EASTSIDE BRIDGE AND MAJOR THOROUGHFARE
CONSTRUCTION FEE DISTRICT UPDATE REPORT
Prepared for:
LOS ANGELES COUNTY
DEPARTMENT OF PUBLIC WORKS
900 South Fremont Ave. Alhambra, CA 91803‐1331
and
CITY OF SANTA CLARITA
TRAFFIC AND TRANSPORTATION PLANNING
23920 Valencia Blvd
Santa Clarita, CA 91355
November 2024
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
TOC‐1
TABLE OF CONTENTS
I. SUMMARY ................................................................................................................................................. 1 A. NEED FOR DISTRICT UPDATE ................................................................................................................ 1 B. UPDATED DISTRICT FEE RATES ............................................................................................................. 2 II. THE BRIDGE AND MAJOR THOROUGHFARE CONSTRUCTION FEE DISTRICT ............................................ 5 A. AUTHORITY ........................................................................................................................................... 5 B. PURPOSE ............................................................................................................................................... 5 C. CONCEPT ............................................................................................................................................... 6 III. EASTSIDE AREA ACCESS ......................................................................................................................... 6 A. BACKGROUND ....................................................................................................................................... 6 B. EXISTING CIRCULATION AND PROPOSED IMPROVEMENTS ................................................................. 7 IV. THE EASTSIDE BRIDGE AND MAJOR THOROUGHFARE CONSTRUCTION FEE DISTRICT ....................... 22 A. THE DISTRICT BOUNDARY ................................................................................................................... 22 B. DEVELOPMENT ANALYSIS ................................................................................................................... 22 C. PROPOSED IMPROVEMENTS AND ESTIMATED COSTS ....................................................................... 23 D. IMPROVEMENT PHASING ................................................................................................................... 24 E. TRAFFIC AND LAND USE ANALYSIS ..................................................................................................... 24 F. THE DISTRICT FEE ................................................................................................................................ 25 G. CONSTRUCTION OF DISTRICT IMPROVEMENTS IN LIEU OF PAYING FEES .......................................... 29 H. CREDIT AWARD AND CASH REIMBURSEMENT ................................................................................... 30 I. RIGHT‐OF‐WAY ACQUISITION ............................................................................................................. 31 J. PROVISIONS FOR UPDATING COSTS AND UNIT INFORMATION ......................................................... 31 K. PROPOSAL FOR DISTRICT CLOSURE .................................................................................................... 32 L. DISTRICT FUNDS .................................................................................................................................. 32 M. THE ENVIRONMENTAL ANALYSIS ........................................................................................................ 33
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
TOC‐2
LIST OF FIGURES
Figure 1: Eastside Bridge and Thoroughfare District Existing and Proposed Developments ............. 4 Figure 2: Proposed Links and Bridges .............................................................................................. 20 Figure 3: Proposed Intersections ..................................................................................................... 21
LIST OF
TABLES
Table 1: Proposed District Fee ............................................................................................................ 3 Table 2: List of Improvements ............................................................................................................ 8 Table 3: Development Analysis ........................................................................................................ 23 Table 4: Soft Cost Percentages ......................................................................................................... 24 Table 5: District Fee Calculation ....................................................................................................... 25 Table 6: Development Analysis of Filed Maps .................................................................................. 45 Table 7: Development Analysis of Vacant Land by Assessor Parcel Number .................................. 48 Table 8: Summary of Development Analysis .................................................................................... 59
LIST OF ATTACHMENTS
ATTACHMENT A: LEGAL DESCRIPTION ............................................................................................. 34 ATTACHMENT B: SUMMARY OF COST ESTIMATES FOR DISTRICT IMPROVEMENTS ....................... 41 ATTACHMENT C: DEVELOPMENT ANALYSIS ..................................................................................... 45 ATTACHMENT D: COUNTY AND CITY CODES PERTAINING TO B&T DISTRICTS ................................ 60 ATTACHMENT E: REGIONAL IMPROVEMENTS ................................................................................. 67 ATTACHMENT F: B&T CASH/CREDIT REQUEST FORM ...................................................................... 69
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
1 I. SUMMARY
The Eastside Bridge and Major Thoroughfare Construction Fee District Report presents to the Los Angeles County Board of Supervisors and the City of Santa Clarita City Council an update for their approval to an existing area of benefit for financing specific improvements in the Eastside area of the Santa Clarita Valley, within the County Los Angeles and City of Santa Clarita jurisdictions. Improvements include, but are not limited to, new and improved roadways, bridges, intersections, and interchanges.
Updating the Eastside Bridge and Major Thoroughfare Construction Fee District, hereinafter referred to as “District”, will provide an equitable financing mechanism by which new development within an identified area will share the costs of providing full mitigation improvements.
State Subdivision Law and both the Los Angeles County and City of Santa Clarita Codes authorize the use of bridge and major thoroughfare construction fee districts for the funding and construction of improvements, provided these facilities are identified on the local agency’s adopted transportation element of its General Plan. Based on the transportation needs in this area of the Santa Clarita Valley, and the limitations of other funding sources, this funding method has been determined to be the best alternative to provide needed improvements.
This report describes the concept and mechanics of the District. Information included in this report will enable subject property owners to determine the fee to be assessed against their property if and when it is developed. A map of the District including proposed and existing developments is included as Figure 1.
A. NEED FOR DISTRICT UPDATE
Some major highway infrastructure improvements have been completed in the Eastside District since it was last updated in 2002. Some of these improvements include:
completion of the Golden Valley Road extension and widening (except sidewalk and street lights), Via Princessa improvements, Soledad Canyon Road street lights, Sierra Highway
streetlights and improvement, Sand Canyon Road widening, Skyline Ranch Road, and numerous intersection upgrades. District improvements for Vasquez Canyon Road, Davenport Road, and Placerita Canyon Road have been removed, and improvements for Shadow Pines Boulevard have been reduced to two lanes as these highways have been removed or revised in the City and County highway plans. Skyline Ranch Road, Vista Canyon Boulevard, and Humphreys Parkway are new roadway improvements for the District, and have been partially constructed. Skyline Ranch Road replaces the extension of Whites Canyon Road, and Vista Canyon Boulevard and Humphreys Parkway now replace portions of Lost Canyon Road. Skyline Ranch Road has been completed.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
2 The major improvements that still remain to be completed in the district are: District‐ wide bus turnouts, portions of Vista Canyon Boulevard and Humphreys Parkway, Golden Valley Road sidewalk and streetlights, Via Princessa extension and widening, Soledad Canyon Road median, Santa Clarita Parkway, Sand Canyon Road widening, Lost Canyon Road, plus numerous intersection upgrades.
The District documentation is also being revised to allow for a yearly change ranging from plus 5% to minus 5% in the fee rate based on the Construction Cost Index (Los Angeles region as reported by the Engineering News Record). This should allow the fee to better
keep pace when there are fluctuations in construction costs. Previously, the District had a built‐in escalation clause that limits the yearly fee increase to a maximum of 2% based on the local Construction Cost Index. However, over the years the construction cost increase has exceeded 2% in several instances.
B. UPDATED DISTRICT FEE RATES
The remaining District improvements to roadways, bridges, and intersections total an estimated $228.9 million. The Summary of Cost Estimates for District Improvements is included as Attachment B. The scope of work has increased on some improvements, and construction costs have gone up. Thus, the overall District estimate to complete the
improvements has not significantly since the last update. However, changes in the scope of work for some of the projects have occurred as a result of changes in road classifications due to County and City Circulation Element updates. In order for projects to be adequately funded, the District fee needs to be updated to keep pace with the significant changes in construction costs and project scope.
The cost of the remaining District improvements is less than the 2002 costs (approximately $228.9 million versus $236.9 million) as many of the improvements that were identified back then have
been built.
To determine District build‐out, a development analysis based on filed tentative maps and the Santa Clarita Valley Area Plan was performed. This analysis indicated that the amount of remaining development is estimated at 7,972.7 factored development units (FDUs).
The remaining District developable area was analyzed for vacant land for which there is
no previously‐recorded map. The Development Analysis is included as Attachment C. The estimated FDUs are 56% of the factored developments units in the previously‐updated District (14,238 FDUs versus 7,972.7 FDUs).
Taking the potential funding and the cash in District into account, the proposed District
fee is proposed to be $23,980 per FDU. The analysis concludes that a District fee increase would reflect the funding necessary to complete the remaining improvements in light of Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
3 the construction costs versus the remaining development. The proposed District fees are shown in Table 1.
Table 1: Proposed District Fee
Land Use Category Factor Proposed District Fee
per Unit or Gross Acre
Residential:
Single Family (per unit) 1.0 per unit $23,980
Townhome/Condo (per
unit)
0.8 per unit $19,190
Apartment (per unit) 0.7 per unit $16,790
Non‐Residential:
Commercial (per gross
acre)
5.0 per acre $119,900
Industrial (per gross acre) 3.0 per acre $71,940
TR 53074
PM065239PM 60821
TTM 65159TTM 63002
PM068498TTM 68601TR066202
TR064989
TR060359TR067233
TR45123TR47573
TR48086
TR060259
TR 60922
TPM 78248TR 69164/TR 83087
PM 83283
EASTSIDE DISTRICT BOUNDARYOTHER DISTRICTCITY BOUNDARYWATER FEATUREAPPROVED PROJECTPENDING PROJECT
EASTSIDE DISTRICT BOUNDARY
SEE SHEET 2VACANT (NO FILED MAP)
LEGEND:FOR DISPLAY PURPOSES ONLYNOT ALL ELEMENTS TO SCALE 02500'5000'
5000'
DISTRICT MAPEASTSIDE B&T DISTRICTFIGURE 1COUNTY OF LOS ANGELES DATE: 10/01/2024SHEET 1 OF 2
HEB 001-01 Eastside B&T District-01.dwg
RECORDED
TTM 67374
TR 53074
TR 071216
PM 68740TM 63003PM 54043
TTM 63002TR 69164/
PM068498
PM065239PM 60821
TTM 65159TPM 78248 TPM 75026TPM 68203TR 61924TR 83087
EASTSIDE DISTRICT BOUNDARYOTHER DISTRICTCITY BOUNDARYWATER FEATUREAPPROVED PROJECTPENDING PROJECT SEE SHEET 1
EASTSIDE DISTRICT BOUNDARY
VACANT (NO FILED MAP)
DISTRICT MAPEASTSIDE B&T DISTRICTFIGURE 1COUNTY OF LOS ANGELES LEGEND:FOR DISPLAY PURPOSES ONLYNOT ALL ELEMENTS TO SCALE5000'2500' 5000'
0 RECORDED / NOT BUILT (B&T FEES DEFERRED)
DATE: 05/13/2024SHEET 2 OF 2
HEB 001-01 Eastside B&T District-02.dwg
RECORDED
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
5 II. THE BRIDGE AND MAJOR THOROUGHFARE CONSTRUCTION FEE DISTRICT
A. AUTHORITY
The State of California Government Code Section 66484, regarding Subdivisions, gives local agencies the authority to adopt local ordinances that “may require the payment of a fee as a condition of approval of a final map or as a condition of issuing a building permit for purposes of defraying the actual or estimated cost of constructing bridges over waterways, railways, freeways, and canyons, or constructing major thoroughfare.” The local adopted ordinance must refer to the circulation element of its General Plan, provide for a public hearing, provide for the establishment of boundaries of an area of benefit, and provide for the identification of the costs, a fair method of allocation of costs to the area of benefit and a fair fee apportionment (to be disclosed at the public hearing). Further, the local ordinance must provide that the payment of fees shall not be required unless the major thoroughfares are in addition to or a reconstruction of any existing thoroughfares serving the area at the time of district adoption. It must further provide that if owners of more than one‐half of the area of property to be benefited by the improvement(s) file proper written protests, the district proceedings as proposed shall be abandoned for at least one year. The local ordinance allows acceptance of considerations in lieu of the payment of fees, permits a local agency to advance money from its general fund or road fund to be reimbursed from bridge and major thoroughfare funds, permits a local agency to incur an interest bearing indebtedness for the construction of bridge or major thoroughfare facilities, and does not preclude an agency from providing funds for the construction of bridge or major thoroughfare facilities to defray costs not allocated to the District.
The Los Angeles County Board of Supervisors adopted Ordinance No. 82‐0050 on March 2, 1982, adding Section 21.32.200 to the Los Angeles County Code, providing for the establishment of bridge and major thoroughfare construction fees to be paid by subdivider or building permit applicants (County Code Section 21.32.200 is included as Attachment D). Within the City of Santa Clarita, payment of such fees was established by City of Santa Clarita Subdivision Code Section 16.21.190 established on November 24, 1992 (now Section 17.51.010D). These codes are consistent with the requirements and provisions of the State law.
B. PURPOSE
The District has been designed to accommodate the needs of future development anticipated by the Los Angeles County Area Wide General Plan and the City of Santa Clarita General Plan. Since the last District update, the Santa Clarita Valley Area Plan was updated and adopted by the Board of
Supervisors on November 27, 2012, and
the City of Santa Clarita General Plan was adopted by the City Council on June 14, 2011. The District will provide local and regional benefits. Many of the District Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
6 improvements will be eligible for local, state and federal funding. The District intends to pursue all potential sources of out‐of‐ district funding for these improvements including, but not limited to, State and Federal Gas Taxes, Propositions A and C Sales Tax, Transportation Planning and Development Sales Tax on Gasoline, County Transportation Tax, State Transportation Improvement Program funding, Federal Transportation Efficiency Act for the 21st Century funds, State and Federal Highway Trust Funds, special grants, and other sources that may be available. The District will provide the matching funds necessary to pursue greater funding from the aforementioned sources.
C. CONCEPT
As authorized by statutes cited above, the adoption of a specific area of benefit permits the County of Los Angeles and the City of Santa Clarita to levy a fee against future development located within the area of benefit. This funding method appropriately assesses developments, which create the need for additional improvements, for the additional public facility costs. The charge is levied in proportion to the estimated number of trips generated by the development which is translated into FDUs. FDUs are described in more detail in “Development Analysis”, Section IV. B, of this report.
The adoption of this type of funding
district does not charge existing development. The
District fee is collected at the time of recordation of a final map or just prior to the issuance of a building permit.
III. EASTSIDE AREA ACCESS
A. BACKGROUND
Historically, access to new development has been provided cooperatively by the County, the City, and land developers. The County and City funded their share with Gas Tax Funds. Land development was primarily concentrated in flatter areas, expanding away from urban centers. Public facilities were constructed to accommodate this expansion.
