SUBMITTED TO:

City of Santa Clarita
ATTN: Danielle Marquez
23920 Valencia Boulevard
Suite 120
Valencia, CA 91355

PROPOSAL
Saugus
Phase I:

Bouquet
Canyon Trail To
Central Park
PROPOSAL # ENG
-
21 -
22 -
C0066
SUBMITTED BY:

Michael Greer, PE, TE
Project Manager
1450 Frazee Road, Suite 100
San Diego, CA 92108
(858) 514-8377
[email protected]
SUBMITTED ON:

February 28, 2022

1450 Frazee Road, Suite 100, San Diego, CA 92108 ● Tele: 858.514.8377 ● Fax: 858.514.8608 ● www.dokkenengineering.com

DOKKEN ENGINEERING
Transportation Solutions from Concept to Construction
February 28, 2022
ATTN: Danielle Marquez
City of Santa Clarita - Purchasing Division
23920 Valencia Boulevard, Suite 120
Valencia, CA 91355

Subject: Proposal # ENG-21-22-C0066 – Saugus Phase I: Bouquet Canyon Trail to Central Park Ms. Marquez,
For the past 35 years, Dokken Engineering has provided “turn-key” solutions for our public works clients. We have enjoyed a long h istory of working with the City of Santa Clarita since 1990 to successfully design and construct multiple projects along local streets, state highways, and watercourses. Understanding the objectives of our clients while addressing the needs of property owners and stake holders has provided successful delivery of nearly 3,000 projects in our history.

Dokken Engineering has extensive exp erience working on Class I Bike Path and other bicycle facilities installation projects. In the past five yea rs, the Dokken Engineering T eam proposed for this proj ect has delivered over 100 miles of bicycle facility projects through construction. These designs have included Class I Bike Paths along rail lines, channels, and roadways, as well as Class II Buffered and UnBuffer ed Bike Lanes, Class III Bike Routes on Urban and Rural Roadways, and Class IV Protected Bikeways of various configurations with and without on-street parking.

The Dokken Team ’s delivery success and long history of completing projects and deliverables on schedule provides assurance t o the City of Santa Clarita and that we have the experience and capabilities to del iver this project involving multiple stakeholders and property owners . Dokken Engineering is uniquely qu alified to deliver this project because:
• Dokken has recent experience on Class I Bike Path projects with similar design challenges. We understand how to efficiently analyze various alternatives to provide pros and cons on a multitude of perspectives and requirements, which helps to successfully obtain project approvals in a timely manner. • Dokken has extensive experience working with the City of Santa Clarita on accessibility improvements to the Class I Bike Path along the Santa Clara River and we understand City requirements. • Dokken has experience working with the public, as well as utility companies, and our staff is experienced in navigating common pitfalls asso ciated with public outreach and utility coordination that can delay a project.

Our team consists of the same staff that has successfully completed similar projects. Michael Greer, our Project Manager, brings over 15 years of experience with expertise in management and bikeway design of transportation projects. He will be supported by a team he personally selected based on his experience with the individual team members on current projects or those recently completed. Our approach is to develop well thought out strategies at project initiation, which allows projects to move forward without ‘surprises’ which can derail cost and schedule.

Dokken E ngineering’s mission is to provide superior service to our clients for all their transit and related civil engineering needs. We strive to be responsive and flexible to our clients, which results in projects being delivered on time and within budget. We ap preciate your consideration of our proposal, and we a re very excited for this opportunity to be continue our relationship with the City of Santa Clarita.

Sincerely,

Michael Greer, PE, TE Mark Tarrall, PE
Project Manager Principal in Charge
[email protected] [email protected]

DOKKEN ENGINEERING TEAM
Project Manager: Michael Greer, PE, TE
• Bikeway Facility Design Experience
• Flood Control District Experience
• Public Outreach Experience
• City of Santa Clarita Experience

Page | 2

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

STATEMENT OF OFFER AND SIGNATURE
Dokken Engineering’s Proposal for Saugus Phase I: Bouquet Canyon Trail to Central Park (#ENG-21-22-C0066) is a firm offer for a 120-day period from the date of this submittal. The proposed work will be performed at a “not-to- exceed” price. Please reference the Cost Proposal, for detailed information regarding our proposed cost.

February 28, 2022
John Klemunes, PE, President Date

INTRODUCTION

Page | 3

SAUGUS PHASE I: BOUQUET CANYON

TRAIL TO CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

1. INTRODUCTION
Dokken Engineering has thoroughly reviewed the request for proposals (RFP) and available materials, incl uding reviewing the videos provided . We understand the challenges this project will present to design , coordinate, and construct. Our team of bikeway, roadway, pedestrian facility, drainage, structures, and utility coordination specialists have visited the project site and developed an understanding of the key project issues presented herein.

Project Approach
The City of Santa Clarita has been working with the County of Los Angeles on preliminary plans for the Saugus Phase I: Bike Trail along Bouquet Creek and through Central Park. Based on our understanding of the Project , we have developed an approach which addresses Stakeholder Coordination , maximizes park access during construction, accounts for Property Owner Coordination, as well as minimizing impact to the existing drainage basin, trees, and public gardens. We have included a Project Overview Exhibit to illustrate the areas of concern along this segment of trail project. Dokken’s in-house capabilities include civil, traffic, structural, environmental, and drainage services which improves uniformity and efficiency of the overall design. Based on our understanding we have developed the following table to identify key project issues , provide our team’s recent experience on such issue , and describe the unique benefit Dokken brings to the City.

Key Project Issue Our Team Experience Dokken Benefit
Stakeholder Coordination
The project requires
coordination between a large
group of stakeholders
including LA County Flood
Control, Santa Clarita Valley
Water Agency, and the City of
Santa Clarita Parks Division.

Dokken has extensive experience
working with multiple stakeholders,
engaging in public outreach, and
hosting Stakeholder Meetings to
ensure all expectations are managed
and concerns addressed.

Our team can work as-needed to
provide required documentation, as
well as coordinate with LA County
Flood Control, Santa Clarita Valley
Water Agency, and the City of Santa
Clarita Parks Division. Dokken brings
our understanding of the process as
well as the project site.

Potential Impacts to Drainage Basin
The proposed Bike Trail
passes by a drainage basin at
the South Entrance of Central
Park with limited space to
improve without impacting
the basin.

Dokken’s in-house water resources
team has significant experience
analyzing basin capacity and impacts
and producing the required
documentation studies for regulatory
agency approvals. Dokken’s in-house
structures team also has significant
experience working side-by-side with
our water resources team to provide
solutions that work for both services.

Having a team of in-house water
quality experts to work hand-in-hand
with Roadway and Bridge designers
provides seamless integration of
drainage solutions that will work
with project limitations and setting.

Many of our specially developed
drainage structure construction
details have been constructed
without issue.

Property Owner Coordination
The proposed Trail passes
behind at least 30 homes
when it is running adjacent to
Bouquet Creek. In addition,
parts of the proposed Trail
are located in SCVWA and LA
County Flood Control District
Right-Of-Way.

Dokken has extensive experience in
public engagement, including
reaching out to residents along
properties adjacent to the project
area so that they better understand
the project and its benefits to them
and the surrounding community. We
can accompany City staff as needed
or prepare exhibits to help the Right
of Way Agents assigned better
complete their coordination efforts
with owners.

We have recent experience creating
Property Owner Exhibits, and have
included an example herein, to help
identify private and public
improvements needed to complete a
project. Dokken’s Right of Way
Manager and Team of Agents also
has experience coordinating
temporary or permanent access
required from the various
stakeholders.

Page | 4

SAUGUS PHASE I: BOUQUET CANYON

TRAIL TO CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

Key Project Issue Our Team Experience Dokken Benefit
Park Accessibility During Construction
The project requires crossing
one of Central Park’s two
entrances. If the entrance
must be closed during
construction, impact to park
access must be limited by
minimizing the time the
access is closed during park
operating hours.

Our team has recent experience
developing staging plans for
structures in high-traffic areas,
including the SR-163/Friars Rd
Interchange and Indian Canyon Drive
over UPRR. We have also recently
developed plans and provided
construction support for multiple
streetscape projects with focus on
pedestrian and bicycle facilities
within the City of Vista, City of Palm
Desert, as well as County and City of
San Diego.

With Dokken, the City has an
experienced team who understands
the importance of working a
functional design in limited space.

We are well-versed in the challenge’s
facing cyclists and pedestrians
throughout construction and will be
able to provide best-fit options for
the City's consideration. Optimal use
of space during interim or temporary
configurations, as well as ultimate
layouts, is always a focus in our
designs and key to project success.

Impacts to Trees and Public Gardens
The proposed Trail runs
adjacent to a Community
Garden as well as existing
trees. The final alignment of
the Bike Trail and its cross
section must provide space to
preserve both.

Dokken has recently worked with
CALTRANS District 1’s Environmental
team to minimize impacts to
Redwood trees on multiple projects.

Our team is experienced in
preserving local environmental
landmarks while still satisfying the
needs of the project.

Dokken also has our own in-house
environmental team that can
coordinate with the City to ensure
that the proposed Bike Trail and
associated structures will not impact
the existing trees and community
garden.

Stakeholder Coordination
The proposed Bike Trail’s proximity to both a channel (Bouquet Creek) and a drainage basin will require active communication with all groups to ensure that the design meets expectations for the two features. LA County Flood Control, Santa Clarita Valley Wa ter Agency, City of Santa Clarita Parks Division all have ownership of the proposed Bike Trail to be constructed in this project. The areas of the Bike Trail owned by LA County Flood and SCVWA are adjacent to the channel (Bouquet Creek) and the City of San ta Clarita portion is adjacent to Central Park. Bouquet Canyon Channel is a FEMA regulated Floodway within the project limits. Within the project limits, the channel is comprised of three main sections . T wo
segments are operated and maintained
by Los Ange les County Flood Control
District (LACFCD) and one segment is
considered a natural channel.

The pavement section along the LACFCD
levee areas must remain at the same
grade as existing and present no
additional encroachment in the channel.

Any railing installed will likely be required
by LACFCD to prove that there is no
entrapment of debris that would cause a
rise in the water surface elevation of the
channel. Due to the limited nature of work
to install fencing and repave the existing asphalt concrete road atop the levee, coupled with the lack of slope stabilization along the creek, we have assumed that the nature of the project will not cause a rise in water surf ace elevation and not require modeling or reporting for LACF CD. As such this task is not included in our scope for this project. However, we have successfully completed such modeling on previous projects and if required by LACFCD we can prepare an amendment to include this report for this project.

Bouquet Creek Channel

Page | 5

SAUGUS PHASE I: BOUQUET CANYON

TRAIL TO CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

Potential Impacts to Drainage Basin
Near the western entrance to Central Park,
grading for the bike trail may impact an
existing small drainage basin adjacent to
the existing sidewalk on Bouquet Canyon.

Any capacity lost would need to be
mitigated by either deepening the existing
basin or d eveloping other strategies such
as the installation of dry wells, overflow
basins, or pump systems which are often
undesirable due to maintenance issues . As
the proposed Bike Trail passes by this
drainage basin at the South Entrance of Central Park there is limited room between the existing sidewalk on the east side of the drive and the basin. Impacts to basin capacity must be considered and minimized and/or mitigated as required by the LA County Flood Control District and property owners since the Trail will impact the basin due to limited clearance to existing infrastructure on either side of the basin.

The alternative depicted in our Project Overview Exhibit, which matches the City’s layout provided with the RFP , illustrates the Trail traversing the parking lot side of this basin, with potential impacts to existing fully grown trees and parking lot lights. Additionally, there is an existing chain link fence that will likely need to be relocated along the basin side of the trail as it appears to be a safety feature to limit access to the basin thus lodge pole fencing may not be allowed here.

Another alternative is to the route the Trail through this area and widen the section adjacent to the sidewalk and roadway to accommodate the 10-ft wide Trail, shoulders, and required fencing offset s. This encroachment on the existing basin would require the construction of a retaining wall between the Trail and basin , a significant amount of regrading within the basin, or potentially the design of a cantilevered trail section that allows water beneath the Trail. Another potential solution to reducing impact on this portion of the basin is a raised Trail crossing over the basin.

Property Owner Coordination
From the park and along the channel , the proposed Trail passes behind 32 private properties adjacent to Bouquet Creek. While it is not anticipated for the trail improvements to extend into any residential parcels, it will be important to engage with those residents early and often so that they understand the project and any potential impacts during construction, as well as the benefits provided by the Trail. Existing private property features such as gates, fences, drainage outlets, and trees as well as access to utility poles will need to be accommodated in the final designs.

As the Trail traverses the “S-Turn” from the park towards the channel, proposed improvements such as grading and potential cross-culvert will need to be coordinated with LA County Flood Control to ensure no negative impacts to the channel are created. There appears to be an
approximate vertical difference of five feet between the Trail along the park as compared to the paved path along the channel, with the channel segment being lower. Like the park entrance area, this area also appears to have the potential to be a basin for water prior to entering the channel. Proper evaluation of flow patterns, topography, and project alternatives will need to occur efficiently to establish proposed improvements with the least negative impact and biggest benefit in this area. With segments at Existing Drainage Basin
Trail Over Basin Example
Trail S-Turn from Park to

Page | 6

SAUGUS PHASE I: BOUQUET CANYON

TRAIL TO CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

either end of the Trail in SCVWA and LA County Flood Control District rights of way, access for construction and future maintenance will also need to be thoroughly coordinated with these important stakeholders. At the southern end of the natural portion of the Bouquet Creek Channel there is a naturally vegetated drainage feature where portions of the park drain directly to the channel. This area may require some minor drainage work such as a cross culvert under the proposed bike path to allow drainage to maintain its current flow pattern.

