule, if applicable, and draft baseline schedule f
or the Work as required under Section 5.2;
(f
) Submittal schedule with list of Project submittals that require City review, and list of the proposed material suppliers;
(
g) Dr
aft schedule of values as required under Section 8.1, to be finalized prior to Contractor’s submission of the first application for payment; (
h) Letter of authorization to execute Change Orders on behalf of Contractor; and
(i) A
ny other documents specified in the Special Conditions. (2) W
eekly Progress Meetings. Contractor, its project manager, superintendent, and any Subcontractors and/or key personnel requested by City, must attend weekly Project progress meetings scheduled with City. The progress meetings Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 15
will be held at Contractor’s office at the Project site unless otherwise directed by City. The subjects for discussion at the weekly progress meetings may include, but are not limited to, any meeting minutes from a previous meeting; review of progress of the Work since the previous meeting; Work schedules, including progress schedules, delivery schedules, and adjustments thereto; the status of submittals, RFIs, or Change Orders; the Contractor’s safety program activities and results, including reports on any serious injuries and/or damage accidents; and any other items affecting the progress of Work. Contractor shall prepare an agenda for progress meeting(s). If there are any questions from City at a progress meeting that require further response from Contractor, Contractor must respond to those questions in writing within five days following the meeting. (3)
Special Meetings. At any time during the progress of the Work, City may schedule special meetings with the Contractor, including, but not limited to, meetings in emergency situations. Contractor, its project manager, superintendent, and any Subcontractors and/or key personnel requested by City, must attend any such special meetings, as directed by City. (4)
Safety Meetings. Contractor must conduct monthly safety committee meetings and weekly toolbox safety talks with its workers. (5) Coor
dination Meetings. In order to fulfill its coordination obligations, Contractor shall hold coordination meetings with other parties relating to other work being performed on or near the Project site or in relation to the Project, including work or activities performed by City, other contractors, or other utility owners. Contractor shall plan, coordinate, and schedule any such meetings with utility companies and City forces installing utilities. At least five days in advanc e
of
any such meeting, Contractor shall notify the Engineer and invite the Engineer to attend the meeting. Contractor shall be responsible for presiding over these m
eetings, as well as preparing and distributing meeting minutes within three wor
king days following any such meeting.
(
G) Construction Records. Contractor shall maintain up-to-date, thorough, legible, and dated daily job reports, which document all significant activity on the Project for each day
that Work is performed on the Project. The daily report for each day must include the num
ber of workers by trade at the Project site, including the hours worked by each wor
ker with title; the equipment used to perform the Work; identification of Subcontractors performing Work; primary Work activities; major deliveries; problems encountered, inc
luding injuries, if any; weather and site conditions; and delays, if any. Contractor must submit the daily job reports to the City either at the close of the same day to which the daily
job report pertains or the following morning. Contractor shall take date and time- stamped photographs to document general progress of the Project, including site c
onditions prior to construction activities, before and after photographs at offset trench lat
erals, existing improvements and utilities, damage and restoration. Contractor shall maintain copies of all subcontracts, Project-related correspondence with Subcontractors, and records of meetings with Subcontractors. Upon request by the City, Contractor shall permit inspection of and/or provide copies of any of these construction records. (
H) Responsible Party. Contractor is solely responsible to City for the acts or omissions of any Subcontractors, or any other party or parties performing portions of the W
ork or providing equipment, materials or services for or on behalf of Contractor or the S
ubcontractors. Upon City’s written request, Contractor must promptly and permanently remove from the Project, at no cost to City, any employee or Subcontractor or employee of
a Subcontractor who the Engineer has determined to be incompetent, intemperate or disorderly, or who has failed or refused to perform the Work as required under the Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 16
Contract Documents. Contractor shall ensure that no alcohol, firearms, weapons, or controlled substances enter or are used at the Project site. (
I) Correction of Defects. Contractor must promptly correct, at Contractor’s sole ex
pense, any Work that is determined by City to be deficient or defective in any way, including workmanship, materials, parts, or equipment, as well as any Work that is impacted by deficient of defective Work. Workmanship, materials, parts, or equipment that do not conform to the requirements under the Contract Documents, as determined by
City, will be considered defective and subject to rejection. Contractor must also pr
omptly correct, at Contractor’s sole expense, any Work performed beyond the lines and gr
ades shown on the Plans or established by City, and any Extra Work performed without City’s prior written approval. If Contractor fails to correct or to take reasonable steps toward correcting Work contemplated by this paragraph within five days following notice f
rom City, or within the time specified in City’s notice to correct, City may elect to have the W
ork corrected by its own forces or by a third party, in which case the cost of correction will be deduc
ted from payment otherwise due to Contractor. If City elects to correct the W
ork due to Contractor’s failure or refusal to do so, City or its agents will have the right to t
ake possession of and use any equipment, supplies, or materials available at the Project site or any Worksite on City property, in order to effectuate the correction, at no extra cost to City. Contractor’s warranty obligations under Section 11.2, Warranty, will not be waiv
ed nor limited by City’s actions to correct Work under these circumstances.
Alternatively, City may elect to retain the Work, and deduct the difference in value, as determined by the Engineer, from payments otherwise due to Contractor. This paragraph als
o applies to any defective Work performed by Contractor during the one-year warranty period under Section 11.2.
(
1) Cont
ractor shall also be responsible for the costs to correct other work that is being performed on or adjacent to the Project site that is impacted by the def
ective Work of Contractor and the City may deduct those costs from payment otherwise due Contractor.
(
2) Cont
ractor is responsible for all claims, costs, losses, damages, expenses, and liabilities incurred or sustained by City or Contractor related to City’s investigation, assessment, and/or remedy of defective Work. (
J) Contractor’s Records. Contractor must maintain all of its records relating to the P
roject in any form, including paper documents, photos, videos, electronic records, appr
oved samples, and the construction records required pursuant to paragraph (G), above. Project records subject to this provision include complete Project cost records and r
ecords relating to preparation of Contractor’s Proposal, including estimates, take-offs, and pr
ice quotes or bids (as applicable).
(
1) Contractor’s cost records must include all supporting documentation, including original receipts, invoices, and payroll records, evidencing its direct costs to perform the Work, including, but not limited to, costs for labor, materials, and equipment. Each cost record should include, at a minimum, a description of the expenditure with references to the applicable requirements of the Contract Documents, the amount actually paid, the date of payment, and whether the expenditure is part of the original Contract Price, related to an execut ed Change
O
rder, or otherwise categorized by Contractor as Extra Work. Contractor’s failure t
o comply with this provision as to any claimed cost operates as a waiver of any rights to recover the claimed cost.
(
2) Contractor must continue to maintain its Project-related records in an or
ganized manner for a period of five years after City’s acceptance of the Project, as
set forth in Section 11.1(C), or following Contract termination, whichever Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 17
occurs first. Subject to prior notice to Contractor, City is entitled to inspect or audit any of Contractor’s records relating to the Project during Contractor’s normal business hours. Contractor’s records may also be subject to examination and audit by the California State Auditor, pursuant to Government Code § 8546.7. The record-keeping requirements set forth in this subsection 2.2(J) will survive expiration or termination of the Contract.
(
K) Copies of Project Documents. Contractor and its Subcontractors must keep c
opies, at the Project site, of all Work-related documents, including the Contract, permit(s), Plans, Specifications, addenda, Contract amendments, Change Orders, RFIs and RFI responses, Shop Drawings, as-built drawings, schedules, daily records, testing and ins
pection reports or results, and any related written interpretations. These doc
uments must be available to City for reference at all times during construction of the Pro
ject.
(
L) Quality Control. Contractor is responsible for implementing quality control ac
tivities to ensure that all materials, products, equipment, services, and workmanship m
eet the quality requirements of the Specifications and Plans, and that the Work complies with the Contract Documents. The quality control activities must include, at a m
inimum, identification of quality standards and references, procedures to ensure ac
tivities and the Work comply with the quality standards, and testing and inspection to v
erify quality of materials and workmanship. When no quality basis is prescribed in the Cont
ract Documents, the quality and testing procedures shall be in accordance with the bes
t acceptable practices of the construction industry for the locale of the Project, for projects of this type, or standards set by engineering or technical societies, whichever is more stringent. Contractor must employ and assign knowledgeable and skilled per
sonnel to perform quality control functions to ensure that the Work complies with the r
equirements of the Contract Documents.
2. 3 Subcontractors.
(A) G
eneral. All Work which is not performed by Contractor with its own forces must be performed by Subcontractors. City reserves the right to approve or reject any and all S
ubcontractors proposed to perform the Work, for reasons including the Subcontractor’s poor reputation, lack of relevant experience, financial instability, and lack of technical abilit
y or adequate trained workforce. Each Subcontractor must obtain a City business license before performing any Work.
(B) C
ontractual Obligations. Contractor must require each Subcontractor to c
omply with the provisions of the Contract Documents as they apply to the S
ubcontractor’s portion(s) of the Work, including the generally applicable terms of the Cont
ract Documents, and to likewise bind their subcontractors. Contractor shall provide t
hat the rights that each Subcontractor may have against any manufacturer, distributor, or supplier for breach of warranty or guarantee relating to items provided by the S
ubcontractor for the Project, will be assigned to City. Nothing in these Contract Documents creates a contractual relationship between a Subcontractor and City, but City is deemed to be a third-party beneficiary of the contract between Contractor and each S
ubcontractor.
(
C) Termination. If the Contract is terminated, each Subcontractor’s agreement must be assigned by Contractor to City, subject to the prior rights of any surety, but only if and to the extent that City accepts, in writing, the assignment by written notification, and as
sumes all rights and obligations of Contractor pursuant to each such subcontract agreement.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 18
(D) Substitution of Subcontractor. If Contractor requests substitution of a listed S
ubcontractor under Public Contract Code § 4107, Contractor is solely responsible for all co
sts City incurs in responding to the request, including legal fees and costs to conduct a hear
ing, and any increased subcontract cost to perform the Work that was to be per
formed by the listed Subcontractor. If City determines that a Subcontractor is unacceptable to City based on the Subcontractor’s failure to satisfactorily perform its Work, or for any of the grounds for substitution listed in Public Contract Code § 4107(a), City may request removal of the Subcontractor from the Project. Upon receipt of a writt en
r
equest from City to remove a Subcontractor pursuant to this paragraph, Contractor shall immediately remove the Subcontractor from the Project and, at no further cost to City, will eit
her (1) self-perform the remaining Work to the extent that Contractor is duly licensed and qualif
ied to do so, or (2) substitute a Subcontractor that is acceptable to City, in c
ompliance with Public Contract Code § 4107, as applicable.
2. 4 Coordination of Work.
(A) Co
ncurrent Work. City reserves the right to perform, have performed, or permit performance of other work on or adjacent to the Project site while the Work is being per
formed for the Project. Contractor is responsible for coordinating its Work with other work being performed on or adjacent to the Project site, including by any utility companies or agencies, and must avoid hindering, delaying, or interfering with the work of other contractors, individuals, or entities, and must ensure safe and reasonable sit e
ac
cess and use as required or authorized by City. To the full extent permitted by law, Contractor must hold harmless and indemnify City against any and all claims arising from or related to Contractor’s avoidable, negligent, or willful hindrance of, delay to, or interference with the work of any utility company or agency or another contractor or subcontractor.
(B) C
oordination. If Contractor’s Work will connect or interface with work performed by
others, Contractor is responsible for independently measuring and visually inspecting such work to ensure a correct connection and interface. Contractor is responsible for any failure by Contractor or its Subcontractors to confirm measurements before proc eeding
wit
h connecting Work. Before proceeding with any portion of the Work affected by the c
onstruction or operations of others, Contractor must give the Project Manager prompt written notification of any defects Contractor discovers which will prevent the proper execution of the Work. Failure to give notice of any known or reasonably discover able
def
ects will be deemed acknowledgement by Contractor that the work of others is not defective and will not prevent the proper execution of the Work. Contractor must also pr
omptly notify City if work performed by others, including work or activities performed by City’s own forces, is operating to hinder, delay, or interfere with Contractor’s timely performance of the Work. City reserves the right to backcharge Contractor for any additional costs incurred due to Contractor’s failure to comply with the requirements in t
his Section 2.4.