Much of
the development in recent years and that which is expected to occur in the future is and will be in outlying areas where topography is more rugged and restrictive. As a result, the cost of providing necessary public facilities, including roadways will continue to increase.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
7 B. EXISTING CIRCULATION AND PROPOSED IMPROVEMENTS
The primary road network for the District consists of eleven arterials which are classified as Major, Secondary, or Limited Secondary Highways on the Los Angeles County Santa Clarita Valley Area Wide Circulation Plan and the City of Santa Clarita General Plan.
This report analyzes build‐out development of the District and identifies the scope of District improvements. The District proposes to provide full mitigation for many of the roadways identified on the Los Angeles County and City of Santa Clarita Plans including intersections and interchanges.
Full mitigation improvements will include full‐width grading, base, pavement, curb, gutter, sidewalks, medians, striping for capacity enhancement, bus turnouts or bus pads (where applicable), bike lanes (where applicable), fully improved and signalized intersections, signal interconnect (where applicable), street lighting, roadway‐related utility relocation, drainage structures within road right‐of‐way, full improvements for bridges and interchanges, and slope stabilization landscape for roadway‐related cut/fill slopes.
Right‐of‐way is assumed to be dedicated by individual development projects, except for State highway projects and roadway widening or roadway construction that are unrelated to private development projects.
The City of Santa Clarita General Plan Circulation Element, dated June 2011, changed the classification of some of the major thoroughfares
in the District. Los Angeles County also
updated their Circulation Element in 2012 with the update of the Santa Clarita Valley Area Plan. The road classification changes included:
1. Vasquez Canyon Road from Bouquet Canyon Road to Sierra Highway is reclassified from secondary highway to limited secondary highway. (Improvements are no longer required)
2. Sand Canyon Road from City of Santa Clarita boundary to Sierra Highway, is reclassified from a major highway to secondary highway along the existing alignment.
3. Shadow Pines Boulevard/Tick Canyon Road from Grandifloras Road to Davenport Road is reclassified from secondary highway to a limited secondary highway.
4. Lost Canyon Road from Jakes Way to Sand Canyon Road is reclassified from a major highway to a secondary highway, re‐alignment, and a new bridge.
5. Skyline Ranch Road from Plum Canyon Road to Sierra Highway – Reclassify planned major highway to a limited secondary highway (replaces previous alignment of Whites Canyon Road).
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
8 6. Davenport Road was reclassified from a secondary highway to a limited secondary highway. No further improvements are currently necessary for this highway.
7. Jakes Way was added as a limited secondary highway. No further improvements are currently necessary for this highway.
8. Placerita Canyon Road was revised to a secondary highway from a limited secondary highway. No roadway improvements are proposed for Placerita Canyon Road at this time.
Below is a list of proposed District improvements. The proposed improvements consist of links, bridges, and interchanges and are depicted in Figure 2. These Improvements have been planned to accommodate forecasted traffic growth occurring both within the District and cumulative traffic from outside the District. The extents of improvements are described in Table 2 below, and the estimated costs are included in Attachment B.
Table 2: List of Improvements
LINKS
LINK#
LOCATION
IMPROVEMENT
GOLDEN VALLEY ROAD
E-100 Via Princessa to south
side of SR-14 bridge
Link Complete
E-101 North side of SR-14
bridge to Green
Mountain Drive
Link Complete
E-102 Green Mountain Drive
to Sierra Highway
Link Complete
E-0103 Sierra Highway to
Via Princessa (City)
Construct sidewalk both sides
Street lights
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
9 LINKS
LINK#
LOCATION
IMPROVEMENT
E-0104 Via Princessa to
Soledad/ Golden Valley
Grade Separation
Construct sidewalk one side and south of Sheriff’s
Station to Via Princessa (remaining sidewalk
complete)
Street lights one side (complete one side)
E-105 Interchange at Soledad
Canyon Road to
Northerly District
Boundary
Improvements complete
WHITES CANYON ROAD
e-202 Westerly District
Boundary to Vasquez
Canyon Road
Link eliminated. Now Skyline Ranch Road (Link E-
E-1400 and E-1401)
VASQUEZ CANYON ROAD
E-0300
E-0301
Westerly District
Boundary to Sierra Hwy
(County)
No Improvements Needed
SANTA CLARITA PARKWAY
E-0402 Westerly District
Boundary to Sierra Hwy
(City)
Grading
6 Lane Street Construction
VIA PRINCESSA
E-0501 Santa Clarita Pkwy to
Golden Valley Road
(City)
Grading
6 Lane Street Construction
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
10 LINKS
LINK#
LOCATION
IMPROVEMENT
E-0502 Golden Valley Road to
Rainbow Glen Drive
(City)
Grading
6 Lane Street Construction (cost and scope of
improvements per PSRE)
E-0503 Rainbow Glen Drive to
May Way (City)
Bus Turnouts
Street Lights
Signing and striping from 4 to 6 lanes
Median Construction
E-0504 May Way to Whites
Canyon Road(City)
Signing and striping
Bus Turnouts
E-0505 Whites Canyon Road to
Weyerhaeuser Way
(City)
Signing and striping
Median
Bus turnouts
E-0506 Weyerhaeuser Way to
Sierra Highway (City)
Bus Turnouts
E-0507 Sierra Hwy to Antelope
Valley Freeway (City)
Bus Turnouts
E-0508 Antelope Valley
Freeway to Golden
Valley Road (City)
Median
Signing and striping 4 to 6 lanes
Bus Pads
SOLEDAD CANYON ROAD
E-0600 Westerly District
Boundary to Ruether
Ave (City)
Bus Turnouts
E-0601 Ruether Ave to
Rainbow Glen Drive
(City)
Bus Turnouts
E-0602 Rainbow Glen Drive to
Langside Avenue (City)
Bus Turnouts
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
11 LINKS
LINK#
LOCATION
IMPROVEMENT
E-0603 Langside Avenue to
Camp Plenty Road
(City)
Bus Turnouts
E-0604 Camp Plenty Road to
Whites Canyon Road
(City)
Bus Turnouts
E-0605 Whites Canyon Road to
Crossglade Avenue
(City)
Median
Bus Turnouts
E-0606 Crossglade Avenue to
Luther Drive (City)
Partial Median
Bus Turnouts
E-0607 Luther Drive to Shangri-
la Drive (City)
Bus Turnouts
E-0608 Shangri-la Drive to
Sierra Hwy (City)
Median
Bus Turnouts
E-0609 Sierra Hwy to Solemint
Road (City)
Bus Turnouts
E-0610 Solemint Road to
Galeton Road (City)
Median (approximately 700 feet)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0611 Galeton Road to Anne
Freda Street (City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0612 Anne Freda Street to
Kenroy Avenue (City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0613 Kenroy Avenue to Sand
Canyon Road (City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0614 Sand Canyon Road to
SR-14 WB Ramps
(City)
Signing and striping 4 to 6 lanes
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
12 LINKS
LINK#
LOCATION
IMPROVEMENT
E-0615
SR-14 Westbound
Ramps to Oak Spring
Canyon Road (City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0616 Oak Spring Canyon
Road to Flowerpark
Drive (City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0617
Flowerpark Drive to
Poppy Meadow Street
(City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0618
Poppy Meadow Street
to Shadow Pines
Boulevard (City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0619
Shadow Pines
Boulevard to SR-14
Ramps (County)
Bus Pads
Signing and striping 4 to 6 lanes
E-0620
SR-14 Ramps to
Easterly District
Boundary (County)
Street Widening to 6 Lanes
Grading
Signing and Striping
E-0620B
Bridge over Bee
Canyon Creek (County)
Widen Bridge from 2 to 6 lanes
SIERRA HIGHWAY
E-0700 Southerly District
Boundary to Placerita
Canyon Road (City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0701 Placerita Canyon Road
to Golden Valley Road
(City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0702 Golden Valley Road to
Rainbow Glen Drive
(City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0703 Rainbow Glen Drive to
Friendly Valley Parkway
(City)
Bus Turnouts
Signing and striping 4 to 6 lanes
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
13 LINKS
LINK#
LOCATION
IMPROVEMENT
E-0704 Friendly Valley Parkway
to Whispering Leaves
Drive (City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0705 Whispering Leaves
Drive to Via Princessa
(City)
Bus Turnouts
Signing and striping 4 to 6 lanes
E-0708 SR-14 off ramps to
Canyon Park
Blvd./Jake’s Way (City)
Bus Turnouts
E-0709 Jakes Way to Sandy
Drive (City)
Bus Turnouts
E-0710 Sandy Drive to Soledad
Canyon Road (City)
Bus Turnouts
E-0711 Soledad Canyon Road
to Scherzinger Lane
(City)
Median
Bus Turnouts
Signing and striping 4 to 6 lanes
Interconnect
E-0712 Scherzinger Lane to
Sierra Cross Road
(City)
Median
Bus Turnouts
Signing and striping 4 to 6 lanes
Interconnect
E-0713 Sierra Cross Road to
City Limit (City)
Street Widening to 6 lanes
Median
Sidewalk- 2 Sides
Bus Turnouts
Signing and striping
Street Lights
Interconnect
Right-of-way acquisition
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
14 LINKS
LINK#
LOCATION
IMPROVEMENT
E-0714 City Limit to Sand
Canyon Road (County)
Street Widening to 6 lanes
Median
Sidewalk-2 Sides
Street Lights
Bus Pads
Signing and striping
Interconnect
E-0715 Sand Canyon Road to
Vasquez Canyon Road
(County)
Street Widening to 6 lanes
Median
Sidewalk- 2 sides
Street Lights
Bus Pads
Signing and striping
Interconnect
Right-of-way acquisition
E-715B Sierra Highway Bridge
over creek
Due to the location of this bridge it has been
renamed E-716B and is included below.
E-0716 Vasquez Canyon Road
to Davenport Road
(County)
Street Widening to 6 lanes
Median
Sidewalk-2 sides
Street Lights
Bus Pads
Signing and striping
Interconnect
Right-of-way acquisition
E-0716B Bridge Over Creek
(County)
Bridge Widening from 2 to 6 lanes
E-0717 Davenport Road to
Northerly District
Boundary (County)
Street Widening to 6 lanes
Median
Sidewalk-2 sides
Street Lights
Bus Pads
Signing and striping
Interconnect
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
15 LINKS
LINK#
LOCATION
IMPROVEMENT
DAVENPORT ROAD
E-0800-801 Sierra Highway to
Easterly District
Boundary (County)
No improvements necessary
SHADOW PINES BLVD
E-0900 Soledad Canyon Road
to Begonias Lane (City)
Interconnect
E-0901 Begonias Lane to
Grandifloras Road
(City)
Sidewalk-two sides
Curb and gutter (one side)
Street Lights (one side)
Interconnect
E-0902 Grandifloras Road to
Davenport Road
(County)
Grading
Construct 2-lane limited secondary highway
E-902B Bridge over Creek
(County)
Construct Bridge – 2 lanes
SAND CANYON ROAD
E-1001 Soledad Canyon Road
to SR-14 Eastbound
Ramps (City)
Median
Signing and striping
Interconnect
E-1002 SR-14 Eastbound
Ramps to Lost Canyon
Road (City)
Street Widening to 6 lanes
Median
Sidewalk-two sides
Street Lights
Bus Turnouts
Signing and striping
Interconnect
E-1002B Bridge over Santa
Clara River (City)
Widen Bridge
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
16 LINKS
LINK#
LOCATION
IMPROVEMENT
E-1003 Lost Canyon Road to
Placerita Canyon Road
(City)
Street Widening to 2 lanes
Construct storm drain
E-1003B Bridge over Iron
Canyon Creek (City)
Widen Bridge
E-1004 Placerita Canyon Road
to Easterly District
Boundary (City)
Street Widening to 2 lanes
E-1005 Soledad Canyon Road
to City Limit (City)
Roadway realignment
Class I Bike Lane
Signing and striping
Retaining Wall
Bus Turnouts
2 Roundabouts
E-1006 City Limit to Sierra
Highway (County)
4 Lane Street Construction (No Bike Lane)
Grading
Right-of-way acquisition
LOST CANYON ROAD
E-1200 Canyon Park Boulevard
to City Limit
Replaced by Links E1203 and E-1204
E-1201 City Limit to Sand
Canyon Road (City)
Replaced by E-1500
E-1202 Sand Canyon Road to
Oak Spring Canyon
Road (City)
Street widening to 2 lanes
Signing and Striping
E-1203 Jakes way to Canyon
Park Blvd. (City)
Signing and Striping
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
17 LINKS
LINK#
LOCATION
IMPROVEMENT
HUMPHREYS PARKWAY (PREVIOUSLY KNOWN AS LOST CANYON ROAD) E-1204 Jakes Way to Vista
Canyon Blvd. (City)
4-Lane Street Construction
(No Bike Lane) – Complete from Jakes Way tie in to
Lincoln Place
CANYON PARK BOULEVARD
E-1300 Railroad Tracks to
Lost Canyon Road
(County)
Complete
SKYLINE RANCH ROAD
E-1400 West District
Boundary to Sierra
Highway (County)
Complete
E-1400B Skyline Ranch Road
Bridge over Mint
Canyon Creek
Complete
VISTA CANYON BLVD.
E-1500 Bridge to Soledad
Canyon Road (City)
Grading
2 Lane Street Construction
E-1500B Vista Canyon Bridge
over Santa Clara
River (City)
Bridge Construction
Bank Stabilization
E-1501 Vista Canyon Bridge
south to transit
station
Grading
2 Lane Street Construction
PLACERITA CANYON ROAD
E-1601 Antelope Valley
Freeway to Easterly
County Line
(County)
No improvements proposed at this time.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
18 LINKS
LINK#
LOCATION
IMPROVEMENT
E-1602 County Line to Sand
Canyon Road (City)
No improvements proposed at this time.
