PROPOSAL
Submitted by NV5, Inc.
1868 Palma Drive, Suite A-E, Ventura, CA 93003

City of Santa Clarita
Inspection and Construction Oversight Services for Copper Hill Drive Bridge Widening, City Project No. S1050
August 17, 2023

TABLE OF CONTENTS
Cover Letter 02

1. INTRODUCTION
Introduction + Project Understanding 03

1. Project Understanding 03

2. Project Objectives 03

3. Key Project Issues 04
Project Approach 07

1. Cost Control 07

2. Schedule Management 07

3. QA/QC Plan 12
Work Plan/Scope of Work 13

2. QUALIFICATIONS
19 19

2. Organization Chart 20

3. Key Staff Biographies 21

4. Resumes 23

5. Project Experience 33
39 7. Local Presence 40

8. References 41
Table of Contents
“ “
The NV5 staff is knowledgeable, courteous and friendly, and they truly care about their projects and the services they provide. From Engineering Design to Inspection to Plan Check Services, the NV5 team can do it all, and we can always rely on them to deliver a quality product on time and within budget. - Matthew Sinacori, Director of Public Works/City Engineer, City of Dana Point City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 1 Jeff Pallesen, PE, QSD/P
Vice President, Operations/
Principal-in-Charge
Michael Dipsia, PE, QSD/P
Project Manager/
Lead Inspector

COMPANY INFORMATION/CONTACT
Name: NV5, Inc.

Address: 1868 Palma Drive, Suite A-E,
Ventura, CA 93003
Telephone Number:

Email of Contact: [email protected]
August 17, 2023
City of Santa Clarita

23920 Valencia Boulevard, Suite 120
Santa Clarita, CA 91355

Dear Selection Committee,
Local Presence:
throughout Los Angeles County and the surrounding area. NV5 has a deep bench of professionals located throughout the City, our team is able to quickly respond and mobilize for any needs that may arise.

Relevant Experience: We have a proven track record of successfully providing inspection and construction oversight services for similar bridge and roadway widening projects throughout California, most of which have been repeat clients.

PN: P26523-0004765.00
• Jellys Ferry Road at Sacramento River Bridge,
County of Tehama
• Hickman Road Over the Tuolumne River Bridge
Replacement Project, County of Stanislaus
• PCH Signal and Median Improvements, City of Malibu
• Belle Terrace Operational Improvements,
• Campus Parkway, County of Merced
Proposed Team:
proposing Michael Dipsia, PE, QSD/P, as Project Manager/Lead Inspector serving as a Structure Representative, Resident Engineer, Senior Construction Engineer, and Construction Manager for project remains on schedule and within budget.

Department of Industrial Relations Registration No.: 1000007705 Proposal Authorization and Validity: This proposal has been signed by Jeff Pallesen, PE, QSD/P, City’s Standard Contract: NV5 does not request any deviations to the City’s Standard Contract (Section D).

NV5 looks forward to the opportunity to work with the City and help you achieve your goals and objectives. If you need [email protected] and
[email protected]. Thank you for your time and consideration.

Sincerely,
NV5

1. INTRODUCTION
INTRODUCTION + PROJECT UNDERSTANDING

PROJECT UNDERSTANDING
The City of Santa Clarita, in collaboration with the
Developer of the Tesoro Del Valle Community (Developer), is seeking a consultant company through a Request
for Proposal to perform comprehensive inspection and
construction oversight services for the Copper Hill Drive Bridge Widening project. This proposed bridge widening
over San Francisquito Creek (a tributary stream of the
Santa Clara River), spans from Avenida Rancho Tesoro to McBean Parkway.

I-girder structure. It is 65 feet wide and 580.23 feet
proposes to widen the bridge by 33 feet, adding four new precast girders per span. In addition, the project will add bridge substructure, including abutments and piers,
have previously been constructed to the future width.

The roadway within the project limits has already been
length. However, the roadway will need to be widened at both bridge approaches.
with a target completion date of January 31, 2025,
the construction improvements are required to be in
accordance with City, County, State, and federal standards, Construction must also meet all permit and environmental commitments, particularly while working within San
Francisquito Creek. The improvements will be constructed access. Stage 2 includes full road closures and detours requiring night work.

The project is being funded by the Developer, and
completion of the widening is needed before the
of homes. Therefore, time is of the essence. In order to accelerate the beginning of construction, the Developer has already order the precast girders, and they are
currently under construction.

CITY OBJECTIVES
the City with comprehensive inspection and oversight
of the bridge construction and roadway improvements.
and understanding of Caltrans Standards who can
work effectively with the City and Developer to deliver a successful project within the budget and schedule
NV5’s team is led by Michael Dipsia, PE, QSD/P.

Mr. Dipsia is a former Caltrans Senior Construction
He knows highway and bridge construction inspection,
contract administration, construction safety compliance, SWPPP, quality control, constructability review, and
construction methods. His problem-solving skills have
been instrumental in resolving issues arising from errors City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 3 INTRODUCTION + PROJECT UNDERSTANDING
community disruptions, and project delays.
project completion and is dedicated to closely collaborating with the City, the Developer, the Contractor, and other relevant personnel on a daily basis. His collaborative
approach will help lead to successful project completion adherence to safety protocols and compliance with

PROJECT ISSUES AND SOLUTIONS
believes that the successful delivery of this project will be determined by how well your inspection and construction oversight consultant is able to handle the key elements and issues of this project.

KEY PROJECT ISSUES
After performing a constructability review, we have
successful delivery of this project. The issues are listed below, with a discussion and suggested solutions laid out • Permit/in-water work/potentially wet winter
•
• Girder construction
• Girder Camber creep
• Closure pour
• Deck forms
Permit restrictions and limitations for working in San
Francisquito Creek bed during construction: The City’s
advertised RFP for this project did not include a copy
of the environmental report or permit restrictions and
limitations for work in the San Francisquito Creek bed
during construction. This permit must be obtained from
all regulatory agencies that have jurisdiction over the watershed and creek bed prior to work beginning in the
San Francisquito creek bed. This will delay several items of work and potentially delay the start of construction.

Additionally, weather prediction models show there is a high chance of a wet winter and spring (November 2023–
Niño. The CPM Schedule shows a range of construction
activities during that period. If the pattern continues, there could be restrictions on in-water work during these rainy periods. We don’t know the full impact, as the permit has not yet been obtained, but these restrictions can cause project right-of-way delays. It is also possible that there could be restrictions on work in the creek bed beyond
to by the Contractor, and an accurate cost bid and CPM
schedule cannot be developed without this information.

These limitations could delay the project completion date, two seasons (end of 2025).

Once the permit has been obtained, NV5 will review
the permit work window restrictions, identify CPM
workarounds to keep the project on schedule and stay in compliance with the permit requirements.

A review of the CPM schedule
shows that the proposed precast post-tension I-girders
Sept 20, 2023. The CPM schedule also shows that the
precast post-tension concrete I-girders starting November 28, 2023. However, there are numerous mature trees
(three-plus trees between the pier walls – spans 2, 3 and 5) that have established roots between the piers with
deck. This will impact the work on setting the precast
post-tension concrete I-girders, as they cannot be placed until these trees are removed and the area is cleared. This could potentially delay the setting of the precast post- tension concrete I-girders if the required permit authorizing the Contractor to work in the watershed area and clear
these trees is not issued in time, as this work is currently scheduled for the week of December 19, 2023. Watershed
access is essential for the Contractor to work in the area, and strip intermediate and end diaphragms and new
bridge deck overhang.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 4 INTRODUCTION + PROJECT UNDERSTANDING
NV5 will identify and address the permit restrictions and environmental concerns for the City and other agency
stakeholders and work with the Contractor to keep the
project on schedule and in compliance.

Girder Construction:
each bridge span would be made prior to precast post-
tension I-girder fabrication. Ordering these girders based on a theoretical dimension shown on the plans presents
pier walls were previously constructed, and any tolerable dimension (girder length) may not equate to the theoretical length of girders as designed. Consequently, if the actual potential for rejecting these girders. This would result in a right-of-way delay.
the girders as cast will meet the tolerances for the
widening.

Girder Camber Creep: In the engineers’ design, it was
intended that the bridge deck would not be placed on
precast girders until three months after post-tensioning center line of the span. At 90 days after post-tensioning of girders, the induced theoretical camber (upward camber) is around 2 inches. Once the bridge deck is placed, the the center span by 1.5 inches, resulting in a net 0.5 inch remaining camber at the center line. If the bridge deck is not poured within 90 days after the post-tensioning of the years after initial prestressing. From a construction as well as an aesthetics point of view, we do not want the camber to go below zero.

NV5 will review the CPM schedule in real time and
coordinate with the Contractor to ensure the schedule
frame.

Closure Pour: The bridge plans’ detail regarding the
overhang will need to be removed, and the horizontal rebar deck is less than 30 inches, it is recommended to use
approved mechanical couplers (with minimum of 60 psi
tensile strength capacity) to connect the horizontal rebar affect concrete bond with the embedded reinforcement if live splice is inadequate or mechanical couplers not used.

The bridge deck where the lap splice is, will be part of the closure pour. The bridge section if not completed properly can potentially cause a longitudinal crack along the entire length of the bridge (BB to EB).

NV5 suggests that the engineers’ design include an
application of liquid methacrylate on the existing side areas of the old and new bridge deck and prior to
placement of closure pour. This will help the concrete
to adhere (like an epoxy adhesive) and will not allow a longitudinal joint to develop or water to penetrate through a potential crack.
plans related to the placement of metal decking (stay-in- 30 days are allowed for the placement of metal decking
(stay-in-place forms). However, the contract Plan Sheets 2 and 3 do not include this as an option. As this contract is already out to bid, it raises a concern that bids will come in higher than necessary, as removing stay-in-place forms is NV5 will review the contract plans and look for options to save time and money. NV5 will work with the Engineer, the City and the Contractor to identify opportunities to

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 5 INTRODUCTION + PROJECT UNDERSTANDING

OTHER PROJECT ELEMENTS
ISSUE NV5 SOLUTION/ACTION
Contractor’s baseline schedule, SWPPP
submittals, Construction RFI and submittals
NV5 will continuously and in a timely manner review the Contractor’s baseline schedule and SWPPP plan and respond to the Contractor’s RFI procurement of materials and progress of work.
hazardous waste
NV5 will oversee the Contractor’s handling and disposal of hazardous Contractor must submit a plan for review and approval regarding the dismantling, transporting and disposing of this material at an approved Hazardous Waste Facility. Proper documentation must be provided and seal at Abutment No. 7 (EB) revealed
deck grades, and debris is collecting on the
joint opening. It appears that the embedded
water-stop below the joint seal at this
location has failed.