2. 5 Submittals. Unless otherwise specified, Contractor must submit to the Engineer for review and acceptance, all schedules, reports, Shop Drawings, samples, test specimens, product data, and similar submittals required by the Contract Documents, or upon request by the Engineer. Unless otherwise specified, all submittals, including Requests for Information, are subject to the general provisions of this Section, as well as specific submittal requirements that may be included elsewhere in the Contract Documents, including the General Requirements and Specifications. At the pre-construction conference, Contractor must submit a submittal schedule to the Engineer that lists each submittal required by the Contract Documents and the scheduled date of submission, consistent with any specified deadlines for submission set forth in the Contract Documents, and that accounts for City review and processing, as required by Document 01 33 00 of the General Requirements.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 19
(A) General. Contractor is responsible for ensuring that all submittals are accurate and conform to the Contract Documents.
(B) Time and Manner of Submission. Contractor must ensure that its submittals are prepared and delivered in a manner consistent with the current City-accepted schedule for the Work and within the applicable time specified in the Contract Documents, or if no time is specified, in such time and sequence so as not to delay the performance of the Work or completion of the Project.
(C) Required Contents. Each submittal must include the Project name and contract number, Contractor’s name and address, the name and address of any Subcontractor or supplier involved with the submittal, the date, and references to applicable Specification section(s) and/or drawing and detail number(s).
(D) Required Corrections. If corrections are required, Contractor must promptly make and submit any required corrections as specified in full conformance with the requirements of this Section, or other requirements that apply to that submittal.
(E) Effect of Review and Acceptance. Review and acceptance of a submittal by City will not relieve Contractor from complying with the requirements of the Contract Documents. Contractor is responsible for any errors in any submittal, and review or acceptance of a submittal by City is not an assumption of risk or liability by City.
(F) Enforcement. Any Work performed or any material furnished, installed, fabricated or used without City’s prior acceptance of a required submittal is performed or provided at Contractor’s risk, and Contractor may be required to bear the costs incident thereto, including the cost of removing and replacing such Work, repairs to other affected portions of the Work or material, and the cost of additional time or services required of City, including costs for the Design Professional, Project Manager, or Inspector.
(G) Excessive RFIs. A RFI will be considered excessive or unnecessary if City determines that the explanation or response to the RFI is clearly and unambiguously discernable from the Contract Documents. City’s costs to review and respond to excessive or unnecessary RFIs may be deducted from payments otherwise due to Contractor.
(H) Availability of Samples. Contractor must make available to City all approved samples on a continuous basis and at a convenient location.
2.6 Shop Drawings. When Shop Drawings are required by the Specifications or requested by the Engineer, they must be prepared according to best practices at Contractor’s expense. The Shop Drawings must be of a size and scale to clearly show all necessary details. If City requires changes, the corrected Shop Drawings must be resubmitted to the Engineer for review within the time specified by the Engineer. For all Project components requiring Shop Drawings, Contractor will not furnish materials or perform any Work until the Shop Drawings for those components are accepted by City. Contractor is responsible for any errors or omissions in the Shop Drawings, shop fits and field corrections; any deviations from the Contract Documents; and for the results obtained by the use of Shop Drawings. Acceptance of Shop Drawings by City does not relieve Contractor of Contractor’s responsibility.
2.7 Access to Work. Contractor must afford prompt and safe access to any Worksite by City and its employees, agents, or consultants authorized by City; and upon request by City, Contractor must promptly arrange for City representatives to visit or inspect manufacturing sites or fabrication facilities for items to be incorporated into the Work.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 20
2. 8 Personnel. Contractor and its Subcontractors must employ only competent and skillful personnel to perform the Work. Contractor and its Subcontractor’s supervisors, security or safety personnel, and employees who have unescorted access to the Project site must possess proficiency in English sufficient to read, understand, receive, and implement oral or written communications or instructions relating to their respective job functions, including safety and security requirements. Upon written notification from the Engineer, Contractor and its Subcontractors must immediately discharge any personnel who are incompetent, disorderly, disruptive, threatening, abusive, or profane, or otherwise refuse or fail to comply with the requirements of the Contract Documents or Laws, including Laws pertaining to health and safety. Any such discharged personnel may not be re- employed or permitted on the Project in any capacity without City’s prior written consent.
Art
icle 3 - Contract Documents
3.1 Interpretation of Contract Documents.
(A) P
lans and Specifications. The Plans and Specifications included in the Cont
ract Documents are complementary. If Work is shown on one but not on the other, Contractor must perform the Work as though fully described on both, consistent with the Cont
ract Documents and reasonably inferable from them as being necessary to produce t
he indicated results. The Plans and Specifications are deemed to include and require ev
erything necessary and reasonably incidental to completion of the Work, whether or not particularly mentioned or shown. Contractor must perform all Work and services and s
upply all things reasonably related to and inferable from the Contract Documents. In the event of a conflict between the Plans and Specifications, the Specifications will control, unles
s the drawing(s) at issue are dated later than the Specification(s) at issue. Detailed dr
awings take precedence over general drawings, and large-scale drawings take pr
ecedence over smaller scale drawings. Any arrangement or division of the Plans and S
pecifications into sections is for convenience and is not intended to limit the Work required by separate trades. A conclusion presented in the Plans or Specifications is only a recommendation. Actual locations and depths must be determined by Contractor’s field inv
estigation. Contractor may request access to underlying or background information in Cit
y’s possession that is necessary for Contractor to form its own conclusions. (B) Du
ty to Notify and Seek Direction. If Contractor becomes aware of a changed c
ondition in the Project, or of any ambiguity, conflict, inconsistency, discrepancy, omission, or error in the Contract Documents, including the Plans or Specifications, Contractor must promptly submit a Request for Information to the Engineer, using an RFI form acceptable to the City, and wait for a response from City before proceeding further with the related Work. The RFI must notify City of the issue, specify the affected Work activity per the progress schedule, specify the time criticality of the RFI, and request clarification, interpretation or direction. The Engineer’s clarification, interpretation or direction will be final and binding on Contractor. If Contractor proceeds with the related W
ork before obtaining City’s response, Contractor shall be responsible for any resulting c
osts, including the cost of correcting any incorrect or defective Work that results. Timely submission of a clear and complete RFI is essential to avoiding delay. Contractor must submit time critical RFIs at least 30 days in advance of the scheduled start date of t he
af
fected Work. Delay resulting from Contractor’s failure to submit a timely and complete RFI to the Engineer is Non-Excusable Delay. If Contractor believes that City’s response t
o an RFI justifies a change to the Contract Price or Contract Time, Contractor must perform the Work as directed, but may submit a timely Change Order request in ac
cordance with the Contract Documents. (See Articles 5 and 6.) Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 21
(C) Figures and Dimensions. In the event of a conflict between figures and scaled dim
ensions, figures control over scaled dimensions.
(
D) Technical or Trade Terms. Any terms that have well-known technical or trade m
eanings will be interpreted in accordance with those meanings, unless otherwise s
pecifically defined in the Contract Documents.
(E) M
easurements. Contractor must verify all relevant measurements in the Cont
ract Documents and at the Project site before ordering any material or performing any
Work, and will be responsible for the correctness of those measurements or for costs t
hat could have been avoided by independently verifying measurements. (F
) Compliance with Laws. The Contract Documents are intended to comply with Laws
and will be interpreted to comply with Laws. If Contractor believes that a r
equirement in the Contract Documents conflicts with Laws, then Contractor shall submit an RFI to City, in accordance with Section 3.1(B), above. Unless otherwise specified by City, in the event of a conflict or inconsistency among (1) the Contract Documents and Laws or
(2) among different Laws, Contractor must comply with the most stringent requirement. If the Plans or Specifications require or describe products or execution of better quality, higher standard, or greater size than required by Laws, the Plans and S
pecifications will take precedence, provided the requirements therein comply with Laws.
If there are no specific requirements for compliance with Laws in the Plans or Specifications, Contractor must nonetheless comply with the requirements of Laws. (G
) Manufacturer’s Recommendations; Standards and Code Compliance.
Unless more stringent requirements are set forth in the Plans or Specifications, Contractor must comply with manufacturer’s instructions and recommendations, reference standards and building code research report requirements in preparing, fabricating, erecting, installing, applying, connecting, and finishing the Work. Contractor must secure City’s advanced written consent for any proposed deviations from referenc e
s
tandards and building code research report requirements and manufacturer’s instructions and recommendations. Contractor must document and explain all such dev
iations to City and provide an acknowledgement by the manufacturer that such dev
iations are acceptable and appropriate for the Project, if applicable.
3. 2 Order of Precedence. Information included in one Contract Document but not in another will not be considered a conflict or inconsistency. Unless otherwise specified in the Special Conditions, in case of any conflict or inconsistency among the Contract Documents, the following order of precedence will apply, beginning from highest to lowest, with the most recent version taking precedent over an earlier version:
(A) Change O
rders;
(B) Addenda;
(C) Contract;
(D) Notice to Proceed;
(E) Attachment for Federal Contract Requirements (only if used); (F) Special Conditions;
(G) General Conditions;
(H
) G
eneral Requirements;
(I) Payment and Performance Bonds;
(J) Specifications;
(K) Plans;
(L) Contractor’s Proposal and attachments;
(M) the City’s Standard Details, as applicable; and
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 22
(N) Any generic documents prepared by and on behalf of a third party, that were not prepared specifically for this Project, such as the Caltrans Standard S
pecifications, Caltrans Special Provisions, or Caltrans Standard Plans.
3. 3 Caltrans Standard Specifications. Any reference to or incorporation of the Standard Specifications of the State of California, Department of Transportation (“Caltrans”), including “Standard Specifications,” “Caltrans Specifications,” “State Specifications,” or “CSS,” means the most current edition of Caltrans’ Standard Specifications, unless otherwise specified (“Caltrans Standard Specifications”), including the most current amendments as of the date that Contractor’s Proposal was submitted for this Project. The following provisions apply to use of or reference to the Caltrans Standard Specifications or Special Provisions:
(A) Lim
itations. The “General Provisions” of the Caltrans Standard Specifications, i.e., sections 1 through 9, do not apply to these Contract Documents with the exception of any specific provisions, if any, which are expressly stated to apply to these Contract Documents.
(B) C
onflicts or Inconsistencies. If there is a conflict or inconsistency between any provision in the Caltrans Standard Specifications or Special Provisions and a provision of these Contract Documents, as determined by City, the provision in the Contract Documents will govern.
(
C) Meanings. Terms used in the Caltrans Standard Specifications or Special P
rovisions are to be interpreted as follows:
(1)
Any reference to the “Engineer” is deemed to mean the City Engineer. (2)
Any reference to the “Special Provisions” is deemed to mean the Special Condit
ions, unless the Caltrans Special Provisions are expressly included in the Cont
ract Documents listed in Section 2 of the Contract.
(3)
Any reference to the “Department” or “State” is deemed to mean City.
3. 4 For Reference Only. Contractor is responsible for the careful review of any document, study, or report provided by City or appended to the Contract Documents solely for informational purposes and identified as “For Reference Only.” Nothing in any document, study, or report so appended and identified is intended to supplement, alter, or void any provision of the Contract Documents. Contractor is advised that City or its representatives may be guided by information or recommendations included in such reference documents, particularly when making determinations as to the acceptability of proposed materials, methods, or changes in the Work. Any record drawings or similar final or accepted drawings or maps that are not part of the Contract Documents are deemed to be For Reference Only. The provisions of the Contract Documents are not modified by any perceived or actual conflict with provisions in any document that is provided For Reference Only. Geotechnical data, reports, and analyses of any kind are “For Reference Only” documents, whether or not they are attached to the Contract Documents.