INTERSECTIONS
INTERSECTION #
LOCATION
IMPROVEMENT
EI-9 Sierra Highway and Soledad
Canyon Road
Intersection augmentation for
additional turn movements
EI-29 Sierra Highway and Sand
Canyon Road (County)
Intersection augmentation
Signal modification
Right-of-way acquisition
EI-31 Sierra Highway and
Davenport Road (County)
New 3-way signal
EI-33 Via Princessa and Golden
Valley Road (City)
New 4-way signal
EI-39 Davenport Road and Shadow
Pines Boulevard (County)
New 3-way signal
EI-42 Sand Canyon Road and
Placerita Canyon Road (City)
New 3-way signal
EI-49 Via Princessa and Lost
Canyon Road (City)
Intersection augmentation for
additional turn movements
EI-54 Lost Canyon Road and Jakes
Way (City)
Intersection augmentation
Roundabout
EI-55 Soledad Canyon Road and
Sand Canyon Road (City)
Intersection augmentation
Signal modification
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
19 INTERSECTIONS
INTERSECTION #
LOCATION
IMPROVEMENT
EI-56 Soledad Canyon Road and
Vista Canyon Blvd. (City)
Intersection augmentation
EI-57 Humphreys Parkway and
Vista Canyon Blvd. (City)
Construct roundabout
intersection
E-708
E-710
E-103
E-705
E-704
E-703E-702
E-701
E-508
E-507
E-506
E-505E-504
E-503
E-502
E-501
E-608
E-607E-606
E-605
E-604
E-603
E-602E-601
E-600 E-611
E-609 E-610
E-711 E-712
E-713
E-714
E-715
E-301 E-716
E-612
E-613 E-615 E-616
E-617
E-618
E-620
E-901
E-902
E-801
E-717
E-1004
E-1003
E-1204
E-1203E-1300
E-1500 E-1202
E-1006
E-1005 E-1001
E-902 Bridge
E-1003 Bridge
E-800
E-104
E-1400
E-902
E-900
E-1500
Bridge
E-700
E-709
E-1400B
E-716B
E-300
E-619
E-620 Bridge
E-1002 Bridge
E-1002
VISTA CYN BL
·|}þ14
SANTA
CLARITA
PKWY
VIA
PRINCESSA
VIA
PRINCESSA
WHITESCANYON RD
PLUMCANYON RD
SKYLINERANCH RD
PLACERITA
CANYON RD
HASKELL
RD
COUNTY OF
LOS ANGELES
CITY OF
SANTA CLARITA
COPPER
HILL DR SHADOW
PINES BLVD
E-402
CANYON PARK BL
LOST
COUNTY OF
LOS ANGELES
GOLDEN VALLEY
RD
ROAD
CANYON
RD
RD
SAND
GOLDEN
RD
CITY OF
SANTA CLARITA
VALLEY
E-1501
HUMPHREYS PKWY
E-614
BOUQUET
CANYON RD
VASQUEZ
CANYON RD
GOLDENVALLEY RD
DAVENPORT
NEWHALLAVE
GOLDEN
VALLEY RD
SIERRA HWY
SOLEDAD
CANYON RD
SOLEDAD
CANYON RD
SIERRA HWY
CANYON RD
LEGEND
PROPOSED EASTSIDE LINKS AND BRIDGES
COMPLETED EASTSIDE LINKS AND BRIDGES
EASTSIDE B&T DISTRICT BOUNDARY
CITY BOUNDARY
FREEWAY
ROADS
RAILROAD
FIGURE 2
PROPOSED LINKS AND BRIDGES
EASTSIDE B&T DISTRICT
COUNTY OF LOS ANGELES
K
0 5,100 10,2002,550
Feet
FOR DISPLAY ONLY
NOT ALL ELEMENTS TO SCALE
G:\Eastside B and T District 0141-001-001\Exh\Figure 2 Eastside Bridge and Thoroughfare District - Link & Bridges.mxd "¯/D
"¯/D
"¯/D
"¯/D"¯/D
"¯/D
"¯/D
"¯/D
"¯/D
"¯/D
"¯/D "¯/D
·|}þ14
SANTA
CLARITA
PKWY
VIA
PRINCESSA
VIA
PRINCESSA
WHITESCANYON RD
PLUMCANYON RD
SKYLINERANCH RD
PLACERITA
CANYON RD
HASKELL
RD
COUNTY OF
LOS ANGELES
CITY OF
SANTA CLARITA
COPPER
HILL DR SHADOW
PINES BLVD
EI-39
CANYON PARK BL
LOST CANYON RD
VISTA
CANYON BL
EI-49
EI-57EI-9
GOLDEN VALLEY
ROAD
HUMPHREYS
PARKWAY
CITY OF
SANTA CLARITA
BOUQUET
CANYON RD
VASQUEZ
CANYON RD
GOLDENVALLEY RD
DAVENPORT
RD
NEWHALLAVE
GOLDEN
VALLEY RD
SIERRA HWY
SOLEDAD
CANYON RD
SOLEDAD
CANYON RD
SIERRA HWY
SAND
CANYON RDEI-33
EI-42
EI-54
EI-56 EI-41
EI-55
EI-29
EI-31
LEGEND
"¯/D PROPOSED INTERSECTION IMPROVEMENTS
EASTSIDE B&T DISTRICT BOUNDARY
CITY BOUNDARY
FREEWAY
ROADS
RAILROAD
FIGURE 3
PROPOSED INTERSECTIONS
EASTSIDE B&T DISTRICT
COUNTY OF LOS ANGELES
K
0 5,100 10,2002,550
Feet
FOR DISPLAY ONLY
NOT ALL ELEMENTS TO SCALE
G:\Eastside B and T District 0141-001-001\Exh\Figure 3 Eastside Bridge and Thoroughfare District - Intersections.mxd Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
22 IV. THE EASTSIDE BRIDGE AND MAJOR THOROUGHFARE CONSTRUCTION FEE
DISTRICT
A. THE DISTRICT BOUNDARY
The legal description of the District (Area of Benefit) is included as Attachment A. It encompasses those properties which have yet to be developed and which will receive benefit from the improvements funded by the District. A map showing the location of the District is included as Figure 1. The boundaries were determined by the topographical features in the Eastside area, ownership/parcel lines, national forest land boundaries, and existing and future access.
General Boundary Description
The District includes the existing Canyon Country community and lies generally within the Friendly Valley, Mint Canyon, Sand Canyon, and Vasquez Canyon areas of the Santa Clarita Valley. Generally, the District's northern, eastern, and southern boundary lines follow the Angeles National Forest and private ownership boundary lines. The westerly District boundary is shared with the Via Princessa and Bouquet Canyon Bridge and Major Thoroughfare Districts along a north‐south ridgeline approximately through and northerly of the intersection of Sierra Highway with Soledad Canyon Road and along the first and second Los Angeles Aqueducts.
B. DEVELOPMENT ANALYSIS
Considerable future development is expected within the District and can be measured in terms of FDUs. The quantity of FDUs was estimated for all vacant land within the District. Where a subdivision map has been filed, but not recorded, to develop vacant land, the FDUs were calculated from the residential development units and non‐ residential acreage specified in the filed map. Where no map has been filed, FDUs for vacant land was estimated based on the General Plan designations for each vacant parcel.
Table 3, Development Analysis, depicts the calculation of FDUs, including applicable land use categories, estimated number of units/acres, and trip factors.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
23 Table 3: Development Analysis
LAND USE CATEGORY Estimated Number of
Units/Acres FACTOR FDUs
Single Family 3,478.8 1.0 3,478.8
Condominium 554.0 0.8 443.2
Apartment 3,773.7 0.7 2,641.6
Total Residential 7,806.5 ‐ 6,563.6
Commercial 247.4 5.0 1,236.8
Industrial 57.5 3.0 172.4
Total Non‐Residential 304.8 ‐ 1,416.1
TOTAL 7,972.7
C. PROPOSED IMPROVEMENTS AND ESTIMATED COSTS
Improvements to be funded by the District are based on a determination of the traffic needs of future development anticipated by the County and City General Plans, and analysis of the improvements designated on the adopted City and County highway plans.
Improvements and associated costs have been estimated for purposes of determining the District fee rates. Actual scope of work and costs may change as the improvements approach the final design stage. The proposed improvements in the District are estimated to cost approximately $228.9 million and are shown in Table 2.
The estimated costs of District improvements include construction costs based on “prevailing wage”, cost of materials, design costs and permitting fees (considered “soft costs”, shown in Table 4 below), and an administrative/management fee equal to 5% of the wage, materials and soft costs.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
24 Table 4: Soft Cost Percentages
Description Intersection Storm
Drain Road Bridge State Hwys.
Road Interchanges
Engineering‐
Design 9.5% 6% 4% 7% 8% 7%
Plan Check 3% 2.5% 2% 2% 3% 3%
Engineering‐
Field 3% 1% 2% 2% 7% 3%
Survey 3% 3% 2% 2% 8% 2.5%
Soils 1% 1% 3% 2% 7% 1%
Geology 0% 0% 0.5% 0.5% 0.5% 0%
Bonds/Fees 1% 8% 8% 5.5% 10% 1%
Erosion
Control
(SWPPP)
0.5% 0% 0.5% 0% 0.5% 0.5%
Army Corps
Wildlife Env.
Inspections
0% 3% 3% 4% 3% 3%
TOTAL : 21.0% 24.5% 25.0% 25.0% 47.0% 21.0%
Several interchanges have been identified as “regional” improvements that will be impacted by the developments in each of the Districts. Therefore, each District being updated at this time will pay a portion of each regional improvement based on the respective District’s percent share of projected vehicle trips that encounter the improvement.
Regional improvements, along with a description, percent share according to District, total estimated cost, and estimated cost to the District, are included in Attachment E.
D. IMPROVEMENT PHASING
Generally, the timing and phasing of construction of District improvements will be determined by when and where development occurs, as well as how many units. The
amount of funds received may also determine the timing of improvements.
E. TRAFFIC AND LAND USE ANALYSIS
The existing highway system generally handles the traffic generated by existing development located within the District. As such, existing development would not require the additional highway improvements if additional development did not occur.
Therefore, the improvements identified in this report are intended to accommodate the Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
25 circulation needs of future development within the District and are expected to improve circulation for future development within the District. Regional improvements within, or funded by, this District are expected to improve circulation for future development on a Valley‐wide basis.
It is estimated that an additional 7,972.7 residential units and 304.8 acres of non‐
residential area will be developed within the District. The anticipated development quantified in the Development Analysis section and categorized above will require an expanded circulation system.
F. THE DISTRICT FEE
The District fee is calculated by dividing the estimated net cost of the remaining improvements by
the estimated number of FDUs. The net cost is the total estimated cost of improvements less anticipated grant funding and funds available. The calculated District fee is shown below:
Table 5: District Fee Calculation
DISTRICT FEE CALCULATION
A LINKS $205,162,224
B INTERSECTIONS $7,772,799
C INTERCHANGES $ ‐
D
REGIONAL IMPROVEMENTS ‐ DISTRICT'S SHARE OF
COSTS (ATTACHMENT E) $15,962,224
E TOTAL DISTRICT COSTS (ROW A+B+C+D) $228,897,247
F EXISTING FUNDS IN DISTRICT ‐ LA COUNTY $11,259,953 G EXISTING CREDITS IN DISTRICT ‐ LA COUNTY $4,727,023 H EXISTING FUNDS IN DISTRICT ‐ SANTA CLARITA $649,521 I EXISTING CREDITS IN DISTRICT ‐ SANTA CLARITA $11,927,890 J APPROXIMATE GRANT FUNDING $42,491,219
TOTAL NET COST OF DISTRICT (ROW E‐F+G‐H+I‐J) $191,151,467 TOTAL FDUS 7,972.7
TOTAL COST PER FDU $ 23,980
To ensure fairness in the method of allocating fees to each land use category within the District boundaries, the fee amount is based on the number of trips measured in FDUs that are generated by each land use category. Therefore, the proportionate share of fees take into account the impacts of peak‐hour vehicle trips on the system as identified in the Los Angeles County Circulation Plan and the City of Santa Clarita Circulation element. The peak hour vehicle trips are based on land use and for residential land uses peak hour trips Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
26 are based on type of unit, and not unit square footage. The traffic model used as the basis for the City and County’s circulation elements for this area do not factor in residential square footage to determine peak hour trips, but instead base trips on the type of residential unit. The traffic models make assumptions on type of units based on zoning.
Square footage of future units cannot be discerned based on zoning and is usually not known until a development proposal gets submitted by a landowner. Therefore, in order to develop a traffic mitigation fee for Bridge and Thoroughfare Districts, the appropriate manner would be to use unit type rather than square footage, as the square footage is not known at the time the mitigation fee is calculated. As summarized above, consistent with Assembly Bill 602, square footage is not an appropriate metric to calculate such fee.
Therefore, the City has identified other policies for equitably calculating the traffic impacts and corresponding fees for developments with lesser impacts, as described in the “Special Cases” at the end of this section IV(F).
Each of the six major land use categories have been assigned FDUs based on the average impact for that category
relative to a single‐family residence as shown below:
Single Family ............................................................. 1.0 FDU Condo/Townhome .................................................... 0.8 FDU Apartment ................................................................. 0.7 FDU Commercial (per gross acre) ................................... 5.0 FDUs Industrial (per gross acre) ....................................... 3.0 FDUs Mixed Use ................................... 0.7/DU res& 5.0/AC (com)
Future development units and/or acres are multiplied by the assigned FDUs and multiplied by the District’s adopted District fee per FDU resulting in a project’s proportionate share of District fees. The District fees for each of the six major land use categories are included in Table 1.
The adoption of this
type of funding district does not levy any fees against existing development. FDUs for recorded subdivisions, which are located within the District, were not included in the District fee calculation, as it has been assumed that District fees were paid at recordation. If District fees were not paid at recordation for non‐residential land uses, then District fees may be collected for the issuance of a building permit.
SPECIAL CASES
Governmental Uses
Governmental improvements, such as those for schools, police, fire protection, and libraries, specifically needed to support benefited development, have been excluded from the development analysis as these uses are assumed to be exempt from District payment.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
27 Lands with Physical Development Constraints
Lands with physical development constraints such as landslides, faults, or other restricted use areas, were considered for future development according to their County or City‐assigned land use. This assumption was made since, in many cases, these types of constraints can be mitigated. Furthermore, these restricted use areas can often be used to accommodate development features such as parking lots and setbacks, and residential densities or non‐residential square footage can often be transferred from landslide areas to other developable portions of a site.
Mixed Use (Residential and Commercial)
Within the District there are proposed development areas that include both residential and commercial uses on the same lot. These “mixed use” areas cannot collect fees based on a single use of the lot as is typical for fee collection in most all other cases. Therefore, fee collection for these uses shall be as outlined henceforth. Fees for residential uses on mixed use lots shall be based on number of units multiplied by the appropriate factor (e.g. 0.8 FDU/unit for condos, 0.7 FDU/unit for apartments), then multiplied by the fee in effect at the time of the project’s map recordation. Fees for the non‐ residential area shall be based on the building square footage divided by 43,560, then multiplied by a factor of 5, then multiplied by the fee in effect at the time of the project’s map recordation.