Park Accessibility During Construction
The Bike Trail will begin at the
main park entrance but will not
impact the existing traffic signal
with this phase of construction.

There is potential for a small
retaining wall along the portion
of Trail adjacent to the roadway
in that area. Once the Trail
passes the first drainage basin,
we come across the park’s secondary, stop-controlled entrance. Vehicles turning off Bouquet Canyon Road to the park at this entrance do not have to stop, while those exiting the park are required to stop before turning right only.

Although this is not the main park entrance, it will be important to maintain safety during stage d construction of the Trail to minimize conflicts. Proper placement of advanced warning signs for any closure of this park entrance will be essential for year-round safety and accessibility to the park and public gardens.

We have depicted the potential layout of an at-grade crossing on our Project Overview Exhibit, with the Trail crossing placed further away from Bouquet Canyon Road than the existing pedestrian crossing. This is done for two reasons, the first (1) is to allow vehicles turning off Bouquet Canyon Road into the p ark the opportunity to slow before meeting the Trail crossing and the second (2) is to separate the existing pedestrian crossing from the future Trail crossing for visibility from vehicles. We would also propose a raised crosswalk for the Trail at this cro ssing to require vehicles to slow for Trail users. Depending on available funding, another option could be to create a box culvert undercrossing to eliminate the potential conflicts presented with an at-grade crossing. Construction of a 2 -section box culvert could be completed over a weekend closure of the entrance; however, the likelihood of utility conflicts would be significantly increased due to depth of excavations.

Impacts to Trees and Public Gardens
The proposed Trail runs adjacent to a Community Garden as well as existing trees. Per discussion at the pre-proposal meeting, t here should be no impact to the Community Garden s. Any trees removed by the project are to be mitigated at a 2:1 or 3:1 ratio, pending final coordination. To avoid costly impacts of these features, the Trail will be designed to minimize grading with the potential to install MSE walls where needed. Environmental specialists can also be consulted to ensure the impacts of the Trail design and its associated structures will not have any unintended consequences for the existing foliage. Additionally, our team of in -house structural designers can aid in the assessment of structural design impacts to offer alternative footing or structure designs as needed. We have recently developed special designs to protect in place street trees around widened or newly placed sidewalks that allow their root structures to remain intact and water to pass beneath pedestrian paths to maintain tree health and vitality.

At-Grade Crossing at Westerly

Park Entrance Adjacent to Existing Basin
(1)
(2)

Page | 7

SAUGUS PHASE I: BOUQUET CANYON

TRAIL TO CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

Public Engagement
Dokken Engineering, and our Project Manager Mike Greer , have extensive experience in public involvement and outreach meetings. We have in -house Spanish translation and interpretation services that are fluent in the language of bicycle facilities. This has proven to be an invaluable tool for our past clients by providing a comprehensive public outreach program that goes above and beyond what is required under State and Fe deral environmental guidelines. By including the public in the process and encouraging public input on our projects, Dokken can identify potentially controversial issues and provide responses in the form of design alternatives in the project planning proce ss prior to project’s going to bid and construction.

Santa Ana Public Outreach

305N 2010326.94E 6265942.33Elev 480.06
305N 2010326.94E 6265942.33Elev 480.06
BUENA VISTA BAPTISTCHURCH OF VISTA CA145 HANNALEI DRIVEVISTA, CAAPN 183-060-06 6,1500.14120,6930.475
PROPERTY IMPACTS1.PERMANENT EASEMENT2.TEMPORARY CONSTRUCTION EASEMENT WORK TO BE COMPLETED1.CONSTRUCT BIKE PATH2.CONSTRUCT RETAINING WALL3.CONSTRUCT DRAINAGE FEATURES4.REPLACE FENCE

LEGENDEXISTING RIGHT OF WAY (R/W)PROPOSED EASEMENT LINETEMPORARY CONSTRUCTION EASEMENT (TCE)PROPERTY BOUNDARYPROPOSED RETAINING WALLFENCETEMPORARY CONSTRUCTION EASEMENT AREA PRE-CONSTRUCTION CONDITION:

P:\1948_Inland_Rail_Trail\460\Property Owner Exhibits\Scratch\AndrewR\10_183-060-06_Fence Exhibit.dwg Wednesday, Apr. 24 2019 10:23am andrewr INLAND RAIL TRAILPROPERTY OWNER EXHIBITFENCE EXHIBIT183-060-06145 HANNALEI DRBUENA VISTA BAPTIST CHURCH PROPOSED PERMANENT EASEMENT:6,150 SQFT (0.141 ACRES)TEMPORARY CONSTRUCTION AREA:20,693 SQFT (0.475 ACRES) APN 183-060-06
APN 183-060-06

PROPOSED PERMANENT EASEMENT

NOT TO SCALENOT TO SCALEPROPERTY RIGHT-OF-WAY IMPACTS
N

HANNALEI DR
PHILLIPS ST.

WOODLAND DR.

BUENA CREEK DR.N.T.S.KEY MAPPHASE 2
PROPOSED CHAINLINKFENCE, L=245'PROPOSED RETAINING WALL
PROPOSED CHAINLINK FENCE, L=917'

ACCESSEASEMENT

PROPOSED BIKE PATH

EXIST FENCE TOBE REMOVED FROMNCTD R/W &REPLACED ON R/W

PRIVATE PROPERTY IMPACTSTEMPORARY CONSTRUCTION EASEMENTSQFTACRESPROPOSED PERMANENT EASEMENTSQFTACRES

EXIST FENCE TO REMAIN

TYPICAL DRAINAGE IMPROVEMENTS

STORM DRAINEXTENSION& RIP RAPDRAINAGEIMPROVEMENTS
PROPOSED CHAINLINKFENCE, L=34'PROPOSED CHAINLINKFENCE, L=217'

REFERENCES

Page | 10

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

2. REFERENCES
SAN DIEGO RIVER TRAIL – WALKER PRESERVE
│

Santee, CA

CLIENT:

CITY OF SANTEE
10604 Magnolia Avenue
Santee, CA 92071

REFERENCE:

Carl Schmitz, PE
City of Santee
(619) 258.4100 x175
[email protected]

SCOPE OF SERVICES:
 Project Management
 Alignment Study
 Community Outreach
 Storm Drain Upgrades
 Water Design
 Drought-tolerant Landscape
Design
 Irrigated Landscape Design
 Informational Kiosks and Signs
 PS&E

Dokken Engineering performed design
services under an on -call contract with the
City of Santee to s upport the construction
of the San Diego River Trail – Walker
Preserve, north of the San Diego River
between Magnolia Avenue and Marathon
Parkway. The scope of services for the trail
included preliminary alignment engineering, right -of-
way engineering,
technical studies, public outreach, bid document preparation, design support during construction, and record drawing preparation. The construction cost for the project was approximately $2M. The City filed a Categorical Exemption (CE) to the California Enviro
nmental Quality Act
(CEQA) for this project since the trail is a minor alteration of land that does not remove healthy, mature trees.

The project included a 1.3 -mile long, 14- foot wide, multi -use public trail within an existing 24-foot wide unpaved haul road previously used by RCP Block and Brick for sand mining operations along the San Diego River on a 107-acre riverfront property. The trail surface consists of 4-inch thick, compacted and stabilized disintegrated granite (D.G.) bordered by a 2-inch by 6-inch composite header boards to keep the surface material in place.

Two-rail lodge pole fencing runs along the trail on both sides, with occasional “pop-outs” for visitors to rest and view the San Diego River on park benches and picnic tables. The project also includes the placement of informational kiosks and interpretive signs, a 20-foot square shade shelter, solar lighting, and potable water amenities such as a drinking fountain, pet fountain, mister, and new fire hydrant. The trail head area has been landscaped with native and drought -tolerant shrubs and trees and is irrigated with recycled water. The other disturbed areas within the existing haul road were replanted with a non-irrigated native seed mix.

Following preliminary alignment studies and prepar ation of a landscape concept plan, Dokken Engineering and the City of Santee hosted an open house public meeting to share the design and public improvements with the community. The Dokken Engineering team also prepared a drainage study and Stormwater Pollution Prevention Plan (SWPPP) in addition to a cultural study to identify archaeologically sensitive sites and a habitat management plan that documents biological resources.

The design of this project evaluated mobility, civil infrastructure, beautification, amenities, and community and environmental considerations in just 8 months. Funding for this project was provided by grants from the Coastal Conservancy, U.S. Fish & Wildlife Service, the State of California Wildlife Conserv
ation Board, the California State Parks
Recreation Trails, Propositions 12 and 84, and local funds from the City’s Capital Improvement Program.

Page | 11

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

SAN PABLO AVENUE STREETSCAPE, PHASES I & II
│

Palm Desert, CA

CLIENT:

CITY OF PALM DESERT
73510 Fred Waring Drive
Palm Desert, CA 92260

REFERENCE:

Randy Bowman
(760) 776.6493
[email protected]

SCOPE OF SERVICES:
 Project Management
 Green Street Design
 Roadway Improvements
 Roundabout Design
 Streetscape Improvements
 Landscape & Irrigation
 Water Quality
 Hydraulics/Hydrology
 Utility Coordination
 Street Lighting/Traffic Signals
 Signing and Striping
 Public Art
 Multi-Agency Coordination
 Design Support During
Construction

The City of Palm Desert
identified the San Pablo
Avenue Corridor as a key area
for transformation to create a
downtown/city center north
of Highway 111. Dokken
Engineering was selected by
the City of Palm Desert to complete PS&E for the Phase I reconfiguration of the San Pablo Avenue Corridor to comply with the goals of the adopted City General Plan. While providing construction support for Phase I, Dokken staff assisted the City with submi ttal of an ATP Grant Application to fund Phase II improvements. Successfully being awarded the $3.2 million ATP Grant, the City again selected Dokken Engineering to complete the Phase II PS&E work. The City hosted public outreach events including “Vision San Pablo” and the feedback was overwhelmingly positive for the transformation of the San Pablo Avenue Corridor into a new downtown area for Palm Desert.

Both phases proposed a “road diet” to reduce the existing travel lanes on San Pablo Avenue from four to
two lanes between Highway 111 to
Magnesia Fall Drive. The Project included components such as roadway improvements, bike lanes, ADA curb ramps, bulb-
outs, planter islands,
drainage facilities, traffic signal improvements, expansion of street parking, landscaping, and installation of artistic features. The goal of the project was to provide an attractive downtown corridor connecting pedestrians, motorist, and cyclists to residential neighborhoods, shopping, restaurants, Palm Desert City Hall, College of the Desert, and Civic Center Park. The design included widened, multi-level sidewalks with shade trees and street furniture, enhancements to the existing community gardens, parking improvements throughout the corridor, and construction of single -lane roundabouts at the San Gorgonio Way, College of the Desert/Civic Center Driveway, and Magnesia Falls Drive intersections. Both phases also added raised midblock crosswalks with in -pavement roadway warning lights to improve pedestrian safety and mobility.

The Phas e I corridor improvements provide pedestrians, cyclists, and motorists with a fun and safe experience near shopping, restaurants, schools, and civic buildings. The varied mini park improvements along existing community gardens required access to the garden s be always maintained. Varied mini park improvements included installation of a bocce ball court, exercise equipment, play and musical equipment, along with ample seating for residents to relax and dine.

The Phase II corridor improvements differ from Phase I by providing a separated cycle track for bikes and neighborhood electric vehicles that connect the City’s offices, recreational space, and the College of the Desert with Phase I. Existing drainage patt erns in this flat elevation environment also needed to be maintained while a new system was installed near the north end of the project.

Page | 12

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

JOHNNY CASH TRAIL AND BICYCLE/PEDESTRIAN BRIDGE
│

Folsom, CA

CLIENT:

CITY OF FOLSOM
Department of Public Works
50 Natoma Street
Folsom, CA 95630

REFERENCE:

Jim Konopka
City of Folsom
(916) 355-7200
[email protected]

SCOPE OF SERVICES:
 Project Management
 Bridge and Trail PS&E
 Aesthetics
 Drainage
 Surveying
 Utility Coordination
 Bid and Construction Support
 Biological Surveys

Dokken Engineering prepared the
Plans, Specifications and Estimate
(PS&E) for the new, multi -use
path and new overcrossing of
Folsom Lake Crossing Road to
connect the existing East Lake
Natoma and Folsom Lake
Crossing trails.

The Johnny Cash Trail was
designated by the Folsom City Council in recognition of the international notoriety by Johnny Cash through his 1955 song, “Fol som Prison Blues.” This project was developed by the City in order to reflect the City of Folsom’s community values of encouraging alternative transportation, facilitating outdoor recreation, supporting the areas, and celebrating its historical heritage; s pecifically the legacy of Johnny Cash and his relationship to the second oldest prison in California. The overcrossing is especially unique in that it was designed with towers reflecting the look of the Romanesque tower of the Folsom State Prison’s east gate.

