Department / Division: Electric Utility Resolution: 26-9552 Date Approved: 4/21/2026 Description of Fee, Rate, or Charge Current Fee
Technology Fee
(3.37%) Applies
(Yes or No)
Charging Dept
/ Div
---------------
Collecting Dept
/ Div Comments Revised Fee Fee Change
Overhead Lines - New 1,417.00$ No Charged by: Date: 4/21/2026 Objective: Recover Cost Inflationary adjustment only. 1,417.00$ Single Family/Residential per lot Electric Utility Fees will be updated via per lot Res. No. 26-9552 Prop 26 Exception: 1, 2, 6 separate study.
Collected by:
Finance Full Cost: 1,417.14$
Overhead Lines - New 871.00$ No Charged by: Date: 4/21/2026 Objective: Recover Cost Inflationary adjustment only. 871.00$ Multiple Units per unit Electric Utility Fees will be updated via per unit Res. No. 26-9552 Prop 26 Exception: 1, 2, 6 separate study.
Collected by:
Finance Full Cost: 871.52$
Overhead Lines - New 8.00$ No Charged by: Date: 4/21/2026 Objective: Recover Cost Inflationary adjustment only. 8.00$ Street Lighting per front foot Electric Utility Fees will be updated via per front foot Res. No. 26-9552 Prop 26 Exception: 1, 2, 6 separate study.
Collected by:
Finance Full Cost: 8.78$
Underground - New 3,928.00$ No Charged by: Date: 4/21/2026 Objective: Recover Cost Inflationary adjustment only. 2,794.20$ Single Family/Residential per lot Electric Utility Fees will be updated via per lot Res. No. 26-9552 Prop 26 Exception: 1, 2, 6 separate study.
Collected by:
Finance Full Cost: 2,794.22$
Underground - New 3,338.00$ No Charged by: Date: 4/21/2026 Objective: Recover Cost Inflationary adjustment only. 2,375.05$ Multiple Units/Residential per unit Electric Utility Fees will be updated via per unit Res. No. 26-9552 Prop 26 Exception: 1, 2, 6 separate study.
Collected by:
Finance Full Cost: 2,375.09$
Underground - New 21.00$ No Charged by: Date: 4/21/2026 Objective: Recover Cost Inflationary adjustment only. 21.00$ Street Lighting per front foot Electric Utility Fees will be updated via per front foot Res. No. 26-9552 Prop 26 Exception: 1, 2, 6 separate study.
Collected by:
Finance Full Cost: 21.57$
Underground - Existing 4,104.00$ No Charged by: Date: 4/21/2026 Objective: Recover Cost Inflationary adjustment only. 4,104.00$ Single Family per lot Electric Utility Fees will be updated via per lot Res. No. 26-9552 Prop 26 Exception: 1, 2, 6 separate study.
Collected by:
Finance Full Cost: 4,104.49$
Date Fee Last
Changed
--------------
Ordinance /
Resolution Number
& Date
Fee Detail
Objective
Prop 26 Exception
(See Reader's Guide)
Full Cost Factor
CITY OF SANTA CLARA MUNICIPAL FEE SCHEDULE
Reference: CMD 109 7 - 1