Assisted Living Facilities
In the event that the District includes assisted‐living facility uses, fees for this type of use are to be collected at a commercial rate, based on the gross acreage of the associated lot(s), as opposed to number of units.
Non‐Residential Land Development not including a Land Division
The County code regarding bridge and major thoroughfare fee payment allows for the collection of B&T fees at either the map recordation or building permit phases of a project. It is the County’s policy to collect only at the map recordation unless no land division is proposed. District fees for land development not including a land division shall be paid prior to the issuance of a building permit. They City requires fees to be paid at recordation of a subdivision map, unless a project falls under a City ordinance which defers fee payment to the building permit phase, or unless a subdivision map is not required for the project.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
28 District fees for non‐residential uses that are part of a land division will be calculated based on the gross acreage of each non‐residential lot.
District fees for non‐residential uses on a vacant parcel that does not include a land division will be calculated based on the gross acreage within the vacant parcel’s boundary.
District fees for non‐residential uses on an under‐utilized parcel that does not include a land division will be calculated, at the discretion of the City and County, based on one of the following calculations:
Retail Commercial
Gross building square footage
Total District Fee Obligation = 16,335 *5 * District Fee per FDU A typical fee calculation of FDUs for a retail commercial development involving a land division would assume gross commercial lot acreage times 5 FDUs times the District fee per FDU. However, the above calculation determines the District fee obligation by estimating the gross project acreage based on a proposed building’s gross square footage and an assumed Floor Area Ratio (FAR). For example, using an FAR of 0.375:1, a retail commercial building on a one‐acre (43,560 square feet) parcel would yield a building square footage of 16,335 (43,560 x 0.375 = 16,335). Therefore, if a lease project is submitted for District fee payment, an assumed gross acreage can be determined by taking the building’s gross square footage and dividing it by 16,335, which has previously been established as generally being one acre of retail development.
Office Commercial/Business Park
Gross building square footage
Total District Fee Obligation = 43,560 *5 * District Fee per FDU
Using an FAR of 1.0:1, an office commercial or business park building on a one‐ acre (43,560 square feet) parcel would yield a building square footage of 43,560 (43,560 * 1 = 43,560). Again, if a lease project is submitted for District fee payment, an assumed gross acreage can be determined by taking the building’s gross square footage and dividing it by 43,560, essentially one acre of commercial office development.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
29 Industrial
Gross building square footage
Total District Fee Obligation = 29,403 * 3 * District Fee per FDU
Using an FAR of 0.675:1, industrial buildings on a one‐acre parcel would yield a building square footage of 29,403 (43,560*0.675=29,403). Again, if a lease project is submitted for District fee payment, an assumed gross acreage can be determined by taking the building’s gross square footage and dividing it by 29,403, essentially one acre for industrial development.
District fees for a lease building are not required if the underlying land paid District fees based on gross acreage, including the land on which the lease building is to be sited.
It should be noted that if a project proposes an upgraded use from that which was paid for the underlying parcel (e.g. commercial use proposed by fees at recordation were paid based on industrial rate), that project would be subject to the difference in fees between that which was paid and the proposed use. Underutilized parcels such as those that may accommodate a future lease structure were not assumed in the development analysis, as these parcels are difficult to identify at this stage.
Non‐Typical Cases
If either Agency (City or County) determines in their discretion that a proposed development project in their respective jurisdiction does not fit into one of the land use categories identified on Table 1, that Agency may develop and have on file a rate sheet for non‐typical land uses based on the estimated number of trips generated by the development project. Development projects that include accessory dwelling units (under Government Code Section 66324), or housing development within a transit priority area or within one‐half mile of a convenience retail store (under Government Code Section 66005.1), will be considered non‐typical “Special Case” land uses due to a lesser impact on the transportation systems funded by the District Fee, and those uses will be the subject of a special non‐typical land use fee calculation.
G. CONSTRUCTION OF DISTRICT IMPROVEMENTS IN LIEU OF PAYING FEES
If a developer constructs District‐
identified improvements prior to map recordation, that
developer becomes eligible for District credit which can be used to offset District fee payments. If the cost of the completed and accepted improvements, along with the soft costs and 5% administrative/management fee, exceeds the District fee obligation, the developer would be given a credit, after improvement completion and acceptance, which can be used to offset future District fee obligations within the District.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
30 If adequate funds are available, the developer may receive a cash reimbursement, as outlined in Section H below.
Thus, a developer has the following options with regard to construction of District‐identified improvements:
• Construct District‐identified improvements for District credit. • Construct District‐identified improvements and receive cash reimbursement from the District, if adequate funds are available.
Implementation of “prevailing wages” labor is required for the construction of District improvements in order for a developer to receive cash reimbursement from the District.1
H. CREDIT AWARD AND CASH REIMBURSEMENT
Credit is awarded upon review and approval of the costs to implement a District project based on supporting documentation submitted by the developer. Generally, credit is awarded after project completion and acceptance. However, the City or County may issue credits at an earlier stage (nearly complete) if the cost documentation is acceptable.
The City or County, in their discretion, may elect to provide cash reimbursement for District credits. The determination of whether or not to provide cash reimbursement for District credits will generally be made in accordance with the below guidelines.
1. The City and County may determine to make loans to a particular District from non‐ District sources (e.g. County General Fund) or from other Districts. If a loan has been made to a particular District, no reimbursement of District credits will be made from that District until the loan(s) have been repaid by that District.
2. The City and County may determine to set aside previously collected funds or earmark funds to be collected for the construction of a particular B&T project or projects within a District. District funds that have been set aside or earmarked for a particular B&T project will be excluded from consideration as a source of funds for reimbursement of District credits.
3. In general, credits will be reimbursed according to the chronological order in which credits were granted, i.e. older outstanding credits will generally be reimbursed prior to credits that were granted more recently.
1 Prevailing wages is defined as the commonly accepted rate paid to workers practicing in the same or similar locality under the same or similar circumstances.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
31 4. The City and County may elect to reimburse a block of credit holders at the same time. In this case, all outstanding credit holders with the same or earlier credit dates will be reimbursed an equal amount.
5. Where a particular District has previously loaned funds to another District, the City and County will generally attempt to make all funds repaid to the lending District available for credit reimbursement in accordance with Item Nos. 1, 2, 3, and 4 above.
6. In general, reimbursement in the form of cash will only be issued when the appropriate B&T District has a cash surplus in unobligated funds; however, it is the sole discretion of the City and/or County to determine whether developers/property owners will be issued reimbursement in the form of cash or credit for B&T‐eligible improvements.
7. Nothing in Items Nos. 1 to 5 above should be interpreted as requiring the City or County to provide reimbursement at any given time. The City or County may elect to continue to accumulate funds in order to fund planned projects.
8. Reimbursement in the form of cash requires prior approval by the City or County and must be specified in the conditions of approval for the project.
If a developer constructs improvements beyond its conditioned obligation, District credit and/or cash may be given subsequent to the improvement’s completion and acceptance as long as the improvement has been described in this report as a District improvement.
I. RIGHT‐OF‐WAY ACQUISITION
If a condition of project approval requires a landowner to dedicate property as right of way for a State improvement, then the landowner will receive credit at fair market value for the property dedicated. If any local improvement requires land acquisitions from a third party, the cost of the property will be added to the estimated cost of the improvement for District credit. However, if right‐of‐way is required to be dedicated for a County improvement, as a condition of project approval, the landowner receives no credit for the value of the dedicated property. Therefore, the cost estimates prepared for District improvement reflect costs for right‐of‐way as described above.
J. PROVISIONS FOR UPDATING COSTS AND UNIT INFORMATION
Projections for build‐out development and the cost of the improvements located within the area of benefit may change over time. Project scope may change due to refinement and the need to comply with requirements imposed by other agencies, including, but not limited to, the California Department of Transportation (Caltrans). A reasonable Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
32 amount of outside funding has been anticipated and formulated into the proposed District fees. Outside funding, not anticipated in the District formation analysis or update, may be received or funds anticipated may not be received. Therefore, in order to equitably assess future development as well as collect sufficient funds to complete the improvements, it will be necessary to periodically re‐evaluate the net cost of the improvements, the remaining land to be developed and the type of development being constructed within the District and to adjust the fee accordingly.
On July 1 of every year the District fees shall be adjusted as follows: calculate the percentage movement for the previous year in the Los Angeles Regional Construction Cost Index (CCI) based on Engineering News Record data for that period. Then, if the percentage movement equals or exceeds a five percent increase, the District fee per FDU will be increased by five percent and rounded up to the nearest $10. If the percentage movement increases less than five percent, the District fee per FDU will be increased by the same percent as the percentage movement and rounded up to the nearest $10. In the event that there is a negative adjustment in the CCI, then the fee shall be adjusted downward by up to five percent.
A separate biennial review to reassess development trends, construction costs, grant funding success, and refinement of project scope will also be conducted.
K. PROPOSAL FOR DISTRICT CLOSURE
In the event that District fees collected from developers exceed the cost of
improvements, the surplus funds, less administrative costs, will be refunded at District closure by the City and/or County to current owners in proportion to District fees paid.
L. DISTRICT FUNDS
The County or City will maintain a separate District Fund for the Eastside District. Funds may be loaned to or from the Eastside District provided that the loans are properly recorded by no less than a Resolution approved by the County Board of Supervisors. The County or City shall make all funds or credits available to the District, as necessary, for the purpose of reimbursing or providing credit to developers/landowners, as outlined in this report, once the improvements are completed, accepted, and the proper documentation filed with the reimbursement request.
Upon annexation, any assets held in the B&T District under the ownership of the County of Los Angeles, but located within the City of Santa Clarita, will be transferred to City of Santa Clarita ownership; and any assets held in the District under the ownership of the City of Santa Clarita, but located within unincorporated Los Angeles County, will be transferred to County of Los Angeles ownership.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
33 To receive credit for constructed and approved improvements, the proper documentation must be submitted to the County or City. No documentation for soft costs is necessary as they are already accounted for in the District fees.
Improvements will be accepted for maintenance by the County or City upon completion and field acceptance. After field acceptance of constructed improvements, credit withdrawal of District funds will be authorized. Along with the “B&T Cash/Credit Request Form” included as Attachment F, copies of contracts, change orders, and purchase orders which detail construction costs will be provided to the County or City. Upon submittal of a request for the withdrawal of credits due, review and determination by the County or City will be completed within 30 days.
M. THE ENVIRONMENTAL ANALYSIS
The County of Los Angeles and the City of Santa Clarita finds the establishment of the proposed District Fees to be statutorily exempt from the California Environmental Quality Act under Public Resource Code Section 21080 (b)(8)(D).