NV5 will work with the Contractor during the construction of the new approach slabs to assure they are constructed to project plans and The bridge deck concrete pour adjacent
embedded reinforcement. Also, placing
concrete at the closure pour could impact
the bar bonding at the closure pour and the
durability of the longitudinal joint.

It was observed that at times Copper Hill will
50-70 mph.

NV5 recommends that stage construction be utilized for the bridge deck affect the bonding of the embedded reinforcement. A concrete bridge deck must be allowed to cure before being subjected to loads, so we placement. If a full closure is not feasible, at the minimum, one full lane hours after completion of the placement of bridge deck.

Reducing the speed limit to 25 mph for 28 days following concrete placement will also help allow the concrete to reach its designed compressive strength.
construction
NV5 is mindful that construction zones can be a distraction to the traveling motorist and local community. NV5 will collaborate with the City and the Contractor to provide advance notice and communication with assist the City with scheduling meetings with residents and businesses to address concerns.
of utilities, a list of utilities to be moved, and contacts for affected utilities and note relocation windows and potential CPM schedule impacts. NV5 will coordinate with the City and the Contractor to notify stakeholders of potential disruptions.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 6

PROJECT APPROACH
PROJECT APPROACH – COST CONTROL, SCHEDULE MANAGEMENT AND QA/QC PLAN

COST CONTROL
We are responsible for managing our own construction
Contractor’s schedule weekly to determine the level
of construction oversight effort needed to manage
the contract effectively, and we will schedule our work budgets tightly controlled and closely monitored.

NV5 manages and monitors the hours charged through
the Deltek Vision project management/accounting system.

Accurate invoicing begins with the use of a detailed
phase/task system to delineate work directives and their charges on a regular basis. At each period’s end, our
Accounting Department will provide a billing worksheet
for the project, broken out by phase/task, and employee..

Following approval of the billing worksheet and draft
invoice, the complete invoice package is reviewed by a
project analyst who checks for accuracy and completeness of backup documentation.

The Contractor’s monthly pay estimate will be reviewed by prepares and forwards a draft progress payment invoice
for Payment to the City for processing.

INTERNAL PROJECT AUDITS
As part of our QC/QA plan, Mr. Dipsia will periodically standardized Quality Control Plan Checklist. This
attendance provides an opportunity for him to spend time understanding of job progress and outstanding issues.

It also allows him to spend time with the City’s Project Manager and gather input from him.

STAFF TRAINING & KNOWLEDGE SHARING
NV5 invests in employee education and development to
ensure our staff is well trained and prepared. We use
a variety of tools to cultivate consistency and reliability, including a training program and coaching plan for each individual staff member. Each individual’s performance
is evaluated annually, and a customized training program is then developed based on personnel and project needs.

Included in our training program are NV5’s annual CM
Workshop and CM Discipline Forum. These workshops
include instruction on technical matters, management
issues, claims assessments, safety training, and team
building.
contains resources such as action plans, core processes, lessons learned, safety information, current forms, process and procedures documents, as well as access to outside
training information.

SCHEDULE MANAGEMENT
Coordination, Communication and Collaboration
establishing advance coordination and weekly meetings
with the Contractor to discuss ongoing issues and
understand the Contractor’s future look-ahead schedule.

We believe successful project delivery begins and ends with coordination, communication and collaboration. To that end, we will set up a partnering session with the Contractor and and the Contractor’s concerns. We will identify early on the solutions to any impacted items of work. Appropriate and timely outreach to the stakeholders, including the public, the Developer, and the City, when issues arise will go a long way in eliminating potential delays.

Reduced impacts to the schedule and/or order of work
equal reduced costs. Reduced costs will lessen the
chances of the Contractor taking issue or presenting a
claim.

NV5 pledges to take ownership of the project delivery while City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 7

PROJECT APPROACH
working to minimize delays and costs, including making
sure that the work is being done in accordance with the providing all required resources and to work within any schedule and meet any project challenges, maintaining a positive public image for the City while minimizing project administrative costs.

CPM SCHEDULE
The Copper Hill Drive Bridge Widening project is currently planned for project award on August 31, 2023, with
completed by January 31, 2025. We have developed
a 112-activity comprehensive baseline schedule to
understand the critical path, identify key issues, and
anticipate the Contractor’s approach to the work. It is included on pages 9-11 for your review.

The CPM/work schedule will need to be prepared by the
Contractor. NV5 will review the schedule, making sure that the Contractor’s schedule is logical and that the work will be completed within the allocated number of working days.

Our construction support services team gives considerable attention to monitoring project schedules. We will
coordinate, review and make recommendations for
changes to the Critical Path Method (CPM) schedule
generated by the Contractor. As changes or discrepancies occur between the CPM schedule and as-built conditions, the project schedule and cost estimates will be updated.

We will review the Contractor’s schedule on a weekly basis.

We will track critical milestones, and if the Contractor has missed or is tracking to miss a particular milestone, we will work closely with the Contractor to formulate a recovery plan so as to minimize any potential impacts.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 8 PAGE HEADERPROJECT APPROACH — SCHEDULE OF WORKActivity IDActivity NameOriginalDurationCalendarStartFinishTotal FloatConstructConstruction Management395d5H26-Sep-202323-Apr-20250dGENERALGENERAL395d5H26-Sep-202323-Apr-20250dCM-10010Firm Selection0d5H26-Sep-2023361dCM-10020Tentative NTP0d5H03-Nov-2023361dCM-10030CM Services368d5H03-Nov-202323-Apr-20250dPre-ConstrucPre-Construction Services7d5H03-Nov-202314-Nov-2023361dCM-10040Project Document Review7d5H03-Nov-202314-Nov-2023361dConstructionConstruction Services362d5H14-Nov-202323-Apr-20250dCM-20080CM / Inspection Services362d5H14-Nov-202323-Apr-20250dClose OutClose Out60d5H30-Jan-202523-Apr-20250dCM-30020Close Out Activities60d5H30-Jan-202523-Apr-20250dConstructConstruction Bid & Award33d5H03-Aug-2023 A14-Nov-20230dGENERALGENERAL33d5H03-Aug-2023 A14-Nov-20230dBD-10010BID OPENING0d5H03-Aug-2023 ABD-10020AWARD CONTRACT0d5H31-Aug-2023 ABD-10030PRE-CONSTRUCTION ACTIVITIES15d5H01-Sep-2023 A14-Nov-20230dBD-10040NTP - CONSTRUCTION0d5H14-Nov-20230dPre-ConstPre-Construction120d5H03-Apr-2023 A14-Nov-2023361dGENERALGENERAL120d5H03-Apr-2023 A14-Nov-2023361dPC-10050Kick-Off Meeting1d5H14-Nov-202314-Nov-20230dPC-10060FAB & DELIVER GIRDERS (By Others)120d5H03-Apr-2023 A26-Sep-2023395dConstructConstruction Milestones302d5H14-Nov-202330-Jan-202560dGENERALGENERAL302d5H14-Nov-202330-Jan-202560dCMS40020First Working Day0d5H14-Nov-2023*1dCMS40030Scheduled Time of Construction302d5H14-Nov-202329-Jan-202560dCMS40040Scheduled Completion Date0d5H29-Jan-202560dCMS40050Construction Project Float0d5H30-Jan-202530-Jan-202560dStage 1A Stage 1A East (South)23d5H15-Nov-202319-Dec-2023338dGENERALGENERAL5d5H15-Nov-202321-Nov-2023356dS1-0010Mobilization / Fence / Project Signs5d5H15-Nov-202321-Nov-20230dS1-0020Install BMPs5d5H15-Nov-202321-Nov-2023356dRoadwayRoadway18d5H22-Nov-202319-Dec-20230d1AE-0010Temp Fence (McBean through (E) Bridge1d5H22-Nov-202322-Nov-20230d1AE-0020Traffic Switch - Delineators / Signs1d5H27-Nov-202327-Nov-20230d1AE-0025Clear & Grub1d5H28-Nov-202328-Nov-20230d1AE-0030Remove / Store Trail Monument1d5H29-Nov-202329-Nov-20230d1AE-0040Demo (E) Curb & Gutter, Sidewalk2d5H30-Nov-202301-Dec-20230d1AE-0045Demo Pavement & Base1d5H04-Dec-202304-Dec-20230d1AE-0047Construct New Curb Rtn. / Sidewalk / Ramp1d5H05-Dec-202305-Dec-20230d1AE-0050Construct Temp 4" AC on 6" AG Base5d5H06-Dec-202312-Dec-20230d1AE-0060Construct Temp. 8' Wide AC Trail3d5H13-Dec-202315-Dec-20230d1AE-0070Adjust Utility Height1d5H18-Dec-202318-Dec-20230d1AE-0080Relocate St. Light & Signal Pole (McBean)1d5H19-Dec-202319-Dec-20230dStage 1B Stage 1B East (North)14d5H20-Dec-202310-Jan-20240dRoadwayRoadway14d5H20-Dec-202310-Jan-20240d1BE-0020Traffic Switch - Interim Striping / Signs1d5H20-Dec-202320-Dec-20230d1BE-0030Remove (E) Barrier Rail1d5H21-Dec-202321-Dec-20230d1BE-0040Grade2d5H22-Dec-202326-Dec-20230d1BE-0050Construct Temp 4" AC on 6" AG Base5d5H27-Dec-202303-Jan-20240d1BE-0060Temp Closure - McBean3d5H04-Jan-202408-Jan-20240d1BE-0070Cut Back (E) Median at Intersection1d5H09-Jan-202409-Jan-20240d1BE-0080Re-Stripe1d5H10-Jan-202410-Jan-20240dStage 2 - WStage 2 - West (North)3d5H11-Jan-202416-Jan-2024321dRoadwayRoadway3d5H11-Jan-202416-Jan-2024321d2WR-0010Set K-rail / Interim Stripe1d5H11-Jan-202411-Jan-2024321d2WR-0020Minor Grading1d5H12-Jan-202412-Jan-2024321d2WR-0030Roadwork1d5H16-Jan-202416-Jan-2024321dBridge WidenBridge Widening3d5H11-Jan-202416-Jan-20240d2W-0020Prep & Install Bearing Pads at (E) Piers & Abutments3d5H11-Jan-202416-Jan-20240dStage 2 - EStage 2 - East (North)4d5H11-Jan-202417-Jan-2024320dRoadwayRoadway4d5H11-Jan-202417-Jan-2024257d2ER-0020Minor Grading2d5H11-Jan-202412-Jan-2024257d2ER-0030AB1d5H16-Jan-202416-Jan-2024257d2ER-0040Base Pave1d5H17-Jan-202417-Jan-2024257dBridge WidenBridge Widening1d5H16-Jan-202416-Jan-2024321d 270310172401081522290512192603101724310714212804111825031017243107142128051219260209162330071421280411182501081522290613202703101724010815222905121926020916230209162330061320270411182501SeptemberOctoberNovemberDecemberJanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuaryFebruaryMarchAprilMayne20242025Firm SelectionTentative NTPCM ServicesProject Document ReviewCM / Inspection SeClose Out ActivitieNINGAWARD CONTRACTPRE-CONSTRUCTION ACTIVITIESNTP - CONSTRUCTIONKick-Off MeetingFAB & DELIVER GIRDERS (By Others)First Working DayScheduled Time of ConstructionScheduled Completion DateConstruction Project FloatMobilization / Fence / Project SignsInstall BMPsTemp Fence (McBean through (E) BridgeTraffic Switch - Delineators / SignsClear & GrubRemove / Store Trail MonumentDemo (E) Curb & Gutter, SidewalkDemo Pavement & BaseConstruct New Curb Rtn. / Sidewalk / RampConstruct Temp 4" AC on 6" AG BaseConstruct Temp. 8' Wide AC TrailAdjust Utility HeightRelocate St. Light & Signal Pole (McBean)Traffic Switch - Interim Striping / SignsRemove (E) Barrier RailGradeConstruct Temp 4" AC on 6" AG BaseTemp Closure - McBeanCut Back (E) Median at IntersectionRe-StripeSet K-rail / Interim StripeMinor GradingRoadworkPrep & Install Bearing Pads at (E) Piers & AbutmentsMinor GradingABBase Pave Copper Hill Drive Bridge WideningCity of Santa Clarita, CaliforniaCopper Hill - CM / Construction09-Aug-2023 PROJECT :CHD-1 , DATA DATE: 26-Sep-2023Page 1 of 3FIGURE 1