The project was broken into three major segments:

Phase I: Folsom Lake Crossing Bike/Pedestrian Overcrossing to the Folsom Prison Road intersection
Phase II: Folsom Prison entry road with an undercrossing of Folsom Prison Road and a bridge over the ravine to Rodeo Park
Phase III: Folsom Lake Crossing Bike/Pedestrian Overcrossing to the El Dorado County line
The overcrossing features a 155 -foot
weathering steel prefabricated steel
truss main span, with 62 -foot precast
UltraBlock abutment approaches
featuring cut stone architectural
treatment reminiscent of the granite
prison walls. Formed concrete gateway
towers capped by standing seam,
weathering steel “witches hat” roofs anchor the main span, providing both a visual tie to the prison and the ominous feeling of entering a prison for trail users crossing the bridge. Accent lighting of the outsides of the towers and security lighting along the bridge complete the effect.

Key issues for this project included the incorporation of aesthetic features that meet the City’s vision of a signature crossing, are buildable, and fit within the available funding, an aggressive grant funding deadline for design, careful planning of drainage design to avoid right of way and tree impacts, the undergrounding of telephone utilities, and consideration of overhead utilities during planned construction of the overcrossing.

PLAN OF STUDY/

SCOPE OF WORK

Page | 13

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

3. PLAN OF STUDY/SCOPE OF WORK
The Dokken Engineering Team, referred to as “Dokken” throughout this Scope of Work, will perform professional and technical engineering services to prepare the construction documents and bid package for authorization to award. This Scope of Work includes a review of the hydraulic and hydrologic designs, civil design, construction cost estimates, specifications, topographical survey, utility research and coordination, preparation of contract documents, and other related support services pursuant to the impro vements of the Saugus Phase I: Bouquet Canyon Trail to Central Park.

SCOPE OF WORK
We have reviewed the work statement and draft scope of work provided with the RFP and evaluated the need for additional or Optional Tasks as identified below. The following is a detailed scope of services, roughly based on the City’s outline, required to successfully deliver this project with Tasks, Subtasks, and Deliverables (a.k.a. Outputs):

TASK 1: PROJECT MANAGEMENT
Project management includes project setup, regular meet ings, deliveries, presentation of work products, development and monitoring of action items, monthly progress reports, work progress monitoring, budget monitoring, extensive communication, and coordination. Upon project kickoff a Project Development Team (PDT) will be established to include City of Santa Clarita staff, Dokken staff, and any other agency representative as deemed necessary to collaborate with stakeholders on the project. Dokken will maintain the same PDT throughout the life of the project to ensure continuity.

Subtask 1.1: Project Kick-off and PDT Meetings
Dokken Engineering will coordinate meetings with the City to facilitate decision making. For each meeting, Dokken will prepare the meeting agenda in consultation with the City Project Manager, provide meeting notices one week prior to the meeting, arrange for appropriate participants to attend, prepare meeting materials (including exhibits, task lists, and agenda), facilitate the meeting, and prepare/distribute meeting minutes within five business days of the meeting. Dokken will consult with the City’s project manager prior to each meeting to review upcoming meeting items. The following meetings are anticipated for this project:
• Kickoff Meeting (1): To start, Dokken will organize a kickoff meeting with key personnel, design team members and stakeholder representatives. The purpose of this meeting is to review the goals and objectives of the project, discuss each team member’s roles and responsibilities and identify critical project issues. • PDT Progress Meetings (12): The PDT meetings will be scheduled monthly and will serve as the primary forum for reviewing the status of the project and identifying and resolving project issues. A Project Schedule and Action Items List will be prepared and updated for each PDT meeting. The schedule and list shows the work items (tasks and subtasks), the dates they are due, who is responsible for the task, critical path, review timelines for City and outside sources, and the date completed. • City Council/Staff Meetings (2): Dokken will attend and present the project at up to two (2) Santa Clarita City Council/Staff meetings to provide a preliminary and final project update to obtain approvals. • Stakeholder Coordination Meetings: Dokken will coordinate, attend, and present project improvements specific to each stakeholder (utility agencies, flood control, residential and commercial property owners, and others) as needed to facilitate decisions to move the project towards construction.

Subtask 1.2: Public Outreach
Dokken will prepare public outreach materials including preparing and distributing Fact Sheets to the stakeholders and biking community and trail users. Dokken will prepare necessary graphics to convey to the participants the major design features of the project and the approximate area impacted by the construction. If necessary, Dokken will facilitate virtual mee tings with stakeholders, the biking community, and trail users to discuss the project, understand and address any of their potential concerns.

Page | 14

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

Subtask 1.3: Schedule and Administration
Dokken will schedule all work necessary to complete the project while administering, monitoring, and controlling the effort and progress of the proposed services as follows:
• Set up an internal project accounting, reporting, and invoicing system • Prepare, monitor, and adjust the Schedule using MS Project; updated monthly • Prepare a Quality Control Plan (QCP) to be utilized throughout the life of the project • Prepare monthly Progress Reports indicating work accomplished the previous month, anticipated work to be completed the next month, issues requiring resolution, milestones achieved, meetings held, actions taken, approval actions required, coordination issues and design schedule impacts to accompany invoices. • Coordinate with the City and Stakeholders to obtain and provide all relevant information needed to complete the bid package and prepare documents for Construction and obtain final approval.

Task 1 Deliverables: Attend and Facilitate 1 Kickoff Meeting, up to 12 PDT Progress Meetings, 2 City Council/Staff Meetings, and Stakeholder Meetings as needed; Meeting Agendas; Meeting Minutes; 1 Public Outreach Meeting; Project Schedule with Updates; Progress Reports with Invoices; and Quality Control Plan TASK 2: SITE AND UTILITY INVESTIGATION
Subtask 2.1: Data Collection and Field Review
Dokken will obtain and review all available data developed as part of this project such as as -builts, available geotechnical and hydraulic studies, infrastructure improvement plans, topographic survey, survey ties, City benchmarks, existing right -of-way, City standards, underground and overhead utilities base maps, aerial photographs, and any applicable previous studies that have been conducted in the vicinity of the project site.

Dokken will perform site visits and take photos to identify and record design issues. Dokken will maintain a project file to log all documents obtained for the project.

Subtask 2.2: Topographic Surveying and Right of Way Engineering Survey Services will include collect City control points, run a traverse and level loop, and search and locate centerline and right o f way monumentation. Utilities identified in the field review will be shot to supplement existing topographic survey information, this includes survey ing of existing SCE power poles with electrical and communication lines within the project area. Right o f way /property lines will be researched and compared to existing drawings to plot and field search positions to compile a record base file. (This is not a boundary survey).

Subtask 2.3: Utility Investigations, Base Mapping, and Potholing Dokken will id entify any potential utility conflicts or areas where additional facility information is needed and coordinate utility potholes throughout the project limits as needed. Dokken will prepare a Pothole Location Exhibit, identifying proposed pothole locations with anticipated facilities to be encountered, requiring approval by the City’s Project Manager prior to scheduling any pothole work or request quotes from subsurface investigation subcontractors. A Utility Pothole Report, with photo logs and field measure ments, will be prepared by the utility investigation subcontractor; to be contracted with as an Other Direct Cost (ODC) for simplicity in billing purposes, flexibility in scheduling, and best potential for lowest negotiated price. We will survey each pothole location (six to eight potholes are anticipated) and update the utility base map to reflect positively identified locations, then revisit the previously identified conflicts to update information, identify additional potential conflicts, then revisit the need for additional potholes if necessary.

Subtask 2.4: Geotechnical Investigations and Report
Dokken will coordinate with the geotechnical subconsultant, RTF&A, to develop a plan for project geotechnical investigations to account for potentia l structure and drainage improvements . A geotechnical investigation of the eastern portion of the site where grading is anticipated would be performed to provide evaluation of existing site conditions and grading recommendations. The investigation would co nsist of excavating a series of backhoe test pits, soil sampling and laboratory testing to determine the engineering characteristics of the existing soils, and preparation of a report summarizing the findings and recommendations. Prior to the start of field work, the locations

Page | 15

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

of the proposed test pits would be field marked and submitted to Underground Service Alert Southern California, DigAlert, for utility locating, as required. DigAlert requires three days advance notification prior to the start of any subsurface excavation. The scope of this proposal includes marking the site and submitting the required DigAlert request. A backhoe would be utilized to excavate four to six shallow test pits. The soils exposed within the test pits would be sampled and test ed to determine laboratory moisture and density relationships. A total of two bulk samples would be obtained for laboratory maximum density determinations.

The results of our field investigation and laboratory testing would be summarized within a formal report that would include recommendations for grading associated with the trail construction suitable for submittal to reviewing agencies. The scope of the investigation would be limited to near surface soils and would not include recommendations for bank pr otection grading along the adjacent flood control channel. Additional sampling for laboratory corrosion testing and R-value testing is not within this scope of work but can be provided as an optional service for additional fee.

Task 2 Deliverables: Documentation Logs; Field Review Notes; Topographic Survey Data and Base Map; Utility Pothole Report; Existing Utility Base Map; Geotechnical Design Report TASK 3: UTILITY COORDINATION
Subtask 3.1: Utility Coordination
Dokken will create a Utility Coordination Matrix to identify all utility agencies and facilities within the area, then systematically contact and meet with each one to engage planners and request as -builts via a 1 st Utility Notice prepared on City letterhead. Dokken will research and document via site visits, all utilities within the project limits and update the utility base map as needed. Second Utility Notices will be prepared for all utilities within the project area to notify each of the identification of potential conflicts and request confirmation along with a check of rights of ownership (i.e. cost liabilities). Meetings will be arranged as needed to gain concurrence of the proposed approach to each potential conflic t, and once in agreement, the need for utility relocation plans and utility agreements will be identified. Third Utility Notices will then be prepared and sent as a Notice to Relocate to each utility with an identified conflict. When agreements are in place and final plans are ready for bid a 4th Utility Notice will be sent to each as a Final Notice to Relocate Immediately, or as needed before or during construction.

Subtask 3.2: Utility Relocation Plans
Dokken will coordinate with impacted utilities to resolve any constructability requirements and prepare relocation plans as required. Dokken will coordinate with the affected utility companies to ensure agency requirements and specifications conform with the bid documents for this project. Where necessary to expedite processes, we will provide draft utility relocation exhibits to illustrate proposed relocation strategies.

Task 3 Deliverables: Utility Coordination Matrix; Utility Conflict Matrix; 1st Utility Notice (Preliminary Project Notice and Request As-built Maps); 2nd Utility Notice (Review and Identify Potential Conflict and Need to Relocate); 3rd Utility Notice (Notice to Relocate); and 4th Utility Notice (Final Notice to Relocate Immediately); Proposed Utility Base Map TASK 4: HYDROLOGY & HYDRAULICS
Subtask 4.1: SUSMP for MS4/Water Quality Permit Compliance Dokken Engineering will prepare a Specific Urban Stormwater Mitigation Plan (SUSMP) in accordance with the County of LA Low Impact Development (LID) Standards Manual and the County of LA Municipal Separate Storm Sewer Systems (MS4) Permit (Order No. R4-2012-0175). The LID Plan is anticipated to include the following features:
• Identification of Project Designation
• Feasibility Assessment of Infiltration and Harvest/Reuse • Source Control Measures to be Implemented
• Calculations of the Stormwater Quality Design Volume (SWQDv) • Stormwater Quality Control Measure(s) Proposed to be Implemented • Proposed Hydromodification Controls and Calculations
• Proposed Maintenance Plan for BMPs as necessary

Page | 16

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

A draft SUSMP will be submitted for review by the City with the 90% PS&E Submittal, comments will be addressed, and the plan will be finalized and submitted with the 100% PS&E Submittal.

Subtask 4.2: Drainage Analysis and Report
A Drainage Report will be prepared to document the hydrology and hydraulic analysis based on City and County of LA criteria and will provide a detailed discussion of the existing conditions, post -project drainage patterns and conditions, results of the on- site hydraulic analyses and any issues of special concern or sign ificance. The analysis will reuse any applicable previously prepared studies and design. Boundary conditions for proposed drainage system outfalls for connections to existing systems will be taken from existing FEMA studies, LA County Flood Control District, or the City will provide or agree to assumed boundary conditions for use in the hydraulic analysis.

A draft report will be submitted for review by the City for comments at the and will be finalized upon completion of the Final PS&E milestone submittal.

Task 4 Deliverables: Draft and Final SUSMP, Draft and Final Drainage Report TASK 5: PLANS, SPECIFICATIONS, AND ESTIMATE (PS&E)
Following the kick -off meeting, Dokken will collect and analyze existing available plans in the area to develop a database of existing facilities and improvements to be protected in place. Dokken will utilize one of the early PDT meetings to consult and advise the City on required aspects of the PS&E package prior to making any final development decisions. Following the review and discussion of the entire PS&E package Dokken will prepare and submit a design schedule for the 60%, 90%, 100%, and Final Submittal Packages to the City for input.