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
34 ATTACHMENT A: LEGAL DESCRIPTION
LEGAL DESCRIPTION
THE AREA OF BENEFIT KNOWN AS EASTSIDE BRIDGE
AND MAJOR THOROUGHFARE CONSTRUCTION FEE
DISTRICT
THAT PORTION OF THE UNINCORPORATED TERRITORY OF THE COUNTY OF LOS ANGELES, STATE OF CALIFORNIA AND THAT PORTION OF THE CITY OF SANTA CLARITA WITHIN THE FOLLOWING DESCRIBED BOUNDARIES:
BEGINNING AT THE NORTHEASTERLY CORNER OF SECTION 16, TOWNSHIP 4 NORTH, RAGE 15 WEST, SAN BERNARDINO MERIDIAN;
THENCE SOUTHERLY ALONG THE EASTERLY LINE OF SAID SECTION 16 TO THE SOUTHERLY LINE OF THE NORTH HALF OF SAID SECTION 16;
THENCE WESTERLY ALONG SAID SOUTHERLY LINE TO THE WESTERLY LINE OF THE NORTHWEST QUARTER OF THE SOUTHEAST QUARTER OF SAID SECTION;
THENCE SOUTHERLY ALONG SAID WESTERLY LINE TO THE NORTHERLY LINE OF THE SOUTHWEST QUARTER OF SAID SOUTHEAST QUARTER;
THENCE EASTERLY AND SOUTHERLY ALONG THE NORTHERLY AND EASTERLY LINES OF SAID SOUTHWEST QUARTER TO THE SOUTHERLY LINE OF SAID SECTION 16;
THENCE WESTERLY ALONG SAID LAST MENTIONED SOUTHERLY LINE TO THE NORTHWESTERLY CORNER OF LOT 1 IN SECTION 21, SAID LAST MENTIONED TOWNSHIP AND RANGE;
THENCE SOUTHERLY ALONG THE WESTERLY LINE OF SAID LOT 1 AND THE WESTERLY LINE OF LOT 4 IN SAID LAST MENTIONED SECTION TO THE NORTHWESTERLY BOUNDARY OF SIERRA HIGHWAY, 120 FEET WIDE, AS SAME EXISTED ON MARCH 4, 2002;
THENCE SOUTHWESTERLY ALONG SAID NORTHWESTERLY BOUNDARY TO THE NORTHERLY BOUNDARY OF SOLEDAD CANYON ROAD, AS SAME EXISTED ON SAID DATE;
THENCE WESTERLY AND NORTHWESTERLY ALONG THE NORTHERLY AND NORTHEASTERLY BOUNDARY OF SOLEDAD CANYON ROAD TO A LINE 50 FEET EASTERLY OF AND PARALLEL WITH, MEASURED AT RIGHT ANGLE TO,
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
35 THE EASTERLY BOUNDARY OF TRACT NO. 23365, AS SHOWN ON MAP FILED IN BOOK 760 PAGES 29 AND 30, OF MAPS, IN THE OFFICE OF THE REGISTRAR‐ RECORDER OF SAID COUNTY;
THENCE NORTHERLY ALONG SAID LAST MENTIONED PARALLEL LINE TO THE MOST SOUTHERLY CORNER OF LOT 82 OF TRACT NO. 30317 AS SHOWN ON MAP FILED IN BOOK 740, PAGES 97 TO 100, INCLUSIVE, OF SAID MAPS;
THENCE NORTHERLY, NORTHWESTERLY AND WESTERLY ALONG THE EASTERLY, NORTHEASTERLY AND NORTHERLY BOUNDARIES OF SAID LAST MENTIONED LOT AND FOLLOWING THE SAME ALONG ALL ITS VARIOUS COURSES AND CURVES TO THE NORTHEASTERLY CORNER OF LOT 57 OF TRACT NO. 30319 AS SHOWN ON MAP FILED IN BOOK 757 PAGES 43, 44 AND 45, OF SAID MAPS;
THENCE WESTERLY AND SOUTHERLY ALONG THE NORTHERLY AND WESTERLY LINES OF SAID LAST MENTIONED LOT TO THE NORTHWESTERLY CORNER OF LOT 55 OF SAID LAST MENTIONED TRACT;
THENCE SOUTHERLY ALONG THE WESTERLY BOUNDARY OF SAID LAST MENTIONED TRACT TO THE NORTHEASTERLY CORNER OF TRACT NO. 8575 AS SHOWN ON MAP FILED IN BOOK 117 PAGES 64, 65 AND 66, OF SAID MAPS;
THENCE WESTERLY AND SOUTHERLY ALONG THE NORTHERLY RND WESTERLY BOUNDARIES OF SAID LAST MENTIONED TRACT AND FOLLOWING THE SAME ALONG ALL ITS VARIOUS COURSES TO THE MOST WESTERLY, NORTHWESTERLY CORNER OF SAID LAST MENTIONED TRACT;
THENCE SOUTHERLY ALONG THE WESTERLY BOUNDARY OF SAID LAST MENTIONED TRACT TO ITS INTERSECTION WITH THE NORTHERLY BOUNDARY OF LOT 2 AS SHOWN ON LICENSED SURVEYOR'S MAP RECORDED IN BOOK 27 PAGE 40, OF RECORDS OF SURVEYS, IN SAID OFFICE OF THE REGISTRAR‐RECORDER;
THENCE WESTERLY ALONG SAID LAST MENTIONED NORTHERLY BOUNDARY TO ITS INTERSECTION WITH THE NORTHEASTERLY PROLONGATION OF THE NORTHWESTERLY BOUNDARY OF PARCEL 4 OF PARCEL MAP NO. 6449 PER MAP FILED IN BOOK 69 PAGES 8 TO 10, INCLUSIVE, OF PARCEL MAPS, IN SAID OFFICE OF THE REGISTRAR‐RECORDER;
THENCE SOUTHWESTERLY ALONG SAID LAST MENTIONED NORTHEASTERLY PROLONGATION TO THE NORTHEASTERLY CORNER OF SAID PARCEL 4;
THENCE SOUTHWESTERLY, NORTHWESTERLY AND WESTERLY ALONG THE NORTHWESTERLY, NORTHEASTERLY AND NORTHERLY LINES OF SAID PARCEL 4 TO THE NORTHWESTERLY CORNER OF SAID PARCEL 4;
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
36 THENCE SOUTHERLY ALONG SAID WESTERLY LINE AND ITS SOUTHERLY PROLONGATION, AND ALONG THE CENTERLINE OF THE FIRST LOS ANGELES AQUEDUCT AS SHOWN ON SAID PARCEL MAP NO. 6449 FOLLOWING THE SAME IN ALL ITS VARIOUS COURSES TO THE NORTHERLY LINE OF LOT 62 OF ST. JOHN SUBDIVISION PER MAP RECORDED IN BOOK 196 PAGES 306 TO 309, INCLUSIVE, OF MISCELLANEOUS RECORDS, IN THE OFFICE OF SAID REGISTRAR‐RECORDER;
THENCE EASTERLY ALONG SAID NORTHERLY LINE TO THE WESTERLY BOUNDARY OF THE LAND DESCRIBED IN DEED RECORDED JUNE 9, 1997, AS INSTRUMENT NO. 97‐ 855038 OF OFFICIAL RECORDS, IN THE OFFICE OF SAID REGISTRAR RECORDER;
THENCE SOUTHERLY AND EASTERLY ALONG THE WESTERLY AND SOUTHERLY LINES OF SAID LAND TO THE EASTERLY LINE OF SAID LOT 62;
THENCE SOUTHERLY ALONG SAID EASTERLY LINE TO THE SOUTHERLY LINE OF FRACTIONAL SECTION 25, TOWNSHIP 4 NORTH, RANGE 16 WEST, SAN BERNARDINO MERIDIAN;
THENCE EASTERLY ALONG LAST SAID SOUTHERLY LINE AND THE SOUTHERLY LINE OF SECTION 30, TOWNSHIP 4 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN TO THE WESTERLY BOUNDARY OF THE SECOND LOS ANGELES AQUEDUCT;
THENCE SOUTHERLY ALONG SAID WESTERLY BOUNDARY TO THE NORTHEASTERLY PROLONGATION OF THE SOUTHEASTERLY BOUNDARY OF THE FIRST LOS ANGELES AQUEDUCT WITHIN SECTION 6, TOWNSHIP 3 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN;
THENCE SOUTHWESTERLY ALONG LAST SAID PROLONGATION AND LAST SAID SOUTHEASTERLY BOUNDARY TO THE EAST‐WEST CENTER LINE OF SECTION 6, TOWNSHIP 3 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN;
THENCE EASTERLY ALONG SAID EAST ‐WEST CENTER LINE TO THE WEST QUARTER CORNER OF SECTION 5, TOWNSHIP 3 NORTH, RANGE 15 WEST;
THENCE EASTERLY ALONG THE SOUTHERLY LINE OF THE NORTHWEST QUARTER OF SAID SECTION 5 TO THE SOUTHEAST CORNER THEREOF; THENCE NORTHERLY ALONG THE WESTERLY LINE OF THE SOUTHWEST QUARTER OF THE NORTHEAST QUARTER OF SAID SECTION 5 TO THE SOUTHERLY LINE OF THE NORTH HALF OF THE SOUTHWEST QUARTER OF THE NORTHEAST QUARTER OF SAID SECTION 5;
THENCE EASTERLY ALONG SAID SOUTHERLY LINE TO THE EAST LINE OF THE WEST 15 ACRES OF THE NORTH HALF OF THE SOUTHWEST QUARTER OF THE NORTHEAST QUARTER OF SAID SECTION 5;
THENCE NORTHERLY ALONG SAID EAST LINE TO THE SOUTHERLY LINE OF LOT 2 OF SAID SECTION 5;
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
37 THENCE EASTERLY ALONG SAID SOUTHERLY LINE TO THE SOUTHEAST CORNER OF LOT 2;
THENCE NORTHERLY ALONG THE EASTERLY LINE OF SAID LOT 2 TO THE NORTHERLY LINE OF SAID SECTION 5;
THENCE EASTERLY ALONG SAID NORTHERLY LINE TO THE NORTHWEST CORNER OF SECTION 4, TOWNSHIP 3 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN;
THENCE EASTERLY ALONG THE NORTHERLY LINE OF SAID SECTION 4 TO THE NORTHWEST CORNER OF SECTION 3, TOWNSHIP 3 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN;
THENCE EASTERLY ALONG THE NORTHERLY LINE OF SAID SECTION 3 TO THE NORTHWEST CORNER OF LOT 3 OF SAID SECTION 3;
THENCE SOUTHERLY ALONG THE WESTERLY LINE OF SAID LOT 3 TO THE SOUTHWEST CORNER THEREOF;
THENCE EASTERLY ALONG THE SOUTHERLY LINE OF SAID LOT 3 TO THE WEST LINE OF THE EAST HALF OF THE SOUTHEAST QUARTER OF THE NORTHWEST QUARTER OF SAID SECTION 3;
THENCE SOUTHERLY ALONG SAID WEST LINE TO THE SOUTHERLY LINE OF THE NORTHWEST QUARTER OF SAID SECTION 3;
THENCE EASTERLY ALONG SAID SOUTHERLY LINE TO THE SOUTHEAST CORNER OF THE NORTHWEST QUARTER OF SAID SECTION 3;
THENCE NORTHERLY ALONG THE EASTERLY LINE OF THE NORTHWEST QUARTER OF SAID SECTION 3 A DISTANCE OF 15.00 CHAINS;
THENCE EAST 15.00 CHAINS;
THENCE SOUTH 5.00 CHAINS;
THENCE EAST 10.00 CHAINS;
THENCE SOUTH 5.00 CHAINS;
THENCE EAST 5.00 CHAINS;
THENCE SOUTH 5.00 CHAINS TO THE SOUTHERLY LINE OF THE NORTHEAST QUARTER OF SAID SECTION 3;
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
38 THENCE EASTERLY ALONG SAID SOUTHERLY LINE 10.00 CHAINS MORE OR LESS TO THE SOUTHEAST CORNER OF THE NORTHEAST QUARTER OF SAID SECTION 3;
THENCE SOUTHERLY ALONG THE EASTERLY LINE OF SAID SECTION 3 TO THE SOUTHWEST CORNER OF SECTION 2, TOWNSHIP 3 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN;
THENCE EASTERLY ALONG THE SOUTHERLY LINE OF SAID SECTION 2 TO THE SOUTHWEST CORNER OF THE SOUTHEAST QUARTER OF THE SOUTHWEST QUARTER OF SAID SECTION 2;
THENCE NORTHERLY AND EASTERLY ALONG THE WESTERLY AND NORTHERLY LINES OF THE SOUTHEAST QUARTER OF THE SOUTHWEST QUARTER OF SAID SECTION 2 TO THE NORTHWEST CORNER OF THE SOUTHWEST QUARTER OF THE SOUTHEAST QUARTER OF SAID SECTION 2;
THENCE EASTERLY ALONG THE NORTHERLY LINE OF THE SOUTHWEST QUARTER OF THE SOUTHEAST QUARTER OF SAID SECTION 2 TO THE NORTHWEST CORNER OF THE EAST‐HALF OF THE EAST HALF OF THE SOUTHWEST QUARTER OF THE SOUTHEAST QUARTER OF SAID SECTION 2;
THENCE SOUTHERLY ALONG THE WESTERLY LINE OF THE EAST‐HALF OF THE EAST‐HALF OF THE SOUTHWEST QUARTER OF THE SOUTHEAST QUARTER OF SAID SECTION 2 TO THE SOUTHERLY LINE OF SAID SECTION 2;
THENCE EASTERLY ALONG SAID SOUTHERLY LINE TO THE SOUTHWEST CORNER OF SECTION 1, TOWNSHIP 3 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN;
THENCE NORTHERLY ALONG THE WESTERLY LINE OF SAID SECTION 1 TO THE NORTHWEST CORNER OF THE SOUTHWEST QUARTER OF THE SOUTHWEST QUARTER OF SAID SECTION 1;
THENCE EASTERLY AND SOUTHERLY ALONG THE NORTHERLY AND EASTERLY LINES OF THE SOUTHWEST QUARTER OF THE SOUTHWEST QUARTER OF SAID SECTION 1 TO THE SOUTHERLY LINE OF SAID SECTION 1;
THENCE EASTERLY ALONG SAID SOUTHERLY LINE TO THE SOUTH‐QUARTER CORNER OF SAID SECTION 1;
THENCE NORTHERLY ALONG THE NORTH‐SOUTH CENTER LINE OF SAID SECTION 1 TO THE NORTHWEST CORNER OF LOT 2 OF SAID SECTION 1;
THENCE EASTERLY ALONG THE NORTHERLY LINE OF SAID SECTION 1 TO THE SOUTHWEST CORNER OF SECTION 31, TOWNSHIP 4 NORTH, RANGE 14 WEST, SAN BERNARDINO MERIDIAN;
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
39 THENCE NORTHERLY ALONG THE WESTERLY LINES OF SECTIONS 31, 30 AND 19 OF TOWNSHIP 4 NORTH, RANGE 14 WEST, SAN BERNARDINO MERIDIAN TO THE NORTHWEST CORNER OF SAID SECTION 19;
THENCE EASTERLY ALONG THE NORTHERLY LINE OF SAID SECTION 19 TO THE SOUTHWEST CORNER OF SECTION 17, TOWNSHIP 4 NORTH, RANGE 14 WEST, SAN BERNARDINO MERIDIAN;
THENCE NORTHERLY ALONG THE WESTERLY LINE OF SAID SECTION 17 TO THE WEST QUARTER CORNER THEREOF;
THENCE EASTERLY ALONG THE SOUTHERLY LINE OF THE NORTH‐HALF OF SAID SECTION 17 TO THE EAST‐QUARTER CORNER THEREOF;
THENCE NORTHERLY ALONG THE EASTERLY LINE OF SAID SECTION 17 TO THE SOUTHEAST CORNER OF SECTION 8, TOWNSHIP 4 NORTH, RANGE 14 WEST; SAN BERNARDINO MERIDIAN;
THENCE NORTHERLY ALONG THE EASTERLY LINES OF SECTIONS 8 AND 5 OF TOWNSHIP 4 NORTH, RANGE 14 WEST, SAN BERNARDINO MERIDIAN TO THE NORTHEAST CORNER OF SAID SECTION 5 AND THE SOUTHEAST CORNER OF SECTION 32, TOWNSHIP 5 NORTH, RANGE 14 WEST, SAN BERNARDINO MERIDIAN;
THENCE NORTHERLY ALONG THE EASTERLY LINE OF SAID SECTION 32 TO THE SOUTHEAST CORNER OF SECTION 29, TOWNSHIP 5 NORTH, RANGE 14 WEST, SAN BERNARDINO MERIDIAN;
THENCE NORTHERLY AND WESTERLY ALONG THE EASTERLY AND NORTHERLY LINES OF SAID SECTION 29 TO THE NORTHEAST CORNER OF SECTION 30, TOWNSHIP 5 NORTH, RANGE 14 WEST, SAN BERNARDINO MERIDIAN;
THENCE EASTERLY ALONG THE NORTHERLY LINE OF SAID SECTION 30 TO THE NORTH‐ QUARTER CORNER THEREOF;
THENCE SOUTHERLY ALONG THE NORTH‐SOUTH CENTER LINE OF SAID SECTION 30 TO THE SOUTH‐QUARTER CORNER THEREOF;
THENCE WESTERLY ALONG THE SOUTHERLY LINE OF SAID SECTION 30 TO THE NORTHEAST CORNER OF SECTION 36, TOWNSHIP 5 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN;
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
40 THENCE WESTERLY ALONG THE NORTHERLY LINES SECTION 36, 35 AND 34 OF TOWNSHIP 5 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN TO THE NORTHWEST CORNER OF SAID SECTION 34;
THENCE SOUTHERLY ALONG THE WESTERLY LINE OF SAID SECTION 34 TO THE NORTHWEST CORNER OF SECTION 3, TOWNSHIP 4 NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN;
THENCE SOUTHERLY ALONG WESTERLY LINES OF SECTIONS 3 AND 10 OF TOWNSHIP NORTH, RANGE 15 WEST, SAN BERNARDINO MERIDIAN TO THE POINT OF BEGINNING.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
41 ATTACHMENT B: SUMMARY OF COST ESTIMATES FOR DISTRICT IMPROVEMENTS
LINK –
INTERSECTION
Year 2002 Year 2024
Status Cost Estimates Cost Estimates
E-0100 $5,052,790 Complete
E-0101 $5,450 Complete
E-0102 $7,382,620 Complete
E-0103 $2,931,680 $1,442,347 Not Complete
E-0104 $13,000,140 $712,672 Not Complete
E-105 $585,640 Complete
E-202 $5,545,380 Complete
E-0300 $3,466,560
Improvements no longer
necessary
E-0301 $18,410,020
Improvements no longer
necessary
E-0402 $1,270,380 $3,597,667 Not Complete
E-0501 $2,820,400 $9,065,133 Not Complete
E-0502 $20,117,140 $27,156,811 Not Complete
E-0503 $2,098,490 $954,378 Partially Complete
E-0504 $77,430 $69,027 Partially Complete
E-0505 $290,350 $1,413,451 Partially Complete
E-0506 $32,180 $69,027 Not Complete
E-0507 $58,800 $138,054 Partially Complete
E-0508 $435,590 $1,706,281 Not Complete
E-0600 $85,200 $207,080 Not Complete
E-0601 $58,800 $138,054 Not Complete
E-0602 $28,400 $69,027 Not Complete
E-0603 $71,000 $172,567 Partially Complete
E-0604 $28,400 $69,027 Not Complete
E-0605 $278,730 $1,114,800 Not Complete
E-0606 $53,600 $199,028 Not Complete
E-0607 $28,400 $69,027 Not Complete
E-0608 $307,630 $555,994 Not Complete
E-0609 $16,930 $34,513 Not Complete
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
42 LINK –
INTERSECTION
Year 2002 Year 2024
Status Cost Estimates Cost Estimates
E-0610 $261,170 $493,794 Partially Complete
E-0611 $224,930 $269,676 Not Complete
E-0612 $67,020 $157,495 Not Complete
E-0613 $15,560 $37,106 Not Complete
E-0615 $49,420 $565,021 Not Complete
E-0616 $64,350 $152,418 Not Complete
E-0617 $48,850 $115,421 Not Complete
E-0618 $64,650 $152,986 Not Complete
E-0619 $14,260 $40,022 Not Complete
E-0620 $6,965,810 $11,654,392 Not Complete
E-0620B $532,000 $1,333,500 Not Complete
E-0700 $48,170 $114,125 Partially Complete
E-0701 $162,320 $383,773 Partially Complete
E-0702 $33,140 $78,045 Partially Complete
E-0703 $48,640 $115,016 Partially Complete
E-0704 $47,370 $112,613 Partially Complete
E-0705 $33,519 $78,747 Partially Complete
E-0708 $14,200 $34,513 Not Complete
E-0709 $14,200 $34,513 Not Complete
E-0710 $28,400 $69,027 Partially Complete
E-0711 $468,420 $2,195,249 Partially Complete
E-0712 $487,660 $1,848,546 Partially Complete
E-0713 $3,776,930 $5,451,406 Not Complete
E-0714 $2,148,280 $8,940,716 Not Complete
E-0715 $1,509,850 $3,229,689 Not Complete
E-0715B Now 716B
E-0716 $8,227,460 $23,701,588 Not Complete
E-0716B $0 $1,200,150 Not Complete
E-0717 $2,267,710 $9,098,990 Not Complete
E-0800 $6,950,350
Roadway downgraded.