3. 5 Current Versions. Unless otherwise specified by City, any reference to standard specifications, technical specifications, or any City or state codes or regulations means the latest specification, code, or regulation in effect on the Contractor’s Proposal submission date.
3. 6 Conformed Copies. If City prepares a conformed set of the Contract Documents following award of the Contract, it will provide Contractor with two hard copy (paper) sets,
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 23
if requested, and one copy of the electronic file in PDF format. It is Contractor’s responsibility to ensure that all Subcontractors, including fabricators, are provided with the conformed set of the Contract Documents at Contractor’s sole expense.
3.7 Ownership. No portion of the Contract Documents may be used for any purpose other than construction of the Project, without prior written consent from City. Contractor is deemed to have conveyed the copyright in any designs, drawings, specifications, Shop Drawings, or other documents (in paper or electronic form) developed by Contractor for the Project, and City will retain all rights to such works, including the right to possession.
Article 4 – Bonds, Indemnity, and Insurance
4.1 Payment and Performance Bonds. Within ten days following issuance of the City’s issuance of a notice of award, Contractor is required to provide a payment bond and a performance bond, each in the penal sum of not less than 100% of the Contract Price, and each executed by Contractor and its surety using the bond forms included with the Contract Documents.
(A) Surety. Each bond must be issued and executed by a surety admitted in California. If an issuing surety cancels the bond or becomes insolvent, within seven days following written notice from City, Contractor must substitute a surety acceptable to City.
If Contractor fails to substitute an acceptable surety within the specified time, City may, at its sole discretion, withhold payment from Contractor until the surety is replaced to City’s satisfaction, or terminate the Contract for default.
(B) Supplemental Bonds for Increase in Contract Price. If the Contract Price increases during construction by five percent or more over the original Contract Price, Contractor must provide supplemental or replacement bonds within ten days of written notice from City pursuant to this Section, covering 100% of the increased Contract Price and using the bond forms included with the Contract Documents.
4.2 Responsibility and Indemnity.
(A) Limitation on Liability. City and each of its officers, employees, consultants and agents including, but not limited to, the City Council and Engineer, shall not be liable or accountable in any manner for loss or damage that may happen to any part of the Work; loss or damage to materials or other things used or employed in performing the Work; injury, sickness, disease, or death of any person; or damage to property resulting from any cause whatsoever except their sole negligence, willful misconduct or active negligence, attributable to performance or character of the Work, and Contractor releases all of the foregoing persons and entities from any and all such claims.
(B) Indemnification. To the fullest extent permitted by law (including, without limitation, California Civil Code § 2782), Contractor shall assume defense of, and indemnify and hold harmless, City and each of its officers, employees, consultants, and agents, including, but not limited to, the City Council and Engineer, from claims, suits, actions, losses and liability of every kind, nature and description, including, but not limited to, claims and fines of regulatory agencies and attorney’s fees and consultant’s fees, directly or indirectly arising out of, connected with or resulting from performance of the Work, failure to perform the Work, or condition of the Work which is caused in whole or part by any act or omission of Contractor, Subcontractors, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether it is caused in part by the negligence of City or by any person or entity required to be indemnified hereunder, except as set forth in subsection (E), below. This indemnity requirement applies to any liability arising from alleged defects in the content or Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 24
manner of submission of Contractor’s Proposal for the Contract. Contractor’s failure or refusal to timely accept a tender of defense pursuant to this Contract will be deemed a material breach of the Contract.
(
C) Third-Party Claims. City will timely notify Contractor upon receipt of any third- party claim relating to the Contract, as required by Public Contract Code § 9201. With r
espect to third-party claims against Contractor, Contractor waives any and all rights to any
type of express or implied indemnity against City and each of its officers, employees, consultants, and agents, including, but not limited to City, the City Council, and Engineer. (
D) Continuing Obligations. To the fullest extent permitted by law (including, without limitation, Civil Code § 2782), the indemnities, releases of liability, and limitations of liability, claims procedures, and limitations of remedy expressed throughout the Cont
ract Documents shall apply even in the event of breach of contract, negligence, fault or strict liability of the party or parties indemnified, released, or limited in liability, and shall s
urvive the termination, rescission, breach, abandonment, or completion of the Work or the terms of the Contract Documents. If Contractor fails to perform any of these defense or
indemnity obligations, City may in its discretion back charge Contractor for City’s costs and damages resulting therefrom and deduct such sums from payments due to Cont
ractor.
(E) E
xceptions. The indemnities in this Section 4.2 shall not apply to City or other indemnified party to the extent of its sole negligence or willful misconduct; nor shall they apply to City or other indemnified party to the extent of its active negligence.
4. 3 Insurance. No later than ten days following issuance of the City’s notice of award, Contractor must procure and provide proof of the insurance coverage required by the Contract Documents in the form of certificates and endorsements acceptable to City. (See Section 1 of the Special Conditions.) The required insurance must cover the activities of Contractor and its Subcontractors relating to or arising from the performance of the Work, and must remain in full force and effect at all times during the period covered by the Contract, through the date of City’s acceptance of the Project. All required insurance must be issued by a company licensed to do business in the State of California, and each such insurer must have an A.M. Best’s financial strength rating of “A” or better and a financial size rating of “VI” or better. If Contractor fails to provide any of the required coverage in full compliance with the requirements of the Contract Documents, City may, at its sole discretion, purchase such coverage at Contractor’s expense and deduct the cost from payments due to Contractor, or terminate the Contract for default. The procurement of insurance will not be construed to limit Contractor’s liability under this Contract or to fulfill Contractor’s indemnification obligations under this Contract.
Art
icle 5 – Contract Time
5.1 Time is of the Essence. Time is of the essence in Contractor’s performance and completion of the Work, and Contractor must diligently prosecute the Work and complete it within the Contract Time.
(A) G
eneral. Contractor must commence the Work on the date indicated in the Not
ice to Proceed and must fully complete the Work in strict compliance with all r
equirements of the Contract Documents and within the Contract Time. Contractor may not begin performing the Work before the date specified in the Notice to Proceed. (B) Ad
vanced Contract Time. Contractor may request an earlier (advanced) time f
or completion, which City may decide to accept or reject, in its sole discretion. Contractor
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 25
is not entitled to any extra compensation in the event that it fails to complete the Project within the advanced Contract Time, but within the original time specified for completion.
(C) Authorization. Contractor is not entitled to compensation or credit for any Work performed before the date specified in the Notice to Proceed, with the exception of any schedules, submittals, or other requirements, if any, that must be provided or performed before issuance of the Notice to Proceed.
(D) Rate of Progress. Contractor and its Subcontractors must, at all times, provide workers, materials, and equipment sufficient to maintain the rate of progress necessary to ensure full completion of the Work within the Contract Time. If City determines that Contractor is failing to prosecute the Work at a sufficient rate of progress, City may, in its sole discretion, direct Contractor to provide additional workers, materials, or equipment, or to work additional hours or days without additional cost to City, in order to achieve a rate of progress satisfactory to City. If Contractor fails to comply with City’s directive in this regard, City may, at Contractor’s expense, separately contract for additional workers, materials, or equipment or use City’s own forces to achieve the necessary rate of progress, and it may exclude Contractor from the Project site, or portions of the Project site, or from certain elements of the Work, if necessary. Contractor shall remain responsible for any resulting delay, including any liquidated damages, and indemnification of City from claims of others. Alternatively, City may terminate the Contract based on Contractor’s default.
5.2 Schedule Requirements. Contractor must prepare all schedules using standard, commercial scheduling software acceptable to the Engineer, and must provide the schedules in electronic form (PDF and native files) as requested by the Engineer. Each schedule must be divided into Work activities of durations of approximately 21 days or less, except for non-field construction activities or as otherwise deemed acceptable to City, and must show the critical path in red. In addition to the general scheduling requirements set forth herein, Contractor must also comply with any scheduling requirements included in the Special Conditions or in the Technical Specifications.
(A) Initial Schedule. If the Contract Time for the Project is greater than 235 Working Days, at the pre-construction conference, Contractor must submit to City for review and acceptance an initial schedule that addresses the first 30 days following the start date set forth in the Notice to Proceed. The initial schedule must include a detailed plan for the Work to be completed in the first 30 days; details of planned mobilization of plant and equipment; sequence of early operations; procurement of materials and equipment; and a summary of the Work beyond the first 30 days.
(B) Baseline (As-Planned) Schedule. Within ten calendar days following City’s issuance of the Notice to Proceed (or as otherwise specified in the Notice to Proceed), Contractor must submit to City for review and acceptance a baseline (as-planned) schedule using critical path methodology showing in detail how Contractor plans to perform and fully complete the Work within the Contract Time, including labor, equipment, materials, and fabricated items. The baseline schedule must show the order of the major items of Work and the dates of start and completion of each item, including when the materials and equipment will be procured. The schedule must also include the work of all trades, reflecting anticipated labor or crew hours and equipment loading for the construction activities, and must be sufficiently comprehensive and detailed to enable progress to be monitored on a day-by-day basis. For each activity, the baseline schedule must be dated, provided in the format specified in the Contract Documents or as required by City, and must include, at a minimum, a description of the activity, the start and completion dates of the activity, predecessor and successor activities, and the duration of the activity.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 26
(C) City’s Review of Schedules. City will review and may note exceptions to the bas
eline schedule, and to the progress schedules submitted as required below, to assure c
ompletion of the Work within the Contract Time. Contractor is solely responsible for resolving any exceptions noted in a schedule and, within seven days, must correct the schedule to address the exceptions. City’s review or acceptance of Contractor’s schedules will not operate to waive or limit Contractor’s duty to complete the Project within the Contract Time, nor to waive or limit City’s right to assess liquidated damages for Contractor’s unexcused failure to do so.
(
D) Progress Schedules. After City accepts the final baseline schedule with no ex
ceptions, Contractor must submit an updated progress schedule, in the format specified by City, for review and acceptance with each application for a progress payment, or when otherwise specified by City, until completion of the Work. The updated pr
ogress schedule must: show how the actual progress of the Work as constructed to dat
e compares to the baseline schedule; reflect any proposed changes in the c
onstruction schedule or method of operations, including to achieve Project milestones within the Contract Time; and identify any actual or potential impacts to the critical path.
Contractor must also submit periodic reports to City of any changes in the projected m
aterial or equipment delivery dates for the Project. In addition, Contractor must submit a three-week look-ahead schedule at each weekly progress meeting. (
1) Float. The progress schedule must show early and late completion dates for each task. The number of days between those dates will be designated as t
he “float.” Any float belongs to the Project and may be allocated by the E
ngineer to best serve timely completion of the Project. (
2) Failure to Submit Schedule. Reliable, up-to-date schedules are essential t
o efficient and cost-effective administration of the Project and timely completion. If Contractor fails to submit a schedule within the time periods specified in this Section, or submits a schedule to which City has noted exceptions that are not corrected, City may withhold up to ten percent from pay
ment(s) otherwise due to Contractor until the exceptions are resolved, the schedule is corrected and resubmitted, and City has accepted the schedule.
In addition, Contractor’s failure to comply with the schedule requirements in t
his Section 5.2 will be deemed a material default and a waiver of any claims for Excusable Delay or loss of productivity arising during any period when Cont
ractor is out of compliance, subject only to the limits of Public Contract Code § 7102.
(
E) Recovery Schedule. If City determines that the Work is more than one week behind s
chedule, within seven days following written notice of such determination, Contractor must submit a recovery schedule, showing how Contractor intends to perform and complete the Work within the Contract Time, based on actual progress to date. T he
r
ecovery schedule must include a written narrative for each action necessary to complete t
he Work within the Contract Time. If sequence changes are necessary, Contractor shall pr
ovide a schedule diagram comparing the original sequence to the revised sequence of the Work. If requested by City, Contractor shall also show the intended critical path; secure appropriate Subcontractor and supplier consent for the recovery schedule; submit a narrative explaining trade flow and construction flow changes, duration changes, added
or
deleted activities, and critical path changes; and identify all near critical paths and man hour
loading assumptions for Subcontractors.