PROPOSED CPM PROJECT SCHEDULE
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 9City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 9 PAGE HEADERPROJECT APPROACH — SCHEDULE OF WORKActivity IDActivity NameOriginalDurationCalendarStartFinishTotal Float2E-0020Prep & Install Bearing Pads at (E) Piers & Abutments1d5H16-Jan-202416-Jan-2024321dStage 2 - WStage 2 - West (Night)8d5H17-Jan-202426-Jan-2024310dBridge WidenBridge Widening8d5H17-Jan-202426-Jan-2024310d2WN-0020Full Closure / Detour - Each Night8d5H17-Jan-202426-Jan-2024310d2WN-0030Set Girders5d5H17-Jan-202423-Jan-20240d2WN-0040Post Tension Girders3d5H24-Jan-202426-Jan-2024310dStage 2 - EStage 2 - East (Night)8d5H24-Jan-202402-Feb-2024308dBridge WidenBridge Widening8d5H24-Jan-202402-Feb-2024308d2EN-0020Full Closure / Detour - Each Night8d5H24-Jan-202402-Feb-2024308d2EN-0030Set Girders5d5H24-Jan-202430-Jan-20240d2EN-0040Post Tension Girders3d5H31-Jan-202402-Feb-2024308dStage 3Stage 3189d31-Jan-202421-Oct-202446dBridge WidenBridge Widening189d31-Jan-202421-Oct-202446d3BR-0010Set K-rail / Interim Stripe1d5H31-Jan-202431-Jan-20240d3BR-0020Demo (E) Barrier / Railing5d5H01-Feb-202407-Feb-20240d3BR-0025Construct Temp Work Platforms15d5H08-Feb-202401-Mar-20240d3BR-0030FRP Diaphragms30d5H04-Mar-202412-Apr-20240d3BR-0035Remove Temp Work Platforms10d5H15-Apr-202426-Apr-20240d3BR-0040Install Deck Forms30d5H29-Apr-202410-Jun-20240d3BR-0045Install Deck Rebar15d5H11-Jun-202401-Jul-20240d3BR-0047Prep Deck Pour / Edge Forms / Set Screed15d5H02-Jul-202423-Jul-20240d3BR-0050Place Deck Concrete1d5H24-Jul-202424-Jul-20240d3BR-0055Cure Deck Pour (28CD) - Strip28d7D25-Jul-202421-Aug-20240d3BR-0060Construct Approach Slabs6d5H22-Aug-202429-Aug-20240d3BR-0065Closure Pour Dowels10d5H08-Aug-202421-Aug-202455d3BR-0075Closure Pour Soffit Forms8d5H22-Aug-202403-Sep-202455d3BR-0076Place Closure Pour1d5H04-Sep-202404-Sep-202455d3BR-0077Cure Closure Poor28d7D05-Sep-202402-Oct-202481d3BR-0080FRP Barrier Rail & Sidwalk15d5H30-Aug-202420-Sep-20240d3BR-0085Metal Railing20d5H23-Sep-202421-Oct-20240d3BR-0090Install Crash Cussions5d5H30-Sep-202404-Oct-202451d3BR-0100Profile & Grind2d5H07-Oct-202408-Oct-202451d3BR-0110Install Electroliers5d5H23-Sep-202427-Sep-202419dStage 3 - WStage 3 - West (North)43d5H31-Jan-202402-Apr-202472dRoadwayRoadway43d5H31-Jan-202402-Apr-202472d3WR-0010Set K-rail / Interim Stripe1d5H31-Jan-202431-Jan-202472d3WR-0020Construct Part New Storm Drain6d5H01-Feb-202408-Feb-202472d3WR-0030Roadwork6d5H09-Feb-202420-Feb-202472d3WR-0040Construct New Street Lignts / Conduit20d5H21-Feb-202419-Mar-202472d3WR-0050Construct New Sidewalk10d5H20-Mar-202402-Apr-202472dStage 3 - EStage 3 - East (North)27d5H03-Apr-202409-May-202472dRoadwayRoadway27d5H03-Apr-202409-May-202472d3ER-0010Set K-rail / Interim Stripe1d5H03-Apr-202403-Apr-202472d3ER-0015Relocate Utilities5d5H04-Apr-202410-Apr-202472d3ER-0020Construct Subgrade / AG Base4d5H11-Apr-202416-Apr-202472d3ER-0030Construct Part Storm Drain8d5H17-Apr-202426-Apr-202472d3ER-0040Construct New Curb & Gutter8d5H29-Apr-202408-May-202472d3ER-0050Base Pave AC1d5H09-May-202409-May-202472dStage 4Stage 453d30-Sep-202411-Dec-202430dBridge WidenBridge Widening53d30-Sep-202411-Dec-202430d4WB-0010Re-Stripe / K-rail / Shift Traffic1d5H22-Oct-202422-Oct-20240d4WB-0020Remove (E) Barrie Ends at Approach5d5H23-Oct-202429-Oct-202442d4WB-0025Demo (E) Approach Slabs (Part)5d5H30-Oct-202405-Nov-202442d4WB-0040Construct New Aproach Slabs5d5H06-Nov-202413-Nov-202442d4WB-0050Prepare Deck for (N) Sidewalk / Barrier5d5H14-Nov-202420-Nov-202442d4WB-0060Place (N) Sidewalk Slab5d5H30-Sep-202404-Oct-202419d4WB-0070FRP (N) Barrier Rail8d5H07-Oct-202417-Oct-202419d4WB-0080Barrier Cure10d7D18-Oct-202427-Oct-202428d4WB-0110Install Electroliers5d5H28-Oct-202401-Nov-202419d4WB-0120Install Metal Railing20d5H04-Nov-202404-Dec-202419d4WB-0130Install Crash Cushion5d5H05-Dec-202411-Dec-202419dStage 4 - WStage 4 - West (South)33d5H22-Oct-202410-Dec-202421dRoadwayRoadway33d5H22-Oct-202410-Dec-202421d4W-0010Set K-Rail Temp Strip / Sign1d5H22-Oct-202422-Oct-20240d4W-0020Construct New Drainage Systems (Portions)20d5H23-Oct-202420-Nov-20240d4W-0030Construct Subgrade / AG Base20d5H23-Oct-202420-Nov-202421d4W-0040Construct New Curb & Gutter6d5H21-Nov-202402-Dec-202421d 270310172401081522290512192603101724310714212804111825031017243107142128051219260209162330071421280411182501081522290613202703101724010815222905121926020916230209162330061320270411182501SeptemberOctoberNovemberDecemberJanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuaryFebruaryMarchAprilMayne20242025Prep & Install Bearing Pads at (E) Piers & AbutmentsFull Closure / Detour - Each NightSet GirdersPost Tension GirdersFull Closure / Detour - Each NightSet GirdersPost Tension GirdersSet K-rail / Interim StripeDemo (E) Barrier / RailingConstruct Temp Work PlatformsFRP DiaphragmsRemove Temp Work PlatformsInstall Deck FormsInstall Deck RebarPrep Deck Pour / Edge Forms / Set ScreedPlace Deck ConcreteCure Deck Pour (28CD) - StripConstruct Approach SlabsClosure Pour DowelsClosure Pour Soffit FormsPlace Closure PourCure Closure PoorFRP Barrier Rail & SidwalkMetal RailingInstall Crash CussionsProfile & GrindInstall ElectroliersSet K-rail / Interim StripeConstruct Part New Storm DrainRoadworkConstruct New Street Lignts / ConduitConstruct New SidewalkSet K-rail / Interim StripeRelocate UtilitiesConstruct Subgrade / AG BaseConstruct Part Storm DrainConstruct New Curb & GutterBase Pave ACRe-Stripe / K-rail / Shift TrafficRemove (E) Barrie Ends at ApproachDemo (E) Approach Slabs (Part)Construct New Aproach SlabsPrepare Deck for (N) Sidewalk / BarrierPlace (N) Sidewalk SlabFRP (N) Barrier RailBarrier CureInstall ElectroliersInstall Metal RailingInstall Crash CushionSet K-Rail Temp Strip / SignConstruct New Drainage Systems (Portions)Construct Subgrade / AG BaseConstruct New Curb & Gutter Copper Hill Drive Bridge WideningCity of Santa Clarita, CaliforniaCopper Hill - CM / Construction09-Aug-2023 PROJECT :CHD-1 , DATA DATE: 26-Sep-2023Page 2 of 3FIGURE 1City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 10City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 10 PAGE HEADERPROJECT APPROACH — SCHEDULE OF WORKActivity IDActivity NameOriginalDurationCalendarStartFinishTotal Float4W-0050Construct New Sidewalk5d5H03-Dec-202409-Dec-202421d4W-0060Pave TIe-In1d5H10-Dec-202410-Dec-202421dStage 4 - EStage 4 - East (South)34d5H21-Nov-202410-Jan-20250dRoadwayRoadway34d5H21-Nov-202410-Jan-20250d4E-0010Set K-Rail Temp Strip / Sign1d5H21-Nov-202421-Nov-20240d4E-0020Demo Temporary Trail1d5H22-Nov-202422-Nov-20240d4E-0030Construct Trail Head Improvements3d5H25-Nov-202427-Nov-20240d4E-0040Re-install Trail Monument1d5H02-Dec-202402-Dec-20240d4E-0050Complete Drainage System10d5H03-Dec-202416-Dec-20240d4E-0060Install Subgrade / AG Base10d5H03-Dec-202416-Dec-20240d4E-0070Install New Curb & Gutter6d5H17-Dec-202424-Dec-20240d4E-0075Install New Street Lights5d5H26-Dec-202401-Jan-20250d4E-0080Install New Sidewalk6d5H02-Jan-202509-Jan-20250d4E-0090Base Pave AC1d5H10-Jan-202510-Jan-20250dStage 5 - WStage 5 - West (Median)8d5H13-Jan-202522-Jan-20253dRoadwayRoadway8d5H13-Jan-202522-Jan-20253d5W-0040Construct Raised Median5d5H13-Jan-202517-Jan-20250d5W-0050Final Lift1d5H20-Jan-202520-Jan-20253d5W-0070Final Sign & Stripe2d5H21-Jan-202522-Jan-20253dStage 5 - EStage 5 - East (Median)15d5H09-Jan-202529-Jan-20250dRoadwayRoadway15d5H09-Jan-202529-Jan-20250d5E-0040Construct Raised Median5d5H20-Jan-202524-Jan-20250d5E-0050Final Lift1d5H27-Jan-202527-Jan-20250d5E-0070Final Sign & Stripe2d5H28-Jan-202529-Jan-20250d5E-0099Punch List15d5H09-Jan-202529-Jan-20250d270310172401081522290512192603101724310714212804111825031017243107142128051219260209162330071421280411182501081522290613202703101724010815222905121926020916230209162330061320270411182501SeptemberOctoberNovemberDecemberJanuaryFebruaryMarchAprilMayJuneJulyAugustSeptemberOctoberNovemberDecemberJanuaryFebruaryMarchAprilMayne20242025Construct New SidewalkPave TIe-InSet K-Rail Temp Strip / SignDemo Temporary TrailConstruct Trail Head ImprovementsRe-install Trail MonumentComplete Drainage SystemInstall Subgrade / AG BaseInstall New Curb & GutterInstall New Street LightsInstall New SidewalkBase Pave ACConstruct Raised MedianFinal LiftFinal Sign & StripeConstruct Raised MedianFinal LiftFinal Sign & StripePunch ListCopper Hill Drive Bridge WideningCity of Santa Clarita, CaliforniaCopper Hill - CM / Construction09-Aug-2023 PROJECT :CHD-1 , DATA DATE: 26-Sep-2023Page 3 of 3FIGURE 1City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 11City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 11