Improvements no longer
necessary
E-0801 $1,858,810
Roadway downgraded.
Improvements no longer
necessary
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
43 LINK –
INTERSECTION
Year 2002 Year 2024
Status Cost Estimates Cost Estimates
E-0900 $13,120 $24,386 Partially Complete
E-0901 $2,562,900 $597,583 Not Complete
E-0902 $10,148,600 $16,164,187 Not Complete
E-0902B $518,700 $1,300,163 Not Complete
E-1001 $86,070 $294,509 Not Complete
E-1002 $764,750 $2,512,052 Not Complete
E-1002B $4,256,000 $10,668,000 Not Complete
E-1003 $15,634,550 $2,532,188 Not Complete
E-1003B $124,490 $312,039 Not Complete
E-1004 $174,750 $481,977 Not Complete
E-1005 $1,081,540 $1,960,234 Not Complete
E-1006 $9,906,520 $17,565,843 Not Complete
E-1200 $7,843,200 Complete
E-1200B $11,970,000 Complete
E-1201 Replaced by E-1500
E-1202 $215,640 $775,636 Not Complete
E-1203 $1,217,646 Not Complete
E-1204 $0 Complete
E-1300 $345,200 Complete
E-1400 $0 Complete
E-1400B $0 Complete
E-1500 $3,202,500 Not Complete
E-1500B $22,932,656 Not Complete
E-1501 $2,008,125 Not Complete
E-1601 $0 Complete
E-1602 $0 Complete
LINKS SUBTOTAL $186,617,609 $205,162,224
EI-5 $1,215,500 Complete
EI-9 $624,170 $632,625 Partially Complete
EI-19 $771,150 Complete
EI-21 $180,600 Complete
EI-29 $709,500 $1,437,514 Not Complete
EI-31 $154,800 $449,923 Not Complete
EI-33 $180,600 $594,541 Not Complete
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
44 LINK –
INTERSECTION
Year 2002 Year 2024
Status Cost Estimates Cost Estimates
EI-38 $154,500 Complete
EI-39 $154,500 $449,923 Not Complete
EI-41 $923,640 $0 Not Complete
EI-42 $154,500 $449,923 Not Complete
EI-46 $224,980 Complete
EI-49 $154,500 $129,961 Partially Complete
EI-50 $154,500 $0 Complete
EI-53 $180,600 Complete
EI-54 $154,800 $0 Not Complete
EI-55 $363,596 Not Complete
EI-56 $1,240,393 Not Complete
EI-57 $2,024,400 Not Complete
INTERSECTION
SUBTOTAL $6,802,340 $9,210,313
TOTAL $193,419,949 $228,897,247 115%
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
45 ATTACHMENT C: DEVELOPMENT ANALYSIS
Table 6: Development Analysis of Filed Maps
Single Family Condos/Town
houses Multi Family Commercial /Business
Park Industrial
Total
FDUs Map
Number Jurisdiction Map Status Units
FDUs
@ Units
FDUs
@ Units FDUs @ SF Acres
FDUs
@ SF Acres FDUs @
1 0.8 0.7 5.00 3
PM 54043 City of Santa Clarita Approved 4 4 0 0 0 0 0 0.00 0.00 0 0.00 0 4.0 PM 60821 City of Santa Clarita Recorded‐Fees Deferred 3 3 0 0 0 0 0 0.00 0.00 0 0.00 0 3.0 PM 68740 City of Santa Clarita Recorded 4 4 0 0 0 0 0 0.00 0.00 0 0.00 0 4.0 PM068498 City of Santa Clarita Recorded 0 0 0 0 0 0 63,960 8.23 41.15 0 0.00 0 41.2 PM65239 City of Santa Clarita Approved 2 2 0 0 0 0 0 0.00 0.00 0 0.00 0 2.0 TR 53074 City of Santa Clarita Approved 119 119 0 0 461 323 0.0 10.60 53.00 0 0.00 0 494.7 TR 63003 City of Santa Clarita Approved 18 18 0 0 0 0 0.00 0.00 0 0.00 0 18.0 TR 65159 City of Santa Clarita Pending 48 48 0 0 0 0 0 0.00 0.00 0 0.00 0 48.0 TTM 63022 City of Santa Clarita Pending 354 354 0 0 0 0 0 0.00 0.00 0 0.00 0 354.0 TTM 67374 City of Santa Clarita Recorded 9 9 0 0 0 0 0 0.00 0.00 0 0.00 0 9.0 TTM 68601 City of Santa Clarita Approved 35 35 0 0 0 0 0 0.00 0.00 0 0.00 0 35.0 Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
46 Single Family Condos/Town
houses Multi Family Commercial /Business
Park Industrial
Total
FDUs Map
Number Jurisdiction Map Status Units
FDUs
@ Units
FDUs
@ Units FDUs @ SF Acres
FDUs
@ SF Acres FDUs @
1 0.8 0.7 5.00 3
VTTM69164 City of Santa Clarita Recorded 0 0 0 0 375 263 20.00 100.00 0 0.00 0 362.5 VTTM 75026 City of Santa Clarita Pending 0 0 300 240 0 0 63.00 315.00 0 0.00 0 555.0 VTPM 78248 City of Santa Clarita Denied 0 0 0 0 0 0 0 41.00 205.00 0 0.00 0 0.0 PM 74160 City of Santa Clarita Recorded 4 4 0 0 0 0 0 0.00 0.00 0 0.00 0 4.0 TPM 80287 City of Santa Clarita Pending 4 4 0 0 0 0 0 0.00 0.00 0 0.00 0 4.0 TTM 82375 City of Santa Clarita Pending 0 0 0 0 20 14 0 0.00 0.00 0 0.00 0 14.0 Soledad and
Lost Canyon
Gas/
Commercial City of Santa Clarita Approved 0 0 0 0 0 0 7,100 0.43 2.2 0 0.00 0 2.2 Chandler
Apartments City of Santa Clarita Approved 0 0 0 0 136 95 0 0.00 0.00 0 0.00 0 95.2 TTM 61924 City of Santa Clarita Recorded 0 0 0 0 164 114.8 0 0.00 0.00 0 0.00 0 114.8 TTM 83087 City of Santa Clarita Recorded 0 0 150 120 348 244 0 0.00 0.00 0 0.00 0 363.6 TR060922 City of Santa Clarita
Recorded ‐B&T
Obligation Met 403 403 0 0 0 0 0 0.00 0.00 0 0.00 0 0.0 Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
47 Single Family Condos/Town
houses Multi Family Commercial /Business
Park Industrial
Total
FDUs Map
Number Jurisdiction Map Status Units
FDUs
@ Units
FDUs
@ Units FDUs @ SF Acres
FDUs
@ SF Acres FDUs @
1 0.8 0.7 5.00 3
18171
Soledad
Canyon Gas
Station
City of Santa Clarita Approved
2,493 0.46 2.30 2.3
TTM 68203 City of Santa Clarita Pending
73 58.4 9.20 46.00 104.4
Valley
Center
Skilled
Nursing
City of Santa Clarita Approved
51,000 3.81 19.05 19.1
City
Subtotal
1,007
1,007
523
418
1,504 1,053
124,553
157
784 0
0 0
3,261.9
TR060259 County Approved 492 492 0 0 0 0 0 0.00 0.00 0 0.00 0 492.0 TR060359 County Approved 34 34 0 0 0 0 0 0.00 0.00 0 0.00 0 34.0 TR064989 County Approved 24 24 0 0 0 0 0 0.00 0.00 0 0.00 0 24.0 TR066202 County Approved 0 0 31 24.8 0 0 0 0.00 0.00 0 0.00 0 24.8 TR067233 County Pending 51 51 0 0 0 0 0 0.00 0.00 0 0.00 0 51.0 TR071216 County Approved 0 0 0 0 0 0 27.68 138.40 0 0.00 0 138.4 TR45123 County Approved 10 10 0 0 0 0 0 0.00 0.00 0 0.00 0 10.0 TR47573 County Approved 75 75 0 0 0 0 0 0.00 0.00 0 0.00 0 75.0 TR48086 County Approved 492 492 0 0 0 0 0 0.00 0.00 0 0.00 0 492.0 PM 83283 County Pending 4 4 0 0 0 0 0.00 0.00 0 0.00 0 4.0 County
Subtotal 1182 1178 31 25 0 0 0 28 138 0 0 0
1,345.2
TOTAL BY
USE
2,189
2,185
554
443.2
1,504 1,052.8
124,553
184.4
922.1
156,06
0 2.3 6.9
4,607.