(
F) Effect of Acceptance. Contractor and its Subcontractors must perform the W
ork in accordance with the most current City-accepted schedule unless otherwise dir
ected by City. City’s acceptance of a schedule does not operate to extend the time for completion of the Work or any component of the Work, and will not affect City’s right to Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 27
assess liquidated damages for Contractor’s unexcused delay in completing the Work within the Contract Time.
(
G) Reservation of Rights. City reserves the right to direct the sequence in which t
he Work must be performed or to make changes in the sequence of the Work in order to f
acilitate the performance of work by City or others, or to facilitate City’s use of its property. The Contract Time or Contract Price may be adjusted to the extent such c
hanges in sequence actually increase or decrease Contractor’s time or cost to perform the Work.
(
H) Authorized Working Days and Times. Contractor is limited to working Monday through Friday, excluding holidays, between the hours of 7:00 AM and 5:00 PM, except as provided in the Special Conditions or as authorized in writing by City in response to a wr
itten request from Contractor. Contractor must make such written request at least two W
orking Days in advance of the proposed Work to be performed on days or during hours not expressly authorized in the Contract Documents. City reserves the right to charge Cont
ractor for additional costs incurred by City due to Work performed on days or during hour
s not expressly authorized in the Contract Documents, including reimbursement of costs incurred for inspection, testing, and construction management services.
5. 3 Delay and Extensions of Contract Time.
(A) No
tice of Delay. If Contractor becomes aware of any actual or potential delay affecting the critical path, Contractor must notify the Engineer within 24 hours in writing, regardless of the nature or cause of the delay, so that City has a reasonable opportunity to mitigate or avoid the delay.
(B) E
xcusable Delay. The Contract Time may be extended if Contractor encounters “Excusable Delay,” which is an unavoidable delay in completing the Work within the Cont
ract Time due to causes completely beyond Contractor’s control, and which Cont
ractor could not have avoided or mitigated through reasonable care, planning, foresight, or diligence, provided that Contractor is otherwise fully performing its obligations under the Contract Documents. Grounds for Excusable Delay may include fire, natural disasters including earthquake or unusually severe weather, acts of terror or v
andalism, epidemic, unforeseeable adverse government actions, unforeseeable actions of third parties, encountering unforeseeable hazardous materials, unforeseeable site c
onditions, or suspension for convenience under Article 13. The Contract Time will not be extended based on circumstances which will not unavoidably delay completing the Work within the Contract Time based on critical path analysis. (
C) Weather Delays. A “Weather Delay Day” is a Working Day during which Cont
ractor and its forces, including Subcontractors, are unable to perform more than 50% of
the critical path Work scheduled for that day due to adverse weather conditions which im
pair the ability to safely or effectively perform the scheduled critical path Work that day.
Adverse weather conditions may include rain, saturated soil, and Project site clean-up r
equired due to adverse weather. Determination of what constitutes critical path Work scheduled for that day will be based on the most current, City-approved schedule.
Contractor shall be entitled to a non-compensable extension of the Contract Time for each Weather Delay Day.
(
1) Contractor must fully comply with the applicable procedures in Articles 5 and 6 of
the General Conditions regarding requests to modify the Contract Time.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 28
(2) Contractor shall not be entitled to an extension of time for a Weather Delay Day to the extent Contractor is responsible for concurrent delay on that day.
(3) Contractor must take reasonable steps to mitigate the consequences of Weather Delay Days, including prudent workforce management and protecting the Work, Project Site, materials, and equipment.
(D) Non-Excusable Delay. Delay which Contractor could have avoided or mitigated through reasonable care, planning, foresight, or diligence is “Non-Excusable Delay.” Contractor is not entitled to an extension of Contract Time or any compensation for Non- Excusable Delay, or for Excusable Delay that is concurrent with Non-Excusable Delay.
Non-Excusable Delay includes delay caused by:
(1) Contractor’s failure to order equipment and materials sufficiently in advance of the time needed for completion of the Work within the Contract Time;
(2) Contractor’s failure to provide adequate notification to utility companies or agencies for connections or services necessary for completion of the Work within the Contract Time;
(3) foreseeable conditions which Contractor could have ascertained from reasonably diligent inspection of the Project site or review of the Contract Documents or other information provided or available to Contractor;
(4) Contractor’s failure, refusal, or financial inability to perform the Work within the Contract Time, including insufficient funds to pay its Subcontractors or suppliers;
(5) performance or non-performance by Contractor’s Subcontractors or suppliers;
(6) the time required to respond to excessive RFIs (see Section 2.5(G));
(7) delayed submission of required submittals, or the time required for correction and resubmission of defective submittals;
(8) time required for repair of, re-testing, or re-inspection of defective Work;
(9) enforcement of Laws by City, or outside agencies with jurisdiction over the Work; or
(10) City’s exercise or enforcement of any of its rights or Contractor’s duties pursuant to the Contract Documents, including correction of defective Work, extra inspections or testing due to non-compliance with Contract requirements, safety compliance, environmental compliance, or rejection and return of defective or deficient submittals.
(11) City’s right to sequence the Work in a manner to avoid disruption to City’s tenants and their contractors or other City contractors and their respective subcontractors, exercised as a result of Contractor’s failure to perform its cooperation and coordination obligations under the Contract Documents.
(E) Compensable Delay. Pursuant to Public Contract Code § 7102, in addition to entitlement to an extension of Contract Time, Contractor is entitled to compensation for costs incurred due to delay caused solely by City, when that delay is unreasonable under
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 29
the circumstances involved and not within the contemplation of the parties (“Compensable Delay”). Contractor is not entitled to an extension of Contract Time or recovery of costs for Compensable Delay that is concurrent with Non-Excusable Delay.
Delay due to Weather Delay Days is not Compensable Delay, and will only entitle Contractor to an extension of time commensurate with the time lost due to such delay.
(F) Recoverable Costs. Contractor is not entitled to compensation for Excusable Delay unless it is Compensable Delay, as defined above. Contractor is entitled to recover only the actual, direct, reasonable, and substantiated costs (“Recoverable Costs”) for each working day that the Compensable Delay prevents Contractor from proceeding with more than 50% of the critical path Work scheduled for that day, based on the most recent progress schedule accepted by City. Recoverable Costs will not include home office overhead or lost profit.
(G) Request for Extension of Contract Time or Recoverable Costs. A request for an extension of Contract Time or any associated Recoverable Costs must be submitted in writing to City within 14 days of the date the delay is first encountered, even if the duration of the delay is not yet known at that time, or any entitlement to the Contract Time extension or to the Recoverable Costs will be deemed waived. In addition to complying with the requirements of this Article 5, the request must be submitted in compliance with the Change Order request procedures in Article 6 below. Strict compliance with these requirements is necessary to ensure that any delay or consequences of delay may be mitigated as soon as possible, and to facilitate cost-efficient administration of the Project and timely performance of the Work. Any request for an extension of Contract Time or Recoverable Costs that does not strictly comply with all requirements of Article 5 and Article 6 will be deemed waived.
(1) Required Contents. The request must include a detailed description of the cause(s) of the delay and must also describe the measures that Contractor has taken to mitigate the delay and/or its effects, including efforts to mitigate the cost impact of the delay, such as by workforce management or by a change in sequencing. If the delay is still ongoing at the time the request is submitted, the request should also include Contractor’s plan for continued mitigation of the delay or its effects.
(2) Delay Days and Costs. The request must specify the number of days of Excusable Delay claimed or provide a realistic estimate if the duration of the delay is not yet known. If Contractor believes it is entitled to Recoverable Costs for Compensable Delay, the request must specify the amount and basis for the Recoverable Costs that are claimed or provide a realistic estimate if the amount is not yet known. Any estimate of delay duration or cost must be updated in writing and submitted with all required supporting documentation as soon as the actual time and cost is known. The maximum extension of Contract Time will be the number of days, if any, by which an Excusable Delay or a Compensable Delay exceeds any concurrent Non-Excusable Delay. Contractor is entitled to an extension of Contract Time, or compensation for Recoverable Costs, only if, and only to the extent that, such delay will unavoidably delay Final Completion.
(3) Supporting Documentation. The request must also include any and all supporting documentation necessary to evidence the delay and its actual impacts, including scheduling and cost impacts with a time impact analysis using critical path methodology and demonstrating the unavoidable delay to Final Completion. The time impact analysis must be submitted in a form or format acceptable to City. The time impact analysis must include (a) schedule diagrams comparing the current activities and sequences to the revised activities and sequences and (b) analysis that clearly demonstrates impact(s) to the critical Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 30
path activities. The time impact analysis must utilize the most current schedule update information that accurately reflects progress on the Project at the time of the schedule impact. The schedule logic for future activities must accurately reflect the approved plan for completing the remaining Work. (4)
Burden of Proof. Contractor has the burden of proving that: the delay was an E
xcusable Delay or Compensable Delay, as defined above; Contractor has fully complied with its scheduling obligations in Section 5.2, Schedule Requirements; Contractor has made reasonable efforts to mitigate the delay and its sc hedule
and c
ost impacts; the delay will unavoidably result in delaying Final Completion; and any Recoverable Costs claimed by Contractor were actually incurred and wer
e reasonable under the circumstances.
(
5) Legal Compliance. Nothing in this Section 5.3 is intended to require the waiv
er, alteration, or limitation of the applicability of Public Contract Code § 7102. (
6) No Waiver. Any grant of an extension of Contract Time, or compensation for Recoverable Costs due to Compensable Delay, will not operate as a waiver of City’s right to assess liquidated damages for Non-Excusable Delay. (
7) Dispute Resolution. In the event of a dispute over entitlement to an ex
tension of Contract Time or compensation for Recoverable Costs, Contractor may not stop Work pending resolution of the dispute, but must continue to c
omply with its duty to diligently prosecute the performance and timely completion of the Work. Contractor’s sole recourse for an unresolved dispute bas
ed on City’s rejection of a Change Order request for an extension of Contract Time or compensation for Recoverable Costs is to comply with the dispute r
esolution provisions set forth in Article 12 below.
5. 4 Liquidated Damages. It is expressly understood that if Final Completion is not achieved within the Contract Time, City will suffer damages from the delay that are difficult to determine and accurately specify. Pursuant to Public Contract Code § 7203, if Contractor fails to achieve Final Completion within the Contract Time due to Contractor’s Non- Excusable Delay, City will charge Contractor in the amount specified in the Contract for each calendar day that Final Completion is delayed beyond the Contract Time, as liquidated damages and not as a penalty. Any waiver of accrued liquidated damages, in whole or in part, is subject to approval of the City Council or its authorized delegee. (A) L
iquidated Damages. Liquidated damages will not be assessed for any Excusable Delay or Compensable Delay, as set forth above. (B) M
ilestones. Liquidated damages may also be separately assessed for failure to m
eet milestones specified elsewhere in the Contract Documents. (
C) Setoff. City is entitled to deduct the amount of liquidated damages assessed agains
t any payments otherwise due to Contractor, including progress payments, Final P
ayment, or unreleased retention. If there are insufficient Contract funds remaining to c
over the full amount of liquidated damages assessed, City is entitled to recover the balanc
e from Contractor or its performance bond surety.
(
D) Occupancy or Use. Occupancy or use of the Project in whole or in part prior to Final Completion does not constitute City’s acceptance of the Project and will not operate as a waiver of City’s right to assess liquidated damages for Contractor’s Non-Excus able
Delay
in achieving Final Completion.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 31
(E) Other Remedies. City’s right to liquidated damages under this Section applies only to damages arising from Contractor’s Non-Excusable Delay or failure to complete the Work within the Contract Time. City retains its right to pursue all other remedies under the Contract for other types of damage, including damage to property or persons, costs or diminution in value from defective materials or workmanship, costs to repair or complete the Work, lost revenues, interest expenses, cost of substitute facilities, claims and fines of regulatory agencies, or other liability caused by Contractor.