Subtask 5.1: 60% PS&E
Dokken will begin preparation of the project plans, specifications, and estimate (PS&E) by developing all plan sheets to the 60% level of design with quantities and engineer’s estimate developed based on those plans. We anticipate development of a draft specification outline at this level to ensure all aspects of the project are properly accounted for. Our quality control process will be followed to ensure that all deliverables are properly checked prior to submitting to the City. The following is a list of sheets proposed to be submitted with the 60% PS&E Package:
• Title Sheet, General Notes, Index of Plans (1) • Drainage Plans/Profiles, Details, & Q’s (4) • Survey Control Sheet (1) • Stage Construction/Traffic Handling (2) • Typical Cross Sections (2) • Sign Plans, Details, & Q’s (2) • Roadway Plans/Profiles (2) • Striping Plans, Details, & Q’s (2) • Construction Details – Roadway (2) • Retaining Wall Plans, Details, & Q’s (2) TOTAL Plan Sheets = 20
Subtask 5.2: 90% PS&E
Upon receipt of the 60% review comments from the City and other stakeholders, Dokken will revise the 60% drawings and will develop the additional plan sheets required to reach 9 0% level of detail. The construction staging/phasing plans will identify a lay down yard location and will include detour plans to maintain access to Central Park. During this phase of the project the draft geotechnical report and hydrology study with draft drainage report will be submitted to the City for review. Dokken will revise the construction cost estimate and technical special provisions (a.k.a. construction specifications) to reflect the revisions to the 90% plan set. Construction specifications will be prepared in the format of the City’s choosing (typically a combination of Caltrans standards and APWA Greenbook standards). An itemized construction bid schedule and cost estimate with item numbers, item descriptions, units of pay, quantities derived from a detailed takeoff, and estimated unit costs will be prepared in Microsoft Excel spreadsheet format. A preliminary construction schedule will be provided to reflect the project plans including anticipated utility relocation work.

Subtask 5.3: 100% PS&E
Dokken will r eview and respond to any City comments from the 9 0% PS&E submittal. Once all comments are addressed, we will continue with the design effort to reach 100% PS&E. Dokken will prepare a revised, 100% design level set of plans, construction specifications, and construction cost estimate with bid schedule. Any changed unit

Page | 17

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

items or cost from the 90% submittal will be identified to the City for clarity. Dokken will review and respond to the comments on the geotechnical and drainage repor ts and will prepare or coordinate preparation of final reports, studies, and calculations.

Subtask 5.4: Final PS&E
Dokken will review and respond to any City comments from the 100% PS&E submittal. Once all comments are addressed, we will continue with the design effort to reach Final PS&E. Dokken will prepare a revised, final set of plans, construction specifications, and construction cost estimate with bid schedule. Any changed unit items or cost from the 100% submittal will be identified to the City for clarity. When the project is complete, Dokken will provide AutoCAD files for all plan sheets via file share (MS-OneDrive) link.

Subtask 5.5: Plan Approvals and Permits
Dokken will coordinate and track timelines required for all plan checks including Engineering Services, Traffic, Building & Safety, Environmental Services, and any outside agencies needed for construction permits. Dokken will provide a final set of approved plans, specifications, and estimate after all plan reviews are completed.

Subtask 5.6: Bidding
Dokken will assist the City in answering written questions during the biding process, attend the Pre-Bid conference, and respond to technical questions from the prospective bidders. Dokken will assist with an addendum to the PS&E package (as needed) resulting from the comments and questions from the Pre -Bid conference. Dokken will assist the City in analyzing the contractor’s bids for competency and completeness and will recommend the lowest responsible bidder. Dokken will assist the City’s RFP preparation for Material Testing and Special Inspection.

Task 5 Deliverables: 60%, 90%, 100%, and Final PS&E Submittals (PDF and Hard Copies as needed) ; Project Design CAD Files As Requested; Agency Permits; Preliminary and Final Draft SWPPP; Attend Preconstruction Meeting; Respond to Bidder Inquiries; Prepare Project Addendum; Bid Analysis; and Responsible Bidder Recommendation TASK 6: CONSTRUCTION SUPPORT
Dokken will provide a cost proposal for construction engineering support services during the construction phase to address any design concerns on an as-needed basis and we understand this to be an optional task.

Subtask 6.1: Construction Support
Dokken will attend contractor progress meetings a s requested by the City, attend regular jobsite meetings and inspection visits, respond to request for information, review shop drawing submittals, revise the construction documents (as needed), analyze the City on contractor change order requests, prepare construction correction notices as needed, and prepare the punch list for the contractor.

Subtask 6.2: As-Built Plans
Dokken will acquire the daily red lined plans from the contractor and the subcontractors and will prepare the As - built drawings upon completion of the project. Final record drawings will be submitted in electronic (CAD/PDF) and hard copies.

Task 6 Deliverables: As-Built drawings to include (1) full sized set on mylar and digital files; Completed MMRP & ECR

SCHEDULE

ID Task  Name Duration Start Finish
1 Saugus Phase 1: Bouquet Canyon Trail 366 days Mon 4/4/22 Mon 8/28/23
2 Notice to Proceed 0 days Mon 4/4/22 Mon 4/4/22
3 TASK 1:  PROJECT MANAGEMENT 205 days Mon 4/4/22 Fri 1/13/23 4 1.1:  Project Kick‐off and PDT Meetings 205 days Mon 4/4/22 Fri 1/13/23 5 1.2:  Public Outreach 40 days Mon 7/4/22 Fri 8/26/22
6 1.3:  Schedule and Administration 205 days Mon 4/4/22 Fri 1/13/23 7 TASK 2:  SITE AND UTILITY INVESTIGATION 60 days Mon 4/4/22 Fri 6/24/22 8 2.1:  Data Collection and Field Review 5 days Mon 4/4/22 Fri 4/8/22 9 2.2:  Topographic Surveying and ROW Engineering 15 days Mon 4/4/22 Fri 4/22/22 10 2.3:  Utility Investigations, Base Mapping, and Potholing 45 days Mon 4/25/22 Fri 6/24/22 11 2.4:  Geotechnical Investigations and Report 30 days Mon 4/25/22
Fri 6/3/22
16 TASK 3:  UTILITY COORDINATION 150 days Mon
4/25/22
Fri 11/18/22
17 3.1:  Utility Coordination 60 days Mon 4/25/22 Fri 7/15/22 18 3.2:  Utility Relocation Plans 90 days Mon 7/18/22 Fri 11/18/22 19 Task 4: HYDROLOGY & HYDRAULICS 120 days Mon 6/6/22 Fri 11/18/22 20 4.1:  SUSMP for MS4/Water Quality Permit Compliance 120 days Mon 6/6/22 Fri 11/18/22 21 4.2:  Drainage Analysis & Report 120 days Mon 6/6/22 Fri 11/18/22 22 TASK 5:  PLANS, SPECIFICATIONS, AND ESTIMATE (PS&E) 235 days Mon 4/4/22 Fri 2/24/23 23 5.1:  60% PS&E 45 days Mon 4/4/22 Fri 6/3/22
24 Agency Review 20 days Mon 6/6/22 Fri 7/1/22
25 5.2:  90% PS&E 60 days Mon 7/4/22 Fri 9/23/22
26 Agency Review 20 days Mon 9/26/22 Fri 10/21/22
27 5.3:  100% PS&E 45 days Mon
10/24/22
Fri 12/23/22
28 Agency Review 10 days Mon
12/26/22
Fri 1/6/23
29 5.4:  Final PS&E 5 days Mon 1/9/23 Fri 1/13/23
30 5.5:  Plan Approvals and Permits 60 days Mon
10/24/22
Fri 1/13/23
31 5.6:  Bidding 25 days Fri 1/20/23 Fri 2/24/23
36 TASK 6:  CONSTRUCTION SUPPORT 111 days Fri 3/24/23 Mon 8/28/23
37 6.1:  Construction Support 100 days Fri 3/24/23 Fri 8/11/23 44 6.2:  As‐Built Plans 11 days Mon
8/14/23
Mon
8/28/23
4/4 8/28
Saugus Phase 1: Bouquet Canyon Trail
4/4
4/4 1/13
TASK 1:  PROJECT MANAGEMENT
4/4 1/13

1.1:  Project Kick‐off and PDT Meetings
7/4 8/26

1.2:  Public Outreach
4/4 1/13

1.3:  Schedule and Administration
4/4 6/24
TASK 2:  SITE AND UTILITY INVESTIGATION
4/4 4/8

2.1:  Data Collection and Field Review
0%
4/25 6/24

2.3:  Utility Investigations, Base Mapping, and Potholing 4/25 6/3

2.4:  Geotechnical Investigations and Report
4/25 11/18
TASK 3:  UTILITY COORDINATION
4/25 7/15

3.1:  Utility Coordination
7/18 11/18

3.2:  Utility Relocation Plans
6/6 11/18
Task 4: HYDROLOGY & HYDRAULICS
6/6 11/18

4.1:  SUSMP for MS4/Water Quality Permit Compliance
6/6 11/18

4.2:  Drainage Analysis & Report
4/4 2/24
TASK 5:  PLANS, SPECIFICATIONS, AND ESTIMATE (PS&E)
4/4 6/3

5.1:  60% PS&E
6/6 7/1
Agency Review
7/4 9/23

5.2:  90% PS&E
9/26 10/21
Agency Review
10/24 12/23

5.3:  100% PS&E
12/26 1/6
Agency Review
1/9 1/13

5.4:  Final PS&E
10/24 1/13

5.5:  Plan Approvals and Permits
1/20 2/24

5.6:  Bidding
3/24 8/28
TASK 6:  CONSTRUCTION SUPPORT
3/24 8/11

6.1:  Construction Support
8/14 8/28

6.2:  As‐Built Plans
20 27 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 3 10 2 Mar '22 Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Aug '23 Sep Critical
Critical Split
Critical Progress
Task
Split
Task Progress
Manual Task
Start‐only
Finish‐only
Duration‐only
Baseline
Baseline Split
Baseline Milestone
Milestone
Summary Progress
Summary
Manual Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Deadline
City of Santa Clarita Proposal # ENG‐21‐22‐C0066 SAUGUS PHASE 1: BOUQUET CANYON TRAIL TO CENTRAL PARK February 28, 2022

Page 18 ends

NA

PROGRAM MANAGEMENT

Page | 19

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

5. PROGRAM MANAGEMENT
Our management approach is to be an extension of the City staff and provide the City an experienced team. Our team will provide the resources and tools necessary to deliver this project with minimal oversight from the City staff.

LINES OF COMMUNICATION
It’s critical that the project team receives confirmation of the scope, budget and schedule prepared by Dokken from the City’ Project Manager. This review allows all parties to understand the project scope and schedule and the submittal milestones. In addition to monthly project team meetings, Dokken Engineering will keep the City Project Manager aware of progress through weekly emails and team conference calls. This approach allows the City Project Manager to provide any required input throughout the project development process.

SCHEDULE AND BUDGET CONTROL
In order to manage the three interdependent elements found in every project – scope, schedule, and budget – it is necessary to implement a sustainable project control methodology. Michael, our Project Manager, will develop and implement the project controls plan. The plan outlines the procedures for conducting work, managing project resources, and reporting project status and progress. The project management tools identified on the right assures on time and within budget project deliverables.

These tools will enable Michael to provide a systematic approach to deliver any project. All project participants, including the City and Dokken Engineering Team, will be aware of the project status in order to make informed management decisions. Our tools and system are designed to respond to these requirements.

Dokken Engineering prepares and maintains project schedules for every project. The schedules are monitored and staffing adjusted to meet milestones. Performance is monitored through quality control checks, review of actual versus planned progress, completion of action items prepared after meetings, monthly invoicing, and progress reporting. Dokken Engineering will use the City standards and formats, making invoice review streamlined and familiar to the City. For our team, quality is not just a priority, it is a core value.

Dokken Engineering has found that the best way to control budget is to ensure the project schedule is followed. This method avoids costly over -runs and extended production times. The key to preserving budgets is to start on time, get it right, and submit the deliverable on time. Utilizing the same design working group from the beginning of the project to the end ensures consistent thought and engineering practice, while eliminating wasteful hours spent “getting familiar” with a project.

The MS Project Schedule will be supplemented with a deliverables schedule that identifies all project deliverables and submittal dates. The deliverables schedule is a critical project management tool because it specifies what is being delivered to the client and when it is to be submitted. The deliverables schedule will be updated monthly and submitted as part of the monthly invoice to report on the sta tus of completed, in -progress and upcoming deliverables.

The combination of the budget and schedule showing task durations and sequencing will enable us to produce a time-phased budget. With a time- phased budget and a work -based method of measuring progres s, a reliable comparison on planned versus actual can be made.

Page | 20

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

PROJECT COMMUNICATION
As an extension of the City staff, Michael and his team will use a suite of communication mechanisms to keep the City informed and to maintain the project schedule. The following diagram identifies the key communication methods to deliver this project.

Dokken Engineering has long-standing history of delivering projects with multiple team members and stakeholders, and we have established communication protocols that all team members understand. We host weekly internal team conference calls to track progress and keep everyone current on project status and recent decisions that affect their awareness and productivity. Our number one goal when working with our clients is successful project delivery.

We identify risks early in the process and develop ways to mitigate these risks. We work closely with o ur clients to keep them informed on the status of their project and any pending decisions, and we are extremely responsive to their needs.

QUALITY CONTROL/QUALITY ASSURANCE
Dokken Engineering and our Team members are committed to the City of Santa Clarita in delivering project documents whose quality exceeds the Industry standards. Quality is not just a priority; it is one of our core values.

From the project outset, QA/QC procedures will be implemented in accordance with the project Scope of Work. Our procedures incorporate continuous product review cycles during plan development, as well as a series of formal review procedures completed for major project deliverables. The review of deliverables needed to satisfy the QA/QC procedure is built into our proposed schedule. The flow chart below outlines our process:

We take quality very seriously, as a quality plan set provides the most competitive bidding opportunities for projects and helps keep projects within their overall budgets, ultimately resulting in a high -quality project being built, on time, and with minimal or no change orders.