1 Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
48 Table 7: Development Analysis of Vacant Land by Assessor Parcel Number
Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 2802003003 UR1 14.86 City 2 29.7 1 29.7
2802003004 UR1 4.97 City 2 9.9 1 9.9
2802004010 UR1 2.66 City 2 5.3 1 5.3
2802004090 UR1 0.90 City 2 1.8 1 1.8
2803032001 Site 9 MX‐C 1.59 City 5 25.3
2803032026 Site 9 MX‐C 0.90 City
2803032034 Site 9 MX‐C 0.83 City
2803032035 Site 9 MX‐C 1.09 City 75.0 0.7 52.5 2803032042 Site 9 MX‐C 0.22 City
2803032043 Site 9 MX‐C 0.42 City
2836013106‐
Com MX‐N 4.93 City 5 24.6
2836013106‐Res MX‐N 4.93 City 6.0 29.6 0.7 20.7 2836013107
Com MX‐N 9.90 City 5 49.5
2836013107 Res MX‐N 9.90 City 6 59.4 0.7 41.6 2836013117 UR2 5.27 City 5 26.4 1 26.4
2836013121 UR2 13.89 City 5 69.4 1 69.4
2836013128 ‐
Com MX‐N 2.75 City 5 13.8
2836013128 ‐
Res MX‐N 2.75 City 6.0 16.5 0.7 11.6
2836013135 Site 4 UR5 35.07 City 850.0 0.7 595.0 Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
49 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 2836013911 Site 4 UR5 1.01 City
2836013912 Site 4 UR5 0.42 City
2836013919 Site 4 UR5 22.29 City
2836014056 Site 3 UR5 9.25 City
Now VTTM
75062
2836014057 Site 3 UR5 30.63 City
Now VTTM
75063
2836014058 UR5 22.78 City 25 569.5 0.7 398.6
2836020058 ‐
Com MX‐N 0.30 City 5 1.5
2836020058 ‐
Res MX‐N 0.30 City 6.0 1.8 0.7 1.3
2836020077 UR2 0.01 City 5 0.0 1 0.0
2836020078‐
Com MX‐N 0.18 City 5 0.9
2836020078‐Res MX‐N 0.18 City 6.0 1.1 0.7 0.8 2836020084 UR2 0.34 City 5 1.7 1 1.7
2836020085 UR2 0.26 City 5 1.3 1 1.3
2836020086‐
Com MX‐N 0.43 City 5 2.2
2836020086‐Res MX‐N 0.43 City 6.0 2.6 0.7 1.8 2836020087‐
Com MX‐N 0.30 City 5 1.5
2836020087‐Res MX‐N 0.30 City 6.0 1.8 0.7 1.3 2836020270 UR2 0.53 City 5 2.7 1 2.7
2836020279 UR2 0.10 City 5 0.5 1 0.5
2836020281 UR2 0.19 City 5 0.9 1 0.9
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
50 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 2839001020 NU4 13.03 City 0.5 6.5 1 6.5
2839002033 NU4 3.17 City 0.5 1.6 1 1.6
2839020001 Site 5 UR5 0.34 City 0.0
2839020002 Site 5 UR5 0.37 City 0.0
2839020003 Site 5 UR5 0.71 City 0.0
2839020004 Site 5 UR5 0.62 City 0.0
2839020005 Site 5 UR5 0.72 City 0.0
2839020006 Site 5 UR5 0.61 City 0.0
2839020007 Site 5 UR5 0.22 City 0.0
2839020008 Site 5 UR5 0.85 City 0.0
2839020009 Site 5 UR5 0.34 City 0.0
2839020010 Site 5 UR5 0.50 City 0.0
2839020011 Site 5 UR5 0.83 City 0.0
2839020012 Site 5 UR5 0.79 City 0.0
2839021006 Site 5 UR5 3.41 City 0.0
2839021007 Site 5 UR5 3.02 City 0.0
2839021008 Site 5 UR5 2.66 City 0.0
2839021009 Site 5 UR5 2.37 City 0.0
2839021010 Site 5 UR5 1.84 City 0.0
2839021016 Site 5 UR5 1.37 City 0.0
2839021017 Site 5 UR5 0.17 City 0.0
2839021018 Site 5 UR5 1.99 City 200.0 0.7 140.0 2840001106 UR1 18.09 City 2 36.2 1 36.2
2840001902 NU2 0.92 City 0.1 0.1 1 0.1
2840003027 UR5 1.34 City 25 33.6 0.7 23.5
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
51 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 2840003900 UR5 0.79 City 25 19.8 0.7 13.9
2840003901 UR5 1.09 City 25.0 27.2 0.7 19.0
2840003902 UR5 3.33 City 25 83.2 0.7 58.2
2840004010 BP 3.90 City 3 11.7
2840004039 BP 0.30 City 3 0.9
2840004040 BP 0.26 City 3 0.8
2840006019 UR1 8.00 City 2.0 16.0 1 16.0
2840007019 CC 0.04 City 5 0.2
2840015025 UR1 6.56 City 2 13.1 1 13.1
2840016002 NU5 19.83 City 1 19.8 1 19.8
2842004023 UR2 12.40 City 5 62.0 1 62.0
2842004024 UR2 68.64 City 5 343.2 1 343.2
2842004030 UR2 0.43 City 5 2.2 1 2.2
2842004031 UR2 3.30 City 5 16.5 1 16.5
2842004032 UR2 4.10 City 5 20.5 1 20.5
2842033009 UR2 0.46 City 5 2.3 1 2.3
2842033010 UR2 0.18 City 5 0.9 1 0.9
2842033011 UR2 0.46 City 5 2.3 1 2.3
2842033017 UR2 0.20 City 5 1.0 1 1.0
2842033018 UR2 0.10 City 5 0.5 1 0.5
2842033019 UR2 0.36 City 5 1.8 1 1.8
2842036064 CC 1.29 City 5 6.4
2844001024 Site 11 MX‐C 0.29 City 0.0
2844001025 Site 11 MX‐C 0.29 City 0.0
2844001032 Site 11 MX‐C 0.19 City 0.0
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
52 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 2844001033 Site 11 MX‐C 0.33 City 0.0
2844001038 Site 11 MX‐C 0.73 City 0.0
2844001046 Site 11 MX‐C 0.39 City 0.0
2844001056 Site 11 MX‐C 1.09 City 0.0
2844001063 Site 11 MX‐C 2.52 City 0.0
2844001068 Site 11 MX‐C 1.64 City 0.0
2844001072 Site 11 MX‐C 1.03 City 0.0
2844001804 Site 11 MX‐C 1.52 City 0.0
2844003904 Site 11 MX‐C 3.62 City 0.0
2844003004 Site 11 MX‐C 0.40 City 0.0
2844003005 Site 11 MX‐C 0.37 City 0.0
2844003006 Site 11 MX‐C 0.63 City 0.0
2844003009 Site 11 MX‐C 0.53 City 0.0
2844003902 Site 11 MX‐C 2.16 City 0.0
2844005016 Site 11 MX‐C 0.60 City 0.0
2844005907 Site 11 MX‐C 2.39 City 5 108.1
2844005028 Site 11 MX‐C 0.89 City 275.0 0.7 192.5 2844016009 CC 1.11 City 5 5.6
2844016012 CC 1.86 City 5 9.3
2844022014 UR5 0.10 City 25 2.6 0.7 1.8
2844042002 UR5 0.84 City 25 21.0 0.7 14.7
2848005044 NU5 25.69 City 1 25.7 1 25.7
2848005075 NU1 28.71 City 0.05 1.4 1 1.4
2848005076 NU1 27.15 City 0.05 1.4 1 1.4
2848008001 NU4 39.39 City 0.5 19.7 1 19.7
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
53 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 2848008018 NU4 39.86 City 0.5 19.9 1 19.9
2848008024 NU4 39.10 City 0.5 19.5 1 19.5
2848008025 NU4 38.93 City 0.5 19.5 1 19.5
2848030008 NU4 10.35 City 0.5 5.2 1 5.2
2848030014 NU4 8.60 City 0.5 4.3 1 4.3
2848030015 NU4 5.33 City 0.5 2.7 1 2.7
2848031003 NU4 9.31 City 0.5 4.7 1 4.7
2848031004 NU4 18.54 City 0.5 9.3 1 9.3
2854001001 CC 0.18 City 5 0.9
2854001002 CC 0.21 City 5 1.0
2854001003 CC 0.06 City 5 0.3
2854001004 CC 0.07 City 5 0.3
2854001005 CC 3.04 City 5 15.2
2854001031 CC 2.13 City 5 10.6
2854001071 CC 0.71 City 5 3.5
2864003919 BP 1.89 City 3 5.7
SF Sub 829.3
Condo Sub
Apt Sub 2269.7 1588.8
Com AC Sub 51.8 280.8
Ind AC Sub 6.3 19.0
City Subtotal 3099.0 2717.9
2812001006 A‐2‐1 41.11 County 0.2 8.2 1 8.2
2812001007 A‐2‐1 4.71 County 0.2 1.0 1 1.0
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
54 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 2812001008 A‐2‐1 20.41 County 0.2 4.1 1 4.1
2812001009 A‐2‐1 6.61 County 0.2 1.3 1 1.3
2812001010 A‐2‐1 10.04 County 0.2 2.0 1 2.0
2812001012 A‐2‐1 5.73 County 0.2 1.1 1 1.1
2812001013 A‐2‐1 14.50 County 0.2 2.9 1 2.9
2813015001 A‐1‐1 40.59 County 0.2 8.1 1 8.1
2813015007 A‐1‐1 44.30 County 0.2 8.9 1 8.9
2813015008 A‐1‐1 129.01 County 0.2 25.8 1 25.8 2813015009 A‐1‐1 21.70 County 0.2 4.3 1 4.3
2813015010 A‐1‐1 143.63 County 0.2 28.7 1 28.7 2813016011 A‐1‐1 102.72 County 0.2 20.5 1 20.5 2813017017 A‐1‐1 35.50 County 0.1 3.6 1 3.6
2813017028 A‐1‐1 2.49 County 0.5 1.2 1 1.2
2813017030 A‐1‐1 2.10 County 1.0 1 1.0
2813017031 A‐1‐1 3.12 County 1.0 1 1.0
2813017032 A‐1‐1 7.49 County 1.0 1 1.0
2813017033 A‐1‐1 1.27 County 1.0 1 1.0
2813017039 A‐1‐1 1.23 County 1.0 1 1.0
2813017042 A‐1‐1 0.21 County 1.0 1 1.0
2813017043 A‐1‐1 4.39 County 1.0 1 1.0
2813017044 A‐1‐1 3.07 County 1.0 1 1.0
2813017045 A‐1‐1 5.57 County 1.0 1 1.0
2813017046 A‐1‐1 0.63 County 0.0 1 0.0
2813017047 A‐1‐1 2.49 County 1.0 1 1.0
2813018006 C‐3 0.11 County 5 0.5
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
55 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 2813018007 C‐3 0.17 County 5 0.9
2813021015 A‐1‐1 0.00 County 0.5 0.0 1
Now PM
83283
2813024002 A‐1‐1 39.66 County 0.5 19.8 1 19.8 2813024004 M1 4.22 County 3 12.7
2839005027 A‐2‐1 9.10 County 0.2 1.8 1 1.8
2853001006
IL (Light
Ind) 3.84 County 3 11.5
2853002007
IL (Light
Ind) 0.58 County 3 1.7
2853008003 R‐1‐11000 32.31 County 2.6 84.0 1 84.0 2854004003 R‐1‐9000 0.36 County 2 1.0 1 1.0
2854004004 R‐1‐9000 18.35 County 2 36.7 1 36.7 2854004005 R‐1‐9000 0.28 County 2 1.0 1 1.0
2854004008 R‐1‐9000 1.80 County 2 3.6 1 3.6
2854004009 R‐1‐10000 3.92 County 2 7.8 1 7.8
2854004016 R‐1‐11000 22.91 County 2 45.8 1 45.8 2854004019 R‐1‐10000 5.02 County 2 10.0 1 10.0 2854061001 A‐1‐1 11.25 County 2 22.5 1 22.5
2854061002 A‐1‐1 9.02 County 2 18.0 1 18.0
3210014022 A‐2‐1 0.09 County 1 1
3210014024 A‐2‐1 2.50 County 1 1
3210014033 A‐2‐1 74.79 County 1 1
3210015026 M‐1.5 27.04 County 3 81.1
3210015027 M‐1.5 5.15 County 3 15.5
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
56 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 3210016005 IO 3.50 County 3 10.5
3210016017 M‐1.5 0.50 County 3 1.5
3210017059 IO 6.29 County 3 18.9
3211008036 A‐2‐1 20.21 County 0.1 2.0 1 2.0
3211008037 A‐2‐1 9.41 County 0.1 1.0 1 1.0
3211008038 A‐2‐1 7.93 County 0.1 1.0 1 1.0
3211008039 A‐2‐1 20.49 County 0.1 2.0 1 2.0
3211008040 A‐2‐1 5.32 County 0.1 1.0 1 1.0
3211008041 A‐2‐1 15.60 County 0.1 1.6 1 1.6
3211008042 A‐2‐1 33.84 County 0.1 3.4 1 3.4
3211008043 A‐2‐1 78.90 County 0.1 7.9 1 7.9
3231001012 A‐1‐1 20.36 County 0.1 2.0 1 2.0
3231001013 A‐1‐1 19.91 County 0.1 2.0 1 2.0
3231002004 A‐1‐1 19.98 County 0.1 2.0 1 2.0
3231002013 A‐1‐1 17.94 County 1.0 17.9 1 17.9 3231006008 A‐1‐10000 1.12 County 1.0 1.1 1 1.1 3231006011 A‐1‐10000 4.07 County 1.0 4.1 1 4.1 3231007006 C‐3 0.43 County 5 2.1
3231007020 C‐3 0.65 County 5 3.2
3231007021 C‐3 0.84 County 5 4.2
3231007036 C‐3 0.23 County 5 1.2
3231007037 C‐3 0.76 County 5 3.8
3231007061 A‐1‐10000 0.27 County 1 0.0
3231007065 CG 0.51 County 5 2.6
3231007066 C‐3 1.70 County 5 8.5
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
57 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs 3231008028 A‐1‐10000 0.89 County 1 1.0
3231008030 A‐1‐10000 1.37 County 1 1.0
3231008032 A‐1‐10000 1.97 County 1 1.0
3231008033 CG 2.22 County 5 11.1
3231008034 CG 1.84 County 5 9.2
3231009012 C‐3 1.68 County 5 8.4
3231019003 A‐1‐10000 0.01 County 1 0.0
3231019004 A‐1‐10000 0.13 County 1 1.0
3231019021 A‐1‐10000 0.01 County 1 1.0
3231019022 A‐1‐10000 0.19 County 1 1.0
3231019024 A‐1‐10000 0.11 County 1 0.0
3231020015 A‐1‐10000 0.17 County 1 1.0
3231020016 A‐1‐10000 2.06 County 4 8.3 1 8.3
3231021002 A‐1‐10000 0.30 County 1 1.0
3231021004 A‐1‐10000 0.29 County 1 1.0
3231021013 A‐1‐10000 1.28 County 4 5.1 1 5.1
3231021019 A‐1‐10000 0.27 County 1 1.0
3231023004 R‐3 0.12 County 1 1.0
3231023009 R‐3 0.11 County 1 1.0
3231025012 R‐3 0.17 County 1 1.0
3231025015 R‐3 0.24 County 1 1.0
County single
family 460.5 460.5
Commercial AC 11.14 55.7
Ind AC 51.13 153.4
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
58 Assessor Parcel
No.
Housing
Element
Site
Number
ZONE
CODE Area (AC) Jurisdiction DU/AC Units Factor FDUs County Subtotal 669.5
TOTAL
3,387.48
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
59 Table 8: Summary of Development Analysis
LAND USE DEVELOPMENT UNITS MULTIPLIER FDUs % OF TOTAL UNITS FILED MAPS COUNTY VACANT LAND CITY VACANT LAND TOTAL Single Family 2,189.0 460.5 829.3 3,478.8 1.0 3,478.8 53.0% Condominium 554.0 0.0 554.0 0.8 443.2 6.8%
Apartment 1,504.0 0.0 2,269.7 3,773.7 0.7 2,641.6 40.2% Total Residential 4,247.0 460.5 3,099.0 7,806.5 ‐ 6,563.6 100.0% LAND USE AREA (ACRES) MULTIPLIER FDUs % OF TOTAL
FILED MAPS COUNTY VACANT LAND CITY VACANT LAND TOTAL Commercial 184.4 11.1 51.8 247.4 5.0 1,236.7 87.8% Industrial 0 51.1 6.3 57.5 3.0 172.4 12.2%
Total Non‐Residential 184.4 62.3 58.2 304.8 ‐ 1,409.1 100.0%
TOTAL
7,972.7
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
60 ATTACHMENT D: COUNTY AND CITY CODES PERTAINING TO B&T DISTRICTS
COUNTY CODE: TITLE 58 Chapter 21.23 §32.32.200
21.32.200 MAJOR THOROUGHFARE AND BRIDGE FEES.
A. A subdivider, as a condition of approval of a final map for property within an area of benefit, or a building permit applicant, as a condition of issuance of a building permit for property within an area of benefit, shall pay a fee as hereinafter established to defray the cost of constructing bridges over waterways, railways, freeways and canyons, and/or constructing major thoroughfares.