Article 6 - Contract Modification
6.1 Contract Modification. Subject to the limited exception set forth in subsection (D) below, any change in the Work or the Contract Documents, including the Contract Price or Contract Time, will not be a valid and binding change to the Contract unless it is formalized in a Change Order (Attachment A), including a “no-cost” Change Order or a unilateral Change Order. Changes in the Work pursuant to this Article 6 will not operate to release, limit, or abridge Contractor’s warranty obligations pursuant to Article 11 or any obligations of Contractor’s bond sureties.
(A) City-Directed Changes. City may direct changes in the scope or sequence of Work or the requirements of the Contract Documents, without invalidating the Contract.
Such changes may include Extra Work as set forth in subsection (C) below, or deletion or modification of portions of the Work. Prior to directing any such changes, City may request information from Contractor regarding the impact of any such City-directed changes on the Contract Price or Contract Time. Contractor will respond to any such request within ten days following City’s issuance of the request. Contractor’s response, including anticipated impacts, must be consistent with requirements of the Contract Documents, including Sections 6.3 and 6.4, below. Contractor must promptly comply with City-directed changes in the Work, when directed by City, in accordance with the original Contract Documents, even if Contractor and City have not yet reached agreement as to adjustments to the Contract Price or Contract Time for the change in the Work or for the Extra Work. Contractor is not entitled to extra compensation for cost savings resulting from “value engineering” pursuant to Public Contract Code § 7101, except to the extent authorized in advance by City in writing, and subject to any applicable procedural requirements for submitting a proposal for value engineering cost savings.
(B) Disputes. In the event of a dispute over entitlement to or the amount of a change in Contract Time or a change in Contract Price related to a City-directed change in the Work, Contractor must perform the Work as directed and may not delay its Work or cease Work pending resolution of the dispute, but must continue to comply with its duty to diligently prosecute the performance and timely completion of the Work, including the Work in dispute. Likewise, in the event that City and Contractor dispute whether a portion or portions of the Work are already required by the Contract Documents or constitute Extra Work, or otherwise dispute the interpretation of any portion(s) of the Contract Documents, Contractor must perform the Work as directed and may not delay its Work or cease Work pending resolution of the dispute, but must continue to comply with its duty to diligently prosecute the performance and timely completion of the Work, including the Work in dispute, as directed by City. If Contractor refuses to perform the Work in dispute, City may, acting in its sole discretion, elect to delete the Work from the Contract and reduce the Contract Price accordingly, and self-perform the Work or direct that the Work be performed by others. Alternatively, City may elect to terminate the Contract for convenience or for cause. Contractor’s sole recourse for an unresolved dispute related to changes in the Work or performance of any Extra Work is to comply with the dispute resolution provisions set forth in Article 12, below.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 32
(C) Extra Work. City may direct, in writing, Contractor to perform Extra Work related to the Project. Contractor must promptly perform any Extra Work as directed or authorized by City in accordance with the original Contract Documents, even if Contractor and City have not yet reached agreement on adjustments to the Contract Price or Contract Time for such Extra Work. If Contractor believes it is necessary to perform Extra Work due to changed conditions, Contractor must promptly notify the Engineer in writing, specifically identifying the Extra Work and the reason(s) the Contractor believes it is Extra Work. This notification requirement does not constitute a Change Order request pursuant to Section 6.2, below. Contractor must maintain detailed daily records that itemize the cost of each element of Extra Work, and sufficiently distinguish the direct cost of the Extra Work from the cost of other Work performed. For each day that Contractor performs Extra Work, or Work that Contractor contends is Extra Work, Contractor must submit no later than the following Working Day, a daily report of the Extra Work performed that day and the related costs, together with copies of certified payroll, invoices, and other documentation substantiating the costs (“Extra Work Report”). The Engineer will make any adjustments to Contractor’s Extra Work Report(s) based on the Engineer’s records of the Work. When an Extra Work Report(s) is agreed on and signed by both City and Contractor, the Extra Work Report(s) will become the basis for payment under a duly authorized and signed Change Order. Failure to submit the required documentation by close of business on the next Working Day is deemed a full and complete waiver for any change in the Contract Price or Contract Time for any Extra Work performed that day.
(D) Minor Changes and RFIs. Minor field changes, including RFI replies from City, that do not affect the Contract Price or Contract Time and that are approved by the Engineer acting within his or her scope of authority, do not require a Change Order. By executing an RFI reply from City, Contractor agrees that it will perform the Work as clarified therein, with no change to the Contract Price or Contract Time.
(E) Remedy for Non-Compliance. Contractor’s failure to promptly comply with a City-directed change is deemed a material breach of the Contract, and in addition to all other remedies available to it, City may, at its sole discretion, hire another contractor or use its own forces to complete the disputed Work at Contractor’s sole expense, and may deduct the cost from the Contract Price.
6.2 Contractor Change Order Requests. Contractor must submit a request or proposal for a change in the Work, compensation for Extra Work, or a change in the Contract Price or Contract Time as a written Change Order request or proposal.
(A) Time for Submission. Any request for a change in the Contract Price or the Contract Time must be submitted in writing to the Engineer within 14 calendar days of the date that Contractor first encounters the circumstances, information or conditions giving rise to the Change Order request, even if the total amount of the requested change in the Contract Price or impact on the Contract Time is not yet known at that time. If City requests that Contractor propose the terms of a Change Order, unless otherwise specified in City’s request, Contractor must provide the Engineer with a written proposal for the change in the Contract Price or Contract Time within five working days of receiving City’s request, in a form satisfactory to the Engineer.
(B) Required Contents. Any Change Order request or proposal submitted by Contractor must include a complete breakdown of actual or estimated costs and credits, and must itemize labor, materials, equipment, taxes, subcontract amounts, and, if applicable, Extra Work Reports. Any estimated cost must be updated in writing as soon as the actual amount is known.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 33
(C) Required Documentation. All claimed costs must be fully documented, and any related request for an extension of time or delay-related costs must be included at that time and in compliance with the requirements of Article 5 of the General Conditions.
Upon request, Contractor must permit City to inspect its original and unaltered bidding records, subcontract agreements, subcontract change orders, purchase orders, invoices, or receipts associated with the claimed costs.
(D) Required Form. Contractor must use City’s form(s) for submitting all Change Order requests or proposals, unless otherwise specified by City.
(E) Certification. All Change Order requests must be signed by Contractor and must include the following certification:
“The undersigned Contractor certifies under penalty of perjury that its statements and representations in this Change Order request are true and correct. Contractor warrants that this Change Order request is comprehensive and complete as to the Work or changes referenced herein, and agrees that any known or foreseeable costs, expenses, or time extension requests not included herein, are deemed waived.”
6.3 Adjustments to Contract Price. The amount of any increase or decrease in the Contract Price will be determined based on one of the following methods listed below, in the order listed with unit pricing taking precedence over the other methods. Markup applies only to City-authorized time and material Work, and does not apply to any other payments to Contractor. For Work items or components that are deleted in their entirety, Contractor will only be entitled to compensation for those direct, actual, and documented costs (including restocking fees), reasonably incurred before Contractor was notified of the City’s intent to delete the Work, with no markup for overhead, profit, or other indirect costs.
(A) Unit Pricing. Amounts previously provided by Contractor in the form of unit prices, either in a Proposal schedule or in a post-award schedule of values pursuant to Section 8.1, Schedule of Values, will apply to determine the price for the affected Work, to the extent applicable unit prices have been provided for that type of Work. No additional markup for overhead, profit, or other indirect costs will be added to the calculation.
(B) Lump Sum. A mutually agreed upon, all-inclusive lump sum price for the affected Work with no additional markup for overhead, profit, or other indirect costs.
(C) Time and Materials. On a time and materials basis, if and only to the extent compensation on a time and materials basis is expressly authorized by City in advance of Contractor’s performance of the Work and subject to any not-to-exceed limit. Time and materials compensation will include allowed markup for overhead, profit, and other indirect costs as follows:
(1) All direct labor costs provided by the Contractor, excluding superintendence, project management, or administrative costs, plus 15% markup;
(2) All direct material costs provided by the Contractor, plus 15% markup (except markup will not be applied to the sales tax component of direct material costs);
(3) All direct plant and equipment rental costs provided by the Contractor, plus 15% markup; and
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 34
(4) All direct labor, materials, and equipment costs provided by Subcontractors plus markup on those costs not to exceed 10% of the cumulative total of those dir
ect costs.
(
5) Increased bond and insurance premium costs are deemed included in the abov
e markups.
6. 4 Limitations on Allowable Costs. Allowable costs in connection with City-authorized time and materials Work or as otherwise authorized by the Contract Documents are subject to the following:
(A) La
bor. Costs are allowed for labor, including forepersons when authorized by City, used in the actual and direct performance of the Work directed by Change Order, excluding superintendence, project management, and administrative costs. Allowable labor
costs include (1) the actual and direct payroll costs to Contractor, consisting of actual wages and any employer payments to, or on behalf of, workers (other than actual wages
) for health and welfare, pension, vacation, training, or other State- or federal- recognized fringe benefit payments, and (2) the labor surcharge percentage, in effect during performance of the Work, as set forth in the publication titled Califor nia
Depar
tment of Transportation Labor Surcharge and Equipment Rental Rates, which is intended to cover worker's compensation insurance, social security, Medicare, federal unem
ployment insurance, State unemployment insurance, and State training taxes. (B) M
aterials. Costs are allowed for the actual cost to Contractor for materials directly required for performance of the Work directed by Change Order. The cost of materials may include the costs of transportation, sales tax, and delivery, if necessarily incurred. If a cash or trade discount by the supplier of the materials is available t o
Cont
ractor, it will be credited to City, regardless of whether the discount is actually taken.
I
f the materials are obtained from a supply or source owned wholly or in part by Contractor, payment therefor will not exceed the current wholesale price for such m
aterials. Costs for consumed materials may be charged on a reasonably estimated bas
is but may not be a percentage of labor. If, in the opinion of City, the cost of materials is excessive, or if Contractor fails to furnish satisfactory evidence of the cost from the s
upplier thereof, then the cost of the materials will be deemed to be the lowest wholesale pr
ice at which similar materials are available in the quantities required and at the time needed.
City reserves the right to furnish materials, and Contractor will have no claim for costs or profits on City-furnished material. If materials are salvaged upon completion, the s
alvage value will be deducted from the cost of materials. (
C) Equipment. Costs are allowed for the actual cost to Contractor for the use of equipment directly required in the performance of the Work directed by Change Order.
For Contractor- or Subcontractor-owned equipment, costs will be allowed based on rent al
r
ates listed for equipment in the California Department of Transportation’s Labor Surcharge and Equipment Rental Rates publication in effect at the time the Work is performed, unless there is no applicable rate for an item of equipment, in which case cost will be based on the rental rate listed in the most recent edition of the Association of Equipment Distributors (“AED”) book. For rented equipment, costs will be allowed bas ed
on ac
tual rental invoices. The equipment used for Work in a Change Order must be of proper size and type. If equipment of an unwarranted size or type is used, the allowable co
sts for use of such equipment will be calculated at the rental rate for equipment of a pr
oper size and type, as determined by City. The rental rates to be paid to Contractor shall constitute full compensation to Contractor for the cost of fuel, power, oil, lubrication, supplies, small tools, small equipment, necessary attachments, repairs and maintenance of
any kind, depreciation, storage, insurance, and any and all costs to Contractor incidental to the use of such equipment. Unless otherwise specified, manufacturer’s ratings, and manufacturer-approved modifications, shall be used to classify equipment for Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 35
determination of applicable rental rates. Individual pieces of equipment having a replacement value of $500 or less will be considered to be small tools or small equipment, and no payment therefor will be made unless it has been rented specifically for the Work directed by Change Order. No payment will be made for time while equipment is inoperative due to breakdowns or for non-Work days. (1) F
or equipment at the Project site, rental time to be paid for equipment shall be t
ime equipment is in operation on Work being performed or on standby as approved by City. The following shall be used in computing rental time of equipment: (a) When hourly rates are listed, less than 30 minutes of operat ion
s
hall be considered to be ½ hour of operation; (b) When daily rates are listed, less than four hours of operation shall be considered to be ½ day of operation. (
2) F
or equipment that must be brought to the Project site to be used ex
clusively on Work directed by Change Order, the rental time may include the t
ime required to move the equipment to the Project site from the nearest available source for rental of such equipment, and to return it to the source, as follows: (a) Costs of loading and unloading equipment are allowable; (2) Cost of transporting equipment in low bed trailers shall not exceed hourly rates charged by
established haulers; (c) Cost of transporting equipment shall not exceed applic
able minimum established rates of California Public Utilities Commission; and (
d) City will not make any payment for transporting and loading and unloadi
ng equipment if equipment is used on Work in any other way than on W
ork directed by Change Order.