PROJECT APPROACH
Although the project documents show that the construction to January 31, 2025), we believe that this project can
be completed in a shorter duration by including a clause offering the Contractor a monetary incentive per day to complete the project ahead of schedule.

Alternatively, for the construction of the bridge deck, the early concrete strength for the construction of intermediate and end diaphragms, bridge deck, barrier rail and approach requirements. This will shorten the concrete curing duration each by 20 days for intermediate and end diaphragm plus 20 days for the bridge deck and 10 days for the concrete barrier rail, resulting in a total savings for the number of working days for the project by 50 working days.

The above proposed savings in the number of working days by either offering the Contractor a monitoring incentive per day or by specifying high early strength concrete could also be useful to keep the project on track in case the up to also be a continuation of the El Niño of 2022 with potential permit restrictions of in-water work during the rainy period, as discussed on page 4, Permit restrictions and limitations for working in San Francisquito Creek
bed during construction.

Completing the project ahead of schedule would provide
•
noise, and general inconvenience to the residents,
businesses and traveling public during construction
• Allow the Developer to receive its occupancy
delays and costs and allow the City to collect fees and The location of this project is in a visible and heavily traveled area of the City. Copper Hill Drive and McBean Parkway are two main arteries to the I-5. This project could inconvenience local residents who are accustomed to
hour and commuting to/from their work or transporting
their kids back and forth from school. In addition to the roadways, there will be impacts to the San Francisquito Creek Trail and bike paths in the area.
local community during construction.

QUALITY CONTROL
NV5 takes a proactive project management approach
by providing our team with a set of inspection and
construction oversight processes and procedures that
allows us to manage construction projects better. We want of your project, Project Manager/Lead Inspector Michael Dipsia will remain in communication with you and regularly • Verify that the quality of construction meets the
•
potential change orders and claims
• Meet with your project manager to verify that needs
and requirements are being met while maintaining
the construction management budget
•
documentation is accurate, timely, complete and
meets State and Federal requirements
Quality Control/Quality Assurance Plan
NV5 will develop and utilize a Quality Control/Quality
are provided a copy to assure that our team members
know their roles and understand their responsibilities and project requirements.
services for which we are responsible, project forms,
project documentation references, checklists, project
samples and reports. This QC/QA Plan includes very
assurance activities and provides for third-party auditing of NV5 will monitor the Contractor’s quality control program and can provide quality assurance sampling, testing, and inspections to verify the accuracy and compliance of the work. We keep logs to track items such as tests performed, samples taken, non-compliance reports, inspection and
testing costs associated with non-compliant work, and
submittals. We will review the Contractor’s weekly and daily schedules before work begins each day and will closely
coordinate with the Contractor to establish an understanding of the critical activities and work to be inspected.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 12

WORK PLAN/SCOPE OF WORK
Daily Documentation
Because we recognize that our inspectors’ daily reports are one of the most important deliverables we provide
inspector’s report. This report provides a standardized documentation process that includes project photographs, quantity measures, daily activities, and all pertinent
elements of a thorough daily diary. The electronic diary quantity calculations for progress payments, and quick
recall of work items performed. All inspectors on this
project will utilize this diary so that all information is collected consistently and completely every day in a
standardized and legible format.

WORK PLAN/SCOPE OF WORK
Based on the Scope of Service activities presented in
construction oversight for projects like the Copper Hill Drive Bridge Widening project, we have developed the
detailed will be fundamental to meet funding and oversight requirements while assuring the project’s objectives are successfully met.

Under the direction of the Developer’s assigned Resident Engineer and Structural Representative, the following task

PRECONSTRUCTION SERVICES
Task 1.01 Review Final Contract Plans
After the constructability review, NV5 will review the
and engineer’s estimate. Our review will identify
required submittals, order of work, schedule constraints, environmental commitments, restricted work windows,
and overall contract requirements, as well as identify any Deliverables: Constructability Review if requested by the City Task 1.02 Prepare Project Schedule
NV5 will prepare a project schedule that includes major preconstruction and construction tasks, sequencing of
work and anticipated durations. We will also include utility to meet Special Provisions, and permit and agreement
requirements. This schedule will be used in review of
the Contractor’s baseline schedule submittal for logic, durations, and contractual constraints.

Deliverables: (1) Preliminary Project CPM Schedule
Task 1.03 Kickoff Meeting/Establish Communication Protocols The NV5 team will initiate a kickoff meeting with the City and Developer to discuss the proposed scope of work
and establish communication protocols and the record-
keeping process, in accordance with the City’s policies and procedures.

Deliverables: Kickoff Meeting Minutes, Communication
Matrix
Task 1.04 Review Permits and Agreements
NV5 will review all permits and agreements with the
various governing agencies. Our review will identify
constraints, work windows, deliverables, timelines for
permit.

Task 1.05 Review Resident Engineer Files
During the preconstruction phase, NV5 will review the
design engineer’s memos, technical reports and studies.

Our review will identify required submittals, order of work, schedule constraints, restricted work windows and overall contract requirements.

Task 1.06 Perform Initial Site inspection
Prior to construction, NV5 will videotape, digitally
photograph, and log preconstruction conditions to create physical constraints, drainage conditions, etc. We will also facilities.

Deliverables: (1) Photographs and Video Documentation
of the Preconstruction Condition of the Project Site and Potential Haul Routes; (2) Video of all Existing Sewer and Storm Drain Systems within the Project Site
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 13

WORK PLAN/SCOPE OF WORK

CONSTRUCTION SERVICES
Task 2.01 Preconstruction Conference
The NV5 team will facilitate a preconstruction conference with the construction Contractor, subcontractors, the City, the Developer, the project designer, utility companies, and other stakeholders after contract approval and before start of work to review the project and discuss coordination
efforts. This meeting will be used to establish managerial and administrative procedures with the Contractor to
discussion topics will include labor compliance, safety and accident prevention, and the stormwater pollution
prevention plan.

Deliverables: (1) Written Agenda and Minutes of
Preconstruction Conference; and (2) Electronic Copies of Preconstruction Meeting Minutes to the Attendees
Task 2.02 Document Controls
NV5 ‘s general record-keeping process will follow the City’s policies and procedures. NV5 has an in-house electronic and easily sharable document control system to support
daily reporting and to manage project submittals, RFIs
including contract drawings and documents, supplemental daily reports, submittal, City directives, correspondence, test results, project photos and videos, meeting minutes, minutes of safety meetings, materials records, survey
data, requests for information, change orders, claims,
any permits and other contract information and progress payments. The NV5 team will coordinate with the City
and modify the process as directed to meet internal City administration procedures.

Task 2.03 Construction Meetings
NV5 will hold weekly progress meetings with the Contractor to review construction progress. Meetings topics will
include project schedule, safety, environmental permits, with stakeholders. We will keep minutes of the meetings, assign action items and responsibilities, and document
will also be held as needed to focus on work plans, activity coordination and other matters as necessary.

Deliverables: (1) Written Agenda and Minutes of each
Progress Meeting; and (2) Electronic Copies of Progress Meeting Minutes to the Attendees
Task 2.04 Schedule Review and Management
NV5 will review the Contractor’s baseline schedule and
monthly schedule updates as required by the contract
determine if the critical path is correct, the activity durations are reasonable, the interrelation between
activities is accurate, all permit restrictions are
represented and the overall logic is realistic. We will use the baseline schedule to evaluate potential delays and
workaround strategies to mitigate delay impacts. As work progresses, monthly schedule updates and Time Impact
Analyses will be reviewed for accuracy against the project change orders, and work resequencing has been included
so that impacts to the critical path can be accurately
assessed.

The Lead Inspector will prepare weekly progress reports documenting the progress of construction. These reports will include schedule construction progress, anticipated activities for the upcoming week, and contract working day status.

Deliverable: (1) Baseline Schedule Review; (2) Monthly
Review of Contractor’s Schedule Updates and Provision
of a Summary of Schedule Status and Effects of Changes
on Completion Date to the City; and (3) Monitor and
Facilitate Utility Coordination with Utility Companies and the Contractor, Incorporate Relocations in the Schedule, and Report Delays and Effects on the Completion Date; (4) Weekly Progress Report
Task 2.05 Weekly Statement of Working Days
The Lead Inspector will prepare a record of weather
conditions, controlling item(s), and the status of working days remaining on a weekly basis. This will be included City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 14

WORK PLAN/SCOPE OF WORK
in the weekly progress reports. A copy will be sent to the Contractor to allow them an opportunity to dispute the
statement.