B. Definitions.
1. Area of benefit means a specified area wherein it has been determined that the real property located herein will benefit from the construction of a bridge and/or major thoroughfare.
2. Bridge facility means any crossing for a highway or local road, involving a railway, freeway, stream or canyon, which is required by the General Plan in order to accommodate new urban development within the area of benefit.
3. Construction means and includes preliminary studies, design, acquisition of right‐ of‐way, administration of construction contracts, and actual construction.
4. Major thoroughfare means those roads designated in the transportation element of the General Plan, the primary purpose of which is to carry through traffic and provide a network connection to the state highway system.
5. The singular number includes the plural, and the plural the singular.
C. The provisions herein for payment of a fee shall apply only if the bridge and/or major thoroughfare has been included in an element of the General Plan adopted by the Board of Supervisors at least 30 days prior to the filing of a map or application for a building permit on land located within the boundaries of the area of benefit.
D. Payment of fees shall not be required unless any major thoroughfares are in addition to, or a widening or reconstruction of, any existing major thoroughfares serving the area at the time of the adoption of the boundaries of the area of benefit.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
61 E. Payment of Fees shall not be required unless any planned bridge facility is a new bridge serving the area or an addition to an existing bridge facility serving the area at the time of the adoption of the boundaries of the area of benefit.
F.
1. Action to establish
an area of benefit may be initiated by the Board of Supervisors upon its own motion or upon the recommendation of the Road Commissioner.
2. The Board of Supervisors will set a public hearing for each proposed area of benefit.
Notice of the time and place of said hearing, including preliminary information related to the boundaries of the area of benefit, estimated costs and the method of fee apportionment shall be given pursuant to Section 65905 of the Government Code.
G.
1. At the public hearing, the Board of Supervisors will consider the testimony, written protests and other evidence. At the conclusion of the public hearing, the Board of Supervisors may, unless a majority written protest is filed and not withdrawn, determine to establish an area of benefit. If established, the Board of Supervisors shall adopt a resolution describing the boundaries of the area of benefit, setting forth the cost, whether actual or estimated, and the method of fee apportionment. A certified copy of such resolution shall be recorded with the County Recorder.
2. Such apportioned fees shall be applicable to all property within the area of benefit, and shall be payable as a condition of approval of a final map or as a condition of issuing a building permit for such property or portions thereof. Where the area of benefit includes lands not subject to the payment of fees pursuant to this section, the Board of Supervisors shall make provisions for payment of the share of improvement cost apportioned to such lands not subject to the payment of fees pursuant to this section, the Board of Supervisors shall make provisions for payment of the share of improvement cost apportioned to such lands from other sources.
3. Written protest will be received by the Clerk of the Board of Supervisors at any time prior to the close of the public hearing. If written protests are filed by the owners of more than one‐half of the area of the property to be benefited by the improvement and sufficient protests are not withdrawn to as to reduce the area represented by the protests to less than one‐half of the area to be benefited, then the proposed proceedings shall be abandoned and the Board of Supervisors shall not, for one year from the filing of said written protests, commence or carry on any proceedings for the same improvement under the provisions of this section.
Any protest may be withdrawn by the owner making the same, in writing, at any time prior to the close of the public hearing.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
62 4. If any majority protest is directed against only a portion of the improvement, then all further proceedings under the provisions of this section to construct that portion of the improvement so protested against shall be barred for a period of one year, but the Board of Supervisors shall not be barred from commencing new proceedings not including any part of the improvement so protested against. Such proceedings shall be commenced by a new notice and public hearing as set forth in Subsection F above.
5. Nothing in this section shall prohibit the Board of Supervisors, within such one‐year period, from commencing and carrying on new proceedings for the construction of an improvement or portion of the improvement so protested against if it finds, by the affirmative vote of four‐fifths of its members, that the owners of more than one‐half of the area of the property to be benefited are in favor of going forward with such improvement or portion thereof.
H. Fees paid pursuant to this section shall be deposited in a planned bridge facility and/or major thoroughfare fund. A fund shall be established for each planned bridge facility project and/or each planned major thoroughfare project. If the benefit area is one in which more than one bridge and/or major thoroughfare is required to be constructed, a separate fund may be established covering all of the bridge projects and/or major thoroughfares in the benefit area. Moneys in such fund shall be expended solely for the construction or reimbursement for construction of the improvement serving the area to be benefited and from which the fees comprising the fund were collected, or to reimburse the County for the costs of constructing the improvement.
I. The Board of Supervisors may approve the acceptance of considerations in lieu of the payment of fees established herein.
J. The Board of Supervisors may approve the advancement of money from the General Fund or Road Fund to pay the costs of constructing the improvements covered herein and may reimburse the General Fund or Road Fund for such advances from planned bridge facility and/or major thoroughfare funds established pursuant to this section.
K. If a subdivider, as a condition of approval of a subdivision, is required or desires to construct a bridge and/or major thoroughfare, the Board of Supervisors may enter into a reimbursement agreement with the subdivider. Such agreement may provide for payments to the subdivider from the bridge facility and/or major thoroughfare fund covering that specific project to reimburse the subdivider for costs not allocated to the subdivider's property in the resolution establishing the area of benefit. If the bridge and/or major thoroughfare fund covers more than one project, reimbursements shall be made on a pro‐rata basis, reflecting the actual or estimated costs of the projects covered by the fund. (Ord. 82‐0240
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
63 Sec. 1, 1982; Ord. 82‐0050 Sec. 1, 1982)
22.48.235. MAJOR BRIDGE AND THOROUGHFARE FEES. Except as otherwise provided in Section 22.48.280, a building or structure shall not be used on any lot or parcel of land, any portion of which is located within a Bridge or Major Thoroughfare District established pursuant to Section 21.32.200, unless the required district fee has been paid as a condition of issuing a building permit.
(Ord. 85‐0168, Sec. 33)
22.48280 EXEMPTIONS – EXISTING BUILDINGS AND STRUCTURES. This Part 4 does not apply to the use, alteration, or enlargement of an existing building or structure or the erection of one or more buildings or structures accessory thereto, or both, on the same lot or parcel of land, if the total value of such alteration, enlargement, or construction does not exceed one half of the current market value of all existing buildings or structures on such lot or parcel of land.
(Ord. 1494 Ch. 4 Art. 4 & 497.1927.)
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
64 CITY CODE: 17.51.010 MAJOR BRIDGE AND THOROUGHFARE FEES
1. A subdivider, as a condition of approval of a final map for property within an area of benefit, or a building permit applicant, as a condition of issuance of a building permit for property within an area of benefit, shall pay a fee as hereinafter established to defray the costs of constructing bridges over waterways, railways, freeways, and canyons, and/or constructing major thoroughfares.
2. The provisions herein for payment of a fee shall apply only if the bridge and/or major thoroughfare has been included in an element of the General Plan adopted by the Council at least thirty (30) days prior to the filing of a map or application for a building permit on land located within the boundaries of the area of benefit.
3. Payment of fees shall not be required unless any major thoroughfares are in addition to or a widening or reconstruction of any existing major thoroughfares serving the area at the time of the adoption of the boundaries of the area of benefit.
4. Payment of fees shall not be required unless any planned bridge facility is a new bridge serving the area or an addition to an existing bridge facility serving the area at the time of the adoption of the boundaries of the area of benefit.
5. Establishing a New Area of Benefit.
a. Action to establish an area of benefit may be initiated by the Council upon its own motion or upon the recommendation of the City Engineer. b. The Council will set a public hearing for each proposed area benefited. Notice of the time and place of said hearing, including preliminary information related to the boundaries of the area of benefit, estimated costs and the method of fee apportionment, shall be given pursuant to Section 65905 of the Government Code.
6. Process for a New Area of Benefit.
a. At the public hearing, the Council will consider the testimony, written protests and other evidence. At the conclusion of the public hearing, the Council may, unless a majority written protest is filed and not withdrawn, determine to establish an area of benefit. If established, the Council shall adopt a resolution describing the boundaries of the area of benefit, setting forth the cost, whether actual or estimated, and the method of fee apportionment. A certified copy of such resolution shall be recorded with the County Recorder.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
65 b. Such apportioned fees shall be applicable to all property within the area of benefit, and shall be payable as a condition of approval of a final map or as a condition of issuing a building permit for such property or portions thereof. Where the area of benefit includes lands not subject to the payment of fees pursuant to this section, the Council shall make provision for payment of the share of improvement cost apportioned to such lands from other sources.
c. Any written protest will be received by the City Clerk at any time prior to the close of the public hearing. If written protests are filed by the owners of more than one‐half (1/2) of the area of the property to be benefited by the improvement, and sufficient protests are not withdrawn so as to reduce the area represented by the protests to less than one‐half (1/2) of the area to be benefited, then the proposed proceedings shall be abandoned and the Council shall not, for one (1) year from the filing of said written protests, commence or carry on any proceedings for the same improvement under the provisions of this section. Any protest may be withdrawn by the owner making the same, in writing, at any time prior to the close of the public hearing. d. If any majority protest is directed against only a portion of the improvement, then all further proceedings under the provisions of this section to construct that portion of the improvement so protested against shall be barred for a period of one (1) year, but the Council shall not be barred from commencing new proceedings not including any part of the improvement so protested against. Such proceedings shall be commenced by a new notice and public hearing as set forth in subsection (D)(5) of this section.
e. Nothing in this section shall prohibit the Council, which in such one (1) year period, from commencing and carrying on new proceedings for the construction of an improvement or portion of the improvement so protested against if it finds, by the affirmative vote of four‐fifths (4/5) of its members, that the owners of more than one‐ half (1/2) of the area of the property to be benefited are in favor of going forward with such improvements or portion thereof.
7. Fees paid pursuant to this section shall be deposited in a planned bridge facility and/or major thoroughfare fund. A fund shall be established for each planned bridge facility project and/or each planned major thoroughfare project. If the benefit area is one in which more than one (1) bridge and/or major thoroughfare is required to be constructed, a separate fund may be established covering all of the bridge projects and/or major thoroughfares in the benefit area. Moneys in such fund shall be expended solely for the construction or reimbursement for construction of the improvement serving the area to be benefited and from which the fees comprising the fund were collected, or to reimburse the City for the costs of constructing the improvement.
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
66 8. The Council may approve the acceptance of considerations in lieu of the payment of fees established herein.
9. The Council may approve the advancement of money from the general fund or road fund to pay the costs of constructing the improvements covered herein and may reimburse the general fund or road fund for such advances from planned bridge facility and/or major thoroughfare funds established pursuant to this section.
10. If a subdivider, as a condition of approval of a subdivision, is required or desires to construct a bridge and/or major thoroughfare, the Council may enter into a reimbursement agreement with the subdivider. Such agreement may provide for payments to the subdivider from the bridge facility and/or major thoroughfare fund covering that specific project to reimburse the subdivider for costs not allocated to the subdivider’s property in the resolution establishing the area of benefit. If the bridge and/or major thoroughfare funds cover more than one (1) project, reimbursements shall be made on a pro rata basis, reflecting the actual or estimated costs of the projects covered by the fund.
11. Except as otherwise provided in this document, a building or structure shall not be used on any lot or parcel of land, any portion of which is located within a major bridge or thoroughfare district established by the City, unless the required district fee has been paid as a condition of issuing a building permit.
12. This fee does not apply to the use, alteration or enlargement of an existing building or structure or the erection of one (1) or more buildings or structures accessory thereto, or both, on the same lot or parcel of land, if the total value of such alteration, enlargement or construction does not exceed one‐half (1/2) of the current market value of existing buildings or structures on such lot or parcel of land.
ZONING CODE
City of Santa Clarita, California
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
67 ATTACHMENT E: REGIONAL IMPROVEMENTS
Interchange
# Location
Description of
Improvements
Percent Share According to District Total
Estimated
Cost 2002
Total
Estimated Cost
3/20241
Estimated
Cost to
District Bouquet Eastside
Via
Princessa Castaic
VP‐0307R
Lyons
Avenue
and
Railroad
Ave.
Bridge
9.8% 15.6% 72.8% 1.9% $14,611,340 $30,099,360 $4,695,500 Signals
Right‐of‐way
acquisition
VP‐0811R
Newhall
Road and
SR‐14 Signals 3.6% 21.2% 75.2% 0.0% $1,198,170 $2,468,230 $523,265 VP‐0900R
Calgrove
and I‐5
Widen under
crossing, Flood
control
channel,
retaining wall,
Signals, Right‐
of‐way
acquisition 3.2% 8.4% 79.3% 9.2% $8,528,300 $17,568,298 $1,475,737 C‐0501R
Parker
Road and I‐
5 Bridge
widening,
Ramps, Signals 3.4% 4.5% 7.0% 85.1% $4,047,820 $8,338,509 $375,233 Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
68 Interchange
# Location
Description of
Improvements
Percent Share According to District Total
Estimated
Cost 2002
Total
Estimated Cost
3/20241
Estimated
Cost to
District Bouquet Eastside
Via
Princessa Castaic
E‐0505R
Via
Princessa
and SR‐14
Widen under
crossing,
Signals 4.9% 83.6% 11.3% 0.1% $4,022,300 $8,285,938 $6,927,044 E‐1100R
Placerita
Canyon
and SR‐14
Signals, Right‐
of‐way
acquisition 14.3% 47.6% 37.5% 0.6% $2,004,410 $4,129,085 $1,965,444 TOTAL: $34,412,340 $70,889,420 $15,962,223
1 Based on CCI from 12/2002 to March 2024
Eastside Bridge and Major Thoroughfare
Construction Fee District Update Report
69 ATTACHMENT F: B&T CASH/CREDIT REQUEST FORM
IO#:____________
District Percentages:
Valencia % Amount: $ Cash Credit
Bouquet Canyon % Amount: $ Cash Credit
Eastside % Amount: $ Cash Credit
Castaic District % Amount: $ Cash Credit
Via Princessa % Amount: $ Cash Credit
Lyons Avenue/ McBean Parkway % Amount: $ Cash Credit
Area Identification:
Link#(s): Intersection #(s): Interchange #(s):
Project Description: ______ ____________________________________________________ ___________________________________________________________________________
ATTACHMENTS Yes No N/A
Signature Page
Applicable District Formation Documents
Applicable District Values
County Project Acceptance Letter
75% Refund Calculations
Site Location Map
Contract & Change Orders
Purchasing Authorizations
Contract Summary
Payment Recap
Cancelled Checks & Supporting Documentation
Additional Documentation
Plans
Completed by:
Name Title ‐ Developer Date
Submitted to:
Name Title – County Date