(3)
Rental period may begin at time equipment is unloaded at Project site and t
erminate at end of the performance of the Work directed by Change Order or day on which City directs Contractor to discontinue use of equipment, whichever occurs first. Rental time to be paid per working day shall be four hours for zero hour
s of operation, six hours for four hours of operation, and eight hours for eight hours of operation, time being prorated between these parameters. Hours to be paid f
or equipment that is operated less than eight hours due to breakdowns, shall not exceed eight less the number of hours equipment is inoperative due to br
eakdowns.
(
D) Specialists. If Work in a Change Order requires the services of a specialist, as determined by City, costs will be allowed for the services of the specialist based on the ac
tual itemized invoice to Contractor for the specialist’s services required in the per
formance of the Work, after deduction of any cash or trade discount available to Cont
ractor, regardless of whether such discount is actually taken. If it is impracticable and not
in accordance with established practice of the specialist’s industry to provide a c
omplete itemization of its services, then costs will be allowed based on the current market price rate for such services. If the Work in a Change Order requires a fabrication or
machining process in a fabrication or machine shop facility off-site, the cost of such off- site Work may be included in allowable costs, if City is notified in writing in advance and appr
oves such costs.
(E) M
arkup. The following non-exclusive list identifies items that are deemed inc
luded in markup for overhead, profit, and other indirect costs, whether incurred by Contractor, Subcontractors, or suppliers, and Contractor shall not invoice or receive pay
ment for these costs separately:
(
D) Drawings and submissions of drawings, including field drawings, Shop Drawings, and sketches;
(E) Employee vehicle and gas expenses;
(F) Estimating;
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 36
(G) Final cleanup;
(H) General administration and preparation of cost proposals, schedule analyses, Change Order requests, and other supporting documentation as necessary; (I) General superintendence;
(J) Handling and disposal fees;
(K) Home office expenses;
(L) Parking expenses of any field labor, foreman, office personnel, and s
uperintendents;
(M) Procurement and use of vehicles and fuel used in Work; (N) Routine field inspection of Work;
(O) Salaries of project management personnel, superintendent, timekeeper, storekeeper, administrative assistants, and secretaries; (P) Small tools and equipment valued at less than $500; (Q) Insurance and bond premiums and costs;
(R) Temporary on-site facilities , including, but not limited to, electrical (power, lighting), fencing, offices, platforms, plumbing, telephones, internet, and water; (S) T ravel expenses; and
(T) O ther incidental Work.
6.5 Un
ilateral Change Order. If the parties dispute the terms of a proposed Change Order, including disputes over the amount of compensation or extension of time that Contractor has requested, the value of deleted or changed Work, what constitutes Extra Work, or quantities used, City may elect to issue a unilateral Change Order, directing performance of the Work, and authorizing a change in the Contract Price or Contract Time for the adjustment to compensation or time that the City believes is merited. Contractor’s sole recourse to dispute the terms of a unilateral Change Order is to submit a timely Claim pursuant to Article 12, below.
6.6 No
n-Compliance Deemed Waiver. Contractor waives its entitlement to any increase in the Contract Price or Contract Time if Contractor fails to fully comply with the provisions of this Article. Contractor will not be paid for unauthorized Extra Work.
Art
icle 7 - General Construction Provisions
7.1 Permits, Fees, Business License, and Taxes.
(A) P
ermits, Fees, and City Business License. Contractor must obtain and pay for all permits, fees, and licenses required to perform the Work, including a City business license. Contractor must cooperate with and provide notifications to all government agencies with jurisdiction over the Project, as may be required. Contractor must provide Cit
y with copies of all records of permits and permit applications, payment of required f
ees, and any licenses required for the Work. Contractor must comply with all permit requirements and conduct all necessary permit coordination activities. Contractor will be r
esponsible, at its sole cost, for any fines, costs, damages, or other liabilities incurred by City resulting from violations or threatened violations of permit requirements or other legal or
regulatory requirements, or from City’s loss of use of any permit, due to Contractor’s activities.
(B) T
axes. Contractor must pay for all taxes on labor, material, and equipment, except Federal Excise Tax to the extent that City is exempt from Federal Excise Tax.
7. 2 Temporary Facilities. Contractor must provide, at Contractor’s sole expense, any and all temporary facilities for the Project. The location of all temporary facilities must be approved by the City prior to installation. Temporary facilities must be safe and adequate for the intended use and installed and maintained in accordance with Laws and the
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 37
Contract Documents. Additional provisions pertaining to temporary facilities may be included in the Specifications or Special Conditions.
(A) Facilities Based on Project Site.
(1) Project with a Defined Fence Perimeter. For a Project with a defined fence perimeter, Contractor must provide any and all temporary facilities, including, but not limited to, an onsite staging area for materials and equipment, a field office, sanitary facilities, utilities, storage, scaffolds, barricades, walkways, elevators and hoists, cranes, and any other temporary structure or facility necessary to safely perform the Work. Unless otherwise directed by City, Contractor will fence and screen the Project site and, if applicable, any separate Worksites, including the staging area, and its operation must minimize inconvenience to neighboring properties.
(2) Project within Public Right-of-Way. For a Project within the public right-of- way, Contractor must provide any and all temporary facilities, including, but not limited to, sanitary facilities, barricades, walkways, ramps, project signs, changeable message boards, and any other temporary structure or facility necessary to provide access to the public and to safely perform the Work.
(A) Utilities. Contractor must install and maintain, at Contractor’s sole expense, the power, water, sewer, and all other utilities required for the Project site, including the piping, wiring, internet and Wi-Fi connections, and any related equipment necessary to maintain the temporary facilities. Contractor is responsible for the cost of utility services necessary to perform the Work.
(C) Removal and Repair. Contractor must promptly remove all such temporary facilities when they are no longer needed or upon completion of the Work, whichever comes first. Contractor must promptly repair any damage to City’s property or to other property caused by the installation, use, or removal of the temporary facilities, and must promptly restore the property to its original or intended condition.
7.3 Noninterference and Site Management. Contractor must avoid interfering with City’s use of its property at or adjacent to the Project site, including use of roadways, entrances, parking areas, walkways, and structures. Contractor must perform the Work in a manner that does not interrupt or otherwise adversely impact any City operations, including the City’s franchise hauler for solid waste. Contractor must also minimize disruption of access to private property in the Project vicinity. Contractor must coordinate with affected property owners, tenants, and businesses, and maintain some vehicle and pedestrian access to their residences or properties at all times. Temporary access ramps, fencing or other measures must be provided as needed. Before blocking access to a private driveway or parking lot, Contractor must provide effective notice to the affected parties at least 48 hours in advance of the pending closure and allow them to remove vehicles.
Private driveways, residences and parking lots must have access to a roadway during non-Work hours.
(A) Offsite Acquisition. Unless otherwise provided by City, Contractor must acquire, use and dispose of, at its sole expense, any Worksites, licenses, easements, and temporary facilities necessary to access and perform the Work.
(B) Offsite Staging Area and Field Office. If additional space beyond the Project site is needed, such as for the staging area or the field office, Contractor may need to make arrangements with the nearby property owner(s) to secure the space. Before using or occupying any property owned by a third party, Contractor must provide City with a copy of the necessary license agreement, easement, or other written authorization from
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 38
the property owner, together with a written release from the property owner holding City harmless from any related liability, in a form acceptable to the City Attorney.
(C) Traffic Management. Contractor must provide traffic management and traffic controls as specified in the Contract Documents, as required by Laws, and as otherwise required to ensure public and worker safety, and to avoid interference with public or private operations or the normal flow of vehicular, bicycle, or pedestrian traffic.
(D) Circularizing Businesses and Residences. At least 48 hours in advance of any Work that may affect businesses or residents, Contractor must notify, by circular, all businesses and residents with street frontage or property that may be affected by the Work. The circular must include Contractor’s name, address, and telephone number; the starting time and date of the Work; the nature and extent of the Work; and the approximate date upon which Contractor expects to complete the Work. The circular must be submitted to the Engineer for approval at least two full Working Days in advance of the proposed distribution date.
7.4 Signs. No signs may be displayed on or about City’s property, except signage which is required by Laws or by the Contract Documents, without City’s prior written approval as to size, design, and location.
7.5 Project Site and Nearby Property Protections.
(A) General. Contractor is responsible at all times, on a 24-hour basis and at its sole cost, for protecting the Work, the Project site, and the materials and equipment to be incorporated into the Work, until the City has accepted the Project, excluding any exceptions to acceptance, if any. Except as specifically authorized by City, Contractor must confine its operations to the area of the Project site indicated in the Plans and Specifications. Contractor is liable for any damage caused by Contractor or its Subcontractors to the Work, City’s property, the property of adjacent or nearby property owners and the work or personal property of other contractors working for City, including damage related to Contractor’s failure to adequately secure the Work or any Worksite.
(1) Subject to City’s approval, Contractor shall provide and install safeguards, including, but not limited to, security fencing, barricades, lighting, and any other security measures necessary to protect the Work; any Worksite, including the Project site; City’s real or personal property and the real or personal property of adjacent or nearby property owners, including plant and tree protections. If instructed by the Engineer, Contractor must, at a minimum, install a temporary chain-link fence with locking gate surrounding the Project site and maintain a lock on the access gate at all times.
(2) City wastewater systems may not be interrupted. If the Work disrupts existing sewer facilities, Contractor must immediately notify City and establish a plan, subject to City’s approval, to convey the sewage in closed conduits back into the sanitary sewer system. Sewage must not be permitted to flow in trenches or be covered by backfill.
(3) Contractor must remove with due care, and store at City’s request, any objects or material from the Project site that City will salvage or reuse at another location. Any such objects or material must be delivered by Contractor in good condition to City’s Street Corporation Yard at 1700 Walsh Avenue, Santa Clara, CA 95050 or, for an SVP Project, 1705 Martin Avenue, Santa Clara, CA 95050.
(4) If directed by Engineer, Contractor must remedy all damage, injury, loss or interruptions as specified by the Engineer. However, acting in its sole discretion, Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 39
City may elect to have the damage, injury, loss or interruptions remedied otherwise, and may deduct the cost from payment otherwise due to Contractor. (5)
Contractor will not permit any structure, pavement, or infrastructure to be loaded in a m
anner that will damage or endanger the integrity of the structure, pav
ement, or infrastructure.
(
6) Cont
ractor will not make any arrangements with any person to permit occupancy or use of any land, structure, or building at the Project site, for any purpose other than performance of the Work, unless specifically required or authorized by the Contract Documents.
(
7) A
ll fire hydrants and water control valves must be kept free from obstruction and av
ailable for use at all times.
(
8) Cont
ractor must shield all welding operations from public view with solid b
arrier(s).
(
9) Cont
ractor must provide protective measures to adequately protect workers and the public from hazards resulting from the Work and to exclude unauthorized per
sons from the Work.