PERSONNEL, EQUIPMENT,

AND FACILITIES

Page | 21

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

6. PERSONNEL, EQUIPMENT, AND FACILITIES

SAN DIEGO OFFICE:
1450 Frazee Road, Suite 100
San Diego, CA 92108
Tel (858) 514-8377
Fax (858) 514-8608

FOLSOM OFFICE – HEADQUARTERS:
110 Blue Ravine Road, Suite 200
Folsom, CA 95630

REDDING OFFICE:
2192 Civic Center Drive
Redding, CA 96001

ORGANIZATIONAL STRUCTURE
Business Classification: CA Corporation
Year of Incorporation: 1986
Years Providing Services: 34

PRIMARY REPRESENTATIVE
Michael Greer, PE, TE
[email protected]
 California Licensed Professional
Engineer, #C79080
 California Licensed Traffic Engineer,
#TR 2845

FIRM EXPERTISE
Project Management
Trail, Road & Bridge Design
Traffic Signals & Lighting Design
Environmental Engineering & Planning

CEQA / NEPA
Quality Assurance / Control
Stakeholder Coordination &
Public/Community Outreach
Utility Design & Coordination
Funding Assistance
Right of Way Engineering
Right of Way Acquisition & Relocation
Hydrology & Hydraulics Engineering

SWQMP/SWPPP
Site Design

www.dokkenengineering.com
Established in 1986, DOKKEN ENGINEERING is a civil, transportation, and structural engineering firm with environmental and right of way services that is headquartered in Folsom, California. Since our founding, we have developed an exceptional depth of experience and expertise, having successful ly completed more than 2,500 infrastructure projects, including site design, roadways, bikeways, structures, environmental and right of way projects across the state.

Dokken employs a multi -disciplinary team of civil engineers, structural engineers, roadway engineers, traffic engineers, right of way agents, environmental specialists, hydrologists, and other specialists. Our technical experts and their support staff work to provide seamless and cost effective project delivery. Having these readily available in-house specialists streamlines project coordination by providing easy and effective communication. Our team is also able to utilize collective experience to plan and troubleshoot projects from various aspects.

Dokken’s team of experts have established p rofessional working relationships with federal and state oversight agencies and have a thorough understanding of regulatory processes and standards, including Caltrans Local Assistance Procedures Manual (LAPM) policies and procedures, FHWA requirements, and regulatory agency requirements.

Dokken works almost exclusively with public agencies and many of our staff have substantial experience working for local agencies, Caltrans, and/or resource agencies. This allows us to better understand and meet the need s of our clients and develop the best approach to achieving project delivery. As a result, project management is streamlined, saving valuable time and money.

TRAIL EXPERIENCE
Dokken Engineering staff have completed
several trail and bike/pedestrian bridge
projects throughout California. S ome of
these projects are listed below:
 Coastal Rail Trail (4 Segments)
 Inland Rail Trail (9 Segments)
 San Diego River Trail – Walker Preserve
 Garcia Bend Trail
 Johnny Cash Trail & Bridge
 Homewood Bike Trail
 Bob Jones Bikeway
 Ojai Valley Trail Bridge
 Flint Wash Pedestrain/Equestrain Trail

Page | 22

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

Road and Bikeway Design Services | Roadway projects are an integral component of Dokken Engineering’s services. Our engineers design simple and complex roadway widening/extension projects, as well as the required improvements to the surrounding area, such as sidewalks, bike and pedestrian pathways, bus stop/pullouts and intersection signalizations. Our roadway projects are supported by engineering staff from our specialty groups.

Structures Design | Dokken has successfully completed hundreds of structure designs, from rural two -lane HBP bridges, to complex multi -level freeway-to-freeway interchanges. Additional structure designs include pedestrian overcrossings, bicycle bridges, viaducts, and retaining/sound walls. Dokken has also provided seismic stability evaluations, retrofit plans, specifications, and estimates. Our structures team has innovative and cost-effective design solutions which save our clients millions of dollars. Paying careful attention to the details of a project’s setting, along with client and community feedback, our designs meet the unique conditions of each project.

Signal/Lighting Design | Dokken Engineering has many in-house specialties including Electrical and Traffic Signal Design for public projects. Dokken Engineering’s internal team has provided traffic signals and street lighting plans for a multitude of intersections and streets including lighting design for freeways, bridges, parking lots, and streetscape projects. Services include layout, design, and estimate of signal modifications, new signals, street lighting plans, ITS and TMS design, striping and sign ing plans, and aesthetic lighting for bridges and streetscapes. Our staff is well versed with signal, lighting, and electrical design requirements, and the California MUTCD. We have designed or modified over 200 traffic signals across California.

Traffic Control/Signing & Striping Plans | Dokken Engineering has prepared hundreds of traffic control plans for various projects and agencies. We are familiar with the traffic control requirements, standards, and permitting process. We develop traffic control plans with a focus on safety, while minimizing impacts to the traveling public. Our team develops traffic striping and signing plans per the latest CA MUTCD and agency design standards to support our projects.

Environmental Services | Dokken has an experienced in-house Environmental Services Group that works on our roadway, bridge, and infrastructure projects throughout California. We have established professional working relationships with federal and state regulatory agencies based on technical exc ellence and a thorough understanding of regulatory processes, including: Environmental Document Preparation (NEPA / CEQA Analysis and Compliance); Technical Studies & Reports; and Environmental Regulatory Permitting & Compliance. Dokken’s hands on approach and technical experience have accelerated schedules for all regulatory requirements of the Federal Clean Water Act (CWA), Sections 401, 402, and 404; the National Environmental Policy Act (NEPA); the National Historic Preservations Act (NHPA), Sections 106 and 110; the Federal Endangered Species Act (ESA), Sections 7 and 10; the California Environmental Quality Act (CEQA); the California Endangered Species Act (CESA); and 1600-16116 California Fish and Game Codes.

Drainage Studies and Water Quality Engine ering | Dokken Engineering has staff dedicated to hydrology, hydraulics, and drainage design. These staff members are experts in assessing drainage issues, conducting analyses, and coordinating with other disciplines to develop balanced, cost-effective solutions. Our group concurrently reviews the project improvements to determine the storm water quality management requirements. Each project includes Site Design and Source Control BMPs and may include Treatment Control BMPs. We engage the City early to develop proposed drainage and water quality concepts that accommodate roadway improvements and correct any existing drainage deficiencies.

Utilities | Our team identifies potential conflicts in collaboration with the utility owner representatives and the local agency and develop a comprehensive plan to ensure that all potential conflicts are verified. We understand the importance of accurate utility mapping, positive verification of utility conflicts through potholing, and developin g conflict resolutions early in the design process. We work side -by-side with the local agency and utility owner representatives, creating exhibits as needed to highlight potential conflicts and resolutions for accurate designs that are compatible with the proposed project improvements and construction sequencing.

Page | 23

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

The Dokken Engineering team will be led by Project Manager, Michael Greer, PE, TE, has 15 years of providing civil engineering expertise during planning, design, and construction phases. He also h as extensive knowledge in the design of trails, roadways, and complete streets in accordance with City, County, Caltrans, and AASHTO standards.

He will be supported by a qualified team of professionals providing all of the services required to successfully deliver this project.

Page | 24

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

RESUMES

MICHAEL GREER, PE, TE

PROJECT MANAGER

EDUCATION
2008, BS Civil Engineering
San Diego State University

REGISTRATION
California Professional Civil
Engineer, #79080

California Professional Traffic
Engineer, #2845

EXPERIENCE
15 Years (with Dokken since
2008)

AFFILIATIONS
American Society of Civil
Engineers (ASCE)

Institute of Transportation
Engineers (ITE)

AREAS OF EXPERTISE
 Project Management
 Roadway Design
 Green Streets
 Roundabout Design
 Traffic Signals
 Lighting (State and City)
 Overhead Sign Illumination
 Ramp Metering Systems
 Traffic Monitoring, County
and Vehicle Class Stations
 Interconnection and Fiber
Optic Networks
 Transit Station Amenities
 Utility Coordination

Mr. Greer designs roadways and complete streets in accordance with City, County, Caltrans, and AASHTO standards. He also works on traffic signals, lighting design, and electrical infrastructure giving him the unique ability to foresee various potential issues related to design. He has also worked in the field as a roadway inspector, allowing him the opportunity to gain valuable knowledge about construction equipment, practices, and techniques.

PROJECT EXPERIENCE
Inland Rail Trail, San Diego County, CA │ Project Engineer for this 7 mile Class I bikeway project located within North County Transit District (NCTD) Sprinter rail line right -of-way. The overall purpose of the IRT project is to provide a safe bikeway fac
ility separated from motorized vehicles that will
traverse the Cities of Vista, San Marcos, and the County of San Diego. The design includes three bridge structures, approximately one mile of retaining walls, landscaping, traffic signal plan modifications, extensive analysis of water quality, off-site drainage, signing and striping, and minor street adjustments at each crossing.

Traffic Striping and Signing Plans Associated with County of San Diego Road Maintenance Projects, San Diego County, CA │ Task Order Manager responsible for the traffic striping and signing plans to support and assist the Department of Public Works County of San Diego Road Maintenance Projects for the past three fiscal years (FY 17/18, FY 18/19, and FY 19/20). In total, over the la st three years we have prepared traffic striping and signing plans for nearly 57 miles of roadway, adding approximately 20 miles of Class II bike lanes and 15 miles of Class III bike routes to County roads during the contracted fiscal years.

Paseo Santa Fe Streetscape Improvements Phase II & III, Vista, CA │ Project Engineer /Project Manager for the PS&E of the South Santa Fe Streetscape Improvements, Phases II and III. Design improvements include roundabouts, utility undergrounding, enhanced landscaping and hardscaping, pedestrian oriented streetscape furnishings, and water quality design features that qualify this roadway as a Green Street.

San Pablo Streetscape Improvements, Phase 1 and 2, Palm Desert, CA │ Project Engineer responsible for the design and preparation of plans for the roadway (including pedestrian and roundabout), traffic ele ctrical (including lighting and signal modifications), and traffic control (including signing and striping) improvements portions of this road -diet project. Roundabout Validation Reports, City Council Study Session on Roundabouts, and Position Paper on the Use of Roundabouts versus Stop Control at Intersections were specifically prepared. He also assisted in stakeholder communication and coordination. Understanding the needs of the corridor and desired impact of these transformative projects were essential in assisting the landscape design team with assembly of the Landscape Features Manual, which will continue to be used as a guide for newly added amenities.

Page | 25

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

MARK TARRALL, PE

PRINCIPAL IN CHARGE

EDUCATION
1997, MS Civil Engineering
Georgia Tech

1996, BS Civil Engineering
Virginia Tech

REGISTRATION
California Professional Civil
Engineer, #C71953

EXPERIENCE
22 Years (with Dokken since
2009)

AFFILIATIONS
American Public Works
Association (APWA)

American Society of Civil
Engineers (ASCE)
Mr. Tarrall has over 22 years of experience and specializes in the management, permitting and design of transportation related projects including local roadway, interchange, bike path, highway widening, and transit projects. Mr.

Tarrall has led both local age ncy and Caltrans projects through the concept planning, preliminary engineering, Environmental Document approval, right of way acquisition, and preparation of Final Plans, Specifications and Estimate.

PROJECT EXPERIENCE
Prospect Avenue Corridor Enhancement, Santee, CA │ Project Manager for the Plans, Specifications and Estimate of this $23 million corridor enhancement road widening. The project relied heavily on right of way coordination with property owners, utility companies and the County of San Diego. A significant component was the Rule 20B undergrounding of overhead electric and communications utilities.

San Diego River Trail, Santee, CA │ Project Manager for the preparation of the PS&E for the 1.3 mile extension of the San Diego River Trail, which provided a walking, cycling, and equestrian trail for public use through the 107 acre riverfront property between Magnolia Avenue and the Lakeside Baseball Field.

The project fills a crucial gap in the overall San Diego River Trail, bringing Santee’s portion of the trail to 3.5 miles, or about 80% complete.

ANTHONY POWERS, PE
QA/QC

EDUCATION
1990, MS Structural
Engineering
University of Texas

1984, BS Civil Engineering
University of Notre Dame

REGISTRATION
California Professional Civil
Engineer, #C51772

EXPERIENCE
37 Years (with Dokken since
2009)

AFFILIATIONS
League of American Bicyclists
Mr. Powers has 37 years of experience in a wide range of projects involving planning, design, construction, maintenance inspection and retrofit of highway and pedestrian bridges, light and heavy rail bridges, tunnels, retaining walls, bike trails and hydraulic structures. Mr. Powers has managed design teams preparing bridge advanced planning studies, feasibility studies, preliminary and final plans, specifications, and cost estimates.

PROJECT EXPERIENCE
Johnny Cash Trail and Pedestrian Overcrossing, Folsom, CA │ Project Manager for the design of a new overcrossing of Folsom Lake Crossing Road and 7,100 feet of new, multi -use path. Key issues for the project included
incorporation of significant architectural features reflecting the City’s historical relationship to Johnny Cash and Folsom Prison; an aggressive funding deadline for design; careful planning of drainage design to minimize right of way and tree impacts; utility coordination; and meeting the safety and security needs of the prison.

Homewood Trail Bridge, City of Homewood, CA │ Mr. Powers was responsible for conceptual design and quality assurance to ensure the bridge design met the needs of the Tahoe City Public Utility District (TCPUD). To meet need and design budget of the TCPUD, it was necessary to develop an efficient design that would meet all Caltrans design criteria to ensure a timely approval by Caltrans Local Assistance.