Deliverables: (1) Preparation and Transmittal of Weekly Statement of Working Days throughout the Duration of
Construction
Task 2.06 Monthly Progress Payment Review
data of contract bid items, prepare quantity sheets,
and develop a progress pay estimate. This estimate
will be used to review applications for payment from
the Contractor. Any differences will be negotiated, re- measured, and documented on a revised request for
payment. Payments will be processed in compliance with
City procedures and submitted to the City for approval. The estimate will include a systematic determination of the quantities of work completed and their values and will be Deliverable: (1) Contractor’s Application for Payment;
Request Document and Backup Suitable for Approval and
Execution by the City
Task 2.07 Project Submittals Management
the Contractor that are subject to review. When we receive submittals from the Contractor, they will be stamped and logged in by date of receipt. The NV5 team will then review and forward the submittals to the design engineer and the City, as appropriate.

Some submittals will require review by Caltrans or other administering agencies. When we receive these submittals from the Contractor, NV5 will determine who needs to
review, perform an independent analysis and circulate
drawings for approval to the appropriate agency and/or
team members.

Deliverables: (1) Comprehensive Log of Submittal Tracking and Response; and (2) Submittal Review per Contract
Documents and (3) Correspondence of Review with Status
(Acceptable, Revise and Resubmit)
Management
The NV5 team will manage Contractor-requested requests
for information during construction. The status of RFIs will be accounted for in our RFI log. The Contractor will be team. We will respond when appropriate. RFIs that might affect the design intent will be submitted to the design engineer. If necessary, we will conduct meetings with
the Contractor and other parties to discuss and resolve requests for information.

Deliverables: (1) Comprehensive Log of RFI Tracking and Circulation; and (2) RFI Response
Task 2.09 Contractor Cost Reduction Proposals
NV5 will monitor and manage the initiation, preparation comments and recommendations to the City.

Evaluation of Cost Reduction Proposal Submittals
Task 2.10 Labor Compliance Interviews
If requested, the NV5 team will conduct periodic labor
Contractor’s payroll records will also need to be submitted to the City. Jobsite postings of wage-rate information and Deliverables: (1) Employee Interview Records
Task 2.11 Contract Change Orders
NV5 will evaluate, negotiate and draft contract change
orders as required. Our process for managing CCOs
• Keeping the City’s Project Manager informed on
status of all CCOs
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 15

WORK PLAN/SCOPE OF WORK
• Maintaining a log of proposed CCOs, indicating action dates and status
• Determining if the condition is actually a changed
condition and documenting rationale
• Coordinating with the City and designer regarding
impacts on the design
• Obtaining Caltrans concurrence for all CCOs within the state right-of-way
• Evaluating the Contractor’s CCO cost estimate and
schedule impacts, and negotiating as required
• Accurately documenting labor, equipment, and
materials used on force account work
• Preparing CCO documentation for City and Contractor
signatures
• Processing and incorporating the CCO into the
progress payment breakdown
Deliverables: (1) Perform Quantity and Cost Analysis as Required for Negotiation of Contract Change Orders; (2) Contract Change Order Documentation Ready for the City’s Approval and Execution; and (3) Contract Change Order
Summary Reports
Task 2.12 Quality Assurance Testing and Source Inspection NV5 will follow the City’s Quality Assurance Plan (QAP) and Source Inspection Quality Management Plan (SIQMP) for
testing materials incorporated into the work. Materials at the fabrication source. NV5 will review test results manufactured and source inspection testing. Material will • NV5 will be tracking and observing QC testing by the
Contractor’s approved laboratory when required by
the contract documents
• Materials accepted by the Lead Inspector: Certain
manufactured materials will be accepted if it
based on the manufacturer’s data sheet and
Deliverables: (1) Laboratory Test Results performed
by the Contractor maintained in NV5 Project Files and
turned over to the City at the completion of the project; (2) Summary Sheet of all Test Reports Submitted by Others
to Substantiate Compliance with Contract Documents;
Source Release Tags furnished by the Contractor and the Applicable Delivered Materials at the Jobsite; (4) Testing Summary Sheets; and (5) Documentation of Source
Inspection and Special Inspections as Required by the
Contract Documents, QAP/SIQMP requirements
Task 2.13 Construction Inspection
The NV5 team will serve as the front line of quality
assurance of the Contractor’s work, and as the eyes
and ears to identify potential problems such as utility they occur. Primary inspection services will include the • Provide day-to-day written inspection reports on all
activities performed by the Contractor
• Determine whether work complies with the contract
documents, City and Caltrans standards, and project
permits, and approve/reject work accordingly
•
through daily diaries
• Verify that the Contractor is implementing the safety plan and safe practices in accordance with Cal/OSHA
regulations
• Schedule quality assurance material testing and
coordinate corrective measures as required for failing
materials
•
and provide feedback on proposed remedial action
from the Contractor
• Perform quantity calculations based on completed
work for progress payments
•
• Prepare a punch list and update as-built drawing
records as the work progresses
•
they are opened in a timely manner
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 16

WORK PLAN/SCOPE OF WORK
Deliverables: (1) NV5 Inspectors’ Daily and Special
Inspection Reports; (2) Digital Photographs to Document Construction Activities, as needed, provided In Hard
Measurements for Compliance with Contract Plans and
Progress Payments; and (4) Updates of As-Built Set of
Plans and Review of Contractor’s Marked Set
The NV5 team will provide coordination and review of
lane closures, detours and staging to make sure that
the traveling public and construction workers can safely for lane closures, and timing of and requirements for
closures.

Deliverables: (1) Detour and Lane Closure Submittal
Review Comments and Approvals and Meeting Minute
Notes; (2) Weekly Input of Lane Closure Requests; and (3) a Copy of Review Comments with Recommendations in a
Trackable Spreadsheet Format
Task 2.15 Safety
NV5 will conduct staff safety meetings every week. We
have a library of safety topics relevant to construction projects that we will choose from to discuss each week. We will track attendance at these staff meetings and discuss reconcile the issue. Attendance, topics and meeting notes The NV5 team will review the Contractor’s Safety Program and Injury and Illness Program for compliance with
contract documents. We will review Contractor safety
inspection reports and report safety violations to the
Contractor and the City. We will track accident reports and circulate them as necessary depending on the severity of the accident. These will be logged and kept in the project Deliverables: (1) Staff Safety Meeting Topic, Attendees and Meeting Notes in Project Files for Each Week; and (2) Complete Accident Forms Tracked in the Project Files
Task 2.16 Permit Monitoring
NV5 will monitor the Contractor’s work for compliance with all biological and environmental requirements. We will also be available to help resolve any potential issues as they arise.

The NV5 team will work closely with the Contractor’s
Biologist on scheduling bird surveys and training prior to starting work. We will notify the Contractor’s Biologist upon project limits.

Task 2.17 Storm Pollution Prevention Plan (SWPPP)
Although SWPPP compliance is the Contractor’s
• Conduct a SWPPP pre-submittal conference
• Review the Contractor’s SWPPP
• Verify that the Contractor’s Water Pollution Control
Manager (WPC) uploads necessary SWPPP
documents in the SMARTS system
• Verify that appropriate and effective BMPs are in
place
• Document ineffective BMPs and recommend changes
• Verify that inspections, documentation and sampling
are in accordance with the Construction General
Permit
• Verify compliance with the approved SWPPP,
recommend changes, and verify that the amendment
is created and logged in the SMARTS system
• Verify that illicit discharges, if any, are reported
• Verify that the Contractor submits annual reports onto the SMARTS system
Deliverable: (1) Monitor and Document All Equipment
Maintenance, Staging, and Dispensing of Fuel, Oil, or
Other Such Activities that will occur in Designated Areas, which will be located to prevent any Runoff from entering Waters of the U.S., including Wetlands; (2) Monitor
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 17

WORK PLAN/SCOPE OF WORK
and Document that the Erosion Control Requirements,
Measures and BMPs are employed in accordance with the
conditions in the Regional Water Quality Control Board’s Task 2.18 Claims Management
NV5 will take the lead in resolving of any contract claims for this project during the construction contract period. We will keep current logs of Notice of Potential Claims and will prepare documents and supporting evidence regarding
claims. We will draft position papers and be available to present the City position at the dispute resolution hearings.

The NV5 team will also be available to provide additional claims resolution support if further action is required.

Claims resolution work, if necessary, is typically handled in the post-construction services and will be performed as determined ahead of time.

Deliverables: (1) Log of Potential Claims; and (2)
Complete Merit and Cost Analysis Documentation per
Claim and Dispute Resolution”; and (3) Prepare Letter
Responses and Position Papers

POST-CONSTRUCTION SERVICES
Task 3.01 Final Completion and Acceptance
NV5 will coordinate a walk-through with the City, the design satisfactory completion of all elements of construction and deliverables, we will submit a Notice of Completion to the Contractor, thus relieving the Contractor from further will receive the Contractor’s warranty letter, review it for compliance with the contract documents, and submit it to the City.
(2) Notice of Completion Form for the City
Task 3.02 Prepare and Recommend Final Payment Request
the PFE, we will meet with the Contractor to attempt to orders. If the Contractor still objects to the PFE, we will Deliverables: (1) Final Pay Estimate, including Finalized Bid Items, Claims, Change Orders, Punch-List Items, and Report of Expenditure Checklist, with Attachments
Task 3.03 As-Built Plans
At the Project’s completion, the NV5 team will receive the Contractor’s prepared as-built drawings and perform a
Deliverables: (1) One Set of Contract Drawings indicating Recorded Changes to the Contract in red, as maintained
by NV5 (in addition to the Contractor’s Marked-up Set of Contract Drawings)
Task 3.04 Final Project Report
Following the completion of work, NV5 will complete the Deliverables: (1) One Hard Copy and One Electronic File of the Final Project Report
Task 3.05 Contract Records
of Completion and Acceptance of Work. Hard copies will be completion.

Deliverables: (1) Copy of the Contractor’s Performance
Bond, good for the Warranty Period; and (2) Final Project Documentation
Additional Tasks
Claim Resolution (as needed)
The NV5 team will also be available to provide additional claims resolution support if further action is required.