(
10) No at
tempt has been made by City to locate private utilities on private pr
operty such as irrigation systems or electrical conduits. (B) P
roject Site Access and Securing Project Site. Contractor and Subcontractor personnel may not occupy or use the Project site for any purpose during non-Work hours, except as may be provided in the Contract Documents or pursuant to prior written aut
horization from City.
(1) P
roject with a Defined Fence Perimeter. If the Project has a defined fence per
imeter, Contractor must at all times limit access to the Project site to nec
essary personnel only. All personnel associated with construction of the P
roject must enter the site through Contractor’s access gate, at the location indic
ated on the Plans. Access for construction personnel will be limited to the hour
s set forth in Section 5.2(H) or as otherwise specified by City. All mail and deliv
eries must be sent to a separate address (at Contractor’s gate), specifically arranged by Contractor for the Project. Contractor is responsible for providing adequat
e signage to alert delivery persons to the new address. (2) P
roject within Public Right-of-Way. If the Project is within the public right-of- way, after completion of Work each day, Contractor must secure the Project site and, to the extent feasible, make the area reasonably accessible to the public unless City approves otherwise. All excess materials and equipment not protected by approved traffic control devices must be relocated to the st aging
ar
ea or demobilized. Trench spoils must be hauled off the Project site daily and open ex
cavations must be protected with steel plates.
(
C) Unforeseen Conditions. If Contractor encounters facilities, utilities, or other unknown conditions not shown on or reasonably inferable from the Plans or apparent from inspection of the Project site, Contractor must immediately notify the City and pr
omptly submit a Request for Information to obtain further directions from the Engineer.
Contractor must avoid taking any action which could cause damage to the facilities or utilities pending further direction from the Engineer. The Engineer’s written response will be f
inal and binding on Contractor. If the Engineer’s subsequent direction to Contractor
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 40
affects Contractor’s cost or time to perform the Work, Contractor may submit a Change Order request as set forth in Article 6 above.
(D) Support and Protection. Contractor shall be responsible for determining where sloping, shoring, bracing, and/or underpinning is necessary and the adequacy of the design, installation, and maintenance of all sloping, shoring, bracing, and/or underpinning for all excavations, including any excavation less than five feet in depth. Contractor must provide, install, and maintain all such sloping, shoring, bracing, and underpinning. The sloping, shoring, bracing, and underpinning must be sufficient to provide support to City’s property and adjacent properties and improvements thereon and protect the Work, adjacent property and improvements, workers, and the public from accidents, injuries, or damage. Contractor shall be solely responsible for any damage or injuries that may result from excavating or trenching. City’s acceptance of any drawings showing the shoring or bracing design or schedule shall not relieve Contractor of its responsibilities under this Section. Contractor must also protect the Work with lights, guardrails, temporary covers, and barricades. Contractor must enclose excavations with proper barricades. Contractor must brace and secure all parts of the Work against storm and accident. Contractor must also provide additional forms of protection as may be necessary under the circumstances. Contractor must provide notifications to adjacent property owners as may be required by Laws. See also, Section 7.15, Trenching of Five Feet or More.
(E) Notification of Property Damage. Contractor must immediately notify the City of damage to any real or personal property resulting from Work on the Project. Contractor must immediately provide a written report to City of any such property damage in excess of $500 (based on estimated cost to repair or replace) within 24 hours of the occurrence.
The written report must include: (1) the location and nature of the damage, and the owner of the property, if known; (2) the name and address of each employee of Contractor or any Subcontractor involved in the damage; (3) a detailed description of the incident, including precise location, time, and names and contact information for known witnesses; and (4) a police or first responder report, if applicable. If Contractor is required to file an accident report with another government agency, Contractor shall provide a copy of the report to City.
7.6 Materials and Equipment.
(A) General. Unless otherwise specified, all materials and equipment required for the Work must be new, free from defects, and of the best grade for the intended purpose, and furnished in sufficient quantities to ensure the proper and expeditious performance of the Work. Contractor must employ measures to preserve the specified quality and fitness of the materials and equipment. Unless otherwise specified, all materials and equipment required for the Work are deemed to include all components required for complete installation and intended operation and must be installed in accordance with the manufacturer’s recommendations or instructions. Contractor is responsible for all shipping, handling, and storage costs associated with the materials and equipment required for the Work. Contractor is responsible for providing security and protecting the Work and all of the required materials, supplies, tools and equipment at Contractor’s sole cost until City has formally accepted the Project as set forth in Section 11.1, Final Completion. Contractor will not assign, sell, mortgage, or hypothecate any materials or equipment for the Project, or remove any materials or equipment that have been installed or delivered.
(B) City-Provided. If the Work includes installation of materials or equipment to be provided by City, Contractor is solely responsible for the proper examination, handling, storage, and installation in accordance with the Contract Documents. Contractor must notify City of any defects discovered in City-provided materials or equipment, sufficiently in advance of scheduled use or installation to afford adequate time to procure Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 41
replacement materials or equipment as needed. Contractor is solely responsible for any loss of or damage to such items which occurs while the items are in Contractor’s custody and control, the cost of which may be offset from the Contract Price and deducted from any payment(s) due to Contractor.
(C) I
ntellectual Property Rights. Contractor must, at its sole expense, obtain any authorization or license required for use of patented or copyright-protected materials, equipment, devices, or processes that are incorporated into the Work. Contractor’s indemnity obligations in Article 4 apply to any claimed violation of intellectual property rights.
(
D) Standards To Apply Where Specifications Are Not Furnished. The following gener
al specifications will apply wherever in the Specifications, or in any directions given by
City in accordance with or supplementing Specifications, it is provided that Contractor shall furnish materials or manufactured articles or will do Work for which no detailed s
pecifications are provided. Materials or manufactured articles will be of the best grade, in quality and workmanship, obtainable in the market from firms of established good r
eputation. If not ordinarily carried in stock, the materials or manufactured articles must conform to industry standards for first-class materials or articles of the kind required, with due consideration of the use to which they are to be put. Work will conform to the usual s
tandards or codes for first-class work of the kind required. Contractor shall specify in wr
iting to City the materials to be used or Work to be performed under this Section 7.6 ten Working Days prior to furnishing such materials or performing such Work.
7. 7 Substitutions.
(A) “
Or Equal.” Any Specification designating a material, product, or thing (collectively, “item”) or service by specific brand or trade name, followed by the words “or equal,” is intended only to indicate the quality and type of item or service desired, and Cont
ractor may request use of any equal item or service. Unless otherwise stated in the S
pecifications, any reference to a specific brand or trade name for an item or service that is used solely for the purpose of describing the type of item or service desired, will be deem
ed to be followed by the words “or equal.” A substitution will only be approved if it is a true “equal” item or service in every aspect of design, function, and quality, as determined by City, including dimensions, weight, maintenance requirements, durability, fit with other elements, and schedule impacts.
(B) R
equest for Substitution. A post-award request for substitution of an item or service must be submitted in writing to the Engineer for approval in advance, within the applic
able time period provided in the Contract Documents. If no time period is specified, the substitution request may be submitted any time within 35 days after the date of award of
the Contract, or sufficiently in advance of the time needed to avoid delay of the Work, whichever is earlier. A separate request for substitution must be submitted for each item or service proposed for substitution. Contractor must submit a digital copy of eac h
r
equest.
(
C) Substantiation. Contractor must substantiate each written request for substitution with the following: (1) product identification, (2) manufacturer’s literature, (3) test results or samples, if applicable, (4) name and address of similar projects on which t
he item has been used and the date of installation, (5) the name, address, and telephone num
ber of manufacturer’s representative or sales engineer, (6) a detailed description of the proposed construction method and drawings illustrating the construction method, (7) an item
ized comparison of the proposed substitution with the product specified that lists all variations, including, but not limited to, dimensions, weights, service requirements, and f
unctional differences, (8) available maintenance, repair, and replacement service for the pr
oposed item, (9) any required approvals or other information for the proposed
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 42
substitute that are necessary for compliance with regulatory agency requirements, (10) any schedule impacts associated with use of the proposed substitute, and (11) any other available data substantiating the proposed substitute as an equal item or service.
Contractor must also state whether the substitute will require any changes to the Contract Documents, or any other separate contract the Contractor may have with the City, and whether use of the proposed substitute requires the payment of any license fee or royalty. Contractor’s failure to timely provide all necessary substantiation, including any required test results as soon as they are available, is grounds for rejection of the proposed substitution, without further review. If a variation from the product specified is not identified in the submittal, the variation may be rejected by City even if the submittal was favorably reviewed.
(D) Burden of Proving Equality. Contractor has the burden of proving the equality of the proposed substitution at Contractor’s sole cost. City has sole discretion to determine whether a proposed substitution is equal, and City’s determination is final.
(E) Approval or Rejection. If the proposed substitution is approved, Contractor is solely responsible for any additional costs or time associated with the substituted item or service. If the proposed substitution is rejected, Contractor must, without delay, install the item or use the service as specified by City.
(F) Contractor’s Obligations. City’s approval of a proposed substitution will not relieve Contractor from any of its obligations under the Contract Documents. If an approved substitution requires any redesign, Contractor must reimburse City for any associated redesign costs. Such costs may be deducted from payments otherwise due Contractor. In the event Contractor makes an unauthorized substitution, Contractor shall be solely responsible for all resulting cost impacts, including the cost of removal and replacement and the impact to other design elements.
7.8 Testing and Inspection.
(A) General. All materials, equipment, and workmanship used in the Work are subject to inspection and testing by City at all times and at all locations during construction and/or fabrication, including at any Worksite, shops, and yards. All manufacturers’ application or installation instructions must be provided to the Inspector at least ten days prior to the first such application or installation. Contractor must, at all times, make the Work available for testing or inspection and must provide, at its sole cost, all information and assistance as required by City, including information and assistance from Subcontractors, fabricators, material suppliers and manufacturers, to perform the testing or inspection. Contractor must provide incidental labor and facilities to provide safe access to Work for testing and inspection, to obtain and handle samples at the Project site or at the source of the products to be tested, and to store and cure test samples. Neither City’s inspection or testing of Work, nor its failure to do so, operate to waive or limit Contractor’s duty to complete the Work in accordance with the Contract Documents.
(B) Scheduling and Notification. Contractor must cooperate with City in coordinating the inspections and testing. At least fifteen days in advance of a first test or inspection of each type, Contractor must submit a schedule of tests or inspections to City, indicating the types of tests or inspections and their scheduled dates. Contractor must deliver adequate samples of materials, proposed mix designs, and/or test specimens to a laboratory or location designated by City, at Contractor’s expense, and schedule all tests required by the Contract Documents in time to avoid any delay to the progress of the Work. Contractor must also notify the Engineer at least three full Working Days before any inspection or testing and must provide timely notice to the other necessary parties as specified in the Contract Documents. If Contractor schedules an inspection or test
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 43
beyond regular Work hours, or on a Saturday, Sunday, or recognized City holiday, Contractor must notify the Engineer at least three Working Days in advance for approval.
If approved, Contractor must reimburse City for the cost of the overtime inspection or testing. Such costs, including the City’s hourly costs for required personnel, may be deducted from payments otherwise due to Contractor.
(C) Responsibility for Costs. City will bear the initial cost of inspection and testing to be performed by City staff or independent inspection and testing consultants retained by City, subject to the following exceptions:
(1) Contractor shall be responsible for the costs of any subsequent inspections or tests which are required to substantiate compliance with the Contract Documents, and any associated remediation costs.
(2) Contractor shall be responsible for inspection costs, at City’s hourly rates, for inspection time lost because the Work is not ready, or Contractor fails to appear for a scheduled inspection.
(3) If any portion of the Work that is subject to inspection or testing is covered or concealed by Contractor prior to the inspection or testing, Contractor shall bear the cost of making that portion of the Work available for the inspection or testing required by the Contract Documents, and any associated repair or remediation costs.
(4) Contractor is responsible for properly shoring all compaction test sites deeper than five feet below grade, as required under Section 7.15 below.