Page | 26

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

JUSTIN THORNBER, PE

CIVIL/TRAIL DESIGN

EDUCATION
2010, BS Civil Engineering
San Diego State University

REGISTRATION
California Professional Civil
Engineer, #C88901

EXPERIENCE
11 Years (with Dokken since
2018)

AFFILIATIONS
American Public Works
Association (APWA)

American Society of Civil
Engineers (ASCE)
Mr. Thornber has a demonstrated history of civil design excellence specifically on-site development plans, construction plans, restoration plans, and grading and erosion control plans. Mr. Thornber is proficient using AutoCAD Civil 3D, Microstation Inroads, HydroCAD, ArcMAP, Flowmaster, Bluebeam, and Projectwise.

PROJECT EXPERIENCE
San Pablo Avenue Streetscape Phases I & II, Palm Desert, CA │ Mr.

Thornber was responsible for preparing the ATP cycle 4 grant application for San Pablo Avenue. He designed the driveways and curb ramps along the San Pablo corridor from Highway 111 to Fred Waring Drive. He developed the cost estimate separated by funding source to aid with funding decisions and reduced construction cost by recommending grind and overlay work, instead of full depth removal, between Royal Palm Drive and Fred Waring Drive.

Paseo Santa Fe Streetscape Phases II & III, Vista, CA │ Design Engineer for the PS&E of the South Santa Fe Streetscape Improvements, Phases II and III.

Design improvements include roundabouts, utility undergrounding, enhanced landscaping and hardscaping, pedestrian oriented streetscape furnishings, and water quality design features that qualify this roadway as a Green Street.

CHARLES TORNACI, PE

STRUCTURES

EDUCATION
1999, BS Mechanical
Engineering
Cal Poly, San Luis Obispo

REGISTRATION
California Professional Civil
Engineer, #C66058

EXPERIENCE
21 Years (with Dokken since
2000)

AFFILIATIONS
American Society of Civil
Engineers (ASCE)
Mr. Tornaci is Dokken’s San Diego structures team leader, both overseeing and performing the structural analysis and design efforts for bridge projects in Southern California. With over 20 years of experience on structural transportation projects spanning over Caltrans, Railroad, and Army Corp facilities, he is very familiar with Caltrans Local As sistance and Division of Structures standards and practices, specializing in innovative and cost - effective design solutions. He has been involved in a wide range of projects involving planning, design, construction, and seismic retrofits of vehicular and pedestrian bridges, retaining walls, and bike trails.

PROJECT EXPERIENCE
Sierra Highway Improvements, Santa Clarita , CA │ Project Manager and Structures Lead Designer responsible for the design of a pedestrian bridge crossing over the Sierra Highway (SR -14U). The project consists of precast concrete slab approach ramps founded on single column bents with platform tops outside of Caltrans right-of-way, leading to the main 150 foot long span crossing over SR -14U. Close coordination and iteration with p roject Geotechnical engineers allowed for the utilization of cost - saving shallow
foundations to support this bridge founded on a mitigated landslide complex in a high seismic region.

Nichi Tunnel, City, CA, Davis, CA | Lead Structures Engineer responsible for the planning studies and cost estimates for a proposed pedestrian railroad crossing. Studies were performed for alignments spanning over (grade separation structure), as well as below (tunnel) existing UPRR tracks.

Page | 27

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

JENA ADDENBROOKE, PE

UTILITY COORDINATION

EDUCATION
2008, BS Civil Engineering
San Diego State University

REGISTRATION
California Professional Civil
Engineer, #C82544

EXPERIENCE
14 Years (with Dokken since
2008)

AFFILIATIONS
Women’s Transportation
Seminar (WTS)
Ms. Addenbrooke has 1 4 years of roadway design experience, specializing in the area of utility coordination. She has an extensive understanding and complies with the FHWA’s regulations and requirements under CFR governing utility relocations to ensure proper and complete utility clearance prior to Right of Way certification. She communicates clearly and efficiently with utility companies, municipal utility departments, clients, Caltrans, and subconsultants to ensure this critical project function is thoroughly and timely addressed.

PROJECT EXPERIENCE
Mid-Coast Corridor Transit Project, San Diego, CA │ Associate Utility Coordinator who assisted with coordination of dry utility relocations. She was responsible for coordinating all utility designs with the respective companies, ensuring relocations were compatible with the combined project plans, processing traffic control and right of way permits for the utility owners, and providing construction support during relocations.

E Palomar St Transit Station, Park & Ride and DAR at I -805, Chula Vista, CA │ Utility Engineer who assisted in utility coordination during the design phase of the I-805 Palomar DAR project. Ms. Addenbrooke identified potential conflicts, prepared pothole plans, monitored all activity in the field, and verified utility conflicts for the project. She also prepared recycled water project utility sheets in accordance with Otay Water District design standards.

ASHLEY ORSABA-FINDERS, PE, QSD/P

DRAINAGE

EDUCATION
2012, Master of Business
Administration, Drexel
University

2007, BS Civil Engineering,
California State University,
Sacramento

REGISTRATION
California Professional Civil
Engineer, #C77894

LEED AP | ENV SP |
Qualified SWPPP Developer/
Practitioner | California
Drinking Water Operator D1

EXPERIENCE
14 Years (with Dokken since
2017)
Ms. Orsaba-Finders has over 1 4 years of experience in project management, civil engineering, site development, environmental engineering, municipal engineering, planning, and GIS analysis. She is experienced in design, hydraulic modeling, planning, drafting and design of civil engineering projects including drainage, utility design, site design, and pump stations.

PROJECT EXPERIENCE
I-80 Auxiliary Lanes, Placer County, CA │ Ms. Orsaba-Finders is the drainage lead for the Caltrans District 3 Interstate 80 Auxiliary Lanes project which will add additional lanes within Placer County along the busy I- 80 corridor within the cities of Roseville and Rocklin. She is currently leading the drainage, water quality, bridge hydraulics, temporary water pollution control, and erosion control disciplines for the project. The project includes the design of basins, water quality features, storm drainage pipeline systems, outfalls, and ditches.

She also was responsible for the Drainage Report, Storm Water Data Report, and Bridge Design Hydraulics Report for the project.

SANDAG South Bay BRT East Palomar Street Improvements, Chula Vista, CA│ │ This project constructed several miles of transit guideway in the Chula Vista area including extensive LID drainage features include bioswales, underground detention vaults, and stormwater treatment BMPs. Ms. Orsaba- Finders performed engineering design, report writing, and drafting in support of the project.

Page | 28

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

SHAWN KENNEY, QSD/P, CPSWQ

DRAINAGE

EDUCATION
2009, BS Civil Engineering
University of New Hampshire

REGISTRATION
California QSD/P, #26884

CPSWQ, #1141

New Hampshire Engineer in
Training, #5198

EXPERIENCE
12 Years (with Dokken since
2016)

Mr. Kenney is experienced in the development of hydrologic and hydraulic models using software such as PondPack, HEC-HMS, HEC-RAS, StormCAD, and AES to analyze existing and proposed project conditions. Approach methodologies, analysis, recommendations, and conclusions are ultimately included in drainage and stormwater reports in accordance with client or public agency requirements. His responsibilities also include the preparation of plans, specifications, and estimates associated with drainage and erosion control improvements.

PROJECT EXPERIENCE
Miramar Street and Athena Circle Improvements, UCSD, San Diego, CA │ Assistant Engineer assisted with the design of the project ’s drainage systems including the underground storm drain pipe network and dual -purpose bioretention basin. He was also responsib le for stormwater reporting and preparation of water pollution control plans. He assisted with developing the estimate and the drainage report.

Lemon Crest Drainage Improvements, San Diego County, CA │ Assistant Water Resources Engineer for the drainage de sign to improve channel hydraulics and protect the channel and adjacent properties from erosion.

Improvements included design of a triple 6 ’x3’ box culvert, clearing a section of the unnamed channel, and erosion control measures such as revegetation, rock slope protection, and a stabilized modular block access road.

ANTHONY LAWSON, RLA

PUBLIC OUTREACH/PLANNING

EDUCATION
BS Landscape Architecture
Cal Poly, San Luis Obispo

REGISTRATION
California Landscape Architect,
#2348

EXPERIENCE
40 Years

AFFILIATIONS
American Society of Landscape
Architects (ASLA)

Mr. Lawson founded ADL Planning Associates, Inc. in 1986 with the mission of providing high quality planning, design and landscape architectural services to developers, builders and public agencies. With more than 40 years in the
industry, Mr. Lawson has obtained valuable experience in the planning, design, permitting and construction support of all project types, including: large scale master planned communities, site specific feasibility studies, parks and recreational facilities, commercial, educational, streetscapes and other civic development. He has served on numerous Commissions, Boards and Committees for the City of Carlsbad and is currently teaching landscape architecture at Mesa Community College in San Diego.

PROJECT EXPERIENCE
• McFadden Avenue Bike Improvements, Santa Ana, CA
• San Pablo Avenue Street & Bike Improvements, Palm Desert, CA • Paseo Santa Fe Streetscape, Vista, CA
• Pioneer Boulevard Streetscape, Artesia, CA
• El Camino Real Street & Bike Improvements, Carlsbad, CA • College Boulevard Street & Bike Improvements, Carlsbad, CA

Page | 29

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

ALAN RASPLICKA, PE, GE

GEOTECHNICAL

EDUCATION
BS Civil Engineering
Cal Poly, Pomona

REGISTRATION
California Professional Civil
Engineer, #C53575

California Geotechnical
Engineer, #GE 2558

EXPERIENCE
28 Years

Mr. Rasplicka has over twenty -eight years of experience in the field of geotechnical and environmental engineering. His experience includes field and laboratory work, field supervision, and environmental and geotechnical investigations. Mr. Rasplicka has performed geotechnical investigations and provided grading and foundation recommendations for many projects, including shopping centers, industrial centers, residences, apartments, office buildings, bridges, aqueducts, and
critical facilities, including medical
buildings, schools, and fire stations. He has also investigated several distressed residences, apartment buildings, condominiums, slopes, and shopping centers.

He has provided expert witness services for distressed residences, expansive soils, retaining walls, gross slope stability, and surficial stability.

PROJECT EXPERIENCE
• Performed peer review of geotechnical reports performed by other geotechnical consultants and also regulatory review of geotechnical reports for the City of Santa Clarita
• Performed geotechnical safety hazard evaluations for several single - family residences for the City of Santa Clarita from conditions resulting from the 2005 rainy season

MIKE LOPEZ, PLS

SURVEYING

EDUCATION
Ventura Community College

REGISTRATION
California Professional Land
Surveyor, #8995

Certified Party Chief, JAC Local
12 EXPERIENCE
32 Years

AFFILIATIONS
California Land Surveyors
Association (CLSA)

Mr. Lopez h as an extensive background in both field and office procedures relative to boundary and cadastral surveys, topographic mapping, construction stakeout, engineering design, GPS control, GIS and CADD mapping. He is also familiar with survey supervision coordination, calculations, and analysis in support of survey crews.

PROJECT EXPERIENCE
AMLI Spanish Hills, CA │ Technical Manager responsible for project surveying. Michael Baker provided stormwater support to AMLI Residential that included developing a stormwater pollution prevention plan (SWPPP) and filing permit registration documents in SMARTS.

On-Call Survey and Mapping, Ventura County , CA │ Survey Manager responsible for project surveying. Michael Baker provided on- call surveying and mapping services to the County Surveyors Office, Engineering Services Department and Watershed Protection District. Services included: topographic mapping, ground control for aerial mapping, and technical map checking of Subdivision and Record of Survey maps, legal descriptions, corner records and lot line adjustment documents.

Page | 30
SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

RELATIONSHIP TO COST
The table below identifies the hours and reimbursement rates for each staff member proposed for the project.

STAFF MEMBER PROJECT ROLE HOURS REIMBURSEMENT RATE
Michael Greer, PE, TE Project Manager 66 $225.00
Justin Thornber, PE Civil/Trail Design 80 $160.00
Charles Tornaci, PE Structures 39 $215.00
Jena Addenbrooke, PE Utility Coordination 52 $165.00
Ashley Orsaba-Finders, PE, QSD/P Drainage 73 $185.00
Shawn Kenney, QSD/P, CPSWQ Drainage 70 $145.00
Dokken Engineering Staff Assistant Engineer 238 $115.00 Dokken Engineering Staff CAD Tech 141 $105.00
Anthony Lawson, RLA Public Outreach/Planning 20 $175.00* Alan Rasplicka, PE, GE Geotechnical 20 $194.37
RTF&A Staff Principal Engineer 5 $285.97
RTF&A Staff Project Engineer 16 $152.05
RTF&A Staff Staff Engineer 12 $87.81
RTF&A Staff Contract Administration 4 $107.47
Mike Lopez, PLS Surveying 3 $175.00
Vertex Surveyors Staff Project Manager / Supervisor 10 $160.00 Vertex Surveyors Staff 2-Man Field Crew 12 $275.00
Vertex Surveyors Staff Technical Support 25 $140.00
Vertex Surveyors Staff Administrative Support 10 $100.00 * Listed as ODC on Cost Proposal along with Property Owner Exhibits and Potholing Services (Total ODC’s = $10,150.33)

SUBCONSULTANTS

Page | 31

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

7. SUBCONSULTANTS
Dokken Engineering has utilized many valuable sub -consultants to complete past projects and has compiled an outstanding team for this project. The team has the capabilities to deliver all services outlined in the RFP . The following identifies one proposed subconsultant on the Dokken Engineering Team, their role, a brief description of the firm and relevant experience.