Claims resolution work, if necessary, is handled in the post-construction services and will be performed as an
determined ahead of time.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 18

2. QUALIFICATIONS

GEOTECHNICAL

ENGINEERING

LAND SURVEY
+ GISCONSTRUCTABILITY
REVIEW
STAFF

AUGMENTATION

PLAN CHECK

SERVICES

BUILDING
+ SAFETY

SERVICES
WATER +

WASTEWATER

ENGINEERING

STRUCTURAL

ENGINEERING

CONSTRUCTION

MANAGEMENT
+ INSPECTION
CIVIL

ENGINEERING
DESIGN
Orange, Riverside, Imperial, and San Diego counties. Throughout the course of completing myriad public works capital improvement projects, our team has demonstrated an unparalleled ability to work well with local agency staff, project stakeholders, engineers and Contractors. We have successfully delivered projects in a timely and cost-effective manner, and we have acquired a keen understanding of local agency requirements, a critical element in the facilitation and effective working relationships with your staff, relevant government agencies and project stakeholders. outreach and community involvement, and we are genuinely committed to public participation as a way of planning and completing projects. Our team routinely performs these services as part of our delivery of public works projects and regards them as a vital component to project success.

NV5, Inc. has been providing engineering and consulting services to public and private sectors for more than 70 years, communities where we live and work.
and grading. Our team includes licensed engineers in a variety of disciplines, licensed Contractors, construction managers, the structure of municipal government and public construction policy and will seamlessly integrate with the City’s team.

Key Services
The successful delivery of our products and services has resulted in repeat clients for a broad range of municipal projects.

FIRM & TEAM QUALIFICATIONS
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 19 Organization Chart
Oversight services. Shown below are team roles and responsibilities.

FIRM & TEAM QUALIFICATIONS
Key Staff Availability
PROPOSED STAFF Q4
2023
Q1
2024
Q2
2024
Q3
2024
Q4
2024
Q1
2025
Q2
2025
Michael Dipsia, Project Manager/Lead
Inspector 100% 100% 100% 100% 100% 100% 100%
Fred Tieu, Field Inspector 100% 100% 100% 100% 100% 100% 100% 30% 100% 100% 100% 100% 100% 100%
Richard Feldman, CPM Scheduling 50% 100% 100% 100% 100% 100% 100% Brad Riel, QA/QC Manager 50% 50% 50% 50% 50% 50% 50%
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 20

FIRM & TEAM QUALIFICATIONS

TEAM QUALIFICATIONS
demonstrates our ability to overcome the challenges of heavy construction operations in or near sensitive riverbed/ waterway, and our innovative approach to this project will minimize the impacts of construction to the riverbed and the remains on schedule and within budget. Included below are brief biographies of our key team members, followed by a providing construction management services for bridge and highway improvements constructed to federal and state standards. Over his career, Mr. Riel has overseen over $600M worth of infrastructure improvement projects, including water, bridge, highway, and roadway widening throughout California. He has overseen the construction BRAD RIEL, PE, QSD/P — QA/QC MANAGER
numerous multimillion-dollar transportation projects. He has served as the Resident Engineer, Structure Representative, Senior Construction Engineer and Construction Manager for Caltrans District 7 and has a good working Manual, Best Management Practices Manual, Materials Sampling and Testing Manual requirements pertaining to highway and bridge construction and the Greenbook.

WHY IS MR. DIPSIA THE BEST CHOICE FOR THE CITY?
Mr. Dipsia has spent more than 18 years as a structure representative and 15 years as a Senior Resident Engineer on Caltrans projects, giving him a unique perspective and thorough understanding of Caltrans standards and procedures, which will help assure that our team can anticipate potential challenges and quickly respond to any issues that may arise, assuring that the City’s project remains on schedule and within budget.

MICHAEL DIPSIA, PE, QSD/P — PM/LEAD INSPECTOR
Construction Senior. He has served as a principal-in-charge, project manager, construction engineer, resident California. His project portfolio includes interchanges, highways, railroad grade separations, reinforced concrete retaining walls, and sidewalks).

JEFF PALLESEN, PE, QSD/P — PRINCIPAL-IN-CHARGE

REFERENCES

Senior Construction Manager,
Ragy Samy
Sr. Transportation Engineer,
Caltrans, 909.851.6870
Arthur Aladjadjian
Superintendent - CM, City of Malibu,
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 21

FIRM & TEAM QUALIFICATIONS
diligence for transportation improvements. She has a complete understanding of Caltrans’ system and procedures attending weekly progress meetings and preparing meeting minutes.

ROSA MARTINEZ — OFFICE ENGINEER
NAME ROLE YEARS EDUCATION, CERTIFICATIONS + LICENSES
Michael Dipsia, PE,
QSD/P
Project Manager/
Lead Inspector
M.S. Civil Engineering (emphasis on Construction
SWPPP Developer/Practitioner (CA) No. 22556
Jeff Pallesen, PE,
QSD/P Principal-in-Charge
Practitioner (CA) No. 01356
Brad Riel, PE, QSD/P QA/QC Manager 36
Fred Tieu, PE, TE,
QSD/P Field Inspector 35 Civil Engineer (CA) No.

Rosa Martinez 25
Richard Feldman CPM Scheduling to Scheduling and Estimating construction projects, including water pollution controls, drainage, utilities, signage and striping, signal light/timing, FRED TIEU, PE, TE, QSD/P — FIELD INSPECTOR
scheduling services for major transportation and capital improvement programs that require strict documentation and scheduling for funding and project accountability. Project responsibilities have included the preparation of master RICHARD FELDMAN — CPM SCHEDULING
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 22 Project Experience
U.S. 101 Highway and Bridge Widening
CALTRANS DISTRICT 7 | LOS ANGELES, CA
Caltrans Structure Representative. Highway and bridge widening that included several retaining walls, sound walls and the installation of new sign structures on U.S. 101, PM 17.9 to 19.5 from Vineland Avenue to North of Tujunga Avenue UC Bridge widening included Laurel Canyon UC, Tujunga Avenue UC, Whitsett Avenue, Coldwater I-10 Widening
CALTRANS DISTRICT 7 | POMONA, CA
Caltrans Structure Representative. Widening of 6-mile stretch of Interstate 10 in the City of Pomona from the 10, 57 and 210 freeway separation to the San Bernardino UC, Park Avenue UC, White Avenue UC, and Indian Hill Avenue UC) and construction of San Antonio Avenue UC were all built above grade and lowered into position. Mr. Dipsia was awarded as Structure Representative of the Year by the Division of Structure Construction for his exceptional performance on this large-scale project.

U.S. 101 Widening
CALTRANS DISTRICT 7 | HARBOR CITY AND SAN PEDRO, CA
Caltrans Structure Representative. Widening of Harbor Freeway (U.S. 101, PM

MICHAEL DIPSIA, PE, QSD/P
Project Manager/Lead Inspector
million dollar highway and bridge projects. He has served as a Structure Representative, Resident Engineer, Senior Construction Engineer, and Construction Manager for of new highway bridge construction, bridge widening, large diameter piles, deep architectural treatment and sculptured walls.

Work Manual, Bridge Deck Construction Manual, Construction Record and Procedure Manual, Prestress Manual, Concrete Technology Manual, Trenching and Shoring Manual, Survey Manual, and local agency standards and requirements pertaining to

CONTACT INFO
[email protected]

EXPERIENCE

EDUCATION
M.S. Civil Engineering
(emphasis on Construction
Management), Rutgers
University, N.J.

LICENSES/CERTIFICATES
Civil Engineer (CA)
Developer/Practitioner,
No. 22556
Engineer

TRAINING
Advance Construction
Contracts, Advance Project
Management I and II (L.A.

Metro, Caltrans, CSU
Northridge)

LEADERSHIP
Coordinated all activities
on Topanga Canyon and
S.R. 27 and acted as
Caltrans Ambassador to
the community

AFFILIATIONS
California Construction
Management Association
of America

FIRM & TEAM QUALIFICATIONS
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 23

FIRM & TEAM QUALIFICATIONS
CALTRANS DISTRICT 7 | LONG BEACH, CA
Caltrans Structure Representative.

I-405 Bridge Widening
CALTRANS DISTRICT 7
Caltrans Structure Representative.

CALTRANS DISTRICT 7 | LOS ANGELES, CA
Caltrans Structure Representative.

I-405 Widening
CALTRANS DISTRICT 7 | TORRANCE, LAWNDALE, REDONDO BEACH AND HAWTHORNE, CA Caltrans Structure Representative.

Regional Gore Area Improvements, Slurry Seal and Slab Replacements CALTRANS DISTRICT 7
Caltrans Resident Engineer. Roadway work included gore area improvements, slurry seal and slab replacement on 118 Templin Highway and I-5 Emergency Hillside Failure
CALTRANS DISTRICT 7
Caltrans Senior Construction Engineer.

I-5 North Corridor Improvements
CALTRANS DISTRICT 7 | LOS ANGELES, CA
Caltrans Senior Construction Engineer. The project added HOV lanes for Interstate 5 North segments 1 & 2 as part of the I-5 North Corridor improvement project from Sheldon Street to SR-118, including Interstate 5/SR-170 interchange.

I-405 Auxiliary Lane
CALTRANS DISTRICT 7 | LOS ANGELES AND CULVER CITY, CA
Caltrans Senior Construction Engineer.

I-405 Slab Rehabilitation
CALTRANS DISTRICT 7 | HAWTHORNE AND CULVER CITY, CA
Caltrans Senior Construction Engineer.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 24 Project Experience
I-680/State Route 4 Interchange
CONTRA COSTA TRANSPORTATION AUTHORITY | WALNUT CREEK, CA Project/Construction Manager. Mr. Pallesen served is serving as Project/ WB directions, as well as widening shoulders to improve on-ramp and off-ramp merging. These widenings consist of JPCP, CRCP, HMA and RHMA roadway types. girder-type bridges. One of these widenings was over Walnut Creek, with multiple agency permitting requirements as well as a creek diversion and a short work window. Mr. Pallesen is responsible for providing resources (staff, equipment, and requirements, and ensuring the provision of the highest quality of services.

Belle Terrace Operational Improvements Project
CITY OF BAKERSFIELD | BAKERSFIELD, CA
Project/Construction Manager. Mr. Pallesen served as Project/Construction Manager between Highway 58 and State Route 99 and the Belle Terrace Bridge over Highway

99. Roughly 1 mile of State Route 99 was widened with concrete pavement and partially resurfaced between Ming Avenue and Highway 58 East. To accommodate the additional lanes on State Route 99, nearly a mile of soil nail walls with aesthetic cast-in-place concrete facing was constructed along State Route 99. The project also reconstructed local roads, pedestrian routes and storm drain facilities along the local streets that parallel State Route 99. Mr. Pallesen was responsible for providing

JEFF PALLESEN, PE, QSD/P
Principal-in-Charge
worked for Caltrans as a Construction Senior. He has served as a principal-in-charge, and local street improvements (widening, overlay, signals, landscaping, drainage understanding of both Caltrans’ standards and procedures and the Federal Highway Administration’s construction guidelines and requirements.