(5) Any Work or material that is defective or fails to comply with the requirements of the Contract Documents must be promptly repaired, removed, replaced, or corrected by Contractor, at Contractor’s sole expense, even if that Work or material was previously inspected or included in a progress payment.
(6) Contractor is responsible for testing and inspection costs due to the following: changes in source or supplier of materials or products after original testing and inspection; changes in means, methods, techniques, sequences and procedures of construction that necessitate additional testing and inspection; and changes in mix designs after review and acceptance of submitted mix designs.
(D) Contractor’s Obligations. Contractor is solely responsible for any delay occasioned by remediation of defective or noncompliant Work or material. Inspection or testing of the Work by City does not in any way relieve Contractor of its obligations to perform the Work as specified. Contractor has an independent duty to test and inspect its Work to ensure that it is safe, complies with the requirements of the Contract Documents, and that it is in proper condition to accommodate or interface with subsequent Work. Any Work done without the inspection(s) or testing required by the Contract Documents will be subject to rejection by City.
(E) Distant Locations. If required off-site testing or inspection must be conducted at a location more than 50 miles from the Project site, Contractor is solely responsible for the additional travel costs required for testing and/or inspection at such locations.
(F) Final Inspection. The provisions of this Section 7.8 also apply to final inspection under Article 11, Completion and Warranty Provisions.
(G) Governing Authorities and Other Public Agencies. If any governing authorities or other public agencies with jurisdiction over the Work, or a portion thereof,
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 44
require any inspection, testing, or approval of the Work, or a portion thereof, Contractor must schedule, conduct, and pay for any such inspection or testing and obtain any required approvals. These governing authorities and agencies may include, but are not limited to, City’s Building Department, Public Works Department, and Fire Department, the Office of Statewide Health Planning Department (OSHPD), and other similar agencies. Contractor must submit any such certificates of inspection or testing or approvals to the City.
(H) Inspections and Tests by Serving Utilities. Contractor must schedule, conduct, and pay for all tests and inspections required by serving utilities for the Work.
(A) Inspections and Tests by Manufacturer’s Representatives. Contractor must, at its sole cost, schedule, coordinate, and ensure the performance of all tests and inspections specified to be conducted by materials or systems manufacturers, including those required by materials or systems manufacturers as a condition of warranty or certification Work.
7.9 Project Site Conditions and Maintenance. Contractor must at all times, on a 24-hour basis and at its sole cost, maintain the Project site and staging and storage areas in clean, neat, and sanitary condition and in compliance with all Laws pertaining to safety, air quality, and dust control. Adequate toilets must be provided, and properly maintained and serviced for all workers on the Project site, located in a suitably secluded area, subject to City’s prior approval. If toilets of the chemically treated type are used, Contractor must furnish at least one toilet for each 20 persons. Contractor shall enforce the use of such sanitary facilities by all personnel at the Project site. Contractor must also, on a daily basis and at its sole cost, remove and properly dispose of the debris and waste materials from the Project site.
(A) Air Emissions Control. Contractor must not discharge smoke or other air contaminants into the atmosphere in violation of any Laws. Contractor must comply with all Laws, including the California Air Resources Board’s In-Use Off-Road Diesel-Fueled Fleets Regulation (13 CCR § 2449 et seq.).
(B) Dust and Debris. Contractor must minimize and confine dust and debris resulting from the Work. Contractor must protect buildings and operating facilities from dust and must use suitable dust screens to protect existing and new machinery, motors, instrument panels, or similar equipment from dust. Contractor must include proper ventilation with dust screens. Contractor must abate dust nuisance by cleaning, sweeping, and immediately sprinkling with water excavated areas of dirt or other materials prone to cause dust, and within one hour after the Engineer notifies Contractor that an airborne nuisance exists. The Engineer may direct that Contractor provide an approved water-spraying truck for this purpose. If water is used for dust control, Contractor shall only use the minimum necessary. Contractor must take all necessary steps to keep waste water out of streets, gutters, or storm drains. See Section 7.19, Environmental Control. If City determines that the dust control is not adequate, City may have the work done by others and deduct the cost from the Contract Price. Contractor shall immediately remove any excess excavated material from the Project site and any dirt deposited on public streets. (See also Document 01 50 00 of the General Requirements.)
(C) Hazards Control. Contractor must prevent the accumulation of wastes that may create hazardous conditions. Contractor must store volatile waste in covered metal containers and remove such waste from the premises daily. Contractor must provide adequate ventilation during the use of volatile or noxious substances.
Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 45
(D) Clean up. Before discontinuing Work in an area, Contractor must clean the area and remove all debris and waste along with the construction equipment, tools, machinery, and surplus materials.
(1) Except as otherwise specified, all excess Project materials, and the materials removed from existing improvements on the Project site with no salvage value or intended reuse by City, will be Contractor’s property.
(2) Hauling trucks and other vehicles leaving the Project site must be cleaned of exterior mud or dirt before traveling on City streets. Materials and loose debris must be delivered and loaded to prevent dropping materials or debris. Contractor must immediately remove spillage from hauling on any publicly traveled way.
Streets affected by Work on the Project must be kept clean by street sweeping.
(3) Contractor shall also, on a daily basis, remove any dust, debris, mud, fill, and spoils from private property, unless the private property owner has requested otherwise in writing.
(E) Disposal. Contractor must dispose of all Project debris and waste materials in a safe and legal manner. Contractor may not burn or bury waste materials on the Project site. Contractor will not allow any dirt, refuse, excavated material, surplus concrete or mortar, or any associated washings, to be disposed of onto streets, into manholes or into the storm drain system. All excess soil from performance of Work shall be disposed at a Class I, II, or III landfill at sites to be chosen by Contractor in accordance with Laws.
Contractor must review and comply with any such regulations and requirements of the agency having jurisdiction over any contemplated disposal site, as applicable. Contractor shall recycle all debris and waste materials with feasible re-use including concrete, asphalt concrete, pavement base materials, steel, and wood. A Project that includes 5,000 square feet or more of building construction, demolition or renovation shall comply with the City of Santa Clara Construction and Demolition Debris Recycling Program per Santa Clara Code Section 8.25.285.
(F) Completion. At the completion of the Work, Contractor must remove from the Project site all of its equipment, tools, surplus materials, waste materials and debris, presenting a clean and neat appearance. Before demobilizing from the Project site, Contractor must ensure that all surfaces are cleaned, sealed, waxed, or finished as applicable, and that all marks, stains, paint splatters, and the like have been properly removed from the completed Work and the surrounding areas. Contractor must clean or replace the filters of any mechanical equipment operated during construction and clean the ducts, blowers, and coils of mechanical equipment operated without filters during construction. Contractor must also mechanically sweep paved areas. Contractor must ensure that all parts of the construction are properly joined with the previously existing and adjacent improvements and conditions. Contractor must provide all cutting, fitting and patching needed to accomplish that requirement. Contractor must also repair or replace all existing improvements that are damaged or removed during the Work, both on and off the Project site, including curbs, sidewalks, driveways, fences, signs, utilities, utility poles, guy wires, underground pipes, conduits, drains, street surfaces, structures, and landscaping (sod, groundcover, shrubs, trees, and the like). Repairs and replacements must be at least equal to the previously existing improvements, and the condition, finish and dimensions must match the previously existing improvements. All replacements must be made with new materials. Contractor must restore to original condition all property or items that are not designated for alteration under the Contract Documents and leave each Worksite clean and ready for occupancy or use by City.
(G) Non-Compliance. If Contractor fails to comply with its maintenance and cleanup obligations or any City clean up order, City may, acting in its sole discretion, elect to Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 46
suspend the Work until the condition(s) is corrected with no increase in the Contract Time or Contract Price, or undertake appropriate cleanup measures without further notice and deduct the cost from any amounts due or to become due to Contractor.
7. 10 Instructions and Manuals. Contractor must provide to City three hard copies and a digital copy of each instruction and manual required by the Contract Documents, unless otherwise specified. These must be complete as to drawings, details, parts lists, performance data, and other information that may be required for City to easily maintain and service the materials and equipment installed for this Project. (A) S
ubmittal Requirements. The instructions and manuals, along with any required guarantees, must be delivered to City for review prior to requesting final ins
pection pursuant to Section 11.1(A), unless otherwise specified. (B) Tr
aining. Contractor or its Subcontractors must train City’s personnel in the oper
ation and maintenance of any complex equipment or systems as a condition pr
ecedent to Final Completion, if required in the Contract Documents.
7. 11 As-built Drawings. Contractor and its Subcontractors must prepare and maintain at the Project site a detailed, complete and accurate as-built set of the Plans which will be used solely for the purpose of recording changes made in any portion of the original Plans in order to create accurate record drawings at the end of the Project. (A) Du
ty to Update. The as-built drawings must be updated as changes occur, on a daily basis if necessary. City may withhold the estimated cost for City to have the as-built drawings prepared from payments otherwise due to Contractor, until the as-built drawings are brought up to date to the satisfaction of City. Actual locations to scale must be identified on the as-built drawings for all runs of mechanical and electrical work, including all s
ite utilities installed underground, in walls, floors, or otherwise concealed. Deviations from the original Plans must be shown in detail. The exact location of all main runs, whether piping, conduit, ductwork or drain lines, must be shown by dimension and elev
ation. The location of all buried pipelines, appurtenances, or other improvements must be represented by coordinates and by the horizontal distance from visible above- ground improvements.
(B) Fi
nal Completion. Contractor must verify that all changes in the Work are depic
ted in the as-built drawings and must deliver the complete set of as-built drawings to t
he Engineer for review and acceptance as a condition precedent to Final Completion and Final Payment.
7. 12 Existing Utilities and Facilities.
(A) G
eneral. The Work may be performed in developed, urban areas with existing ut
ilities, both above and below ground, including utilities identified in the Contract Documents or in other informational documents or records. Underground utilities are inher
ent in Work involving digging of trenches or other excavations and Contractor is to apply
its skill and industry to verify the information available. Contractor must take due c
are to locate identified or reasonably identifiable utilities before proceeding with t
renching, excavation, or any other activity that could damage or disrupt existing utilities.
This may include excavation with small equipment, potholing, or hand excavation, and, if practical, using white paint or other suitable markings to delineate the area to be ex
cavated. Except as otherwise provided herein, Contractor shall be responsible for costs resulting from damage to identified or reasonably identifiable utilities due to Cont
ractor’s negligence or failure to comply with the Contract Documents, including the r
equirements in this Article 7. Contractor shall take immediate action to restore any service installation damaged by Contractor’s operations. If City determines that Juliette Substation Expansion Project 2025 Form GENERAL CONDITIONS 2462 Page 47
Contractor has not responded to damaged service installations in a timely manner or has not diligently pursued restoration of damaged service installations, City may restore service installations and deduct the cost from payments otherwise due to Contractor. (B) U
nidentified Utilities. Pursuant to Government Code § 4215, if, during the performance of the Work, Contractor discovers utility facilities not identified by City in the Cont
ract Documents, Contractor must immediately provide written notice to City and the ut
ility. City assumes responsibility for the timely removal, relocation, or protection of existing main or trunkline utility facilities located on the Project site if those utilities are not identified in the Contract Documents. Contractor shall be compensated in accordance wit
h the provisions of the Contract Documents for the costs of locating, repairing damage not
due to Contractor’s failure to exercise reasonable care, and removing or relocating su
ch utility facilities not indicated in the Plans or Specifications with reasonable accuracy, and for equipment on the Project necessarily idled during such work. Contractor will not be assessed liquidated damages for delay in completion of the Work, to the extent the delay was caused by City’s failure to provide for removal or relocation of such utility facilities.
(
C) Service Laterals or Appurtenances. In accordance with Government Code § 4215
, nothing herein will be deemed to require City to indicate the presence of existing s
ervice laterals or appurtenances whenever the presence of such utilities on the Project site can be inferred by Contractor from the presence of an underground transmission m
ain or other visible facilities, such as buildings, new asphalt, meters and junction boxes, on or adjacent to the Project site.