ROLE: LANDSCAPE ARCHITECTURE

ADL PLANNING ASSOCIATES
2979 State Street
Suite C
Carlsbad, CA 92008
(760) 729.8637
ADL Planning Associates is a full-service planning and landscape architectural firm providing comprehensive consulting, design and construction support services since 1986. With a focus on municipal and public sector, or CIP improvements, the firm has desi gned and oversaw the installation of many successful Roadway Projects, Streetscapes, Bike Lanes and Trails throughout the southland.

Key factors of experience attributable to ADL for this proposed project include:
• Significant Public Street Landscape Improvement projects addressing:
• Multi-Modal Improvements
• Green Street, Urban Forest & Low Impact Development (LID) Projects • Road Diet & Traffic Calming
• Pedestrian and Bike Trail experience
• Public Street Plazas Improvements
• Significant experience collaborating with Dokken Engineering throughout southern California
ADL is presently working with Dokken Engineering on numerous public works projects in the communities of Carlsbad, Vista, San Diego, Palm Desert, Newport Beach and Santa Ana. Additionally, ADL has or is currently providing landscape design consulting services directly to the cities of Menifee, La Mesa, San Marcos, Oceanside, Artesia, La Mirada and Carson California. Experience working directly with the public agencies, coupled with bike and trail experience will position ADL to execute this design assignment effectively, efficiently, and successfully.

ROLE: GEOTECHNICAL

R.T. FRANKIAN &
ASSOCIATES, INC.
26027 Huntington Lane
Suite A
Santa Clarita, CA 91355
(661) 257.5800
R. T. Frankian & Associates, Inc., is one of the longest established geotechnical consulting firms in Southern California. We specialize in geotechnical engineering, environmental engineering, engineering geology, storm water infiltration/environmental compliance, and geot echnical services, which include materials testing and inspection. Our main office and laboratory are located within the County of Los Angeles in the City of Santa Clarita. We operate a small corporate and administrative office in Burbank, California. The firm is a California corporation and was founded in 1963.

The projects we have worked on include geotechnical investigation, analysis, inspection and testing of over 150 miles of new roads and highways, 85 miles of public storm drains, 90 miles of sanitary sewer, 250 miles of utility lines, 35 miles of soil cement and the placement of nearly 250 million cubic yards of compacted fill, nearly 35 bridges, and over 45 schools and 15 hospitals.

Relevant project experience includes:
• City of Santa Clarita Paved Trail and Paseo System
• Vista Canyon Open Space Trail System

Page | 32

SAUGUS PHASE I: BOUQUET CANYON TRAIL TO

CENTRAL PARK
PROPOSAL #ENG-21-22-C0066

ROLE: SURVEYING

VERTEX SURVEYING, INC.
28348 Constellation Road
Suite 800
Santa Clarita, CA 91355
(661) 254.1928
Since 2001 Vertex Survey, Inc. (formerly Pinnacle Land Surveying) has provided land surveying services to municipalities, counties, planners, design professionals, contractors, developers, and private parties. Our services range from boundary and topographic surveys, construction staking, mapping, aerial topographic surveys, monumentation, ALTA preparation, as well as legal descriptions. Field surveying projects have contributed to planning, design and construction of water treatment plants, wastewater treatment plants, pumping stations and pipelines, reservoirs, residential developments, roads, bridges, landfills, commercial buildings, parks, fire stations, as well as infrastructure.

Vertex Survey, Inc. is and has recently provided various surveying and mapping services to several Cities in accordance with Chapter 10 of the Caltrans Local Assistance Procedure Manual as well as to Caltrans Survey Standards. These projects have included bridge widening, grade separations, and street improvements. Our team understands the important aspects of construction staking that will b e required for this project. Relevant project experience includes:
• Williams S. Hart School District/ Survey at Golden Valley HS and West Ranch HS
• Multiple Improvements for College of the Canyons with multiple contractors
• Vista Canyon Ranch, Santa Clarita/Contracted by: JSB Development • Runkle Canyon, Simi Valley Contracted by: KB Home
• Deerlake, Chatsworth Contracted by: Foremost Communities • Santa Clarita Valley Water Agency/Plat to Accompany Legal Description / State Board of Equalization

FORMS

NOTICE TO PROPOSERS REGARDING CONTRACTUAL REQUIREMENTS
PROFESSIONAL SERVICES AGREEMENT – DESIGN

PROPOSAL # ENG-21-22-C0066
Saugus Phase I: Bouquet Canyon Trail to Central Park
City Project No. C0066
City of Santa Clarita, California

SUMMARY OF INDEMNITY AND INSURANCE REQUIREMENTS

1. These are the Indemnity and Insurance Requirements for Contractors providing services or supplies to City of Santa Clarita (City). By agreeing to perform the work or submitting a proposal, you verify that you comply with and agree to be bound by these requirements. If any additional Contract documents are executed, the actual Indemnity language and Insurance Requirements may include addi tional provisions as deemed appropriate by City’s Risk Manager.

2. You should check with your Insurance advisors to verify compliance and determine if additional coverage or limits may be needed to adequately insure your obligations under this agreement. These are the minimum required and do not in any way represent or imply that such coverage is sufficient to adequately cover the Contractor’s liability under this agreement. The full coverage and limits afforded under Contractor’s policies of Insurance sha ll be available to Buyer and these Insurance Requirements shall not in any way act to reduce coverage that is broader or includes higher limits than those required.

The Insurance obligations under this agreement shall be: 1—all the Insurance coverage and limits carried by or available to the Contractor; or 2 —the minimum Insurance requirements shown in this agreement, whichever is greater. Any insurance proceeds in excess of the specified minimum limits and coverage required, which are applicable to a given loss, shall be available to City.

3. Contractor shall furnish the City with original Certificates of Insurance including all required amendatory endorsements and a copy of the Declarations and Endorsement Page of the CGL policy listing all policy endorsements to City before work begins. City reserves the right to require full- certified copies of all Insurance coverage and endorsements.

I. INDEMNIFICATION:
(A) To the fullest extent permitted by law, including without limitation Civil Code sections 2782 and 2782.8, CONSULTANT shall defend (with legal counsel reasonably acceptable to CITY), indemnify and hold harmless CITY and its officers, agents, departments, officials, representatives and employees (collectively “Indemnitees”) from and against any and all clai ms, loss, cost, damage, injury (including, without limitation, economic harm, injury to or death of an employee of CONSULTANT or its subconsultants), expense and liability of every kind, nature and description that arise from or relate to (including, witho ut limitation, incidental and consequential damages, court costs, attorneys’ fees, litigation expenses and fees of expert consultants or expert witnesses incurred in connection therewith and costs of investigation) that arise from or relate to, directly or indirectly, in whole or in part, from: (1) any negligent act or omission of CONSULTANT, any subconsultant, anyone directly or indirectly employed by them, or anyone that they control; (2) any actual or alleged infringement of the patent rights, copyright, trade secret, trade name, trademark, service mark or any other intellectual or proprietary right of any person or persons in consequence of the use by CITY, or any other Indemnitee, of articles or Services to be supplied in the performance of this Agreem ent; or (3) any breach of this Agreement (collectively “Liabilities”). Such obligations to defend, hold harmless and indemnify any Indemnitee shall not apply to

the extent such Liabilities are caused by the sole or active negligence or willful misconduct of such Indemnitee, but shall apply to all other Liabilities.
(B) The foregoing indemnification provisions will not reduce or affect other rights or obligations which would otherwise exist in favor of the CITY and other Indemnitees. (C) CONSULTANT shall place in its subconsulting agreements and cause its subconsultants to agree to indemnities and insurance obligations in favor of CITY and other Indemnitees in the exact form and substance of those contained in this Agreement.

II. INSURANCE
(A) Before commencing performance under this Agreement, and at all other times this Agreement is effective, CONSULTANT will procure and maintain the following types of insurance with coverage limits complying, at a minimum, with the limits set forth below:

Type of Insurance Limits
Commercial general liability: $1,000,000
Professional liability $1,000,000
Business automobile liability $1,000,000
Workers compensation Statutory requirement
(i) Commercial general liability insurance will meet or exceed the requirements of ISO-CGL Form No. CG 00 01 11 85 or 88. The amount of insurance set forth above will be a combined single limit per occurrence for bodily injury, personal injury, and property damage for the policy coverage.

Automobile coverage will be written on ISO Business Auto Coverage Form CA 00 01 06 92, including symbol 1 (Any Auto). Liability policies will be endorsed to name CITY, its officials, and employees as “additional insureds” under said insurance coverage and to state that such insurance will be deem ed “primary” such that any other insurance that may be carried by CITY will be excess thereto. Such endorsement must be reflected on ISO Form No. CG 20 10 11 85 or 88, or equivalent. Such insurance will be on an “occurrence,” not a “claims made,” basis a nd will not be cancelable or subject to reduction except upon thirty (30) days prior written notice to CITY. (ii) Professional liability coverage will be on an “occurrence basis” if such coverage is available, or on a “claims made” basis if not available. When coverage is provided on a “claims made basis,” CONSULTANT will continue to renew the insurance for a period of at least three (3) years after this Agreement expires or is terminated. Such insurance will have the same coverage and limits as the policy that was in effect during the term of this Agreement, and will cover CONSULTANT for all claims made by CITY arising out of any errors or omissions of CONSULTANT, or its officers, employees or agents during the time this Agreement was in effect.
(B) CONSULTANT will furnish to CITY duly authenticated Certificates of Insurance evidencing maintenance of the insurance required under this Agreement, including endorsements, and such other evidence of insurance or copies of policies as may be reasonably required by CITY from time to time.

Insurance must be placed with California- admitted insurers with (other than workers compensation) a current A.M. Best Company Rating of at least “A:VII.”
(C) Waiver of Subrogation: The insurer(s) agree to waive all rights of subrogation against CITY, its elected or appointed officers, officials, agents, volunteers and employees for losses paid under the terms of the workers compensation policy which arise from work performed by CONSULTANT for CITY. (D) Should CONSULTANT, for any reason, fail to obtain and maintain the insurance required by this Agreement, CITY may obtain such coverage at CONSULTANT’s expense and deduct the cost of such insurance from payments due to CONSULTANT under this Agreement or terminate pursuant to TERMINATION section. In the alternative, should CONSULTANT fail to meet any of the insurance requirements under this Agreement, City may terminate this Agreement immediately with no penalty. (E) Should CONSULTANT’S insurance required by this Agreement be cancelled at any point prior to expiration of the policy, CONSULTANT must notify City within 24 hours of receipt of notice of cancellation. Furthermore, CONSULTANT must obtain replacement coverage that meets all contractual requirements within 10 days of the prior insurer’s issuance of notice of cancellation. CONSULTANT must ensure that there is no lapse in coverage.
(F) The CITY shall be entitled to any coverage in excess of the minimums required herein.

I h
ave read and understand the above requirements and agree to be bound by them for any work performed for the City.

Au
thorized Signature: ______________________________ Date: ___________________ Pr
inted Name: ____________________________________
2/28/2022
John Klemunes, PE

DESIGNATION OF SUBCONTRACTORS/SUBCONSULTANTS

PROPOSAL
# ENG-21-22-C0066
Saugus Phase I: Bouquet Canyon Trail to Central Park
City Project No. C0066
City of Santa Clarita, California
Listed below are the names and locations of the places of business of each subcontractor, supplier, and vendor who will perfo rm work or labor or render service in excess of ½ of 1 percent, or $10,000 (whichever is greater) of the prime contractor's total bid . If no Subcontractors will be used fill out the form with N/A. Please add additional sheets if needed.

Subcontractor DIR Registration No. Dollar Value of Work Location and Place of Business
Bid Schedule Item No’s:

License No. Exp. Date: / / Phone ( )
Subcontractor DIR Registration No. Dollar Value of Work Location and Place of Business
Bid Schedule Item No’s: Description of Work
License No. Exp. Date: / / Phone ( )
Subcontractor DIR Registration No. Dollar Value of Work Location and Place of Business
Bid Schedule Item No’s: Description of Work
License No. Exp. Date: / / Phone ( )
NOTE: A contractor or subcontractor shall not be qualified to propose on, be listed in a proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perform public wor k pursuant to Section 1725.5 of the Labor Code. It is not a violation of this section for an unregistered contractor to submit a proposal that is authorized by Section 7029.1 of the Business and Professions Code or by Section 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perform public work pursuant to Section 1725.5 of the Labor Code at the time the contract is awarded.

ADL Planning Associates 1000061511
2979 State Street, Suite C, Carlsbad, CA 92008
Description of Work
Public Outreach/Planning
PLA #2348 3/31/2023 (760) 729-8637
Vertex Survey, Inc. 1000023128
28348 Constellation Road, Suite 800, Santa Clarita, CA 91355 Surveying
PLS 8995 (661) 254-19289/30/2023
R.T. Frankian & Associates, Inc.
26027 Huntington Lane, Suite A, Santa Clarita, CA 91355 Geotechnical Engineering
(661) 257-5800CE 53575 6/30/2023
$10,000
Task 1
$9,233.59
Task 2
$10,075.17
Task 2

REFERENCES

PROPOSAL # ENG-21-22-C0066
Saugus Phase I: Bouquet Canyon Trail to Central Park
City Project No. C0066
City of Santa Clarita, California
The following are the names, addresses, and telephone numbers of three public agencies for which proposer has performed work of a similar scope and size within the past 3 years. If the instructions on this form conflict with the references requested in the scope of work, the scope of work shall govern. Complete this form out accordingly. Fill out this form completely and upload it with your proposal.