Districts 9 and 10 resident engineers in claims avoidance, partnering, and contract administration. He also taught classes in Caltrans Districts 6, 9, and 10 in asphalt providing input to design engineers as to the methods of construction, production rates, overall buildability of a project, and constructability reviews.

CONTACT INFO
[email protected]

EXPERIENCE

EDUCATION
B.S. Civil Engineering

LICENSES/CERTIFICATES
Civil Engineer (CA)
Developer/Practitioner
(CA) No. 01356

AFFILIATIONS
California Construction
Management Association
of America

FIRM & TEAM QUALIFICATIONS
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 25

FIRM & TEAM QUALIFICATIONS
24th Street Improvements
CITY OF BAKERSFIELD | BAKERSFIELD, CA
Project/Construction Manager. Mr. Pallesen served as
constructability review, providing resources (staff, equipment, and technical), ensuring staff was fully equipped and versed Beltway Operational Improvements
CITY OF BAKERSFIELD | BAKERSFIELD, CA
Assistant Construction Manager. Mr. Pallesen served as Assistant Construction Manager for the $81M Beltway Route 99 to Cottonwood Road, and at the State Route 99/Ming Avenue interchange. The project involved operational retaining walls of various types, including spread footing, soldier pile, soldier pile/ground anchor combination and 72-inch tangent pile. Mr. Pallesen was responsible for providing resources (staff, equipment, and technical), ensuring staff was highest quality of services.

S.R. 178/Morning Drive Widening - Phase 2

BAKERSFIELD, CA
Construction Manager/Project Manager. Mr. Pallesen served as Construction Manager/Project Manager for the $22M two to four lanes from Masterson Street to Miramonte Drive. Just east of Miramonte Drive, the roadway was transitioned were realigned and/or widened where they intersect with State Route 178. A new signal was installed at the realigned and utility relocations along the 3.2 mile roadway alignments. Mr. Pallesen was responsible for providing resources (staff, requirements, and ensuring the provision of the highest quality of services.

SR 178/Morning Drive Interchange

BAKERSFIELD, CA
Construction Manager/Project Manager. Mr. Pallesen served as Construction Manager/Project Manager for the award- winning $26M State Route 178 and Morning Drive Interchange – a primary thoroughfare that links key parts of the City.

The project involves construction of a new interchange on State Route 178 from 0.65 mile west of Morning Drive to along both sides of Morning Drive. Sound and retaining walls were built at several locations. Mr. Pallesen was responsible for providing resources (staff, equipment, and technical), ensuring staff was fully equipped and versed in the City of City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 26 Project Experience
Hickman Road over Tuolumne River Bridge Replacement
COUNTY OF STANISLAUS | WATERFORD, CA
Project Manager, Resident Engineer and Structures Representative. Mr. Riel is serving as Project Manager, Resident Engineer and Structures Representative for this $18M bridge replacement project. The new bridge will be a 750-foot-long bridge shafts. Mr. Riel is responsible for overall contract administration, source inspection budget management.

Jellys Ferry Road Bridge
COUNTY OF TEHAMA | GERBER, CA
Structure Representative. Mr. Riel is serving as Structure Representative for this in length. The project also realigns 6,390 feet of Jellys Ferry Road and relocates the Bureau of Land Management (BLM) recreational facilities. The new bridge is supported by 10-foot and 12-foot diameter cast-in-drilled-hole (CIDH) concrete piles up to 100 feet deep in igneous rock. Mr. Riel is responsible for reviewing all structural aspects of this project.

S.R. 99/Fulkerth Interchange
CITY OF TURLOCK | TURLOCK, CA
Resident Engineer and Structures Representative. Mr. Riel served as Resident Engineer and Structures Representative for this $11M project, which is located at the Fulkerth Road and S.R. 99. The work consisted of undercrossing and ramp widenings ground anchor retaining walls, Type 1 and Type 5 retaining walls, curbs, sidewalk, Mr. Riel was responsible for overall contract administration, source inspection and

BRAD RIEL, PE, QSD/P
QA/QC Manager
Caltrans prior to joining NV5, providing construction management services for bridge and highway improvements constructed to federal and state standards. Over his career, Mr. Riel has overseen over $600M worth of infrastructure improvement projects, including water, bridge, highway, and roadway widening throughout California.

CONTACT INFO
[email protected]

EXPERIENCE
36 years

EDUCATION
B.S. Civil Engineer

LICENSES/CERTIFICATES
Civil Engineer (CA)
Developer/Practitioner

FIRM & TEAM QUALIFICATIONS
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 27

FIRM & TEAM QUALIFICATIONS
relocations, and managing information between multiple adjacent projects and stakeholders (Caltrans TID, City of Turlock).

Beltway Operational Improvement Project
TRIP/CITY OF BAKERSFIELD | BAKERSFIELD, CA
Structure Representative. Mr. Riel served as Structure Representative for this $81M project that improved safety and management services, including inspection, progress payments, contract change orders, structural submittal and falsework reviews, correspondence with the Contractor and local agencies and attending weekly meetings.

S.R. 99/219 (Kiernan Avenue) Interchange
COUNTY OF STANISLAUS | MODESTO, CA
Structure Representative. Mr. Riel served as Structure Representative for the $25M project, which included bridge replacement, freeway widening, interchange improvement, and pumping plant replacement. The improvements spanning State Route 99, added four additional travel lanes to State Route 219 (Kiernan Avenue) within the project limits, plant was constructed 16 feet below the water table. Construction methods included sheet pile shoring, tie-backs, seal courses, and dewatering wells. Responsibilities include full turn-key construction management services. Mr. Riel was also responsible for constructability review and construction management services.

Atwater-Merced Expressway
COUNTY OF MERCED | MERCED, CA
Structure Representative.
local roads, and several signalized intersections. The constructability review recommended alternative staging of a detour the project schedule by 6 months. Mr. Riel was responsible for construction management services, contract change orders, oversight of structural activities and inspection, submittal and falsework reviews, correspondence, and attending weekly meetings.

Grant Line Road/S.R. 99 Interchange Reconstruction

ELK GROVE, CA
Resident Engineer/Structure Representative. Mr. Riel served as Resident Engineer/Structure Representative for the off-ramps, four new signalized intersections, and realignment of local roadways to accommodate the new interchange. He construction, accelerated the bridge construction schedule, and eliminated the need for several temporary freeway ramps Wheeler Ridge Road/I-5 Interchange

KERN COUNTY, CA
Senior Structures Representative. Mr. Riel served as Senior Structures Representative for this interchange project. He was responsible for all of the bridge and retaining wall construction on the project. He also performed structural analysis and approval for all falsework and shoring designs, led the effort on dispute resolutions, provided solution for technical issues, and coordinated all inspection and submittal reviews, working closely with the project designer in addition to Caltrans, Tejon Ranch, and Kern County. The project, located at I-5 and Wheeler Ridge Road, consisted of constructing a structure. Other services included widening portions of the adjoining Wheeler Ridge Road, Laval Road, and freeway intersection of Wheeler Ridge Road and Laval Road.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 28 Project Experience
Slab Replacement
CALTRANS DISTRICT 7 | SANTA CLARITA TO PALMDALE, CA
Caltrans Field Inspector.

Templin Highway and I-5 Emergency Hillside Failure
CALTRANS DISTRICT 7
Caltrans Field Inspector.
drainage and well monitoring systems at Templin Highway and Interstate 5. This was a Caltrans District 7
CALTRANS DISTRICT 7 | LOS ANGELES, CA
construction projects, including water pollution controls, drainage, utilities, signage and striping, detours, erosion control, landscaping, construction staging, construction materials, reports, construction operations, and environmental. Electrical engineering • I-10: Atlantic Boulevard, San Gabriel Boulevard, Rosemead Boulevard, Santa Anita Avenue, Baldwin Avenue, and Peck Road
• I-5: Rosecrans, Valencia, Magic Maintain, and Lake Hugh • S.R. 14: San Fernando, Santiago, Avenue S, Palmdale, Avenue P (Columbus), Avenue L, Avenue K, Avenue J, Avenue I, and Avenue H
• I-210:

CITY OF LANCASTER | LANCASTER, CA
Mr. Tieu performed professional engineering work in the reviewed, evaluated, investigated, and responded to citizen requests. He collected and FRED H. TIEU, PE, TE, QSD/P
Field Inspector
detours, erosion control, landscaping, construction staging, construction materials, reports, construction operations, and environmental. He has served as resident engineer communication systems.

EXPERIENCE
35 years

EDUCATION
B.S. Electrical Engineering

LICENSES/CERTIFICATES
Civil Engineer (CA)
No. 72915

No. 2335
Developer/Practitioner

FIRM & TEAM QUALIFICATIONS
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 29 Project Experience
Belle Terrace Operational Improvements

CITY OF BAKERSFIELD
and Local roadway, signal and drainage improvements. Responsible for organizing and Contractor’s SWPPP and subsequent amendments to State Water Resources Control

CITY OF BAKERSFIELD
Cottonwood Road, and at the SR-99/Ming Avenue interchange. The project involves numerous sub-stages of construction. Responsible for organizing and maintaining

ROSA MARTINEZ
Ms. Martinez is capable of assisting the resident engineer in all aspects of required Storm Water Pollution Prevention Program and the General Permit.

CONTACT INFO
[email protected]

EXPERIENCE
25 years

EDUCATION
Engineering Curriculum)

FIRM & TEAM QUALIFICATIONS
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 30

FIRM & TEAM QUALIFICATIONS
Westside Parkway, Phase 1 & 2

CITY OF BAKERSFIELD
meeting minutes, payment applications, contract change orders, submittal packages, as-built drawings, and daily reports.

Also reviewed construction payment applications, distributed project documents, reports, deliverables and plans and Caltrans’ practices.

SR 178 Widening, Phase 2

CITY OF BAKERSFIELD
Drive/Bedford Green to Masterson Street and to a four-lane facility from Masterson Street to Miramonte Drive. In addition, SR 178 at Morning Drive Interchange, Phase 1

CITY OF BAKERSIFELD
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 31 Project Experience
Valley Center Road Improvement Project, Phase II
COUNTY OF SAN DIEGO | SAN DIEGO, CA
Senior Scheduler
responsible for the review of monthly updates and reports, Contractor delay claims, and independent review of delays. Provided technical assistance to owner in achieving settlement of delay related changes to the contract. Segment 1 of the project was situated in tough mountainous terrain. The remaining three segments required maintenance of access to commercial and residential driveways and cross streets and the reconstruction of two bridges. Schedule management on this project was made Beltway Operation Improvements
CITY OF BAKERSFIELD | BAKERSFIELD, CA
Project Scheduler. The $81M Beltway Operational Improvements project was to Route 99 to Cottonwood Road, and at the State Route 99/Ming Avenue interchange.

The project involves operational improvements to interchange ramps and construction stages with numerous sub-stages of construction. Project responsibilities included the review of the baseline schedule, review of monthly update schedules, analysis of Contractor time impact analysis submittals, and schedule delay analysis.

Pelandale Avenue Interchange Reconstruction
CITY OF MODESTO | MODESTO, CA
Project Scheduler. The $38M construction consisted of a new bridge over State Route at four intersections, multiple retaining walls (both standard Type 1 MSE designs), review of the baseline schedule, review of monthly update schedules, analysis of Contractor time impact analysis submittals, and schedule delay analysis.

FIRM & TEAM QUALIFICATIONS

RICHARD FELDMAN
CPM Scheduling
improvement programs that require strict documentation and scheduling for funding and project accountability. Project responsibilities have included the preparation of coordination with multiple stakeholders and agency representatives during the conduct of schedule and cost analysis.

CONTACT INFO
Richard.Feldman@
nv5.com

EXPERIENCE

EDUCATION
B.A. Philosophy

TRAINING
Associated General
Contractors of California,
San Francisco District,
Construction Education
Committee
BART/Bechtel Saturday
University, Estimating
Workshop
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 32

PROJECT EXPERIENCE

PROJECT EXPERIENCE
similar challenges.

PROJECT NAME

BRIDGE CONSTRUCTED OVER WATER/ WATERWAY ADJACENTBRIDGE DEMOLITION, REPLACEMENT, WIDENINGROADWAY/APPROACH CONSTRUCTION, RECONSTRUCTION OR WIDENINGENVIRONMENTAL COMPLIANCE/PERMITSUTILITY RELOCATION/COORDINATIONTRAFFIC CONTROL/TRAFFIC HANDLINGSWPPP MONITORING Hickman Road Bridge over the Tuolumne River
Jellys Ferry Road at Sacramento River Bridge
680/S.R. 4 Interchange
Balfour Avenue/S.R. 4 Interchange
Kiernan Avenue/S.R. 99 Interchange
Pelandale Avenue/S.R. 99 Interchange
Westside Parkway Bridge over Kern River (Phase 4)
San Joaquin River Pedestrian Bridge
Orwood Road Bridge Replacement

RELEVANT PROJECTS
provided inspection and construction oversight services.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 33

KEY INFORMATION
DATES: MAY 2020-CURRENT
KEY PERSONNEL: JEFF PALLESEN,

BRAD RIEL, RICHARD FELMAN

SERVICES/PROJECT FEATURES
REFERENCE: Mark Hamblin, PE, County of Stanislaus,
NV5 is providing full construction management services for this $18M bridge is subject to shutdowns. Since it is the only southern access to the City of Waterford, it is a vital link for the region.
shoulders and one 5-foot-wide sidewalk placed along the upstream edge. The safe pedestrian and bike access. It is supported by 10-foot diameter drilled- the Tuolumne River channel. The new bridge will also carry a new water line, Road alignment and tie into a revised signalized intersection at State Route construction.

HICKMAN ROAD OVER THE TUOLUMNE RIVER BRIDGE REPLACEMENT PROJECT COUNTY OF STANISLAUS | STANISLAUS COUNTY, CA

PROJECT EXPERIENCE
• Construction Management +
Inspection
• Bridge over Waterway
• Federal Funding
• Caltrans LAPM/Construction
Manual Requirements
• Roadway Widening/
Realignment
•
•
• Utility Relocations and
Coordination
• Pedestrian Access
• Regulatory Permit Compliance
• Multiple Stakeholders
• Public Outreach and
Coordination
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 34

SERVICES/PROJECT FEATURES

KEY INFORMATION
DATES: FEBRUARY 2020-AUGUST 2022
KEY PERSONNEL: JEFF PALLESEN,

BRAD RIEL, RICHARD FELDMAN
REFERENCE: Shawn Furtado, PE, Civil Engineer, County of Tehama, 530.228.2619
NV5 provided the Structure Representative and Structures Inspection services a new bridge upstream on a more functional alignment. The project included Subsurface conditions were vastly different than what was called out in the plans what would have been appropriate given the real site conditions. As a result, the Contractor requested additional compensation for work that fell outside the originally agreed-upon scope. In response to these challenges, Mr. Riel and the Construction Management (CM) team were actively engaged in negotiations with the Contractor and Tehama County to address the claims being made by the Contractor. necessary and reasonable costs were being paid out. These discrepancies were beyond our control, and it’s important to have a collaborative approach to resolve these issues. Effective communication and negotiation between all parties involved of the project. The primary aim is to arrive at a resolution that takes into account the legitimate additional costs incurred due to the unforeseen differences in site conditions while also keeping those costs as reasonable as possible.

Jellys Ferry Road at Sacramento River Bridge
COUNTY OF TEHAMA | TEHAMA COUNTY, CA

PROJECT EXPERIENCE
• Structure Representative +
Structures Inspection
• Constructability Review
•
Review
• Bridge over Waterway
• Roadway Realignment
• Relocation of Recreational
Facilities
• Caltrans LAPM/Construction
Manual Requirements
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 35

SERVICES/PROJECT FEATURES

KEY INFORMATION
DATES: SEPTEMBER 2018-AUGUST 2021
KEY PERSONNEL: JEFF PALLESEN,

BRAD RIEL, RICHARD FELDMAN,

ROSA MARTINEZ
REFERENCE: Ravi Pudipeddi, PE, Civil Engineer IV,
99 and local roadway, signal, pedestrian route and drainage improvements in the feet in elevation along a horizontal curve with a cross-slope of 10%. The other Route 99. Both bridges required erection of falsework systems and demolition ground anchors. The soil conditions consisted almost entirely of poorly graded construction very challenging.

NV5 provided full suite of construction management services, including resident engineering, structures representative, construction inspection, utility coordination, environmental compliance, materials testing, schedule and budget management, and contract administration.

Belle Terrace Operational Improvements
CITY OF BAKERSFIELD | BAKERSFIELD, CA

PROJECT EXPERIENCE
• Construction Management +
Inspection
• Structures Representative
• Materials Testing
• Utility Coordination
• Environmental Compliance
• Bridge Construction
• Roadway Widening
• Federal Funding
• MASH-Compliant Crash Cushions
• HMA Paving
• Retaining Walls
•
• Pedestrian Improvements
• Storm Drain Improvements
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 36

PROJECT EXPERIENCE
NV5 is providing on-call construction management support services to the City Canyon Boulevard (SR-27) to John Tyler Drive and Median Improvements from Webb Way to Puerco Canyon Road (north of John Tyler Drive). will facilitate signal timing adjustment and streamline monitoring from a remote management. This project also includes curb ramp upgrades in some areas. The needed safety upgrade will include the installation of Intelligent Transportation System (ITS) devices, such as closed-circuit television (CCTV) cameras, a queue detection system, dedicated short-range communication (DSRC), and changeable message signs (CMS).

The Median Improvements project south of Puerco Canyon is to reconstruct the Canyon Road. This proposed project includes constructing new median curbs with a stamped concrete median. This project will also add bike refuge lanes at the intersections.

REFERENCE: Arthur Aladjadjian, Public Works Superintendent, City of

SERVICES/PROJECT FEATURES

KEY INFORMATION
DATES: FEBRUARY 2022-CURRENT
KEY PERSONNEL: MICHAEL DIPSIA,

JEFF PALLESEN, RICHARD FELDMAN,

ROSA MARTINEZ
PCH Signal System and Median Improvements
CITY OF MALIBU | MALIBU, CA
• Construction Management
Support
•
• Landscaping + Irrigation
• Bike Lane Improvements
• ADA Compliant Design Services
• Stamped Concrete Median
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 37

PROJECT EXPERIENCE
REFERENCE: Joe Giulian, Supervising Engineer, County of Merced, 209.385.7601

KEY INFORMATION
DATES: 2017-CURRENT
KEY PERSONNEL: BRAD RIEL, RICHARD

FELDMAN, ROSA MARTINEZ
SERVICES/PROJECT FEATURESNV5 is providing full construction management services for all four phases of the $90M Campus Parkway corridor project. Once constructed, Campus Parkway will complete the southeastern portion of the Merced Loop System, which will circle the City of Merced and connect surrounding communities, including the City of Atwater.

Rascal Creek. The project also includes large portions of work inside the state right-of-way, as well as inside the City of Merced. Work within these other of the new alignment, the NV5 team had to coordinate energization and signal activation in three jurisdictions with two separate power providers being done by three separate Contractors.

Campus Parkway
COUNTY OF MERCED | MERCED, CA
• Construction Management +
Inspection
• Structures Representative
• Materials Testing
• Utility Coordination
• Environmental Compliance
• Bridge Construction
• Roadway Realignment
•
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 38

CONFLICT OF INTEREST STATEMENT

CONFLICT OF INTEREST STATEMENT
•
outcome of the Contract or the construction project.
•
project that will follow.
•
construction project.

City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 39

LOCAL PRESENCE

LOCAL PRESENCE
any needs that may arise.

County and the surrounding area. Throughout the course of completing myriad public works capital improvement projects, our team has demonstrated an unparalleled ability to work well with local agency staff, project stakeholders, engineers and contractors. We have successfully delivered projects in a timely and cost-effective manner, and we have acquired a keen understanding of local agency requirements, guidelines, codes, and regulations, which are critical elements in the facilitation and resolution of project issues.

Our work with local, state and federal agencies keeps us in the forefront of current updates to policies and procedures, City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 40

REFERENCES

REFERENCES
Provided below are references of clients for whom inspection and construction oversight services have been performed in

CLIENT NAME/CONTACT RELEVANT SERVICES
County of Stanislaus
Address: 1716 Morgan Road,
Modesto, CA 95358
Contact: Mark Hamblin, PE,
Project Name/Services: Construction Management Services for Hickman Road Over the Tuolumne River Bridge Replacement Project Dates: May 2020-Current
Contract Amount: $2.5M
County of Tehama
Address: 9380 San Benito Ave.,
Gerber, CA 96035
Contact: Shawn Furtado, PE,
Civil Engineer IV,
530.228.2619
Project Name/Services: Structures Representative and Inspection for Jellys Ferry Road at Sacramento River Bridge
Dates: February 2020-August 2022
Contract Amount: $2M
City of Malibu
Address: 23825 Stuart Ranch Road,
Contact: Arthur Aladjadjian,
Public Works Superintendent,
Project Name/Services: CM Support Services for the PCH Signal System and Median Improvements projects
Dates: February 2022-Current
Contract Amount: $683K (Signal System) and $389K (Median Improvements)
City of Santa Clarita | Inspection and Construction Oversight for Copper Hill Drive Bridge Widening NV5 | 41