1. City of Santee, 10604 Magnolia Avenue, Santee, CA 92071 Name and Address of Owner / Agency

Carl Schmitz, PE, (619) 258-4100

Name and Telephone Number of Person Familiar with Project Preliminary Engineering, PS&E,
$3.6 Million to date Construction Support On-going

Contract Amount Type of Work Date Completed

2. City of Palm Desert, 73510 Fred Waring Drive, Palm Desert, CA 92260 Name and Address of Owner / Agency

Randy Bowman, (760) 776-6493

Name and Telephone Number of Person Familiar with Project

$1.6 Million PS&E, Construction Support 2021
Contract Amount Type of Work Date Completed

3. City of Vista, 200, Civic Center Drive, Vista, CA 92084 Name and Address of Owner / Agency

Conrad “Skip” Hammann, (760) 802-5605
Name and Telephone Number of Person Familiar with Project

$1.9 Million PS&E, Construction Support 2021
Contract Amount Type of Work Date Completed

The following are the names, addresses, and telephone numbers of all brokers and sureties from whom Proposer intends to procure insurance bonds:

Dealy, Renton & Associates, P.O. Box 12675, Oakland, CA 94604, (510) 465-3090

EQUAL OPPORTUNITY/AFFIRMATIVE ACTION STATEMENT
PROPOSAL # ENG-21-22-C0066
Saugus Phase I: Bouquet Canyon Trail to Central Park
City Project No. C0066
City of Santa Clarita, California
T
he offeror hereafter described will not discriminate against any employee or applicant for employment because of race/color, national origin, sex, sexual preference, religion, age, or handicapped status in employment or the provisions of services.
___
_____________________________________
Signature
___
______________________________________
Typed Name and Title
John Klemunes, PE, President

CITY OF SANTA CLARITA DISCLOSURE STATEMENT
P
ROPOSAL # ENG-21-22-C0066
Saugus Phase I: Bouquet Canyon Trail to Central Park
City Project No. C0066
City of Santa Clarita, California
T
he following information must be disclosed:

1. List the names of all persons having a financial interest in the Request for Qualifications.

2. I
f any person identified pursuant to No. 1 above is a corporation or partnership, list the names of all individuals owning more than ten percent of the shares in the corporation or owning any partnership interest in the partnership.

3. I
f any person identified pursuant to No. 1 above is a non-profit organization or a trust, list the names of any persons serving as a director of the non-profit organization or as a trustee or b
eneficiary or trustor of the trust.

4. H
as the offeror had more than $250.00 worth of business transacted with any member of the C
ity of Santa Clarita staff, boards, commissions, committees, and Council within the past twelve months? If yes, please indicate the person(s) with whom you have conducted business.

N
OTE: Attach additional pages as necessary.
____
_____________________________
Signature of Offeror
____
_____________________________
Print or Type Name of Offeror
____
_____________________________
Date
N/A
N/A
N/A
N/A
John Klemunes, PE
2/28/2022

ACKNOWLEDGEMENT & ACCEPTANCE OF SCOPE OF WORK
P
ROPOSAL # ENG-21-22-C0066
Saugus Phase I: Bouquet Canyon Trail to Central Park
City Project No. C0066
City of Santa Clarita, California
By providing the three (3) required signatures below, the Contractor acknowledges full understanding, complete agreement to, and accepts in its entirety, all Scope of Work for the Saugus Phase I: Bouq uet Canyon Trail to Central Park . The Contractor will be expected to perform maintenance practices and uphold the standards herein to the established Scope of Work throughout the length of the contract. *S
upervisor’s Signature:___________________________________________Date:__________ *Es
timator’s Signature:____________________________________________Date:__________ *
Owner’s Signature:______________________________________________Date:__________ *
All three signatures required
2/28/2022
2/28/2022
2/28/2022

Addendum No. 1
February 8, 2022

PROPOSAL # ENG-21-22-C0066

Addendum No. 1

PROPOSAL # ENG-21-22-C0066
Saugus Phase I: Bouquet Canyon Trail to Central Park
This addendum must be acknowledged via BidNet and should be included with the proposal response.

There was a non-mandatory, pre-proposal meeting on February 2, 2022 beginning at 10:00 a.m.

The meeting was located at Central Park, 27150 Bouquet Canyon, Santa Clarita, CA 91350.

Attending Staff:

• Araz Valijan – Project Manager, Public Works
• Alexander Porlier – Project Manager, Public Works
• Patrick De Guzman – Engineer, Public Works
• Christine Saunders – Administrative Analyst, Clerk & Contract Services • Ines Guevara – Office Assistant, Clerk & Contract Services

Attending Vendors:

• Kristina Jacob, Santa Clarita Valley Water Agency
• Jennifer Gangl, Nagle Earthworks
• Chris Bretall, GHD, Inc.
• Charles Tornaci, Dokken Engineering
• Michael Greer, Dokken Engineering
• Ashley Haire, Alta Planning + Design
• Michael Ip, MNS Engineers
• Narasimha Murthy, CWE
• Rick Estrada, Vertex Survey, Inc.

The following questions were asked and answered:

Q1) Has this project undergone environmental clearance? A1) Yes, however, there may be consideration of tree removal involved.

Q2) If tree removal is required, will it be necessary to salvage those trees? A2) No.

Q3) Will there be any additions or modifications to the right of way in the project area? A3) No new right of way is anticipated. The right of way will, however, need to be mapped by the awarded consultant.

Addendum No. 1
February 8, 2022

PROPOSAL # ENG-21-22-C0066

Q4) What is the preferred width of the trail?
A4) 10 feet from edge-to-edge of the pavement allowing 1-2 feet of clearance for the existing lodgepole fencing.

Q5) Who is responsible for maintaining the existing irrigation? A5) City of Santa Clarita Parks Division.

Q6) Does the City wish to keep the existing wooden lodge-pole fencing? A6) Yes.

Q7) Will new fencing be needed on the channel side of the trail? If so, what type of fencing is preferred? Are there footings/foundations for the fencing? A7) New fencing will be needed. Vinyl fencing is acceptable. There are footings/foundations for the fencing.

Q8) Is there any landscaping involved in the scope of work? A8) No.

Q9) Are there any drainage outfalls along the channel?
A9) Please see the below video links of the Bouquet Creek Channel.

Q10) Will lighting be required?
A10) No.

Q11) Are there any gates on the trail?
A11) No, please see the below video links of the Bouquet Creek Channel.

Q12) Will there be any signal modifications or intersection improvements involved in the scope of work?
A12) No.

Q13) Are there any issues with homeless encampments in the project area? A13) No.

Q14) Do the homes along the route have private access to the trail? A14) No. If any issues arise related to homeowner access, they will be addressed.

Q15) Has there been any previous outreach to homeowners regarding this project? A15) There was a hit-the-trail event in May 2021 where homeowners and the community were invited to see the potential of the future trail.

Q16) Will translation services be required for public outreach meetings? A16) Yes, in Spanish.

Q17) Will sub-grade investigations of the turf/dirt be required? A17) No.

A
ddendum No. 1
February 8, 2022
PROPOSAL # ENG-21-22-C0066
Q18
) Will fencing along the channel be required to be “break away?” A18) We will determine this when we go into design for the project.

Q
19) Will the trail end at the curb return at the entrance of the park? A19) Yes.

Q
20) Will trail markers for emergency purposes may be added? A20) That can be something we can consider after the trail has been constructed.

The following was reviewed:
• P
roject scope of work
• Bidding Guidelines
Attachments:
• Pr
e-Proposal Meeting Agenda
• Pre-Proposal Meeting Attendee Sign-In Sheet
• Conceptual Exhibit
• Bouquet Creek Channel GoPro Videos:
o Bouquet Trail WB https://www.youtube.com/watch?v=VUFdBvxtCAI o Bouquet Trail EB https://www.youtube.com/watch?v=9RdQg78vLsM • Channel GoPro Footage Timestamps
E

ND OF ADDENDUM
T
his addendum must be acknowledged via BidNet and should be included with the response. ____________________
________________ ____________
Contractor’s Representative Date
____________________
________________
Company Name
2/28/2022
Dokken Engineering
COST PROPOSAL ‐ ESTIMATED HOURS BY TASK
City of Santa Clarita
Saugus Phase I: Bouquet Canyon Trail
BILLING RATE
TASK 1:  PROJECT MANAGEMENT

1.1:  Project Kick‐off and PDT Meetings

1.2:  Public Outreach

1.3:  Schedule and Administration
TASK 2:  SITE AND UTILITY INVESTIGATION

2.1:  Data Collection and Field Review

2.2:  Topographic Surveying and Right of Way Engineering

2.3:  Utility Investigations, Base Mapping, and Potholing

2.4:  Geotechnical Investigations, Coring, and Testing
TASK 3:  UTILITY COORDINATION

3.1:  Utility Coordination

3.2:  Utility Relocation Plans
TASK 4:  HYDROLOGY & HYDRAULICS

4.1:  SUSMP for MS4 Permit/Water Quality Compliance

4.2:  Drainage Analysis and Report
TASK 5:  PLANS, SPECIFICATIONS, AND ESTIMATE (PS&E)

5.1:  60% PS&E

5.2:  90% PS&E

5.3:  100% PS&E

5.4:  Final PS&E

5.5:  Plan Approvals and Permits

5.6:  Bidding
TASK 6:  CONSTRUCTION SUPPORT (OPTIONAL TASK)

6.1:  Construction Support

6.2:  As‐Built Plans
TOTAL HOURS WITHOUT OPTIONAL TASK 6
TOTAL COST WITHOUT OPTIONAL TASK 6
TOTAL HOURS WITH OPTIONAL TASK 6
TOTAL COST WITH OPTIONAL TASK 6
TASK DESCRIPTION
Principal Engineer
Project Manager
Project Engineer
Staff Engineer
Contract Administration
TOTAL HOURS  OTHER DIRECT
COST   TOTAL COST
Principal / Licensed Surveyor
Project Manager / Supervisor
2‐Man Field Crew
Technical Support Staff
Administrative Support Staff
TOTAL HOURS  OTHER DIRECT
COST   TOTAL COST
$       285.97   $         194.37   $         152.05   $           87.81   $       107.47   $       175.00   $       160.00   $       275.00   $       140.00   $       100.00 ‐$                  ‐ $   ‐$                  ‐$                  66 5,000.00$         17,300.00$ ‐$   ‐$   42 ‐$   7, 870.00$
‐$   ‐$   12
5,000.00$            6,990.00$
‐$   ‐$   12 ‐$   2,
440.00$
52 01 61 245 7 ‐$                  9,233.59$         3 10 12 25 10 60 150.33 $           10,075.17$     190 5,150.33$         35,093.76$ ‐$   ‐$   6 ‐$   1, 095.00$
‐$   3
10 12 25 10 60 150.33$              10,075.17$         64 150.33$               10,710.17$ ‐$   ‐$   44
5,000.00$            10,660.00$
5 20 16 12 4 57 9,233.59$             ‐$   76 ‐$   12,
628.59$
‐$                  ‐ $   ‐$                  ‐$                  86 ‐$                   12,250.00$ ‐$   ‐$   68 ‐$   9, 880.00$
‐$   ‐$   18 ‐$   2,
370.00$
‐$                  ‐ $   ‐$                  ‐$                  180 ‐$                   22,800.00$ ‐$   ‐$   72 ‐$   9, 120.00$
‐$   ‐$   108 ‐$   13,
680.00$
‐$                  ‐ $   ‐$                  ‐$                  354 ‐$                   52,310.00$ ‐$   ‐$   108 ‐$   15, 740.00$
‐$   ‐$   108 ‐$   15,
740.00$
‐$   81 ‐$   11,
805.00$
‐$   27 ‐$   3,
935.00$
‐$   ‐$   19 ‐$   3,
095.00$
‐$   ‐$   11 ‐$   1,
995.00$
‐$                  ‐ $   ‐$                  ‐$                  42 ‐$                   6,310.00$ ‐$   ‐$   30 ‐$   4, 550.00$
‐$   ‐$   12 ‐$   1,
760.00$
5 2 0 1 6 1 2 4 5 7 3 1 01 22 51 0 6 0 8 7 6
1,429.86$  3,887.40$    2,432.76$    1,053.69$    429.88$      ‐$                  9,233.59$         525.01$      1,599.96$  3,300.00$  3,499.91$  999.97$      150.33$           10,075.17$     10,150.33$       139,753.76$ 5 2 0 1 6 1 2 4 5 7 3 1 01 22 51 0 6 0 9 1 8
1,429.86$  3,887.40$    2,432.76$    1,053.69$    429.88$      ‐$                  9,233.59$         525.01$      1,599.96$  3,300.00$  3,499.91$  999.97$      150.33$           10,075.17$     10,150.33$       146,063.76$ GRAND TOTAL
HOURS
GRAND TOTAL
OTHER DIRECT
COSTS
GRAND TOTAL
COST
VERTEX SURVEYORSRTF&A
DOKKEN ENGINEERING 4/5/2022